Project : Ancillary Builidng (B06/B15A/C09A)

Date: 28-01-2023
Location : Kandal

REPORT SUMMARY SUBMITTAL-PMIS

Submitted Date Completed Date


Doc.Type PMIS No. Items Revision Remark
(DD/MM/YY) (DD/MM/YY)
N0 INSPECTION REQUEST_(IR)
MATERIAL INSPECTION REQUEST_(MIR)

TIA_B06_MASTER SCHEDULE_30OCT2022_
NPPIA-G-71-51-SMT-GN-1659 02 29-Nov-2022 9-Dec-2022 Resubmit
REV02_DETAIL#STM-001

TIA_B06_MASTER SCHEDULE_2023315_
1 Submittal (SMT) NPPIA-G-71-51-SMT-GN-2165
REV03_DETAIL#STM-001-a
03 17-Mar-2023 RR by MCC

NPPIA-G-71-51-SMT-GN-2293 TIA_B06_MASTER SCHEDULE_20230411_REV04_DETAIL#STM-001-b 04 11-Apr-2023

TIA_C09A_ANCILLARY_BUILDINGS_MASTER_SCHEDULE_30OCT2022_REV02_DETAIL#STM
NPPIA-G-71-51-SMT-GN-1660 02 29/11/2022 12-Sep-2022 Resubmit
-002

TIA_C09A_ANCILLARY_BUILDINGS_MASTER_SCHEDULE_20230315_REV03_DETAIL#STM-
2 Submittal (SMT) NPPIA-G-71-51-SMT-GN-2166
002-a
03 17-Mar-2023 RR by MCC

TIA_C09A_ANCILLARY_BUILDINGS_MASTER_SCHEDULE_20230411_REV04_DETAIL#STM-
NPPIA-G-71-51-SMT-GN-2294 04 11-Apr-2023
002-b

NPPIA-G-71-51-SMT-GN-1661 TIA_B15A_MASTER SCHEDULE_30OCT2022_REV02_DETAIL#STM-003 02 29/11/2022 12-Sep-2022 Resubmit

3 Submittal (SMT) NPPIA-G-71-51-SMT-GN-2167 TIA_B15A_MASTER SCHEDULE_2023315_REV03_DETAIL#STM-003-a 03 17-Mar-2023 RR by MCC

NPPIA-G-71-51-SMT-GN-2295 TIA_B15A_MASTER SCHEDULE_20230411_REV04_DETAIL#STM-003-b 04 11-Apr-2023

NPPIA-G-71-51-SMT-GN-1989 TIA_C09A_B15A_B06_STRUCTURAL WORK ITP AND CHECK LIST #STM-004 00 10-Feb-2023 24-Feb-2023 Resubmit

4 Submittal (SMT)

NPPIA-G-71-51-SMT-GN-2388 TIA_C09A_B15A_B06_STRUCTURAL WORK ITP AND CHECK LIST (REV1) #STM-004-a 01 1-May-2023 On progress
Project : Air Traffic Control Tower
Date: 28-05-2022
Location : Kandal

REPORT SUMMARY SUBMITTAL-PMIS

Doc.Type PMIS No. From PMC PMIS No. Sub. Items Revision Receive Date Submit Date Complete Date Remark
Field Instruction_(FI)
Field Instruction_(FI)

Non-Conformance Report_(NCR)
Non-Conformance
Report_(NCR) NPPIA-G-01-51-NC-QC-0012 NPPIA-G-71-51-NC-GN-0017 PMC_AB-C09A-001 Casting lean Concrete without IR 00 11-Feb-23 20-Mar-23 30-Mar-23 Apporved
Project : Ancillary Builidng (B06/B15A/C09A)
Date: 28-01-2023
Location : Kandal

REPORT SUMMARY SUBMITTAL-PMIS


Submitted Date Completed Date
Doc.Type PMIS No. Items Revision Remark
N0 (DD/MM/YY) (DD/MM/YY)

Submittla (STM)

Approved and
NPPIA-G-71-51-SMT-GN-1573 ANCILLARY C09A,B15A,B06-Material Steel Reinforced Bar #SMT-STR-001 00 16-Nov-22 12-Oct-22
Resubmit

1 Submittla (STM) Revised and


NPPIA-G-71-51-SMT-GN-1763 ANCILLARY C09A_B15A_B06-Material Steel Reinforced Bar (E-001-Rev1-a&b) #SMT-STR-001-a 01 16-Nov-22 1-Dec-23
Resubmit

NPPIA-G-71-51-SMT-GN-2005 ANCILLARY C09A,B15A,B06-Material Steel Reinforced Bar #SMT-STR-001-b 02 13-Feb-23 10-Mar-23 Approved

2 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy28 MPa +Small Agg + Water tight Approved As
NPPIA-G-71-51-SMT-GN-1668 00 1-Dec-22 17-Dec-22
Slump 16+-2cm (CONCRETE TRAIL MIX CODE CS112) #STM-STR-002 Note

3 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy28 MPa Slump 16+-2cm Approved As
NPPIA-G-71-51-SMT-GN-1669 00 1-Dec-22 17-Dec-22
(CONCRETE TRAIL MIX CODE CS036) #STM-STR-003 Note

4 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy28 MPa + Small Agg Slump 16+-2cm Approved As
NPPIA-G-71-51-SMT-GN-1671 00 1-Dec-22 19-Dec-22
(CONCRETE TRIAL MIX CODE CS205) #STM-STR-005 Note

5 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy28 MPa Slump 12+-2cm (CONCRETE TRIAL MIX CODE Revised and
NPPIA-G-71-51-SMT-GN-1672 00 1-Dec-22 19-Dec-22
CS006) #STM-STR-006 Resubmit

6 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy28 MPa Slump 12+-2cm (CONCRETE TRIAL MIX CODE Reciept
NPPIA-G-71-51-SMT-GN-1933 01 28-Jan-23 20-Feb-23
CS006) #STM-STR-006-a Acknowledge

7 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy16 MPa Slump 16+-2cm (CONCRETE TRIAL MIX CODE Approved As
NPPIA-G-71-51-SMT-GN-1699 00 1-Dec-22 19-Dec-22
CS032-2) #STM-STR-007 Note

8 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy20 MPa + Small Agg+ Water tight Slump 14+-2cm Revised and
NPPIA-G-71-51-SMT-GN-1764 00 16-Dec-22 30-Dec-22
(CONCRETE TRIAL MIX CODE CS095) #STM-STR-008 Resubmit

9 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy20 MPa Slump 16+-2cm (CONCRETE TRIAL MIX CODE Revised and
NPPIA-G-71-51-SMT-GN-1765 00 16/12/2022 30-Dec-22
CS034-3) #STM-STR-009 Resubmit

10 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy20 MPa+Small Agg+ Water tight Slump 12+-2cm Revised and
NPPIA-G-71-51-SMT-GN-1766 00 16-Dec-22 30-Dec-22
(CONCRETE TRIAL MIX CODE CS080) #STM-STR-010 Resubmit

11 Submittla (STM) NPPIA-G-71-51-SMT-GN-1924 ANCILLARY C09A_B15A_B06_Material Waterproofing #STM-STR-011 00 25-Jan-23 23-Feb-23 AAN

12 Submittla (STM) ANCILLARY C09A_B15A_B06_Material Concrete Cy28 MPa Water tight P8 Slump 14+-2cm (CONCRETE TRIAL
NPPIA-G-71-51-SMT-GN-1929 00 27-Jan-23 1-Feb-23 Approved
MIX CODE CS097) #STM-STR-012

Approved As
13 Submittla (STM) NPPIA-G-71-51-SMT-GN-2000 ANCILLARY C09A_B15A_B06_Material Anti Termite #STM-STR-013 0 44968 45002
Note
Project : Ancillary Builidng (B06/B15A/C09A)
Date: 28-01-2023
Location : Kandal

Submittla (STM) NPPIA-G-71-51-SMT-GN-2002 ANCILLARY C09A_B15A_B06_Material Sand backfilled for structural work #STM-STR-014 00 11-Feb-23 17-Mar-23 RR

14

Submittla (STM) NPPIA-G-71-51-SMT-GN-2156 ANCILLARY C09A_B15A_B06_Material Sand backfilled for structural work (Rev1) #STM-STR-014-a 01 15-Mar-23 24-Mar-23 Approved

15 Submittla (STM) NPPIA-G-71-51-SMT-GN-2085 ANCILLARY C09A_B15A_B06_Material coupler 28mm for structural work #STM-STR-015 00 1-Mar-23 24-Mar-23 Approved

Submittla (STM) NPPIA-G-71-51-SMT-GN-2358 ANCILLARY C09A_Material Approval Anti-termite HDPE pipe fitings #STM-STR-C09A-016 00 27-Apr-23 12-May-23 Approved

16 Submittla (STM) NPPIA-G-71-51-SMT-GN-2359 ANCILLARY B15A_Material Approval Anti-termite HDPE pipe fitings #STM-STR-B15A-016 00 27-Apr-23 12-May-23 Approved

Submittla (STM) NPPIA-G-71-51-SMT-GN-2360 ANCILLARY B06_Material Approval Anti-termite HDPE pipe fitings #STM-STR-B06-016 00 27-Apr-23 12-May-23 Approved

Submittla (STM) NPPIA-G-71-51-SMT-GN-2198 ANCILLARY C09A_B15A_B06_Sample TEKCOM Film Faced Plywood #STM-STR-017 00 23-Mar-23 RR

17

Submittla (STM) NPPIA-G-71-51-SMT-GN-2199 ANCILLARY C09A_B15A_B06_Material TEKCOM Film Faced Plywood #STM-STR-017-a 00 23-Mar-23 7-Apr-23 Approved

18 Submittla (STM) Approved As


NPPIA-G-71-51-SMT-GN-2212 ANCILLARY C09A_B15A_B06_Material Sika for Expansion Joint and others #STM-STR-018 00 24-Mar-23 11-Apr-23
Note

Submittla (STM) NPPIA-G-71-51-SMT-GN-2221 ANCILLARY C09A_B15A_B06_Material Concrete Block for formwork #STM-STR-019 00 28-Mar-23 6-Apr-23 RR

19

Submittla (STM) NPPIA-G-71-51-SMT-GN-2312 ANCILLARY C09A_B15A_B06_Material Concrete Block for formwork #STM-STR-019-a 01 19-Apr-23 10-May-23 Approved

20 Submittla (STM) NPPIA-G-71-51-SMT-GN-2246 ANCILLARY C09A_B15A_B06_Material Anti termite F.A.C.T #STM-STR-020 00 31-Mar-23 27-Apr-23 Approved
Project : Ancillary Builidng (B06/B15A/C09A)
Date: 28-01-2023
Location : Kandal

REPORT SUMMARY SUBMITTAL-PMIS

Submitted Date Completed Date


Doc.Type PMIS No. Items Revision Remark
(DD/MM/YY) (DD/MM/YY)
INSPECTION REQUEST_(IR)
MATERIAL INSPECTION REQUEST_(MIR)

Inspection Test Plan (ITP) NPPIA-G-71-51-ITP-GN-0001 ANCILLARY C09A,B15A,B06-ITP for structural work and checklist # ITP-STR-001 01 07-Mar-23
REPORT SUMMARY SUBMITTAL-PMIS

Submit Status
No. Documennts
Submit Date Revision Date Status
Project : Ancillary Builidng (B06/B15A/C09A)
Date: 28-01-2023
Location : Kandal

REPORT SUMMARY SUBMITTAL-PMIS

Submitted Date Completed Date


Doc.Type PMIS No. Items Type Revision Remark
(DD/MM/YY) (DD/MM/YY)
N0
INSPECTION REQUEST_(IR)
Submittla (STM)
MATERIAL INSPECTION REQUEST_(MIR)

1 Inspection Request (IR) NPPIA-G-71-51-IR-GN-0304 AAB_C09A_Bench Mark Inspection_#IR-STR-C09A-001 IR 00 17-Jan-23 On going

2 Submittla (STM) NPPIA-G-71-51-SMT-GN-1886 AAB_C09A_Bench Mark for survey work_#SMT-STR-C09A-01 SMT 00 17-Jan-23 01/25/2023 ANN

Material Inspection
3 Request_(MIR) NPPIA-G-71-51-MIR-GN-0103 ANCILLARY C09A,B15A,B06-Material Inspection Request Steel Reinforced Bar (Material Delivery) #MIR-001 MIR 00 4-Feb-23 On progress

4 Inspection Request (IR) AAB_C09A_Pile Cap Lean Concrete_#IR-STR-C09A-002 IR 00 13/02/2023 On going

5 Inspection Request (IR) AAB_C09A_Pile Cap Lean Concrete_#IR-STR-C09A-002a IR 00 13/02/2023 On going

6 Inspection Request (IR) AAB_C09A_Survey work level of pile caps lean concrete_#IR-STR-C09A-003 IR 00 13/02/2023 On going

7 Inspection Request (IR) AAB_C09A_level cutting piles foundation_#IR-STR-C09A-004 IR 00 13/02/2023 On going

8 Report (RPT) NPPIA-G-71-51-RPT-GN-0087 Ancillary C09A-Confirmation Letter-No-Application-Anti-Termite-Pile-Cap-Bottom_#RPT_C09A_001 RPT 00 14/02/2023 On going

9 Material Inspection
Request_(MIR) NPPIA-G-71-51-MIR-GN-0105 AAB_C09A-Material Inspection Request Steel Reinforced Bar (Material Delivery) #MIR-002 MIR 00 10-Feb-23 On going

10 Material Inspection
Request_(MIR) NPPIA-G-71-51-MIR-GN-0108 ANCILLARY C09A,B15A,B06-Material Inspection Tensile test Steel Reinforced Bar #MIR-003 MIR 00 23-Feb-23 On going
Project : Ancillary Builidng (B06/B15A/C09A)
Date: 28-01-2023
Location : Kandal

REPORT SUMMARY SUBMITTAL-PMIS

Submitted Date Completed Date


Doc.Type PMIS No. Items Type Revision Remark
(DD/MM/YY) (DD/MM/YY)
N0
INSPECTION REQUEST_(IR)
Submittla (STM)
MATERIAL INSPECTION REQUEST_(MIR)

1 Inspection Request (IR) NPPIA-G-71-51-IR-GN-0321 AAB_B15A_Bench Mark Inspection_#IR-STR-B15A-001 IR 00 22-Feb-23 On going