You are on page 1of 1

CADANGAN KERJA-KERJA HIASAN DALAMAN MASJID SG.

PINANG (Masjid Cina) TARIKH: 11 OCT 2017


Printed Tile
NO. RUANG PERKARA BAHAN KELUASAN (ft2) KOS (RM) TOTAL KOS (RM) CATATAN
1. Ruang Solat Utama i)Pandangan Hadapan a)Dinding i)Printed Tile 50 57,500
1150
b)Tiang i)Printed tile 176 50 8,800

ii)Pandangan Sisi Kanan a)Dinding i)Printed Tile 670 50 33,500

b)Tiang i)Printed Tile 132 50 6,600

c)Tingkap i)Frosted Sticker 96 50 4,800

ii)Pandangan Sisi Kiri a)Dinding i)Printed Tile 670 50 33,500

b)Tiang i)Printed Tile 132 50 6,600

c)Tingkap i)Frosted Sticker 96 50 4,800

TOTAL 3,122 156,100


2. Ruang Solat Wanita i)Pandangan Sisi Kanan a)Dinding i)Printed Tile 178 50 8,900
i)Aras Tanah
b)Tiang i)Printed Tile 60 50 3,000

c)Tingkap i)Frosted Sticker 24 50 1,200

ii)Pandangan Sisi Kiri a)Dinding i)Printed Tile 178 50 8,900

b)Tiang i)Printed Tile 60 50 3,000

c)Tingkap i)Frosted Sticker 24 50 1,200

iii)Pandangan Belakang a)Dinding i)Printed Tile 378 50 18,900

b)Tiang i)Printed Tile 80 50 4,000

TOTAL 982 49,100


3. Ruang Solat Wanita i)Pandangan Sisi Kanan a)Dinding i)Printed Tile 202 50 10,100
ii)Aras Satu
b)Tiang i)Printed Tile 60 50 3,000

c)Tingkap i)Frosted Sticker 48 50 2,400

ii)Pandangan Sisi Kiri a)Dinding i)Printed Tile 202 50 10,100

b)Tiang i)Printed Tile 60 50 3,000

c)Tingkap i)Frosted Sticker 48 50 2,400

iii)Pandangan Belakang a)Dinding i)Printed Tile 378 50 18,900

b)Tiang i)Printed Tile 80 50 4,000

TOTAL 1,078 53,900


4. Aras dua i)Pandangan Hadapan a)Dinding i)Printed Tile 588 50 29,400

b)Tiang i)Printed Tile 152 50 7,600

ii)Pandangan Sisi Kanan a)Dinding i)Printed Tile 180 50 9,000


c)Tingkap i)Frosted Sticker 36 50 1,800

iii)Pandangan Sisi Kiri a)Dinding i)Printed Tile 180 50 9,000


c)Tingkap i)Frosted Sticker 36 50 1,800

iv)Pandangan Belakang a)Dinding i)Printed Tile 588 50 29,400

b)Tiang i)Printed Tile 152 50 7,600

TOTAL 1,912 95,600


TOTAL KESELURUHAN KOS (RM) 354,700