Professional Documents
Culture Documents
JUNE 2022
Acknowledgements DISCLAIMER
This document is published in collaboration by the Structural
Engineering Society New Zealand (SESOC) and the New
2022 PANEL OF EXPERTS: Zealand Geotechnical Society (NZGS). Both of these
• Tony Fairclough – Panel Chair: Tonkin & Taylor organisations are not-for-profit Technical Societies of
• Andy Dodds – Lead Author: Arup Engineering New Zealand (ENZ).
• Tessa Beetham: Aurecon
This document supersedes the Auckland Structural Group
• Bishal Subedi: Aurecon
publication “Piling Specification” (Rev G, 2002).
• Paul Berriman: Brian Perry Civil
• Lian Ching Oh: G round Anchorages Every reasonable effort has been made during the
• James Harrison: Fulton Hogan preparation of this document to ensure that the statements
• Gil Johnstone: Fulton Hogan made and opinions expressed within represent a robust
• Andrew Langbein: Tonkin & Taylor specification for the construction of bored or driven piles
• Martin Larisch: Jacobs in New Zealand. However, no liability or responsibility
• Malcolm McWhannell: Heron Construction associated with the application of this document shall be
• Rob Presland: Holmes Consulting directed to or accepted by the authors, SESOC, NZGS and/
• Nicola Ridgley: BECA or ENZ. The use of this document implies full acceptance of
• Michael Robinson: BECA this condition.
• Nick Wharmby: March Construction All users of this specification are fully and solely responsible
• Mike Abbott: Revex Piling for ensuring, on a case-by-case basis, that the contents and
• Paul Burton: Geotechnics recommendations which are contained within this document
• Jonathan Shelley: KGA are appropriate for the particular circumstances and
conditions that are associated with its proposed application.
ACKNOWLEDGEMENT OF
2002 PANEL OF EXPERTS Any reference or recommendation that is contained in
The 2020 Panel of Experts wish to acknowledge the this document does not relieve any user of their obligation
team that compiled and issued the original Auckland to consider all matters to which the information contained
Structural Group (ASG) Piling Specification that this herein relates to the particular circumstances of its
document is based upon. Such superseded specification, proposed application.
of which the last version was issued in 2002, was NOTE: All users of this document must take appropriate
prepared by the following Panel of Experts: professional advice prior to entering into a construction
• Albert Smith: Smithbridge contract which incorporates all or parts of this document.
• Andrew Langbein: Tonkin & Taylor
• Chris MacKenzie: Holmes Consulting Group
• Dean Coleman: Hauraki Piling Limited
IMPORTANT NOTICE
The contents of this document are subject to periodic review,
• Dick Salter: Downer Construction
updates, changes, additions, and/or deletions. The latest
• Glyn East: Opus International Consultants
version of this document is published on the SESOC and
• John Young: Gilberd Hadfield Piling Company Limited
NZGS websites:
• Malcolm Stapleton: Babbage Consultants Limited –
http://www.sesoc.org.nz http://www.nzgs.org.nz
liaison with the New Zealand Geotechnical Society
• Paul Swinburne: Brian Perry Civil It is the responsibility of all users to ensure that they
• Stuart Tucker: Beca Carter Hollings & Ferner Limited are at all times using the latest and current version of
this document.
DOCUMENT STATUS: Comments and feedback on this specification from
Revision: I - Updated document for public use. appropriately qualified and experienced engineering design
Issue Date: June 2022 and/or construction specialists is encouraged. Feedback
Lead Editor: Andy Dodds should be submitted to the documents owners (SESOC
Administration Support: We thank the following and NZGS).
individuals for their support Teresa Roetman,
Sally Fullam, Amanda Blakey
© COPYRIGHT
The owners authorise reproduction of this document, in
DOCUMENT OWNERS:
whole or in part, so long as no charge is made for the
Structural Engineering Society New Zealand (SESOC)
supply of copies, and the integrity and attribution of the
PO Box 3839, Christchurch 8140
contributors and publishers of the document is not interfered
SESOC Executive Officer:
with in any way.
Email: executiveofficer@sesoc.org.nz
This document may be reproduced and distributed in whole,
New Zealand Geotechnical Society Inc (NZGS) in any medium physical or electronic, provided that the
c/o Engineering New Zealand, PO Box 12-241, terms of this license are adhered to, and that this license is
Wellington 6144 displayed in the reproduction.
NZGS Secretary: Email: secretary@nzgs.org Any whole publication in standard (paper) book form shall
Cover photograph reproduced with the permission of require the citation of the original publishers and authors.
Annaliese Boot. The publishers and author’s names shall appear on all outer
PHOTOGRAPHS: We thank the following individuals for surfaces of the book. On all outer surfaces of the book the
use of photographs: Annaliese Boot, Stephen Crawford, original publisher’s name shall be as large as the title of the
Gil Johnstone, Andrew Langbein, Malcolm McWhannell. work and cited as possessive with respect to the title.
CONTENTS
1 GENERAL 1 1.11 NATURE OF GROUND AND
SUBSURFACE CONDITIONS 2
1.1 SCOPE AND INTERPRETATION 1
1.12 PROVING BORE REQUIREMENTS 3
1.2 DEFINITIONS AND NOTATIONS 1
1.13 SETTING OUT AND AS-BUILT
1.2.1 DEFINITIONS 1 LOCATIONS 3
1.2.2 NOTATION 1 1.14 TOLERANCES 3
1.3 PROJECT SPECIFIC 1.15 SUPERVISION 3
REQUIREMENTS 1
1.16 OBSERVATION 3
1.4 HEALTH AND SAFETY 1
1.17 PILE SUPPORT DURING
1.5 METHOD STATEMENT 2 CONSTRUCTION 4
1.6 PILING PROGRAMME 2 1.18 PROTECTION OF EXISTING
1.7 PILE DESIGN 2 STRUCTURES AND PROPERTY 4
1.8 PILE LENGTHS 2 1.19 EXISTING SERVICES 4
1.9 PILE CONSTRUCTION 2 1.20 COMPLETION 4
1.10 HANDLING, STORAGE AND
MARKING OF PILES 2
• Best Practice Guidelines for Working at Height in Submission of a tender shall be deemed as evidence
New Zealand (MBIE, 2019) that the Contractor accepts the full and sole
• Good Practice Guideline for Temporary Works responsibility for the method of working, including
(TWfNZ, GPG01, 2019) the maintenance of pile excavation stability, the
• Working (Piling) Platform Information Poster construction of defect free piles and positioning the
(TWfNZ, Working Platforms, 2018) completed piles within the required tolerances to the
approximate founding depth specified.
1.5 METHOD STATEMENT
The Contractor shall provide a detailed method 1.10 HANDLING, STORAGE AND
statement for each piling operation to be undertaken MARKING OF PILES
in executing the works including consideration All operations such as handling, transporting, lifting
of potential handling and installation effects. The and pitching of piles shall be carried out in such a
method statement shall describe all proposed manner as to prevent damage to the piles and/or
equipment and detail the construction sequence. their coatings.
The method statement shall be submitted to the
Engineer prior to commencement of piling work Piles and pile casings shall be stacked on suitable
on Site. supports on firm ground, in a manner which
will eliminate excessive handling stresses or
The Engineer’s review of the Contractor’s method other damage.
statement shall not relieve the Contractor of
its obligations to meet the requirements of this Piles to be driven shall be clearly marked with paint
Specification and the Project Specific Requirements. prior to installation with the pile number, overall
length and at regular intervals, the cumulative length
1.6 PILING PROGRAMME measured from the pile tip.
The Contractor shall submit a detailed programme
for the execution of the piling work prior to piling 1.11 NATURE OF GROUND AND
work commencing on site. SUBSURFACE CONDITIONS
It is deemed that the Contractor has inspected the
1.7 PILE DESIGN site and considered the nature of the ground through
The drawings shall clearly stipulate all key design which piles are to be constructed.
intents and assumptions and all as-built conditions
that must be checked and verified during The Contractor shall inform the Engineer of any
construction. The requirements specified on the circumstances which indicates, in the Contractor’s
drawings or the Project Specific Requirements opinion, that ground conditions differ from those
are the minimum requirements for the piles in the reported or which could have been inferred from
completed structure. ground investigation reports or preliminary
pile results.
All piles must be designed by an appropriately
qualified and experienced Chartered Professional Should the Contractor consider that such a
Engineer and in accordance with the relevant change in the ground conditions could not have
requirements of AS2159. been reasonably foreseen by an experienced
contractor when tendering and will, in the
1.8 PILE LENGTHS Contractor’s opinion, change the construction
The final as-built length of all piles shall be confirmed methodology or substantially increase the
on site and varied to take due account of the actual Contractor’s costs, then redress may be sought in
ground conditions that are encountered on site. accordance with the unforeseen physical conditions
clause(s) and section(s) of the project Conditions
The actual pile lengths may need to be adjusted of Contract.
during or after boring or driving to achieve the
required pile capacity or embedment. No warranty is expressed or implied that any
information, opinions or conclusions, given in
1.9 PILE CONSTRUCTION any factual or interpretative ground investigation
The Contractor shall construct the piles of the report, supplied in good faith by the Engineer, will
type(s) and dimensions specified on the drawings to present a complete or accurate picture of the whole
the requirements of this Specification and the Project of the site.
Specific Requirements.
1.13 SETTING OUT AND AS-BUILT The Contractor shall not carry out any remedial
LOCATIONS work on any pile, without the written approval of
The position of all piles shall be accurately set out the Engineer.
by the Contractor. The pile positions shall be
checked by the Contractor immediately prior 1.15 SUPERVISION
to installation. The Contractor shall nominate a suitably experienced
person as the “Piling Supervisor”. The Contractor
After construction, the actual pile locations shall shall submit a curriculum vitae for the proposed
be surveyed by an appropriately qualified and Piling Supervisor prior to commencement of
suitably experienced surveyor employed by the pile construction.
Contractor for this purpose. The Contractor shall
submit an as-built pile plan to the Engineer within The Piling Supervisor shall be responsible for
five (5) working days of exposure of the specified ensuring that all piling operations comply with
cut-off level. Partial as-built information may be the requirements of this Specification. The Piling
submitted throughout construction of the piles Supervisor shall also ensure that all monitoring
as required. and pile records are maintained up to date and are
available for inspection by the Engineer.
1.14 TOLERANCES
The Contractor shall make all necessary provisions to The Piling Supervisor shall not be removed from the
the pile construction procedure, initial spotting and works without the Engineer being notified one week
inclination of piles, in order to achieve installation in advance. The Contractor shall nominate a suitable
of piles to the specified tolerances. Unless specified replacement before the Piling Supervisor is removed
otherwise in the Project Specific Requirements, from the works.
all piles shall be installed so as to achieve the
following tolerances: 1.16 OBSERVATION
• Plan position of the pile top at its The Engineer requires to have the opportunity of
commencement level: observing all phases of the piling operations and of
Within 75 mm of the plan location shown on inspecting particular items such as (but not limited
the drawings to) set and rebound, the bottom of bored piles, spoil
• Vertical elevation of the pile top at its from excavations, jointing of casings, concreting,
commencement level: fabrication of reinforcing cages, etc. The Contractor
Plus 40 mm or minus 75 mm from the vertical shall therefore keep the Engineer informed daily or as
elevation shown on the drawings agreed with the Engineer as to the work anticipated
• Verticality of the as-built pile shaft: to be carried out on the next working day.
1H : 75V or straighter
2.1.4 CONCRETING OF PILES The concrete pour shall continue to a height above
The placement of concrete for piles shall be in strict the specified cut off level to ensure that sound,
accordance with the requirements of this specification homogenous concrete is achieved.
for placement in dry and/or submerged conditions,
and where appropriate, in general accordance with the Unless approved otherwise by the Engineer, in
relevant requirements of NZS3109, noting the following: a dry pile bore, concrete shall be placed using a
chute, hopper and discharge pipe or pump line.
The Contractor shall include its proposals for The concrete may fall freely below the discharge
placing and compacting concrete in the method point up to 10 m as long as concrete placement can
statement submitted in accordance with Section 1.5. be controlled and there is no segregation of the
Concrete mix design, placement and compaction concrete (such as may be caused by concrete hitting
techniques proposed shall ensure a sound, dense and the pile reinforcement during placement).
homogenous in-situ concrete is achieved along the
entire pile shaft.
The reinforcing steel shall always be adequately requirements which are stipulated in this
supported to prevent displacement during or after specification and the recommendations that are
placement of the concrete. described in the publication “Recommended
Practice Tremie Concrete for Deep Foundations (CIA,
Where only a short section of reinforced concrete is to 2012) and/or Guide to Tremie Concrete for Deep
be placed at the top of the pile (for example, to make Foundations (EFFC/DFI, 2018)”.
connection with a reinforced concrete superstructure),
the Contractor shall ensure that adequate support is 2.1.5.1 Workplan
provided to the concrete to prevent any settlement of The Contractor shall provide a detailed written
the newly placed or plastic concrete. workplan for underwater concreting work as part
of the method statement that is to be submitted to
Concrete shall be placed such that the specified satisfy Section 1.5 of this specification. The workplan
construction joint can be prepared at the top of the must be submitted for review and approval by the
pile. Where not specified, construction joints shall be Engineer no less than five (5) working days prior to
Type B in accordance with NZS3109. underwater concreting works commencing on site.
The workplan shall explain in detail the proposed
No concrete shall be placed when there is any danger method of placement of concrete, including the
of adverse weather causing damage to plastic or sequence of operations in the event that either a
partially set concrete due to movement of pile casings. blockage occurs or the concrete charge is lost
during concreting.
Where temporary casing is used to effect a dry pile
bore, there must be a sufficient head of concrete 2.1.5.2 Tremie
inside the casing when extracted to fill the annulus Where used, the bore of the tremie shall be smooth
left by the casing as well as resist any outside to allow the free flow of concrete and have a uniform
groundwater infiltrating into the fresh concrete. internal diameter of at least:
• six times the maximum size of aggregate; or
The pile concrete shall remain flowable until after • 100 mm,
temporary casings are withdrawn so that an annulus whichever is the greater.
is not formed. For long piles, this may require the
casing to be withdrawn progressively unless the The external shape and dimension of the tremie,
concrete mix is appropriately retarded to ensure that including its joints, shall allow its free movement
concrete set has not occurred within the pile prior within the reinforcement cage. The maximum outside
to casing withdrawal. Particular care shall be taken diameter of the tube, including its joints, should be
by the Contractor to avoid collapse of the pile bore not more than:
during extraction of the temporary casing. • 0.35 times the pile diameter, or the inner diameter
of the casing; or
Measurement and recording of the actual versus • 0.45 times the inner diameter of the reinforcing
theoretical concrete volume shall be undertaken by cage for circular piles, unless agreed otherwise with
the contractor during concreting of the pile. the Engineer,
whichever is smaller.
Any interruption to the continuous concreting
procedure (truck exchange, breaking of the tremie The tremie shall be equipped with a hopper that is
or any other unforseen circumstances) shall also be of sufficient size and volume to receive and convey
recorded by the contractor. fresh concrete at a rate which is sufficient to prevent
concrete spillage or the formation of construction
2.1.5 PLACING CONCRETE UNDER WATER defects. For placement of the first concrete pour it
The preferred method of placing concrete in piles is essential that the tremie pipe is continuously
shall be in a dry excavation. However, should either: flowing full until at least 1.5 m of the pile bore is
• the depth of water at the base of the pile at the filled. Where concrete is pumped to the tremie, the
commencement of concrete placement exceed hopper shall hold a minimum capacity of concrete to
75 mm; or fill not less than 1.5 m of bore depth and should have
• the inflow of water exceeds 200 mm of bore depth a means of holding this concrete until ready for the
per hour; or initial discharge.
• the use of drilling fluid prove necessary to maintain
excavation stability, The tremie and hopper shall be clean and watertight
then concrete shall be placed using a tremie throughout including joints. All previously hardened
and a methodology that meets the appropriate concrete shall be removed from the tremie prior
to insertion of the tremie in the pile. A bung, • the discharge pipe shall at all times penetrate the
hinged flap or sacrificial closure plate (closed concrete which has previously been placed with a
tremie) or travelling plug of suitable material e.g. minimum embedment of 1.5 metres and maximum
vermiculite (open tremie) shall be employed prior embedment of 12.0 metres; and
to commencement of concrete placement to ensure • surging of the tremie pipe is not permitted.
that fresh concrete can be placed without it coming
into contact with water or drilling fluid. Concrete Towards the completion of the pour when the head
shall not be placed directly into a pile under pressure of concrete in the tremie is becoming low, under
(e.g. via a concrete pump). no circumstances shall the tremie arrangement be
plunged up and down to release the last of the
2.1.5.3 Concrete Mix concrete. Instead, the Contractor shall calculate the
The following shall apply to concrete to be placed required amount of concrete to fill the pile shaft and
underwater: fill the hopper with the correct amount (plus some)
• minimum cementitious materials of not less than then lift the tremie out slowly releasing the last of
400 kg/m3 the concrete to the hole.
• maximum aggregate size 20 mm
• target concrete slump shall be 220 mm, ±40 mm 2.1.5.5 Loss of Immersion of Tremie Pipe
• minimum slump retention of 2hrs (extended further When the immersion of the tremie pipe is lost during
as required) concreting (for example, to repair breakages or to
• maximum total water content of 180 kg/m3 remove a blockage), further placement of concrete
(regional variations may be acceptable subject to shall not proceed unless:
Engineers approval) • the concrete into which fresh concrete is to be
placed has maintained its workability; and
As an alternative for concrete mixes that have a • the tremie pipe is re-immersed sufficiently deep
slump greater than 200 mm, spread tests may be into the previously placed concrete (as noted
undertaken with the target construction criteria the above – refer to Section 2.1.5.4); and
same as defined in NZS3104 (i.e. the spread diameter • no water or other contaminant is introduced into
of the concrete shall be 550 mm +/- 50 mm and no concrete which will remain below the final pile cut-
less than 450 mm after 2 hours age). off level; and
• the base of the tremie pipe is fully sealed and
All pile concrete, including any additive requirements, watertight and can withstand the pressures that
shall be designed, manufactured, supplied and will be applied to it at re-immersion depth. This
certified by an organisation that holds a current and seal can be released when the re-immersed
appropriate Certificate of Audit for the manufacture tremie pipe is embedded 1.5 m into the existing
and supply of concrete in accordance with NZS3104. workable concrete.
of the pile has been exposed, forming a faultless Care shall be taken to avoid shattering or otherwise
interface. Where the preparation of a construction damaging the remaining section of the pile. Any
joint is not possible, or the quality of a construction cracked or defective concrete or reinforcement shall
joint cannot be verified, the pile shall be abandoned be cut away and the pile repaired to provide a full and
and the empty bore above the placed concrete sound section at the pile cut off level.
backfilled with an appropriate material approved by
the Engineer. 2.2 STRUCTURAL STEEL
Integrity tests shall be carried out to document the 2.2.1 PROJECT SPECIFIC REQUIREMENTS
quality of any pile where loss of immersion of the The following items, where appropriate, are
tremie pipe has occurred, or where a construction detailed on the drawings or in the Project
joint has been formed in the pile. Refer to Section 5.1 Specific Requirements:
for requirements for integrity testing. • steel grade(s) and category(ies) of steel
• steel material quality assurance requirements
2.1.6 PRECAST CONCRETE PILES • steel fabrication quality assurance requirements
Precast concrete piles shall be cast in one continuous • weld category(ies)
operation and shall be properly cured according to • weld procedures and weld inspection/testing
the concrete specifications or as specified on the requirements
drawings or within the Project Specific Requirements. • corrosion protection for piles including
steel/concrete interfaces that are at risk of
All precast pile units shall be handled, transported accelerated corrosion
and erected so that no damage is caused to them at • details of the steelwork such as whether it
any stage. All precast pile units shall only be lifted is temporary or permanent, structural or
using properly designed and installed lifting devices. • non-structural in nature
The Contractor shall be responsible for the design,
provision and subsequent removal of lifting devices 2.2.2 REFERENCED DOCUMENTS
as required. This Specification shall be read in conjunction
with the following standards, guidelines, and other
2.1.6.1 Splicing of Precast Piles documents, which are deemed to form part of this
Details of the design, manufacture and tests of Specification. In the event of this Specification being
the jointing system shall be submitted to the at variance with any provision of these referenced
Engineer prior to the commencement of precast documents, the requirements of this Specification
pile manufacture. shall take precedence. All materials and workmanship
shall comply with these documents unless expressly
A spliced pile shall be capable of withstanding the noted otherwise. All documents referenced below
same driving stresses as a single unjointed pile shall be the latest revision, complete with current
of the same cross sectional dimensions, length amendments, as at the commencement of the
and materials. Contract Works.
• AS/NZS1554.1 Welding of Steel Structures
The welding of a joint to main reinforcement in lieu • BS3100 Specification for Steel Castings for General
of a lapped connection with projecting bars shall Engineering Purposes
not be permitted without the prior approval of • NZS3404 Steel Structures Standard
the Engineer. • AS/NZS5131 Structural Steelwork – Fabrication
and Erection
Each pile splice shall be square to the axis of the
pile. The alignment of the spliced pile sections shall 2.2.3 STEEL H PILES
not vary by more than ±5 mm from a 1000 mm Steel H piles shall comply with the requirements of
long straight edge. The centroid of the splice shall NZS3404. Certified mill test reports, test certificates
lie within ±5 mm of the centroid of the adjacent issued by the mill or independent test agencies shall
pile sections. be provided as evidence of compliance with the
material supply standards referenced in NZS3404.
2.1.6.2 Cutting off and Preparing of Pile Heads
When the pile has been installed in accordance with 2.2.4 STEEL PIPE PILE AND STEEL CASING
the requirements of this Specification, the concrete MANUFACTURING PROCESS
at the head of the pile shall be cut off to the levels All piles shall be of the type and minimum cross
specified on the drawings. section dimensions as specified on the drawings or
Project Specific Requirements.
Steel casings and pipe piles shall be Engineer All piles and production facilities shall be made
approved longitudinally or spirally welded steel or available for inspection by the Engineer at any time.
an approved substitute. Where steel casings or All sheet piles shall be carefully examined at the
pipe piles are used as structural elements in a time of delivery to the site, and damaged piles shall
finished structure, they shall comply with the steel be repaired or replaced. The Contractor shall ensure
grade and other requirements as specified on the that all interlocks are clean and free from distortion.
Drawings or Project Specific Requirements. The
casing and pipe pile walls shall not have holes or 2.2.5.2 Welding
weld discontinuities. Welding of sheet piles shall comply with Section
2.2.6.
The rolling or manufacturing tolerances for steel
casings or pipe piles shall be such that the actual Welded site splices shall comply with Section 2.2.7.
weight of section does not differ from the theoretical
weight by more than ±5%. The external diameter Where sheet piles are to be spliced by butt welding,
at any section, measured using a steel tape on the the interlocks shall not be welded unless a seal weld
circumference, shall not differ from the theoretical is required.
diameter by more than ±1%. The deviation from
straightness on any longitudinal face shall not exceed 2.2.6 WELDING
1/600 of the length of the pile, nor 5 mm in any Where not specified in the Project Specific
3000 mm length. Requirements, all welds shall be weld category SP in
accordance with NZS3404.
The Contractor shall submit details of the
manufacturing and welding processes to All welding procedures shall be in accordance with
the Engineer, before commencement of pile AS/NZS1554. The Contractor shall submit full details
manufacture. The Contractor shall provide the of the proposed welding procedures and electrodes,
Engineer with works test certificates, analyses, with drawings and schedules as required. Welding
and mill certificates, together with the pipe consumable selection shall be in accordance with
manufacturer’s certificate showing details of the AS/NZS1554.
pile number, cast number of the steel and a record
of all tests and inspections carried out. The Only welders qualified to AS/NZS1554 or who have
Contractor shall give the Engineer adequate notice attained a similar standard shall be employed on
of the start of each stage of the manufacturing the Works. Proof of welders proficiency and
process and any production tests, and shall make qualification shall be made available to the Engineer
facilities available to the Engineer for inspection. The on request.
Contractor shall provide the Engineer with samples
when required. Splices between adjacent lengths of pile shall be
made with full penetration butt welds, complete
2.2.5 STEEL SHEET PILES with backing plates (where required). All work
associated with welding shall be protected from
2.2.5.1 Manufacture the weather.
All steel sheet piles shall be manufactured from steel
material that complies with NZS3404, BS EN 10248, Where not specified in the Project Specific
BS EN 10249 or some other Engineer approved Requirements, weld inspection methods and
standard. Certified mill test reports, test certificates permissible levels of weld imperfections shall be in
issued by the mill or independent test agencies shall accordance with AS/NZS1554.
be provided as evidence of compliance with the
material supply standards referenced. The Contractor shall submit and agree with
the Engineer a programme of independent
Unless approved prior in writing by the Engineer, weld inspection and testing required prior to
only new sheet piles shall be used for permanent commencement of any welding. The level of weld
works. inspector independence shall be agreed with the
Engineer prior to commencement of any welding.
All fabricated pile components, such as corners,
junctions, box piles, and high modulus piles, shall be Weld inspections shall be carried out in accordance
fabricated and supplied in accordance with the sheet with AS/NZS1554. As a minimum the extent of non-
pile manufacturer’s written instructions. destructive examination (NDE), other than visual,
shall be as set out in Table 2.2.6.
Visual Means
Other Means
Weld
Category Magnetic Particle or Radiography or
Visual Scanning (1)
Visual Examination (2)
Liquid Penetrant Ultrasonics
NOTES:
(1) Visual scanning shall determine that no welds called for in the Drawings or Specification are omitted. Visual scanning shall also detect gross
welding defects.
(2) Visual examination shall determine whether the required weld quality (in accordance with Table 6.2 of AS/NZS1554.1) has been achieved.
(3) Per Appendix D, NZS3404
Where the proportion of NDE called for above is less 2.2.8 DRIVING SHOES
than 100%, the Contractor shall agree a programme Cast steel driving shoes shall be of steel to BS3100
of testing with the Engineer prior to commencement Grade A1. Flat plate and welded fabricated steel
of any welding. The test programme shall consider shoes shall be mild steel complying with NZS3404.
variables such as steel grade, welding process, Fabricated pile shoes, or the strengthening to the
equipment used and different welders employed on toe of a pile in lieu of a shoe, or the strengthening
the works. of the head of a pile for driving, shall be made using
material of the same grade as the pile.
The weld test programme shall involve full testing of
the first 5% of welds, in order to pick up and correct 2.2.9 PREPARATION OF PILE HEADS
the cause of any major defect at the commencement If a steel structure is to be welded to the piles, the
of welding. The frequency of testing may then be piles shall be cut square and to within 5 mm of the
progressively reduced on the basis of continuing level specified.
compliance with this Specification. In the event of a
non-compliant test result, a return to full testing of If the pile heads are to be encased in concrete, they
the next 5% of welds will be required. shall be cut to within 20 mm of the levels specified,
and protective coatings (where specified) removed
Non-compliant welds shall be repaired and re-tested from the surfaces of the pile heads down to a level
to the satisfaction of the weld inspector. 100 mm above the soffit of the concrete.
noted otherwise. All documents referenced below All operations such as handling, transporting and
shall be the latest revision, complete with current pitching of piles shall be carried out in such a
amendments, as at the commencement of the manner as to prevent damage to piles.
Contract Works:
• NZS3605 Timber Piles and Poles for use in 2.3.6 SPLICING OF TIMBER PILES
Buildings Piles shall be provided in one piece unless
• NZS3640 Chemical Preservation for Round and specified otherwise or agreed prior in writing by
Sawn Timber the Engineer.
3.1 SCOPE and meet all of the above requirements is the sole
This section covers the construction of piles with responsibility of the Contractor.
or without the use of permanent steel casings to
maintain bore stability. Piles will be excavated to the Surplus lengths of casings shall be cut off when
required depths necessary to achieve the specified construction of the superstructure begins.
loads, and then backfilled with reinforced concrete. Unless noted otherwise in the Project Specific
This section also covers the use of timber, steel or Requirements, all such lengths shall remain the
precast concrete piles placed in predrilled sockets. property of the Contractor and shall be removed
from the site on completion of the Works.
3.2 PROJECT SPECIFIC REQUIREMENTS
The following items, where appropriate, are detailed The casing walls shall not have holes or weld
in the Project Specific Requirements: discontinuities that would prevent or impede
• disposal of excavated material dewatering if required by the Engineer.
• requirement for support fluid
• pressure grouting A short length of temporary casing shall be provided
• trial piles for all piles to maintain an upstand of at least 0.9 m
• Schedule of inspection and testing requirements above the adjacent ground surface level to prevent
for dry and wet bores contamination of the pile bore and provide a safe
barrier prior to and during concreting.
3.3 REFERENCED DOCUMENTS
This Specification shall be read in conjunction 3.4.2 TEMPORARY STEEL CASINGS
with the following standards, guidelines, and other The Contractor shall assess the requirements and
documents, which are deemed to form part of this complete the detailed design of all temporary casings.
Specification. In the event of this Specification being
at variance with any provision of these referenced A short length of temporary casing shall be provided
documents, the requirements of this Specification for all piles to maintain an upstand of at least 0.9 m
shall take precedence. All materials and workmanship above the adjacent ground surface level to prevent
shall comply with these documents unless expressly contamination of the pile bore and provide a safe
noted otherwise. All documents referenced below barrier prior to and during concreting. Contamination
shall be the latest revision, complete with current from flood waters shall be considered if applicable
amendments, as at the commencement of the at the site. Alternative methods to prevent
Contract Works: contamination and provide a safe barrier may be
• NZS3404 Steel Structures Standard submitted to the Engineer for review.
• AS2159 Piling Design and Installation
The use of vibration to install and remove temporary
3.4 STEEL CASINGS casings shall be subject to the requirements of
Section 1.18.
3.4.1 PERMANENT STEEL CASINGS
All permanent steel casings shall be manufactured When the temporary casing is being extracted,
from steel that complies with the relevant a sufficient quantity of concrete shall be
requirements of the standards that are listed in maintained within it to ensure that the pressure
Section 2.2.2. from external water, support fluid or soil is exceeded
and that the pile concrete is not reduced in section
Casings shall be of the minimum thickness specified or contaminated.
on the drawings, or other such greater thickness
as is necessitated by the conditions met and the The casing walls shall not have holes or weld
Contractor’s method of working. The choice of discontinuities that would prevent or impede
the casing thickness to withstand driving stresses dewatering if required by the Engineer.
Unless approved prior in writing by the Engineer, permanent casing and surrounding ground shall
all temporary casings shall be removed as soon as be completely filled with compacted sand or other
practicable upon completing the construction of any approved material.
individual pile.
The use of explosives is forbidden without the prior
3.5 BELLING OR UNDER REAMING written approval of the Engineer.
Where specified on the drawings, each pile bore shall
be constructed with a mechanically enlarged base On completion of excavation, loose, disturbed or
which shall be no smaller than the size specified and softened soil shall be removed from the pile bore
shall be concentric with the pile shaft to within 10% using an appropriate method. The base cleanliness
of the shaft diameter. Where not specified on the shall be checked via visual assessment, video,
drawings the sloping surface of the bell shall make sounding (via a weighted tape) or similar Engineer
an angle to the axis of the pile of not more than approved methodology. If a sounding methodology
35°. At the specified diameter of the under-ream at is selected, the base cleanliness shall be checked at
the perimeter of the base, there shall be a minimum no less than three (3) locations across the pile base.
height of 150 mm. Examples of base testing weights are provided in
Appendix D.
3.6 PILE GROOVING AND ROCK
SOCKETS Pumping from pile bores shall not be permitted
If sidewall grooving is specified on the drawings unless groundwater inflow is limited to an inflow
but details are not provided, each pile bore shall be of water not exceeding 200 mm of bore depth per
spirally grooved with a 50 x 50 mm finger withdrawn hour and written approval of the Engineer obtained.
to achieve a pitch of 350 mm ±100 mm, over the Due care shall be taken to ensure that the pile bore
entire length of minimum embedment shown on (sidewall and base) remains stable at all times until
the drawings. If a temporary or permanent casing the completion of construction.
is used, the minimum length of embedment, as
specified on the drawings, shall be measured from The Contractor shall immediately notify the Engineer
below the bottom of the casing. should any hole collapse occur. The Contractor
shall then propose for the prior approval of the
A grooving trial shall be carried out on the first Engineer remedial works to repair or mitigate all
production pile. The Contractor shall allow for consequences of undesirable ground disturbance
inspection of the grooved pile by the Engineer. should base or side wall instability occur.
All rock sockets shall be of the minimum length and
diameter as shown on the drawings. 3.8 CONSTRUCTION OBSERVATIONS
The Engineer shall be given the opportunity to
As an alternative to grooving, particularly if rock observe the geotechnical conditions encountered,
with an unconfined compressive strength of greater confirm key design assumptions, and all aspects
than 5.0 MPa is encountered, a minimum rock socket of pile construction before concrete is poured
roughness as stipulated on the drawings shall be in accordance with the approved Inspection and
achieved within all rock socket zones. Testing Plan or otherwise agreed between the
Engineer and Contractor. The Contractor shall
The base of all rock sockets shall achieve the inform the Engineer at least one working day in
cleanliness requirements as stipulated in Section advance when such observations will be required.
3.7 below. This section shall be read in conjunction with
Section 3.7.
3.7 EXCAVATION FOR PILES
To avoid damage to recently cast piles, no pile shall Within dry pile bores the base cleanliness shall be
be excavated within a horizontal distance between confirmed by the Contractor via visual inspection
pile centrelines that is less than three (3) times and assessment and/or video techniques within
the pile diameter without the prior approval of deeper pile bores where, in the opinion of the
the Engineer. Engineer, a robust visual assessment cannot be
completed. If required, video inspections shall
Each pile shall be in intimate contact with the also be completed in accordance with the Project
ground over its full length so that it is able to Specific Requirements.
effectively transmit loads. Any space between the
All video assessments shall be completed remotely • permanent casing steel grade, cross reference to
using equipment that is lowered progressively down non-destructive examination (NDE), position of
the pile excavation. Such equipment shall be capable splices, welder’s information, time of weld
of taking clear, focussed, high quality video images • water levels inside the pile
which should be referenced with the pile number, • confirmation of cleaning of pile base, including the
depth, date of inspection and orientation. The recorded depth of the shaft at the end of drilling
images shall be retained by the Contractor as part of and immediately prior to placing concrete
the permanent pile as-builts records. Where visibility • weather conditions (including tide and wave height
permits, visual inspection of shaft cleanliness may be if applicable) at the time of concreting
undertaken from the surface using spotlights, mirrors • concreting records, including the total volume
or similar methods. For cleanliness assessments of concrete placed, the volume supplied with
of wet bores, where pumping is permitted under each truck, slump measurements and number
Section 3.7, the Contractor shall dewater the bore of cube or cylinder samples taken, time of
to allow visual inspection of the shaft and base. batching, and concrete placing start and
Alternative assessments such as a weighted tape completion times
may be used with the prior agreement of the • the time and date of casing extraction
Engineer, if dewatering would cause bore instability, (if applicable)
or if groundwater inflow exceeds the capacity of the • the design and actual constructed elevation of the
dewatering equipment. top of the pile
• cross reference proving investigation bores
Video footage shall only be instructed within a wet (if appropriate)
bore by the Engineer if such footage will provide • pile load test records (if applicable)
clear imagery of the shaft without additional • the Contractors signature verifying that all work
treatment such as the addition of flocculant agents. has been completed satisfactorily
For wet bores, cleanliness assessments shall • weighted tape tests (if applicable)
comprise as a minimum, a base cleanliness check
using a weighted tape or similar instrument per A copy of the proposed Pile Construction Record
Section 3.7. Card shall be submitted by the Contractor for review
and approval by the Engineer no less than one week
The Contractor shall provide all necessary facilities, prior to the commencement of pile construction.
equipment and personnel to enable the Engineer to
safely observe any pile and fulfil the inspection and All pile construction record cards shall be
testing schedule as required in Section 3.2 above. progressively submitted by the Contractor to the
The Contractor shall ensure that the appropriate Engineer as the construction is advanced and
requirements of the publication “Good Practice within two (2) working days of the completion
Guidelines for Excavation (WorkSafe, 2016) are of concrete placement of each pile. An example
strictly followed at all times during construction and bored pile construction record card is provided
that all observations are completed using the safest in Appendix B. It is noted that all items shown
practicable method. on this example may not be relevant to all projects.
4.1 SCOPE AND INTERPRETATION The use of a pile driving analyser (PDA) may also
This section covers the installation of driven piles, be used to check driving resistance, subject to the
including steel H piles, steel pipe piles (both bottom requirements of Section 5.3.
and top driven), precast concrete piles, timber piles
and sheet piles. The driving sets and rebound shall be measured and
recorded for each pile at the completion of driving.
Use of modified or alternative driven pile techniques, When a set or resistance is being measured, the
such as those that employ modified Hiley formulas to following requirements shall be met:
account for underwater driving conditions or driven • the pile shall be in good condition, without damage
precast plugs, shall be agreed by the Engineer. or distortion
• the hammer blow shall be in line with the axis of
4.2 PROJECT SPECIFIC REQUIREMENTS the pile, and the impact surfaces shall be flat and
The following items, where appropriate, are detailed perpendicular to the hammer axis
in the Project Specific Requirements: • the hammer shall be in good condition, delivering
• trial piles the required energy per blow as specified in
• pile acceptance criteria, i.e. minimum depth, Section 4.7 and operating correctly
embedment into founding strata, set and resistance • the rebound shall be measured and recorded
• pile testing requirements, i.e. number or frequency
and type of testing The set shall be recorded as the penetration in
millimetres per blow averaged over ten blows
4.3 REFERENCED DOCUMENTS dropped from a constant drop height.
This Specification shall be read in conjunction
with the following standards, guidelines, and other For piles that exhibit hydraulicing, characterised
documents, which are deemed to form part of this by no/low set with high rebound, driving shall be
Specification. In the event of this Specification being temporarily suspended to allow pore pressures to
at variance with any provision of these referenced dissipate and then attempt to drive again, repeating
documents, the requirements of this Specification as necessary until hydraulicing is no longer observed
shall take precedence. All materials and workmanship or the set at re-drive is achieved to the satisfaction
shall comply with these documents unless expressly of the Engineer. The set shall be measured over the
noted otherwise. All documents referenced below first ten blows.
shall be the latest revision, complete with current
amendments, as at the commencement of the 4.6 PILE DRIVING
Contract Works: The Contractor shall carry the sole responsibility
• AS2159 Piling Design and Installation for providing all necessary equipment for the
pitching, positioning and driving of piles. The driving
4.4 PILE LOADS procedure shall avoid damage to the piles.
All piles shall be driven to depths such that they are
capable of achieving the ultimate driving resistances The Contractor shall provide the Engineer with
specified on the drawings. information on the efficiency and energy of the
driving equipment, including when mandrels or
4.5 SET AND RESISTANCE followers are used. Where a drop hammer is used,
The ultimate driving resistance of each pile shall be no drop shall exceed 2500 mm for a bottom driven
checked in accordance with one of the methods pile or 2000 mm for a top driven pile unless agreed
set out in Appendix C. Other methods of assessing prior by the Engineer or measured driving stresses
ultimate driving resistance may be used where indicate a greater drop height will not exceed the
approved in advance by the Engineer. maximum permissible driving stresses as specified
in Table 4.6-1. The Contractor shall include in its
method statement details of the proposed pile
Driving plug material should be recharged when the • the level of the top of the reinforcement cage
plug becomes powdered resulting in a soft response before and after pouring (if applicable)
indicating a loss of driving efficiency, or at 40 minute • concreting records, including the total volume of
intervals during continuous driving, whichever is concrete placed, the volume supplied with each
lesser. The recharge plug length shall be between truck, slump measurements and number of cube
300 mm and 500 mm long. A recharge plug shall or cylinder samples taken, time of batching, and
have at least 20 blows and no more than 75 blows concrete placing start and completion times
applied to it prior to measuring the set. Recharge of (if applicable)
the driving plug does not require cement to be added. • depth to top of concrete for each truck placed and
depth of tremie tube (if appropriate)
TABLE 4.12-1: Aggregate properties for driving plug
Sieve Size Percent Passing 4.14 ADDITIONAL REQUIREMENTS FOR
DRIVEN TIMBER PILES
Gradation 19 mm 100
13.2 mm 0-5 4.14.1 SUPPLIED PILE COMPONENTS
Crushing In all situations where pile components are supplied
230 kN per NZS4407 Test 3.10
Resistance by the Client or Principal, the Contractor shall
Solid Density At least 2.60 per NZS4407 Test 3.7.1 review the structural capacity of such components
and confirm that they can be installed without
The use of alternative driving plugs shall be agreed over-stressing.
with the Engineer prior to commencement of
pile driving. The Contractor shall notify the Engineer if any
supplied pile component is identified as being at risk
4.12.2 PILE CONSTRUCTION RECORD CARD of being over-stressed during installation.
In addition to the requirements that are specified
in Section 4.10, the following as-built information 4.14.2 PILE HEADS
shall be verified on site and recorded on the Pile If excessive damage to the pile head is observed
Construction Record Card: or anticipated, or as shown on the drawings, the
• the amount of material used to form the driving head of the pile shall be trimmed to a circular cross
plug, the time(s) and date(s) that any recharge section and fitted with a tight steel ring. This ring
material is added to the pile, and the length of shall be not less than a 50x12 mm mild steel flat, and
the plug the join shall be butt welded over the full section.
• reinforcement checklist The top of the ring shall be positioned between
• the level of the top of the reinforcement cage 10 mm and 20 mm below the top of the pile. If the
before and after pouring ring is displaced during driving, it shall be refitted. If
• concreting records, including the total volume of the ring is broken, a new ring shall be fitted.
concrete placed, the volume supplied with each
truck, slump measurements and number of cube As an alternative to a ring, a metal helmet may be
or cylinder samples taken, time of batching, and used. The top of the pile must be trimmed to fit
concrete placing start and completion times closely into the recess in the underside of the helmet.
• depth to top of concrete for each truck placed and
depth of tremie tube (if appropriate) 4.14.3 DRIVING SHOES
• The number of blows for each driving plug Where used, pile shoes shall be attached to the pile
(or part) by steel straps fixed, spiked or bolted to the timber.
The shoes shall be coaxial with the pile and firmly
4.13 ADDITIONAL REQUIREMENTS FOR bedded into it.
OPEN ENDED STEEL PIPE PILES
(TOP DRIVEN) 4.15 ADDITIONAL REQUIREMENTS FOR
STEEL SHEET PILES
4.13.1 PILE CONSTRUCTION RECORD CARD
In addition to the requirements that are specified 4.15.1 SUPPLIED PILE COMPONENTS
in Section 4.10, the following as-built information In all situations where pile components are supplied
shall be verified on site and recorded on the Pile by the Client or Principal, the Contractor shall
Construction Record Card: review the structural capacity of such components
• reinforcement and other pre-pour checks and confirm that they can be installed without
(if applicable) over-stressing.
4.15.2 STORAGE
If sheet piles of different grades are stored on site,
each pile shall be clearly marked showing its grade,
with piles of different grades stored separately.
5.1 INTEGRITY TESTING The Engineer may order additional integrity testing
of any pile when the Engineer has reasonable cause
5.1.1 PROJECT SPECIFIC REQUIREMENTS to doubt the integrity of the pile.
The following items, where appropriate, are detailed
in the Project Specific Requirements: 5.1.4 INDEPENDENT OBSERVER
• the number, type and location of the piles to All integrity testing shall be carried out by a suitably
be tested qualified and experienced independent specialist in
• the stages in the programme when integrity testing strict accordance with the methodologies outlined
will be required in ASTM D5882 (sonic echo) and/or ASTM D6760
(crosshole sonic logging). The Contractor shall submit
5.1.2 REFERENCED DOCUMENTS for approval by the Engineer the name of such
This Specification shall be read in conjunction specialist, their professional qualifications, relevant
with the following standards, guidelines, and other experience, a description of the test equipment and
documents, which are deemed to form part of this any associated calibration certificates, a test method
Specification. In the event of this Specification being statement and a programme for executing the work,
at variance with any provision of these referenced prior to integrity testing commencing on site. Upon
documents, the requirements of this Specification request, a copy of the unprocessed test data shall be
shall take precedence. All materials and workmanship provided to the Engineer within 48 hours.
shall comply with these documents unless expressly
noted otherwise. All documents referenced below 5.1.5 INTERPRETATION OF RESULTS
shall be the latest revision, complete with current AND REPORTING
amendments, as at the commencement of the The interpretation of test results shall be carried out
Contract Works: by suitably experienced and competent persons.
• ASTM D5882 Low Strain Impact Integrity Testing of Preliminary results of each test shall be submitted
Deep Foundations to the Engineer within two (2) working days of
• ASTM D6760 Integrity Testing of Concrete Deep completion of the test. The final test results and
Foundations by Ultrasonic Crosshole Testing findings shall be submitted to the Engineer within
ten (10) working days of completion of the test.
5.1.3 METHOD
Where integrity testing is required by the Project The report shall contain a summary of the method
Specific Requirements, the method to be adopted used in conducting the test, a summary of the
shall be either: method of interpretation, including all assumptions,
• full depth coring of the pile, or calibrations, and corrections used in the analysis.
• sonic echo/impulse method, or The units and scales shall be clearly marked on all
• crosshole sonic logging method diagrams. Current calibration certificates shall be
provided for all impulse equipment.
If crosshole sonic logging is adopted and unless
agreed otherwise by the Engineer, black steel access 5.1.6 ANOMALOUS RESULTS
tubes shall be used. In the event that an anomalous test result is returned
in a pile, the Contractor shall review the construction
Other methods, such as thermal integrity records and demonstrate to the Engineer that the
profiling, may be proposed by the Contractor for pile complies with the drawings and Project Specific
consideration by the Engineer. Any subsequent Requirements. If appropriate, the Contractor shall
approval by the Engineer is subject to the provision propose additional investigation or remedial works
of satisfactory evidence of performance by the to demonstrate compliance with the drawings and
Contractor. Project Specific Requirements. The Contractor shall
not carry out any remedial work on any pile, without
the prior written approval of the Engineer.
CIA. (2012). Recommended Practice Tremie Concrete TWfNZ. (2018). Working Platforms. Temporary Works
for Deep Foundations. Sydney: Concrete Institute forum (NZ). Retrieved from https://www.sesoc.org.
of Australia. nz/membership/special-committees/temporary-
EFFC/DFI. (2018). Guide to Tremie Concrete for Deep works-forum-nz/
Foundations,. Deep Foundation Institute, European TWfNZ. (2019). Temporary Works Procedural Control.
Federation of Foundation Constractors. Retrieved Temporary Works forum (NZ). Retrieved from
from http://www.dfi.org/publications.asp https://www.sesoc.org.nz/membership/special-
MBIE. (2012). Approved Code of Practice for Load- committees/temporary-works-forum-nz/
lifting Rigging. Wellington: Ministry of Business, WorkSafe. (2009). Approved Code of Practice
Innovation and Employment. Retrieved from for Cranes. Wellington: Department of Labour.
Approved Code of Practice for Load-lifting Retrieved from Approved Code of Practice for
Rigging: https://worksafe.govt.nz/topic-and- Cranes: https://worksafe.govt.nz/topic-and-
industry/load-lifting-and-rigging/ industry/cranes/
MBIE. (2019). Best practice guidelines for working WorkSafe. (2016). Good Practice Guidelines
at height in New Zealand. Ministry of Business, for Excavation Safety. Wellington: Worksafe
Innovation & Employment. Retrieved from New Zealand. Retrieved from Good Practice
https://worksafe.govt.nz/topic-and-industry/ Guidelines for Excavation Safety: https://worksafe.
working-at-height/working-at-height-in-nz/ govt.nz/topic-and-industry/excavation/excavation-
safety-gpg/
A2 E
XAMPLE PROJECT SPECIFIC REQUIREMENTS
DOCUMENT: CAST IN PLACE BORED PILE
The oldest rocks in the area are greywacke and argillite A2.2.2 R
EQUIREMENTS FOR ALKALI-
of the Waipapa Group. These rocks outcrop north, AGGREGATE REACTION
south and southwest of the harbour and constitute the All concrete for use in piles shall meet the
basement to younger coastal and estuarine sediments requirements of NZS3109. The Contractor shall
at the site. Basement rocks are discontinuous and are supply the Engineer with the concrete mix design
not encountered in the Marsden Point area. five working days prior to placing concrete on site.
A2.2.3 W
ELD CATEGORY FOR WELDS IN
ACCORDANCE WITH NZS3404
All welds shall be category SP.
A3 E
XAMPLE PROJECT SPECIFIC REQUIREMENTS
DOCUMENT: DRIVEN STEEL H PILE
A3.1.3 SITE DATUM AND GRID REFERENCES A3.1.6 REQUIREMENTS FOR TOLERANCES
All levels shown on the drawings and referred to in Piles shall be constructed in accordance with the
the specifications are in terms of chart datum. Grid following tolerances:
references are specified in terms of the Mount Eden • tops of piles shall not vary more than 75 mm
co-ordinate system. horizontally and 25 mm vertically from their true
position as specified on the drawings
A3.1.4 NATURE OF THE GROUND AND • the maximum permitted deviation of piles
SUBSURFACE CONDITIONS from the vertical at any level shall be not more
A factual geotechnical report has been prepared for than 1:75
this project and may be inspected at the offices of
Sardine & Glass Limited at 131 Victory Street, Auckland. A3.1.7 REQUIREMENTS FOR QUALITY
MANAGEMENT
The site is located in Marsden Bay on the Refer to the Preliminary and General section for
southwestern side of the entrance to Whangarei requirements for Quality Management.
harbour. The seabed level at the existing wharf is
approximately 8 to 9 metres below chart datum. A3.1.8 REQUIREMENTS FOR PRODUCER
Much of the seabed in the dredge area is mantled STATEMENTS
with algae covered shell. Zones of active sediment Producer Statements are not required.
transport occur along the north-eastern margin and
southwestern corner of the dredge area. Blacksmiths A3.2 MATERIALS
Creek extends inland generally southwest from the
western end of the development. A3.2.1 CORROSION PROTECTION FOR
STEEL PILES
The oldest rocks in the area are greywacke and Corrosion protection is not required for the steel
argillite of the Waipapa Group. These rocks outcrop H piles.
north, south and southwest of the harbour and
constitute the basement to younger coastal and A3.2.2 W
ELD CATEGORY FOR WELDS IN
estuarine sediments at the site. Basement rocks ACCORDANCE WITH NNZ3404
are discontinuous and are not encountered in the All welds shall be category SP.
Marsden Point area.
The Hiley dynamic pile-driving formula estimates the C = sum of temporary compressions of
ultimate axial compressive pile capacity for a driven pile dolly, packings and ground
pile. It is considered a less accurate assessment of (mm)
the driven pile capacity than that determined using
wave equation analysis software (e.g. GRLWeap). n= efficiency of blow (dimensionless)
The estimate is referred to as the ultimate driving
resistance to driven piles and is expressed as: h= free-fall height of hammer (mm)
C2 TEMPORARY COMPRESSION
C2.1 Total temporary compression C is derived C2.3 If field measurements are not possible
from: C shall be determined by:
(1) Calculating the compressive stress in the pile
C = Cc + Cp + Cq (timber, concrete or steel). This is calculated from
where: the required ultimate driving resistance ÷ average
cross-sectional area of the pile. This is not the
Cc = e
lastic compression of pile head compressive driving stress within the pile,
or dolly which would need to be calculated using wave
equation software, then
Cp = elastic compression of the pile itself (2) Use figures C1 and C4 to calculate the theoretical
elastic compression.
Cq = quake of the ground beneath the pile
C2.4 In calculating Cp, the length L of the pile
C2.2 Wherever possible Cp and Cq should be shall be the distance from pile top to the centre of
determined by field measurements (see Paragraph driving resistance. The assumed centre of driving
C6), especially in soft or peaty soils, or where soft resistance shall be taken as:
ground exists below the pile toe, or in circumstances • Half the pile penetration depth in soil which is
where resistance is reduced on re-driving. Field homogeneous and provides resistance by skin
measurement is important to allow confirmation or friction only, or
revision of preliminary estimates of R. The theoretical • The toe of the pile where resistance is by end
elastic compression of the pile head or dolly (Cc) bearing only, or
should be added to the field measured Cp and Cq. • Interpolation between the two cases above,
if appropriate.
NOTES:
If a short dolly in the helmet or driving cap is used in combination with 75 mm packing, the two
compressions should be added together to obtain Cc.
E is modulus of elasticity. The value of E given for concrete is only valid when it is manufactured
from ordinary Portland cement. It will be greater for rapid-hardening or aluminous cement concrete.
The reader should refer to the worked examples which are provided below for more detail regarding
these calculations. When reviewing the following examples particular note must be taken of the pile
material type (i.e. Pinus Radiata Timber or Steel) and that Figure C4 only applies to Pinus Radiatia
Grade F11.
Figure C1
Figure C2
Figure C3
Figure C4
C3 BLOW EFFICIENCY
C3.1 The efficiency of the hammer blow is to be C3.2 The coefficient of restitution ‘e’, as
determined from the following formulae, according determined experimentally for different materials
to the relationship between pile, hammer weight W and conditions:
and ground conditions.
For piles driven with single-acting or drop hammer is
approximately:
C4 BEARING CAPACITY
C4.1.1 The Hiley formula, being an empirical design C4.2.1 Where piles are driven with single-acting
tool, has its accuracy improved when adjusted with drop hammers in leader guides inclined on an angle,
site-specific data. The ultimate axial compressive pile the ultimate driving resistance calculated from the
capacity should be obtained whenever possible from Hiley formula should be reduced. Table C1 provides
test loadings. If a sufficient proportion of piles are recommended percentages by which calculated
tested, the data obtained may be used for refining values for vertical piles, should be reduced to suit
variables in the formula, which can then be readily different rake angles.
applied to the control of the remaining piles.
TABLE C1: Reduction of calculated value of R for raked
C4.1.2 If load tests are not used, the ultimate piles (see note 1) (Paragraph C4.3.1)
1 in 10 1.5
C4.2 STRENGTH REDUCTION FACTOR
1 in 8 2.0
C4.2.1 The ultimate axial compressive pile capacity,
1 in 6 3.0
determined either by test loadings or as the
ultimate driving resistance derived from the Hiley 1 in 5 4.0
formula, shall be multiplied by a strength reduction
factor appropriate to the circumstances prevailing, 1 in 4 5.5
particularly the reliability of the available data and 1 in 3 8.5
the consequences of failure of the structure being
considered. Guidance is provided in AS2159 (ULS 1 in 2 14.0
loads) and B1 VM/4 (seismic overstrength loads). NOTE:
Strength reduction factors may be increased for 1. R
is the ultimate driving resistance from the formula in
temporary loads. Paragraph C1.
EXAMPLE 1 EXAMPLE 2
6 m long 300 mm SED pole driven to an ultimate 15 m long 200 mm UC60 driven to an ultimate
driving resistance of 400 kN driving resistance of 700 kN
Driven with a 500 kg hammer dropping 1.5 m no Driven with a 2 tonne hammer dropping 1 m.
cushioning and assumed as a friction pile.
Assumed end bearing on rock and 75 mm helmet
Average pole cross-sectional area = 0.089 m2 packing
Driving stress = 4.5 MPa
Cc = 1.5 mm (Fig C1) Cross-sectional area = 75.8 cm2
Cp = 0.45 × 3 = 1.35 mm (Fig C3) Driving stress = 92 MPa
Cq = 2 mm (Fig C4) Cc = 6 mm (Fig C2)
Cc + Cp + Cq = 4.9 mm Cp = 0.45 (Fig C3) × 15 (metres long) = 6.8 mm
Cq = 2 mm
Pile weight (P) = 6m × 0.089 m2 × 9 kN/m3 = 4.8 kN Cc + Cp + Cq = 14.8 mm
C6 FIELD MEASUREMENTS
C6.1 The recording of set (S), and temporary C6.2 The resulting graphical record will be as
compressions of pile (Cp) and of the ground (Cq) on shown in Figure C5.
site, can be done by:
a) Erecting a horizontal straight-edge close to the FIGURE C5: Field measurement of temporary compression
face of the pile. and set.
PAGE 46
APPENDIX D