Professional Documents
Culture Documents
TOPIC OUTLINE
Objective Fuel Properties
Boiler History Type of Horizontal Boiler
Boiler Operation Four Boiler Basic System
Boiler Definition Boiler Safety Features
Boiler Classification Boiler Maintenance
Parts of Boiler Boiler Star-up
Thermodynamic Principle Best Practices
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
OBJECTIVE
To Reappraisal all Mechanical Engineers, Certified
Plant Mechanics and Tenders in Field of Fired Pressure
Vessel-Boiler (Low and Medium).
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
History
Aeolipilae are hollow brazen
vessels, which have an opening or
mouth of small size, by means of
which they can be filled with water.
Prior to the water being heated over
the fire, but little wind is emitted. As
soon, however, as the water begins
to boil, a violent wind issues forth.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
BOILER OPERATION
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
BOILER OPERATION
To tend or operate the fired pressure vessel
safely in accordance with the manufacturer’s
standard operating procedure in response to
plant operational requirements.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
DEFINITION
BOILER
- a closed vessel in which water is heated
and transformed into steam through the
application of heat energy obtained from the
combustion of fuel or from electric, nuclear,
solar or geothermal means.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
BOILER CLASIFICAION
1. As to axis of shell (vertical or horizontal)
2. According to use in which they are put
a. Heating/ process
b. Power generation
3. According to location of furnace
a. Internally fired
b. Externally fired
4. According to relative position of water and hot gases
a. Water tube
b. Fire tube
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
HORIZONTAL BOILER
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
HORIZONTAL BOILER
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
HORIZONTAL BOILER
First Pass
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
HORIZONTAL BOILER
Second Pass
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
HORIZONTAL BOILER
Third Pass
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
VERTICAL BOILER
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
VERTICAL BOILER
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
STEAM DEFINITON
*** the vapor state of water.
PRINCIPLE OF STEAM PRODUCTION
Steam
H2O
Air
Fuel
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
THERMODYNAMIC PRINCIPLE
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
EVAPORATION PROCESS IN
STEAM BOILER
BASIC BOILER
FORMULAS
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
250
Temperature ºC
200
150
100
50
0.5 1 2 5 10 20
Parameters Philippines
Suspended Particulates 150 mg/m3
CO 500 mg/m3
Combustion Triangle
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
PRODUCTS OF COMBUSTION
The Combustion process produces a fire. The fire burns the fuel and changes
Chemical energy to heat energy. Fuel plus air make hot gas. Hot gas
contains the fuel Heat energy.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
COMBUSTION OF FUEL
CALORIFIC VALUES
All fuels contains Hydro Carbons of varying proportions.
Complete combustion will produce CO2 and H20 discharged in
vapor state as flue gas.
COMPLETE COMBUSTION
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
24(32) lb O2
= 3.43
12(16) + 32 lb fuel
lb O2 lb air
= 3.43 X 4.3
lb fuel lb O2
lb air
= 14.78
lb fuel
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
M= r V
= 0.96 kg/li (60li/hr)
= 57.6 kg/hr or 127 lbs/hr
127 lbs fuel X 14.78 lb air
hr lb fuel
T Y P E S O F HORIZONTAL B O I L E R
2. Wet Back
The hot gases from the furnace pass into a water - cooled rear reversing
chamber inside the shell thus increasing the heat transfer area.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
Eccentric arrangement
Centric arrangement
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
2. Fuel system
4. Draft system
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
H2O Softener
Boiler
BFP
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
Fuel System
Steam IN
Steam Oil
Pre- Heater
Steam OUT
Pressure
Electric oil Gauge
Heater 200- 100 psig
Nozzle
230 deg F
Gate
Valve Check
Valve
Check
Valve
Bottle Washer
Steam outlet
Valve
Make-up
Condensate Water
tank
Holding Tank
Boiler
Air
BFP
Check Valve
Feed Pump
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
Exhaust Stack
Draft System
Inlet
Damper
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
MAX LIMIT
Appearance Clear
Color Clear/Milky white
pH 7
M-alkalinity (ppm) 1200
Total Hardness (ppm) 0-25
Total Dissolved Solids (ppm) 1500 3000
Dissolved Oxygen 0
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
They are valves, gages and other connection devices attached directly to
the boiler and necessary for safe and efficient operation.
Steam pressure gages - the steam pressure inside the boiler and is connected to
the highest point of the steam space, the steam gages should be calibrated
to least 1 1/2 times the set pressure of safety value.
Water gage - The actual water level inside the boiler drum usually the lowest
water level is 3 in. above the highest fire tube boiler.
Boiler safety valve - To prevents boiler pressure from rising above a certain
predetermined pressure by allowing excess steam to escape into the atmosphere
when that point is reached. Thus guarding against possible explosion
through excessive pressure.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
C. Low - fire hold switch - Safeguard boiler from shifting from low fire to
high fire position during start up to prevent thermal shock , usual setting is
10 psig steam pressure developed before it shift to high pressure.
D. Modulating control - This pressure control switch will give signal to the
modutrol motor to shift from low fire to high fire or vise versa position.
E. Fire eye flame control - Shutdown the fuel supply to the burner when
there was no fire in the combustion chamber and triggers the operation
of the programmer controls for one complete cycle before shut down.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
Start-up of Boiler
It is to note that the following steps may not apply to all types of boilers and each
boiler requires some additional steps to be followed as per its system design.
However, the basic steps remain the same:
With main power breakers in the “on” position, the water supply and fuel supply
System are aligned to support boiler operation, and the burner switch is in the “off”
Position, perform the following steps.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
1. Ensure that the vent valve on the boiler is open and check there is no pressure
in the boiler.
2. Check that the steam stop valve is closed.
3.Check that all the valves for fuel are open, and let the fuel circulate through the
system until it comes to the temperature required by the manufacturer
recommendation.
4.Check and open the feed water valves to the boiler and fill the water inside the
boiler drum to just above the low water level. This is done because it is not
possible to start the boiler below the low water level due to safety feature which
prevent boiler from starting. Also, the level is not filled much because if filled too
much, the water inside the boiler might expand and over pressurize the boiler.
5.Start the boiler in automatic mode. The burner fan will start the purging cycle
which will remove any gases present in the furnace by forcing it out through the
funnel.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
6. After the pre-set purge time the pilot burner will ignite. The pilot burner
consists of two electrodes, through which a large current is passed, via the
transformer, producing the spark between the electrodes. The pilot burner is
supplied with diesel oil and when the oil passes over, the former ignites.
7. The main burner which is supplied by heavy oil catches fire with the help of
pilot burner.
8. Check the combustion chamber from the sight glass to ensure the burner
has lit and the flame is satisfactory.
9. Keep a close eye on the water level as the pressure increases and open the
feed water when the level of water inside the gauge glass is stable.
10. Close the vent valve after the steam starts coming outside.
11. Open the steam stop valve.
12.Once the working steam pressure is reached, blow down the gauge glass
and float chambers to check for the alarms
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
TO STOP BURNER
1. Pull blower and control switch.
2. Do not pull feed water pump switch until boiler has cooled
MAINTENANCE
Daily Procedure
1. Blow down boiler using bottom rear blow - off. Blow down when
burner is firing. Blow down should be conducted for the duration
directed by the water chemistry .
2. Blow down water column to low water cut off point.
3. Check level oil in storage tank.
4. Check lubricating oil in compressor oil cup, ( when compressor is
used ) fill with non - detergent oil.
5. Check stack temperature. If above normal check fire side of boiler
for dirt, over firing, or improper combustion.
6. When using a condensate tank or dearator check temperature of
water supplied to unit. If below 160 deg.F, investigate the
condensate return heat source.
7. Check oil pump suction conditions ,. Oil pump suction Should not
exceed 130 deg. or 5 pounds pressure.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
MAINTENANCE
Weekly Procedure
1 . Check combustion control operation as outlined in check list
section of service manual . Investigate and correct at once any
failure to shut off fuel valve.
.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
Weekly Procedure-cont.
MAINTENANCE
Monthly Procedure
1. Check the belt tension and adjust if required on all belt drive pumps
and compression.
2. Turn down feed water grease cups. Note every 3 months fill cups with
new grease( Standard oil company no. 18 superia)
3. Lift the steam safety valve by the manual lever to make sure it is
operating freely.
5. Check rear head flue gas leaks and tighten bolts a required
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
MAINTENANCE
Semi- Annual Procedure
1. Cool boiler slowly to room temperature. (Warning: failure to cool the
boiler slowly will effect life of boiler and possibly cause tube leak).
2. Gradually remove all the fasteners around the rear door flange, pry
the head loose from the boiler and swing it away on the davit.
3. Remove the remaining two upper rear panels.
4. Using flue brush , and vacuum cleaner, brush though the tubes to the
from end of the boiler.
5. Soot and scale may be removed from the front end of the boiler by
removing the clean out cover located at the bottom of the cover
plate and inserting vacuum cleaner hose.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
7. Always replace the sealing rope around the edge of the rear refractory with
new rope and clean off any old cement. The new rope may be held in place
with cement.
8. Replace the outer sealing rope on the upper rear panels with the new rope.
The new rope may be held in place with cement.
10. Close the rear head and rear panels. Tighten all fasteners evenly to seat
the sealing rope.
13. Remove the peep sight glass, clean and replace. Note inspect the
gasket and replace if necessary.
15. Examine belts for signs of wear. Replace worn belts before they
fail, so as to prevent shut down.
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
MAINTENANCE
Annual Procedure
1. Follow steps 1 to 12 listed under semi - annual procedure.
BEST PRACTICES
CONDENSATE
Contributes to energy and cost savings
- for every 5 deg C improvement will give 1% fuel gain
Every kg of condensate not returned would require:
Q= mCpDt
Q=1(4.19KJ/Kg C)(80-30)C
Q=209.5 KJ/kg
BEST PRACTICES
CONDENSATE- cont.
Contributes to energy and cost savings
BEST PRACTICES
INSULATION
EXAMPLE OF ENERGY LOSS IN KW / 100 M length of 2 inch
diameter pipe at Steam Temperature of 150 deg C.
BEST PRACTICES
STEAM LEAK
ENERGY LOSS in kgs of steam per diameter of leak
SUMMARY
• Boiler efficiency/combustion
– Keep clean both water & fire side of the boiler
– Ensure P/T of bunker oil is maintained
– Atomizing nozzle & compressed air properly
working(replace nozzle at least once/year
– Ensure air/fuel controller is properly working for
finer calibration (0-25-50-100)
– Keep fireside tightly closed except where
combustion air is coming from
GTG Engineering Services
Engineers . Consultant . Designer . Contractor
SUMMARY
SUMMARY