Professional Documents
Culture Documents
i
1
Plagiarism Form
THE UNIVERSITY OF THE WEST INDIES
When submitting a group assignment for assessment each member of the group will be required to sign the
following declaration of ownership which will appear on the coursework submission sheet.
1. We have read the Plagiarism Regulations as set out in the Faculty or Open Campus Student
Handbook and on university websites related to the submission of coursework for assessment.
2. We understand that plagiarism is a serious academic offence for which the University may
impose severe penalties.
3. The submitted work indicated above is our own work, except where duly acknowledged and
referenced.
4. This work has not been previously submitted for credit either in its entirety or in part within the
UWI or elsewhere. Where work was previously submitted, permission has been granted by my
Supervisor/Lecturer/Instructor as reflected by the attached Accountability Statement.
5. We understand that we may be required to submit the work in electronic form and accept that the
University may check the originality of the work using a computer-based similarity detection
service.
2
NAME: Damian Frank
19/01/22
DATE____________________________________________________
3
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ N/A
SUPERVISOR’S REMARKS:
⮚ Produce a draft Gantt Chart with tasks/ activities from start of project to its completion.
⮚ Get basic wind parameters and topographical map from Dr. Cooper, that shows contours etc. of
the site before any construction.
⮚ Get soil investigation/geotechnical report of the site from Dr. Cooper.
GROUP’S SIGNATURES:
4
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Acquired topographic map, rivers, soils and Trinshed map.
Challenges:
➢ Problems opening files with a suitable software.
➢ Delay in acquiring wind data.
Solutions:
➢ Software issues were resolved by informing Dr. Cooper about the challenges, and a session
was conducted showing which software to use and how to open files.
➢ Dr. Cooper was contacted in regards to obtaining data, and said he will provide the relevant
information when it has been provided to him.
SUPERVISOR’S REMARKS:
➢ Complete the Gantt chart by inputting the relevant commencement and completion dates.
➢ Get seismic information for the site, from Seismic Research Centre.
5
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Revised Gantt chart by inputting dates for tasks.
⮚ Got link to seismic website, and a rough estimate was given of the wind parameters.
Challenges:
➢ Problems operating and adding data in the QGIS Software.
Solutions:
➢ Watching videos and lecture recording to learn how to operate the QGIS.
SUPERVISOR’S REMARKS:
➢ Revise the Gantt chart by inputting additional tasks discussed, and proper ordering of works.
➢ Get an actual estimate of the seismic information (SS and S1 values) for the site.
6
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Gantt chart revised and completed.
⮚ Got information on the seismic parameters.
Challenges:
Solutions:
SUPERVISOR’S REMARKS:
➢ Proceed with the tasks outlined in Gantt Chart.
➢ Start to visualize and document how you will size the buildings (using the building codes and
architectural books recommended etc.).
7
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Started conceptual design of buildings. Created some sketches for the residential buildings.
Challenges:
Solutions:
SUPERVISOR’S REMARKS:
➢ Size all buildings, including those besides residential.
➢ Start to set out the site layout.
➢ Can use the library resources for how to proceed with setting out the site.
8
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚
Challenges:
➢ Difficulty in attaining setback values for reference, for site layout.
Solutions:
SUPERVISOR’S REMARKS:
➢ Undertake corrective action to get back on track with the Gantt Chart. Complete the two site
layouts by Monday, November 1st, 2021, and be prepared to perform the Preliminary designs.
➢ Send an email to Dr. Clarke with the hand sketches of the two alternatives by Monday,
November 1st 2021, including the necessary details (i.e. location of the outfall drains, drains
and their runs (using arrows), building locations, and roads etc.)
9
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Completed the two alternative site layouts.
Challenges:
Solutions:
SUPERVISOR’S REMARKS:
➢ Proceed as according to Gantt Chart.
➢ Prepare the preliminary designs and start to do the costing.
10
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Started the preliminary designs for each individual section.
Challenges:
Solutions:
SUPERVISOR’S REMARKS:
➢ Continue with the preliminary designs.
11
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Continued the preliminary designs for each individual section.
Challenges:
Solutions:
SUPERVISOR’S REMARKS:
➢ Continue to finalise the preliminary designs, so a materials list can be compiled, to provide a cost
estimate of the entire budget. Start to focus on decision matrix.
12
THE UNIVERSITY OF THE WEST INDIES
Group #: 1
PROGRESS:
⮚ Continued the preliminary designs for each individual section.
Challenges:
Solutions:
SUPERVISOR’S REMARKS:
➢ Procedure for drainage design explained
➢ Continue to finalise the preliminary designs
13
Note all meeting logs were signed with the following signatures above.
14
Table of Contents
1.Introduction .................................................................................................................................... 24
1.1. Project Scope ............................................................................................................................. 24
1.2. Project References..................................................................................................................... 24
1.3. Points of Contact ....................................................................................................................... 25
1.4. Aim ............................................................................................................................................. 25
1.5. Objectives................................................................................................................................... 26
2. Project Overview ................................................................................................................27
2.1. Limitations ................................................................................................................................. 27
2.2. Assumptions............................................................................................................................... 27
3. Feasibility Analysis .............................................................................................................28
3.1 Preliminary Study ..................................................................................................................... 28
3.1.1 Site Location .............................................................................................................................. 28
3.1.2 Soils............................................................................................................................................. 29
3.1.3 Hydrology .................................................................................................................................. 31
3.1.4 Topography ............................................................................................................................... 33
3.1.5 Climate ....................................................................................................................................... 37
3.1.6 Natural Hazards ........................................................................................................................ 40
3.2 Environmental Impact Assessment ......................................................................................... 49
3.2.1 Introduction ............................................................................................................................... 49
3.2.2 Project Description ................................................................................................................... 49
3.2.3 Major Project Activities: .......................................................................................................... 50
3.2.4 Environmental Impact Assessment (EIA) .............................................................................. 53
3.3 Engineering Alternatives:......................................................................................................... 61
3.3.1 Structural Designs ..................................................................................................................... 61
3.3.2 Pavement Design ..................................................................................................................... 216
3.3.3 Storm Water Management ..................................................................................................... 280
3.3.4 Water Supply System .............................................................................................328
3.3.5 Wastewater Management .......................................................................................345
4. Sustainability.....................................................................................................................357
5. Health & Safety ..................................................................................................................360
6. Selected Alternative ..........................................................................................................364
7. Conclusion ........................................................................................................................365
15
8. References.........................................................................................................................366
9. Appendix ...........................................................................................................................371
16
List of Figures
17
Figure 27: Sketch of the Double Bedroom Apartment Complex Ground, 1st, 2nd&,3rd Floor
Plan for Reinforced Concrete Moment Resisting Frame .............................................................. 94
Figure 28: Sketch of the Single Bedroom Apartment Complex Ground, 1st & 2nd Floor Plan
for Reinforced Concrete Moment Resisting Frame ..................................................................... 109
Figure 29: Sketch of the Two (2) Bedroom Triplex Floor Plan for Reinforced Concrete
Moment Resisting Frame ............................................................................................................... 124
Figure 30: Sketch of the Three (3) Bedroom Duplex Floor Plan for Reinforced Concrete
Moment Resisting Frame ............................................................................................................... 138
Figure 31: Sketch of the Community Centre Floor Plan for Steel Moment Resisting Frame . 152
Figure 32: Sketch of the Policlinic Floor Plan for Steel Moment Resisting Frame................... 162
Figure 33: Sketch of the Double Bedroom Apartment Complex Ground, 1st, 2nd&,3rd Floor
Plan for Steel Moment Resisting Frame ....................................................................................... 172
Figure 34: Sketch of the Single Bedroom Apartment Complex Ground, 1st & 2nd Floor Plan
for Steel Moment Resisting Frame ................................................................................................ 184
Figure 35: Sketch of the Two (2) Bedroom Triplex Floor Plan for Steel Moment Resisting
Frame ............................................................................................................................................... 196
Figure 36. Flexible versus Rigid Pavement Structural Layout ................................................... 217
Figure 37. Flexible versus Rigid Pavement Load Distribution ................................................... 217
Figure 38. Collector road cross section ......................................................................................... 218
Figure 39. Access road cross section.............................................................................................. 218
Figure 40. Proposed Access Road cross section............................................................................ 219
Figure 41. Proposed Collector Road cross section ....................................................................... 220
Figure 42. Car Parking Layout...................................................................................................... 256
Figure 43. Concrete Car Parking Driveway ................................................................................ 257
Figure 44. showing Tarmac Car Parking Driveway and damage caused due to oil spill on
surface .............................................................................................................................................. 258
Figure 45. showing Grass Block Pavers for a driveway. ............................................................. 260
Figure 46. showing Gravel paving for a residential driveway. ................................................... 260
Figure 47. showing Asphalt paving for a residential driveway and commercial car parking lot.
.......................................................................................................................................................... 261
Figure 48. showing Resin bound driveway on the left, and on the right, a variety of textures
and colours for this type of paving material. ................................................................................ 262
Figure 49. showing Block paving for a residential driveway. ..................................................... 262
Figure 50. showing Grass Block paving layout. ........................................................................... 272
Figure 51. showing the layout of Gravel and Grass Block Pavers. ............................................. 272
Figure 52. showing the various layouts of Clay Brick Pavers. .................................................... 274
18
Figure 53 shows the comparison between stormwater runoff on natural vs impervious
environments ................................................................................................................................... 281
Figure 54 shows the comparison between stormwater runoff on natural vs impervious
environments ................................................................................................................................... 282
Figure 55 shows the comparison between stormwater runoff on natural vs impervious
environments ................................................................................................................................... 282
Figure 56: Image of corrugated HDPE pipe ................................................................................. 283
Figure 57: Image showing section of typical storm sewer manhole/catch basin with slump ... 284
Figure 58: Image showing HDPE manhole................................................................................... 284
Figure 59: Image showing rain garden ......................................................................................... 285
Figure 60: Image showing box drain ............................................................................................. 286
Figure 61: Image showing curb and gutters ................................................................................. 287
Figure 62: Image showing Tree well ............................................................................................. 288
Figure 63: Image showing infiltration trench ............................................................................... 289
Figure 64: Image showing Tree well ............................................................................................. 290
Figure 65: Image showing section of detention basin .................................................................. 291
Figure 66: Image showing detention basin being used as a green area when empty. ............... 291
Figure 67 showing entire catchment of proposed site with the left sub catchment in blue and
the right sub catchment in green ................................................................................................... 292
Figure 68 showing the section upstream of the right tributary. ................................................. 295
Figure 69 showing the section upstream of the left tributary. .................................................... 295
Figure 70 showing pipe sizes and flow velocity layout 1 .............................................................. 308
Figure 71 showing the effect the detention basin has on the post-development peak discharge.
.......................................................................................................................................................... 309
Figure 72. Sketch showing plan view of the detention basin on site for layout 1 ...................... 312
Figure 73. Sketch showing sectional view of the detention basin on site for layout 1 ............... 313
Figure 74 showing the effect the detention basin has on the post-development peak discharge.
.......................................................................................................................................................... 319
Figure 75 showing total costs of storm sewer system ................................................................... 321
Figure 76 shows costing of detention basin layout 1 .................................................................... 322
Figure 77 shows costing of Box Drain System layout 2 ............................................................... 323
Figure 78 shows costing of detention basin layout 2 .................................................................... 323
Figure 79. Image of a Grid/Looped Distribution System ............................................................ 330
Figure 80. Image of a Branched/Tree Distribution System......................................................... 331
Figure 81. Extended Aeration Treatment Process ....................................................................... 349
19
List of Tables
Table 1. Shows the Properties of the Soil Found on the Proposed Site ........................................ 30
Table 2. Showing Borehole Data (Geotechnical Assessment for the Slope Stability Analyses at
the Bon Air North Site,2015)............................................................................................................ 30
Table 3. Showing Borehole Groundwater Depth (Geotechnical Assessment for the Slope
Stability Analyses at the Bon Air North Site,2015) ........................................................................ 32
Table 4. Potential Environmental Impacts on environmental resources on proposed site. ....... 50
Table 5. Scale of how severe impacts can be on the environmental resources on the proposed
site. ...................................................................................................................................................... 51
Table 6. Impact Rating of Occurrences ......................................................................................... 51
Table 7. Probability Rating of an occurrence taking place ........................................................... 52
Table 8. Environmental Impact Assessment: Pre-Construction, During Construction, Post
Construction ...................................................................................................................................... 60
Table.9 Showing multi-criteria ranking and description .............................................................. 62
Table.10 Showing ranking of alternatives ...................................................................................... 62
Table.11 Showing weighting factors ................................................................................................ 63
Table.12 Showing scores of alternatives ......................................................................................... 63
Table 13. Calculated AADT for Layout #1. .................................................................................. 221
Table 13. Calculated AADT for Layout #2. .................................................................................. 221
Table 14. Calculated ESAL values for each vehicle type. ........................................................... 223
Table 15. Summary Table showing total cost of Asphalt Pavement for Proposed Collector
Road. ................................................................................................................................................ 242
Table 16. Summary Table showing total cost of Asphalt Pavement for Proposed Access Road.
.......................................................................................................................................................... 244
Table 17. Summary Table showing total cost of PCC Pavement for Proposed Collector Road.
.......................................................................................................................................................... 246
Table 18. Summary Table showing total cost of PCC Pavement for Proposed Access Road. . 248
Table 19. Summary Table showing Total Road cost of Asphalt Road works for Alternative # 1.
.......................................................................................................................................................... 249
Table 20. Summary Table showing Capital cost of PPC roadworks for Alternative # 1. ........ 250
Table 21. Summary Table showing Capital cost of roadworks for Alternative # 2. ................. 250
Table 22. Summary Table showing Capital cost of roadworks for Alternative # 2. ................. 251
Table 23. Rating System for Multicriteria Analysis. ................................................................... 252
20
Table 24. Table showing Measure of Effectiveness of the Proposed Alternatives. ................... 253
Table 25. Table showing Calculated Weighting Factor for each Criteria. ................................ 254
Table 26. Table showing the Weighted Score for each Alternative. ........................................... 254
Table 27. Summary Table showing Estimated Road User Cost. ................................................ 255
Table 28. Potential Environmental Impacts on environmental resources of proposed Paving
Material............................................................................................................................................ 259
Table 29. Calculated ESAL value for Car Parking lots. ............................................................. 264
Table 30. Summary Table showing total cost of Asphalt Pavement for Proposed Car Parks. 271
Table 31. Summary Table showing cost of various alternatives for the Proposed Car Parks. 276
Multicriteria Analysis of Paved Driveways: ................................................................................. 276
Table 32. Rating System for Multicriteria Analysis. ................................................................... 277
Table 33. Table showing Measure of Effectiveness for the Proposed Paved Driveways. ......... 277
Table 34. Table showing total score of each Alternative for the Proposed Car Parks. ............ 278
Table 35. Summary Table showing Total cost of Car Parks for Alternative # 1. ..................... 279
Table 36. showing land cover characteristics corresponding runoff coefficients and percentage
of area covered by land cover. ....................................................................................................... 303
Table 37 showing land cover characteristics corresponding runoff coefficients and percentage
of area covered by land cover. ....................................................................................................... 314
Table 38 showing ranking and description ................................................................................... 325
Table 39 showing ranking of alternatives ..................................................................................... 326
Table 40 showing weighting factors .............................................................................................. 326
Table 41 showing scoring of alternatives ...................................................................................... 327
Table 42. Residential/Domestic Water Consumption .................................................................. 333
Table 43. Commercial and Institutional Water Consumption ................................................... 334
Table 44. Ranking Key ................................................................................................................... 342
Table 45. Measure of Effectiveness for the Proposed Alternatives ............................................ 343
Table 46. Calculated Weighting Factor for each Criteria ........................................................... 343
Table 47. Weighted Score for each Alternative ............................................................................ 344
Table 48. Residential/Domestic Wastewater Flows...................................................................... 347
Table 49. Commercial and Institutional Wastewater Flows ....................................................... 348
Table 50. Ranking Key ................................................................................................................... 354
Table 51. Measure of Effectiveness for the Proposed Alternatives ............................................ 355
Table 52. Calculated Weighting Factor for each Criteria ........................................................... 355
Table 53 showing scores of alternatives ........................................................................................ 356
21
Table 54 showing infrastructural cost break down ..................................................................... 365
22
Executive Summary
The purpose of this project is to propose at least two suitable alternative designs for an affordable
housing development at the Bon Air Gardens North location. This development is to include a
total of 354 units, a community centre, health centre and other recreational facilities. A detailed
feasibility study for each alternative will be conducted to determine the best possible design for
the development. Numerous factors were taken into consideration for this project such as the
topographic and geological features, the seismic region of the site, the hydrological data (I.e.,
rainfall data etc.) and other environmental data, as these would impact the designs and layout of
the proposed community. Such data would impact the structural design and orientation of the
buildings, drainage, water supply designs and pavement designs.
23
1. Introduction
1.1. Project Scope
The scope of this study aims to evaluate 2 proposed alternatives and the preliminary designs for
all infrastructure in the proposed settlement at Bon Air North. The following considerations must
be incorporated within or a part of the settlement design to satisfy the requirements outlined for
the proposed settlement.
● The settlement is expected to have 354 housing units.
● Proper site planning of settlement
● Architectural Designs of housing
● Civil and Environmental Engineering Design (Structures, Transportation, Surface
water drainage, Potable Water and Wastewater systems).
As part of site planning and the development of 354 housing units, the settlement is expected to
include a community centre, health services, and recreational facilities. The design will also be
centred on being sustainable, by having a minimal carbon footprint and using greener alternatives
to traditional infrastructure.
The development will also take into consideration storm water runoff ensuring that there is a net
zero increase in flows within the ravines, adequate and proper drainage on site and no increase in
flooding or runoff lower catchment due to the site. Covid 19 protocols, environmental impacts and
feasibility of the alternatives will also be considered in the design of the settlement.
Guidelines for sub-division, residential and road layout, wastewater, water supply and storm
water management are:
● WASA Guidelines for Design and Construction of Water and Wastewater Systems in
Trinidad and Tobago (WASA 2014)
● International Building Code (ICC 2018)
● SMALL BUILDING CODE GUIDE (1997)
● Preliminary Design of Structural Members (Clarke 2020)
24
● Environmental Management Act No. 34 (1995)
● The American Association of State Highway and Transportation Officials (AASHTO)
1993 Manual.
● Guide to Developers and Applicants for Planning Permission (Town and Country
Planning Division of The Ministry of Planning and Division 1988)
● Traffic and Highway Engineering 4th Edition Manual (Garber and Hoel 2009)
● Dr. Vincent Cooper – Provided guidance on the water supply, stormwater management
design and wastewater treatment designs.
● Dr. Trevor Townsend – Provided guidance on the economic analysis of roads and site
location
● Keeshan Ramkissoon, Curtis Dookie, Sasier Gokool, Ian Cox - Mentors
● Ms. Allison Elecock - Fortune - Manager, Wastewater Treatment Plant
● Dr. Richard Clarke – Provided guidance on the preliminary
● Mr. Ovi Mottley – Provided guidance on the QGIS software
● Mr. Derek Outridge - Provided guidance on costings
● Mr. Mel Best - Wastewater plant operator
● Mr. Lacey Williams
1.4. Aim
● To determine the overall feasibility of the construction of this settlement at the location
based on the current and projected physical, economic, social, and environmental
conditions of the location in Bon Air North.
● To provide conceptual designs for the most practicable infrastructural and structural system
alternatives to be suggested in the residential community's final planned design.
● To determine the comparative feasibility of each alternative considered for the
development of the residential community using the method of multi-criteria decision
analysis.
25
1.5. Objectives
● To research and design the alternatives for the structural systems and infrastructure systems
that will be used for the development of a residential community in Bon Air North. The
alternative structural systems which were used in the structural designs are reinforced
concrete moment resisting frame and steel moment resisting frame. The alternative
infrastructure systems are on the stormwater drainage system, road network layout, and
road structural design
● To conduct a preliminary environmental impact assessment on the Bon Air North Housing
Development. These findings will be used in the multi-criteria decision-making process to
determine the most feasible option of alternatives considered for the infrastructure and
structural systems
● To comply with engineering standards, layout standards, site development standards, local
policies and legislation listed under Project References to create the housing development
and to include the principle of sustainable development, within the feasibility, throughout
the design process.
26
2. Project Overview
Climate Change has been over the headlines recently, especially amid the COP-26 Climate
Summit, in which more than 200 countries participated to discuss the issue. It has been projected
and slowly being realized that climate change will exacerbate extreme weather conditions which
will affect us drastically in the Caribbean as our small island states are particularly at risk due to
the effects of climate change. In addition to climate change, the challenges brought by increasing
populations include the lack of affordable housing, as a result, this housing development is
intended to be resilient against the effects of climate change while being affordable to potential
settlers. The proposed 354 units will be derived from having 2 story 3-bedroom townhouses,
triplex apartment complexes, 5 story double room apartment complexes, and 3 story single room
apartment complexes. The development is catered for the middle class of society and will be
designed around sustainability, Covid 19, and flood control. The settlement will include as
mentioned prior a community centre with an administrative office, gym, mini-Mart, youth centre,
laundry mart, health services, and recreational facilities, making the development somewhat self-
sufficient. The design of structures on site are influenced by the site topography as it is very
elevated, as a result, measures will be put in place so that the development of this site, which is
located higher up the catchment, would not bring adverse effects to the residents on the lower
catchment. Soil retaining measures will also be applied to preserve natural slopes and prevent land
slippage.
2.1. Limitations
Due to the ongoing pandemic, access to the site was limited. Therefore, most data came from
secondary sources. These sources included information gathered from points of contact, online
resources and the data provided from the lecturers.
2.2. Assumptions
The assumptions made were that the data given was accurate and the most recent, and that there
was no development yet on site.
27
3. Feasibility Analysis
3.1 Preliminary Study
3.1.1 Site Location
The proposed location of the settlement is in Bon Air Gardens North, and its surrounding
communities located in Arouca, Eastern Trinidad. Arouca is a planned community situated in
eastern Trinidad, it is located along the East-West corridor, West of Trincity and East of D’Abadie.
The proposed site is approximately 24 hectares of land situated north of the Priority Bus Route at
the foothills of the Northern Range. The proposed site is bordered between the north of Pine Ridge
Heights neighbourhood off Lopinot Road, as well as two tributaries, Jamba Ravine Tributary and
Jamba Ravine, on the East and West of the site respectively, which trail down to the Oropuna River
in Oropune, South-West to site. According to Town and Country Planning, the lands for the
proposed site are currently classified for urban development. Currently the Housing Development
Corporation (HDC) has an on-going housing settlement project to date, but for this study the
proposed location will be assumed as undeveloped land.
With reference to road maps from Google Earth and Google Maps, the only access to the entire
site is through two entry points on a collector road, Nathaniel Critchlow Boulevard, both running
from the South of the site. Nathaniel Critchlow Boulevard intersects Pine Ridge Drive which both
intersect the collector street, Lopinot Road. Lopinot Road further intersects the main highway, the
Eastern Main Road, as well as the Priority Bus Route. As a result, the site has close access to a
main transportation hub. The lands consist of overgrown bushes and weeds or farming
development and is very sloped and has two tributaries running through the site. As a result, cutting
and filling will be considered in developing the land for housing.
28
Figure 1. Showing a General Location of the Proposed Settlement
3.1.2 Soils
The Design team obtained GIS data for the soil distribution in the Bon Air North region. The
attribute information for the soil was utilized to categorize the different soil types in the area using
this data, which was entered into QGIS. Fine sandy loam soil, sandy clay loam soil, and gravelly
sandy clay loam soil were the three (3) soil types found within the site area. Fine Sandy Loam soil
was determined to make up most of the soil within the project's perimeter. Texture code No. 32
along the West to North-West region of the site, the drainage classification was noted as free
drained with an infiltration rate of 2.0- 6.0 in/hr. Texture code No.34 along the North-East region
of the site, the drainage classification was also noted as free drained with an infiltration rate of
0.50-2.0 in/hr. Lastly, texture code No.41 along the South- South-West region of the site, the
drainage classification was impeded, resulting in an infiltration rate of 25.0-50.0 in/hr. Table.1
shows the properties of the soil found on the proposed site.
As it relates to the Alternatives (Layout one & Layout two), all components including buildings,
most infrastructure fall mainly on two soils, Texture Code No.32 (Fine Sandy Loam) and Texture
Code No.34 (Sandy Clay Loam) and a small percentage of the infrastructure and buildings on
texture Code No.41 falls on the Gravelly Sandy Clay Loam.
29
Soil Texture Infiltration rate
Texture Code Soil Texture Name Drainage
Abbreviation (in/hr.)
To further investigate the Bon Air North site, a pre-existing geotechnical report was also analysed
in conjunction with the QGIS data file. Based on the field investigation conducted on March 14th
and 15th in the year 2015 by Trinitoplan Consultants LTD., four (4) boreholes were analysed. The
main soil stratigraphy found on the site is Phyllite which is a sedimentary rock which is a form of
shale. This soil was described as dense to very dense sand and gravel with a natural moisture
content ranging from 8% - 22%.
The Atterberg Limits Tests reveal that the samples fall within the CL part of the Plasticity Chart
shown below, indicating that they are low plasticity clays with Liquid Limits ranging from 48 to
58, Plastic Limits of 26, and Plasticity Indices of 22 to 32. The Grain Size Distribution shows that
silt and sand make up most of the soils. Clay concentrations ranged from 4 % to 40 %, silt contents
30
from 14 % to 35 %, and contents from 24 % to 56 %, and gravel contents from 0 % to 22 %, based
on the soil investigation.
3.1.3 Hydrology
Due to the numerous peaks in height in the island's northern sections and the varying distributions
in soil composition in these areas, the drainage pattern on Trinidad is dendritic. Many tributaries
are generated along a main river when water naturally carves a passage from higher to lower
elevation, through soft soil or around less permeable material, because surface runoff flows from
the Northern Range's higher elevations to lower elevations. The Jamba Ravine and the Jamba
Ravine Tributary run along the boundaries of the proposed site due to its position. The larger of
the two tributaries (Jamba Ravine) flows closer to the Bon Air North site's northern section, while
the smaller tributary (Jamba Ravine Tributary) flows south-west (See Figure.3). It should also be
noted that the proposed site is located within the Arouca watershed which is found within the
western Peninsula (Hydrometric Area 9) (See Figure.2).
The site is situated on a sloping piece of ground. This will exacerbate design concerns with the
new drainage system. As a result, rivers are found in valleys, which are one of the least desirable
areas for residential construction since the slope of the terrain favours the flow of water, generating
a channel that may cause significant flood damage to buildings and infrastructure. Given that
Trinidad receives about 70 inches of rain per year on average, this is a major factor. Because of its
31
tropical environment, the nation has two distinct seasons which are rainy and dry. The water levels
encountered on the site during the ground study and the groundwater table are revealed to be
phreatic, and their level is likely to fluctuate with seasonal rainfall, according to a field
investigation done by Trinitoplan Consultants LTD on March 14th and 15th, 2015.
BH 1 11.0
BH 2 9.5
BH 3 None Recorded
BH 4 None Recorded
Table 3. Showing Borehole Groundwater Depth (Geotechnical Assessment for the Slope
Stability Analyses at the Bon Air North Site,2015)
32
Figure 3. Showing the Watershed of Trinidad and the Drainage Basin of the General Area of
the Proposed Site
Figure 4. Showing the Tributaries running along the Boundaries of the Proposed Site
3.1.4 Topography
Topography can be defined as the physical makeup of an object or surface, inclusive of its
structural composition, both natural and man-made, and the relief of the land (Merriam-Webster
Dictionary n.d.). The country of Trinidad is located off the northern edge of South America and is
approximately situated 11 kilometres off the coast of northeast Venezuela and 113 kilometres
south of Grenada. Similarly, it’s topography can be compared to that region (Encyclopaedia
Britannica Inc n.d.). The island’s topography varies according to location, and this can be more
easily seen when considering the three ranges of the island; The Northern, Central and Southern
Ranges, that gradually increase in elevation from South to North. In the northern part of the island,
the land is more elevated. There, the Northern Range was formed, where the highest peak of the
island, Mount Aripo can be found. Near this range, the town of Arouca is located, and within it is
the Bon Air North site.
33
Figure 5. Showing the Topography of Trinidad and highlighting the Three Mountain Ranges
of the island.
(Source adapted from Google Image, https://www.researchgate.net/figure/A-Sun-shaded-digital-
elevation-model-showing-Trinidads-principal-geomorphic-features_fig3_228431933)
34
Figure 6. Showing the Northern Range where the site area is closely located.
(Source adapted from Google Image, https://www.researchgate.net/figure/Map-of-Trinidad-showing-
the-location-of-the-study-area-after-Darsan-et-al-2012_fig11_272790222)
As previously stated, the Bon Air North development site is located in the town of Arouca, near
the Northern Range of Trinidad. The site can be described as predominantly steep with the land
sloping towards both the northwest and southeast sides. In the figures below, the general relief of
the site area can be seen. The area at the southwest position/entrance of the site, the land is
relatively flat, gaining elevation as one moves towards the northeast part of the site.
35
Figure 7. Showing the Longitudinal Profile of the Site Area.
Figure 8. Showing the Section Profile at the Southwestern part of the Site Area.
36
Figure 9. Showing the Section Profile along the Central part of the Site Area.
Figure 10. Showing the Section Profile along the North-eastern part of the Site Area.
3.1.5 Climate
Climate is defined as the average weather over a given area or region over an extended period. It
is concerned with data such as temperature, air pressure, humidity, precipitation, sunshine,
cloudiness, and wind speeds. The climate in the Caribbean is tropical and it is controlled by the
North-eastern trade winds and the elevations of given areas in the region. Trinidad and Tobago
are located in the Southernmost parts of the region and is within close proximity of the equator, as
a result, the temperatures in Trinidad and Tobago, from 73 to 90°F which is approx. 23 to 32°C,
with a mean daily temperature of 27°C. There are also only two seasons experienced by the twin
republic of Trinidad and Tobago; a dry season from January to May which can be identified by
moderate to strong low-level winds along with warm days and cool nights, and a rainy season from
June to December, which can be identified by low winds speeds, humid days, humid nights, and
increased rainfall. It must be noted though, that generally, the wet season is warmer than the dry
season with September being the warmest in the wet season and March being the driest in the dry
season. It must also be noted that the months of transition from both the dry to the wet season and
vice versa are the months of May and December respectively. The hurricane season which is in
effect during the months of June to November, the wet season, must also be mentioned as this
season usually can be very disastrous for the Caribbean islands, with the season peaking in the
months between August and October. This information of the seasons and the characteristics
37
specific to each season is very important and it greatly affects any given project both during the
pre-construction phase and during the construction phase.
Figure 11. Showing the Possible Rainfall Totals for December 2021
Figure 12. Showing the Possible Rainfall Totals for January to March 2022
38
Figure 13. Showing the Possible Rainfall Totals for March to May 2022
Figure 14. Showing the Possible Accumulated Rainfall Totals for Dry Season 2022
39
3.1.6 Natural Hazards
A natural hazard can be defined as a natural event that can cause fatalities, disruption of day-to-
day human activities, and extreme damage to property. The island of Trinidad is primarily faced
with hazards such as flooding, landslides, earthquakes, and sometimes hurricanes. These hazards
can potentially be of substantial risk to project sites before, during, and after construction. It must
be noted though that their effects can be mitigated by proper design practices, having adequate
infrastructure on site (i.e., drainage etc.), and by properly layout out a given site, other mitigating
strategies can further be taken to ensure that the effects of these hazards are kept at a minimum.
The following images below show the typical hazards faced by the island of Trinidad and a brief
explanation of each hazard.
Increased precipitation due to climate change and increased impervious surfaces have increased
the frequency of flooding events due to current drainage infrastructure not being able to facilitate
increased surface runoff. From the map, the circled area is estimated to be our area of interest,
within this area according to the flood map. We can see that this area’s flood susceptibility ranges
from very high to low flooding susceptibility.
40
Figure 15. Showing the Flood Susceptibility Map of Trinidad
Landslides can simply be defined as the movement of land due to gravity. During heavy rainfall
landslides occur due to groundwater pressures destabilizing slopes, deforestation of elevated
areas and earthquakes, as they also destabilize slopes. From the landslide multi risk map, we can
see that our estimated area of interest is of very high to very low risk. From the landslide
susceptibility map, we can see that our area of interest ranges from very high to very low
susceptibility.
41
Figure 16. Showing the Landslide Multi Risk Map of Trinidad
42
Figure 17. Showing the Landslide Susceptibility Map of Trinidad
Earthquakes can be defined simply as the shaking of the earth due to tectonic or volcanic origins.
The island of Trinidad is at high risk of earthquakes as it is located on the boundary between two
tectonic plates: The Caribbean plate and the South American plate and a couple of faults can be
found on the island. As a result, structures are to be designed in such a way to deal with the
effects of earthquakes according to code. Values used in designing earthquake-resistant
structures, the spectral acceleration and peak ground acceleration can all be obtained from the
UWI seismic research centre for a given return period.
43
Figure 18. Showing Tectonic Plates in the region
44
Figure 19. Showing the Fault Lines in the region
45
Figure 21. Showing Spectral Acceleration Map Trinidad
Note: S1 value for Bon Air North area with RP = 2475yrs is 0.381 from range of 0.371 - 0.391
46
Figure 22. Showing Spectral Acceleration Map Trinidad
Note: Ss value for Bon Air North area with RP = 2475yrs is 1.51 from range of 1.461 - 1.550
A hurricane is defined as a type of storm called a tropical cyclone and they tend to form over both
tropical and subtropical waters. Tropical cyclones can be classified based on their wind speeds;
tropical cyclones with maximum sustained winds less than 39 miles per hour are called tropical
depressions, tropical cyclones which have maximum sustained winds of 39 mph or higher are
called tropical storms and tropical cyclones with maximum sustained winds of 74 mph and above
are called hurricanes.
A wind scale called the Saffir-Simpson Hurricane Wind Scale is a 1 to 5 category scale, and it is
based on a hurricane's maximum sustained winds. The higher the category of the hurricane, the
greater the hurricane's potential for property damage.
47
As mentioned prior the hurricane season ranges from the months of June to November, with the
season peaking in the months between August and October. From the NOAA maps we can see
that the likelihood of Trinidad getting a direct hit from hurricanes are very low.
Figure 23. shows the tracks and likelihood of how Hurricanes would have affected the region
in August
Figure 24. shows the tracks and likelihood of how Hurricanes would have affected the region
in September
48
3.2 Environmental Impact Assessment
3.2.1 Introduction
Your design team has been hired to provide affordable housing within a 24-hectare site in Bon Air
Gardens North. The Housing Development Corporation proposes to develop the site for 354
housing units. The new community will have amenities such as a community centre, health
services and recreational facilities. The site is in a catchment drained by the Dunderhill Ravine.
Several floods occurred recently in the lower catchment and at the bridges of the Eastern Main
Road and the Priority Bus Route. Part of the problem is inadequate stormwater management
facilities, made worse by unplanned housing developments surrounding the proposed site. Your
design team must develop the infrastructure to control flooding, even with the new housing
community. Sustainability must be the hallmark of your design. You are therefore to choose
solutions for your housing community such that it makes zero net increase in flows within the
ravine and has a minimum carbon footprint. It means therefore that your design should be partial
to green technologies, including pervious pavements, rooftop gardens, rainwater harvesting and
retention basins, and the choice of materials for the buildings. Bear in mind the lessons from the
49
pandemic in terms of changes in social interaction and how the economy might be transformed in
the future.
Pre-Construction: This entails design of site infrastructure and site preparation, clearance,
grading etc.
Post Construction: This entails the removal of excess material and equipment from the site and
long-term mitigation strategies.
50
Impacts
Table 5. Scale of how severe impacts can be on the environmental resources on the proposed
site.
Probability
51
Probability Impact
Low (3) Moderate (6) Moderate (9) High (12) High (15)
Low (2) Moderate (4) Moderate (6) Moderate (8) High (10)
Low (1) Low (2) Low (3) Moderate (4) Moderate (5)
52
3.2.4 Environmental Impact Assessment (EIA)
Pre-Construction Phase
53
trenchworks
entering nearby
water courses
54
During Construction Phase
55
regularly to adhere
to the Water
Pollution Rules,
2019 Trinidad and
Tobago before
being discharged
56
regeneration,
creation, and
protection of
ecosystems on site
57
Post Construction Phase
58
and machinery over on equipment to
threshold levels reduce noise
during daily generated
operations ● Following
regulations set for
noise level by the
EMA, Noise
Pollution Control
Rules, 2001
(NPCR)
● Planting trees
around the site to
act as sound barrier
and dampers
59
the environment debris. Solid waste
(i.e., waste left by to ensure the area is
animals and safe for use
rodents, areas, and ● Adequate provision
materials prone to of garbage bins
mosquito around the
promoting) development to
help reduce
likelihood of
littering
● Development of an
appropriate
schedule regarding
garbage collection
and disposal (both
commercially and
residentially)
60
3.3 Engineering Alternatives:
The designs include a mixture of housing to provide 354 units for all demographics. Many people
from all various financial levels and backgrounds may live in this welcoming atmosphere because
of the range of housing accommodations offered to interested members. The affordable housing
development will provide recreation and entertainment facilities (community centre), green areas,
stormwater and wastewater management, road and traffic considerations, a policlinic which was
designed fully equipped for the safety and well-being of occupancy in the community, especially
in the event of a pandemic.
On both the alternative sites can be found a two-story community centre which contains the
administration department for the community, fully equipped gym, mini market, laundry mart,
training centre, conference room, and a multi-purpose hall to host events. The roof was designed
as a concrete slab to cater for water tanks on the roof, and the possibility of future expansion. The
fully equipped policlinic was designed to handle events such as a pandemic where the roof was
also designed as a concrete slab to cater for water tanks on the roof, and the possibility of future
expansion to accommodate quarantine areas. In this design you'll find two consultation rooms,
four (4) examination rooms, a nurse station, procedure and lab and a pharmacy. Four (4) five-story
double bedroom apartment complexes containing 30 units, four (4) three-story apartment single
bedroom complexes containing 30 units, eighteen (18) triplex double room structure with two
bedrooms, one being a master bedroom, kitchen, and dining/living area to cater for middle class
people. These structures can be identified on both alternatives with the difference in material for
the construction. Alternative one (layout one), thirty (30) three-bedroom reinforced concrete
duplex structure containing 60 units can be seen which may differ from alternative two (layout
two) where sixty (60) single unit steel frame townhouses can be seen which will be catered for the
upper-class people. The variety of living accommodations, all designed in reference to Trinidad
Building code, would be available to interested future occupants to allow for many different
income brackets and backgrounds.
61
Multi-Criteria Analysis
Rank Description of
Rating
5 Ideal
4 Very Good
3 Moderate
2 Poor
1 Very Poor
I II
Reinforced Concrete Steel Frame
2 Material Availability 5 2
3 Time of Construction 2 3
4 Design Life 3 4
5 Sustainability 2 3
6 Aesthetic 4 3
Table.10 Showing ranking of alternatives
62
Objective Ranking Relative Weight Weight Factors
(x100)
2 2 5: (n - 1) (5/22) x100=22.72
5 3 2: (n - 2) (2/22) x100=9.1
6 5 2: (n - 4) (2/22) x100=9.1
Total 22 100
Table.11 Showing weighting factors
Objective
Alternatives
I II
Reinforced Concrete Steel Frame
The results obtained from conducting the Multiple Criteria Analysis proved that reinforced
concrete is the better option as it achieved the highest value, that of 87.89 points.
63
Community Centre
Figure 25: Sketch of the Community Centre Floor Plan for Reinforced Concrete Moment
Resisting Frame
64
REFEREN
CALCULATIONS OUTPUT
CES
Calculation - Preliminary Structural Design of a Reinforced
Concrete Framed for the Community Centre
Community Centre
Reinforced PLAN
Concrete
Designer’s Dead Load = 3.6 kN/m2
Handbook, Live Load = 1.4 kN/m2
Reynolds & Density of Normal weight concrete = 24 kN/m3
Steedman
Calculating Building Weight
Beams Weight
No. of beams = 17
Maximum span = 8.95 m
Therefore, use beam sizes of 0.35m = 350
For d = (8950/26) + 300 = 644= 650mm = 0.650m
Total beam length = (24.49 x 3) + (18.30 x 4) = 134.4 m
No. of floors = 2
65
REFEREN
CALCULATIONS OUTPUT
CES
Therefore, total beam weight = 24 x 134.4 x 0.650 x 0.35 x 2 = Total
1467.6kN Building
Weight, W
= 5007 kN
Columns Weight
Maximum beam span = 8.95 m
Therefore, h = 0.35m
No. of columns = 12
Column height = 4m
No. of floors = 2
Therefore, total column weight = 24 x 0.35 x 0.35 x 4 x 12 x 2 =
282.24 kN
Plan
Dr. R. Clarke
Preliminary
Design of
Structural
66
REFEREN
CALCULATIONS OUTPUT
CES
Members
Notes
Part A
Internal Frame
F1 + F2 = 500.7
F1 + 1.67F1 = 500.7
2.67F1 = 500.7
F1 = 187.5 kN
F2 = 313.2 kN
Tributary
Calculate Moments Due to Seismic Load in Shorter Direction width =
8.95 m
Average Tributary width = (8.95+8.95)/2=8.95 Dead
m Load=32.2
Dead Load = 3.6 x 8.95 = 32.22 kN/m 2 kN/m
Live Load = 1.4 x 8.95 = 12.53 kN/m Live
Load=
12.53
kN/m
67
REFEREN
CALCULATIONS OUTPUT
CES
68
REFEREN
CALCULATIONS OUTPUT
CES
Summary
69
REFEREN
CALCULATIONS OUTPUT
CES
Dr. R. Clarke
Preliminary
Design of
Structural
Members Internal Column
Notes Part E
Recall:
Beam depth, d = 650mm
Beam width, b = 350 mm
Therefore, I = (350 x 6503)/12 = 8.0 x 109 mm4
70
REFEREN
CALCULATIONS OUTPUT
CES
KU = I/L = 1.25 x109 /4000 = 0.3 x 106 mm4
Mupper =
17.9 kNm
Mlower =
11.9 kNm
External Column
71
REFEREN
CALCULATIONS OUTPUT
CES
Dr. R. Clarke
Preliminary
Design of Internal Support Rebar:
Structural
Members MU = 0.9Asfy(d-a/2)
Notes Part F a = Asfy/(0.85fc’b)
fy = 410 MPa
fc’= 30 Mpa
Therefore, As = 2774.8mm2
Use 4 T32 bars = 3216.8mm2
Span Rebar
Mu = 23.9 x 104As – 8.49As2
417 x 106 = 23.9 x 104As – 8.49As2 Use 3 T32
Therefore, As = 1868.8 mm2 bars for
Use 3 T29 bars = 1981.5mm2 External
ϕMn = 0.9 x 1981.5 x 410 x (650 – (1981.5 x 410)/ (0.85 x 30 x 350 Rebar
x 2))10-6 = 442> 417 kNm
72
REFEREN
CALCULATIONS OUTPUT
CES
Therefore OK
Summary:
73
REFEREN
CALCULATIONS OUTPUT
CES
Summary
Use T10 at
100mm c/c
Calculate Column Moment Rebar spacing in
the
Consider Load Case, U = 1.4D + 0.5L + 1.4E confinemen
Section = 350mm x 350mm t zone of
Ultimate (applied) Moments: 1800mm
from the
Internal Column, MU = 0+ 0.5(11.9) + 1.4(375.6) = 531.8 kNm top and
bottom of
External Column, MU = 1.4(30.7 x 32.22/32.22+ 12.53) + 0.5(30.7 x 12.53/32.22
+12.53) + 1.4(187.8) = 298.2 kNm the column.
Otherwise,
Ultimate Axial Loads:
use T10 at
Internal Column, PU = 1.4(895.7) + 0.5(336.4) + 1.4(66.5)
200 c/c
= 1515.3 kN
spacing
External Column, PU = 1.4(463) + 0.5(336.4/2) + 1.4(66.5)
= 825.4 kN
Internal
Kn = Pu/(ϕfc’Ag) = 1515.3 x103/ (0.8 x30 x 3502) = 0.5
Rn = MU / (ϕfc’Agh = 455.6 x106/ (0.8 x 30 x 3503) = 0.4
74
REFEREN
CALCULATIONS OUTPUT
CES
⸫ γ = 0.8
(ACI Interaction Chart R3 60.8)
External
Kn = Pu/(ϕfc’Ag) = 825.4 x103/ (0.8 x30 x 3502) = 0.3
Rn = MU / (ϕfc’Agh = 417.5 x106/ (0.8 x 30 x 3503) = 0.4
Column Hoops:
75
REFEREN
CALCULATIONS OUTPUT
CES
Summary
76
Cost Estimation
CONCRETE
Total= 264.64 m3
REBAR
MASONRY
Consider 400 x 200 x 150 ASTM C90 unreinforced hollow concrete unit
77
GRADE SLAB
Consider 125mm thick and 610 BRC (30.5m x1.8m roll)
78
Policlinic
Figure 26: Sketch of the Polyclinic Floor Plan for Reinforced Concrete Moment Resisting
Frame
79
Calculation - Preliminary Structural Design of a Reinforced Concrete Framed for the Policlinic
REFEREN
CALCULATIONS OUTPUT
CES
Policlinic
PLAN
2
Dead Load = 3.6 kN/m
Live Load = 1.4 kN/m2
Density of Normal weight concrete = 24 kN/m3
Reinforced
Concrete
Calculating Building Weight
Designer’s
Handbook,
Floor Slabs Weight
Reynolds & Floor slab area = 373.4 m2
Steedman Thickness, h=6in = 0.152 m
Density of concrete = 24 kN/m3
Floor slab weight = 24 x 373.4 x 0.152 = 1362.2 kN
No. of floor slabs = 1
Therefore, total floor slab weight = 1362.2 x 1 = 1362.2
kN
Beams Weight
No. of beams = 17
Maximum span = 8.00 m
Therefore, use beam sizes of 0.35m = 350
For d = (8000/26) + 300 = 607= 625mm = 0.625m
Total beam length = (24.40 x 3) + (15.30 x 4) = 134.4 m
No. of floors = 1
Therefore, total beam weight = 24 x 134.4 x 0.625 x 0.35 x 1 =
705.6kN
Columns Weight
80
REFEREN
CALCULATIONS OUTPUT
CES
Maximum beam span = 8.00 m
Therefore, h = 0.35m
No. of columns = 12
Column height = 3m
No. of floors = 1
Therefore, total column weight = 24 x 0.35 x 0.35 x 3 x 12 x 1 =
105.84 kN
Plan
Internal Frame
Dr. R. Clarke
Preliminary
Design of
Calculating Vertical Distribution of Seismic Load
Structural
81
REFEREN
CALCULATIONS OUTPUT
CES
Members
Notes Assuming equal spans in the longer direction
Part A
Seismic Load, V = 0.1W = 0.1 x 2173.6 = 217.4 kN
Also, V = F1
F1 = 217.4 N
Seismic
Load, V =
Calculate Moments Due to Seismic Load in Shorter 217.4kN
Direction
F2 = 0
F1 = (217.4) / (3-1)
=108.7 kN
82
REFEREN
CALCULATIONS OUTPUT
CES
Summary
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part B
83
REFEREN
CALCULATIONS OUTPUT
CES
𝑃𝐴=𝑃𝐶 𝑃𝐶L =0
MO =
TMA centreline: 652.2 kNm
Pa =
14.9𝑃𝐴=M𝑂
43.8kN
14.9𝑃𝐴=652.2 Pb =
𝑃𝐴= (652.2/14.9) = 43.8kN
43.8𝑘𝑁
Dr. R. Clarke Therefore Pc = 43.8 kN
Preliminary
Design of Calculate Gravity Moments in Beams
Structural Consider a UDL of 1kN/m and using equal spans with F total
Members load:
Notes Part C
Mg, support = -FL2/10 = -7.452/10 = -5.6 kNm
Mg, span = -0.08FL2 = 0.08 x 7.452 = 4.4 kNm
Therefore,
MD, SUPPORT = -26.8 x 5.6 = -150.1 kNm
MD, SPAN = 26.8 x 4.4 = 117.9 kNm
ML, SUPPORT = -10.4 x 5.6 = -58.2kNm M D,
ML, SPAN = 10.4 x 4.4 = 45.8 kNm support= -
150.1kNm
Calculate Gravity Moments in Columns MD, span =
By Moment Distribution of subframes 117.9kNm
ML, support
= -58.2kNm
84
REFEREN
CALCULATIONS OUTPUT
CES
ML, span =
45.8kNm
Internal Column:
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part D
Internal Column
Recall:
Dr. R. Clarke Beam depth, d = 625mm
Preliminary Beam width, b = 350 mm
Design of Therefore, I = (350 x 6253)/12 = 7.1 x 109 mm4
Structural
Members Column size = 350 x 350 mm
Notes Part E Therefore, I = (350 x 3503)/12 = 1.25 x 109 mm4
85
REFEREN
CALCULATIONS OUTPUT
CES
External Column
Mupper =
Calculate Gravity Axial Forces in Columns 0 kNm
Mlower =
Dead load = 3 x 3.6 x 7.452 +6 x 0.352 +(6 x 0.352 x 24) = 20.7 kNm
617.8kN
Live load = 3 x 1.4 x 7.452 = 233.1kN
External column dead load = 599.4/2 + (6x 0.352 x 24) =
317.34kN
86
REFEREN
CALCULATIONS OUTPUT
CES
Structural Internal Support Rebar:
Members
MU = 0.9Asfy(d-a/2)
Notes Part F
a = Asfy/(0.85fc’b)
fy = 410 MPa
fc’= 30 Mpa
Use 3 T22
bars for
Span
Rebar
87
REFEREN
CALCULATIONS OUTPUT
CES
Summary:
Therefore OK
88
REFEREN
CALCULATIONS OUTPUT
CES
Summary
Internal
Kn = Pu/(ϕfc’Ag) = 1042.8 x103/ (0.8 x30 x 3502) = 0.35
Rn = MU / (ϕfc’Agh = 455.6 x106/ (0.8 x 30 x 3503) = 0.4
89
REFEREN
CALCULATIONS OUTPUT
CES
External
Kn = Pu/(ϕfc’Ag) = 563.9 x103/ (0.8 x30 x 3502) = 0.2
Rn = MU / (ϕfc’Agh = 54.04 x106/ (0.8 x 30 x 3503) = 0.1
Column Hoops:
90
REFEREN
CALCULATIONS OUTPUT
CES
Summary
91
Cost Estimation
CONCRETE
Footings (assume pad footing 2.4 x 2.4 x 0.4) = 12 x 2.42 x 0.4 = 27.65 m3
Total= 122.32 m3
REBAR
MASONRY
Consider 400 x 200 x 150 ASTM C90 unreinforced hollow concrete unit
92
GRADE SLAB
93
Double Bedroom Apartment Complex
Figure 27: Sketch of the Double Bedroom Apartment Complex Ground, 1st, 2nd&,3rd Floor
Plan for Reinforced Concrete Moment Resisting Frame
94
Calculation - Preliminary Structural Design of a Reinforced Concrete Framed for the Double
Bedroom Apartment Complex Ground, 1st, 2nd ,3rd & 4th Floor Plan
REFEREN
CALCULATIONS OUTPUT
CES
Double Bedroom Apartment Complex
PLAN
2
Dead Load = 3.6 kN/m
Live Load = 1.4 kN/m2
Reinforced Density of Normal weight concrete = 24 kN/m3
Concrete
Designer’s Calculating Building Weight
Handbook,
Reynolds & Floor Slabs Weight
Floor slab area = 630.7 m2
Steedman Thickness, h=6in = 0.152 m
Density of concrete = 24 kN/m3
Floor slab weight = 24 x 630.7 x 0.152 = 2300.8 kN
No. of floor slabs = 5
Therefore, total floor slab weight = 2300.8 x 5 = 11504
kN
Beams Weight
No. of beams = 67
Maximum span = 5.59 m
Therefore, use beam sizes of 0.35m = 350
For d = (5590/26) + 300 = 515 = 550mm = 0.55m
Total beam length = (62.75 x 3) + (10.05 x 14) = 328.9 m
No. of floors = 5
Therefore, total beam weight = 24 x 328.9 x 0.55 x 0.35 x 5 =
7597.6kN
Columns Weight
Maximum beam span = 5.59 m
Therefore, h = 0.5m
No. of columns = 42
Column height = 3m
No. of floors = 5
Therefore, total column weight = 24 x 0.5 x 0.5 x 3 x 42 x 5 =
3780 kN
95
REFEREN
CALCULATIONS OUTPUT
CES
Building Total Weight, W Total
W = 11504 + 7597.6 + 3780 = 22881.6 kN Building
Weight, W
= 22881.6
kN
Plan
Internal Frame
F1 + F2 + F3 + F4 + F5= 2288.2
96
REFEREN
CALCULATIONS OUTPUT
CES
F1 + 1.75F1 + (1.4 x 1.75) F1+(1.3 x 1.4 x 1.75) F1+(1.2 x 1.3 x 1.4 x 1.75) F1
= 2288.2
12.2F1 = 2288.2
F1 = 187.5 kN
F2 = 328.2 kN
F3 = 459.5 kN
F4 = 597.4 kN
F5 = 716.8 kN
Dr. R. Clarke
Preliminary
Design of 𝑀𝑎𝑐=Σ𝐹𝑖=2, 𝑛×ℎ1 / 2(𝑛𝑐𝑜𝑙−1)
Structural 𝑀𝑎𝑑=Σ𝐹𝑖=1, 𝑛×ℎ2 / 2(𝑛𝑐𝑜𝑙−1)
Members Mab = Mae = ½ (Mac + Mad)
Notes Part B External moment = ½ internal
moment
F2 = (328.2+459.5+597.4+716.8) / (3-1)
= 1050.95kN
F1 = (187.9+328.2+459.5+597.4+716.8) / (3-1)
=1144.9 kN
97
REFEREN
CALCULATIONS OUTPUT
CES
Summary
Dr. R. Clarke
Preliminary
Design of
Structural
98
REFEREN
CALCULATIONS OUTPUT
CES
Members Calculate Axial Loads Due to Seismic
Notes Part C Loads
10.10𝑃𝐴+4.06(0.77/4.83) 𝑃𝐴=8958.6
10.7𝑃𝐴=8958.6
𝑃𝐴= (8958/10.9) = 821.8𝑘𝑁 M D,
Therefore PB = 131 kN support= -
39.8kNm
Dr. R. Clarke Calculate Gravity Moments in Beams MD, span =
Preliminary Consider a UDL of 1kN/m and using equal spans with F total 31.14kNm
Design of load: ML, support
Structural = -15.5kNm
Members Mg, support = -FL2/10 = -4.82/10 = -2.3 kNm ML, span =
Notes Part D Mg, span = -0.08FL2 = 0.08 x 4.82 = 1.8 kNm 12.1kNm
Therefore,
MD, SUPPORT = -17.3 x 2.3 = -39.8 kNm
99
REFEREN
CALCULATIONS OUTPUT
CES
MD, SPAN = 17.3 x 1.8 = 31.14 kNm
ML, SUPPORT = -6.72 x 2.3 = -15.5kNm
ML, SPAN = 6.72 x 1.8 = 12.1 kNm
Internal Column
Recall:
Dr. R. Clarke Beam depth, d = 550mm
Preliminary Beam width, b = 350 mm
Design of Therefore, I = (350 x 5503)/12 = 4.85x 109 mm4
Structural
Members Column size = 500 x 500 mm
Notes Part F Therefore, I = (500 x 5003)/12 = 5.2 x 109 mm4
100
REFEREN
CALCULATIONS OUTPUT
CES
Mupper =
3.2 kNm
Mlower =
4.2kNm
External Column
101
REFEREN
CALCULATIONS OUTPUT
CES
Internal Support Rebar:
MU = 0.9Asfy(d-a/2)
a = Asfy/(0.85fc’b)
fy = 410 MPa
fc’= 30 Mpa
Span Rebar
Mu = 20.3 x 104As – 8.49As2 Use 3 T25
62.9 x 106 = 20.3 x 104As – 8.49As2 bars for
Therefore, As = 313.9 mm2 External
Use 3 T12 bars = 339.3mm2 Rebar
ϕMn = 0.9 x 339.3 x 410 x (550 – (339.3 x 410)/ (0.85 x 30 x 350 x
2))10-6 = 67.9> 62.9 kNm
Therefore OK
102
REFEREN
CALCULATIONS OUTPUT
CES
Summary:
103
REFEREN
CALCULATIONS OUTPUT
CES
Summary
Use T10 at
100mm c/c
spacing in
Calculate Column Moment Rebar the
confinemen
Consider Load Case, U = 1.4D + 0.5L + 1.4E t zone of
Section = 500mm x 500mm 1150mm
Ultimate (applied) Moments: from the
top and
bottom of
Internal Column, MU = 0+ 0.5(4.2) + 1.4(572.45) = 803.5 kNm
the column.
External Column, MU = 1.4(10.8 x 17.3/17.3+ 6.72) + 0.5(10.8 x 6.72/17.3
Otherwise,
+6.72) + 1.4(286.2) = 413.1 kNm use T10 at
Ultimate Axial Loads: 200 c/c
Internal Column, PU = 1.4(280.8) + 0.5(96.8) + 1.4(131) spacing
= 624.9 kN
External Column, PU = 1.4(220.4) + 0.5(96.8/2) + 1.4(821.8)
= 1483.3 kN
Internal
Kn = Pu/(ϕfc’Ag) = 624.9 x103/ (0.8 x30 x 5002) = 0.1
Rn = MU / (ϕfc’Agh = 1124.9 x106/ (0.8 x 30 x 5003) = 0.4
104
REFEREN
CALCULATIONS OUTPUT
CES
External
Kn = Pu/(ϕfc’Ag) = 1483.3 x103/ (0.8 x30 x 5002) = 0.2
Rn = MU / (ϕfc’Agh = 578.34 x106/ (0.8 x 30 x 5003) = 0.2
1< ρg = 2 < 6 OK
Column Hoops:
105
REFEREN
CALCULATIONS OUTPUT
CES
Summary
106
Cost Estimation
CONCRETE
Footings (assume pad footing 2.9 x 2.9 x 0.6) = 42 x 2.92 x 0.6 = 211.93 m3
Total= 1143.74 m3
REBAR
MASONRY
Consider 400 x 200 x 150 ASTM C90 unreinforced hollow concrete unit
107
GRADE SLAB
108
Single Bedroom Apartment Complex
Figure 28: Sketch of the Single Bedroom Apartment Complex Ground, 1st & 2nd Floor Plan
for Reinforced Concrete Moment Resisting Frame
109
Calculation - Preliminary Structural Design of a Reinforced Concrete Framed for the Single
Bedroom Apartment Complex Ground, 1st & 2nd Floor Plan
REFEREN
CALCULATIONS OUTPUT
CES
Single Bedroom Apartment Complex
PLAN
Beams Weight
No. of beams = 47
Maximum span = 6.86 m
Therefore, use beam sizes of 0.4m = 400
For d = (1680/26) + 300 = 564 = 600mm = 0.6m
Total beam length = (59.78 x 2) + (10.28 x 8) = 201.8 m
No. of floors = 3
Therefore, total beam weight = 24 x 201.8 x 0.6 x 0.4 x 3 =
3487.1kN
Columns Weight
Maximum beam span = 6.86 m
Therefore, h = 0.4m
No. of columns = 30
Column height = 3m
No. of floors = 3
110
REFEREN
CALCULATIONS OUTPUT
CES
Therefore, total column weight = 24 x 0.4 x 0.4 x 3 x 30 x 3 =
1036.8 kN Total
Building
Weight, W
Building Total Weight, W = 11604 kN
W = 7080 + 3487.1 + 1036.8 = 11604kN
Plan
Internal Frame
Seismic
Dr. R. Clarke Load, V =
Preliminary 1160.4kN
Design of
Structural
Members
Notes
Part A
111
REFEREN
CALCULATIONS OUTPUT
CES
Calculating Vertical Distribution of Seismic Load
F1 + F2 + F3 = 1160.4
F1 + 1.75F1 + (1.75 x 1.4) F1 = 1160.4 Tributary
5.2F1 = 1160.4 width = 5.14
m
F1 = 223.2 kN Dead
F2 = 390.5 kN Load=18.5
F3 = 546.7 kN kN/m
Live
Dr. R. Clarke Load=
Preliminary 7.2kN/m
Calculate Moments Due to Seismic Load in Shorter
Design of
Direction
Structural
Members
Average Tributary width = (4.11+6.17)/2=5.14
Notes Part B
m
Dead Load = 3.6 x 5.14 = 18.5 kN/m
Live Load = 1.4 x 5.14 = 7.2 kN/m
112
REFEREN
CALCULATIONS OUTPUT
CES
Moment of 1st floor internal column
Mac = [(390.5+546.7) x 3] / 2(3-1) = 702.9 kNm
Summary
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part C
113
REFEREN
CALCULATIONS OUTPUT
CES
Calculate Axial Loads Due to Seismic
Loads
10.28𝑃𝐴+4.11(1.03/5.14) 𝑃𝐴=4547.1
11.1𝑃𝐴=4547.1
𝑃𝐴= (4547.1/11.1) =409.6𝑘𝑁
Therefore PB = 82.1kN
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part D
114
REFEREN
CALCULATIONS OUTPUT
CES
Dr. R. Clarke
Calculate Gravity Moments in Beams
Preliminary
Consider a UDL of 1kN/m and using equal spans with F total
Design of
load:
Structural
Members
Mg, support = -FL2/10 = -6.862/10 = -4.7 kNm
Notes Part E
Mg, span = -0.08FL2 = 0.08 x 6.862 = 3.8 kNm
Therefore,
MD, SUPPORT = -18.5 x 4.7 = -86.95 kNm
MD, SPAN = 18.5 x 3.8 = 70.3 kNm
M D,
ML, SUPPORT = -7.2 x 4.7 = -33.84 kNm support= -
ML, SPAN = 7.2 x 3.8 = 27.36 kNm 86.95kNm
MD, span =
Calculate Gravity Moments in Columns 70.3kNm
By Moment Distribution of subframes ML, support
= -
Internal Column: 33.84kNm
ML, span =
27.36kNm
Internal Column
Recall:
Beam depth, d = 600mm
Beam width, b = 400 mm
Therefore, I = (400 x 6003)/12 = 7.2 x 109 mm4
115
REFEREN
CALCULATIONS OUTPUT
CES
Mupper =
8.7 kNm
Mlower =
6.6 kNm
External Column
116
REFEREN
CALCULATIONS OUTPUT
CES
Internal support at top, MU = 1.4(86.95) + 0.5(33.84) + 1.4(465.9) = 790.9
kNm
Ext support at top, MU = 1.4(86.95) + 0.5(33.84) + 1.4(232.5) = 464.15kNm
Span at bottom, MU = 1.4(70.3) + 1.6(27.36) = 142.2 kNm
Therefore, As = 4155.3mm2
Use 6 T32 bars = 4825.2mm2
117
REFEREN
CALCULATIONS OUTPUT
CES
Summary: Use 3 T19
bars for
Span
Rebar
118
REFEREN
CALCULATIONS OUTPUT
CES
Summary
119
REFEREN
CALCULATIONS OUTPUT
CES
External
Kn = Pu/(ϕfc’Ag) = 2019.8 x103/ (0.8 x30 x 4002) = 0.5
Rn = MU / (ϕfc’Agh = 401.5 x106/ (0.8 x 30 x 4003) = 0.3
120
REFEREN
CALCULATIONS OUTPUT
CES
Summary
121
Cost Estimation
CONCRETE
Columns = 30 x 0.42 x 10 = 48 m3
Footings (assume pad footing 2.4 x 2.4 x 0.5) = 30 x 2.42 x 0.5 = 86.3 m3
Total= 617.9 m3
REBAR
MASONRY
Consider 400 x 200 x 150 ASTM C90 unreinforced hollow concrete unit
122
GRADE SLAB
123
Two (2) Bedroom Triplex
Figure 29: Sketch of the Two (2) Bedroom Triplex Floor Plan for Reinforced Concrete
Moment Resisting Frame
124
Calculation – Preliminary Structural Design of a Reinforced Concrete Framed for the Two (2)
Bedroom Triplex Building.
REFERENC
CALCULATIONS OUTPUT
ES
Three (3) Bedroom Duplex
PLAN
Beams Weight
No. of beams = 10
Maximum span = 9.69 m
Therefore, use beam sizes of 0.4m = b
For d = (9690/26) + 300 = 679.7 = 700mm = 0.7m
Total beam length = (29.07 x 2) + (6.00 x 4) = 82.14 m
No. of floors = 2
Therefore, total beam weight = 24 x 82.14 x 0.7 x 0.4 x 2 =
1104kN
125
REFERENC
CALCULATIONS OUTPUT
ES
Columns Weight
Maximum beam span = 9.69 m
Therefore, h = 0.4m
No. of columns = 8
Column height = 3m
No. of floors = 2
Therefore, total column weight = 24 x 0.4 x 0.4 x 3 x 8 x 2 =
184.32 kN
Total Building
Weight, W =
2674.12 kN
Plan
Internal Frame
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes
Part A
126
REFERENC
CALCULATIONS OUTPUT
ES
F1 + F2 = 267.4
F1 + 1.75F1 = 267.4
2.75F1 = 267.4
F1 = 97.2kN
F2 = 170.2
kN
127
REFERENC
CALCULATIONS OUTPUT
ES
Summary
128
REFERENC
CALCULATIONS OUTPUT
ES
MO = 1580.2
kNm
Dr. R. Clarke Pa = 790.1 kN
Preliminary Pb = 790.1
Design of Kn
Structural
Members Overturning Moment, Mo = [(97.2 x 4) + (170.2 x 7)] / [ 2-1]
Notes Part C
= 1580.2 kNm
Pa = Pb
9.69Pa = Mo
Pa = 1580.2/9.69
Pa = 790.1 kN
Pb = 790.1 kN
MD, support= -
25.92kNm
Calculate Gravity Moments in Beams MD, span =
20.52kNm
ML, support =
Consider a UDL of 1kN/m and using equal spans with F total -10.08kNm
load: ML, span =
7.98kNm
Mg, support = -FL2/10 = -4.852/10 = 2.4 kNm
Mg, span = -0.08FL2 = 0.08 x 4.852 = 1.9 kNm
Therefore,
MD, SUPPORT = -10.8 x 2.4 = -25.92 kNm
129
REFERENC
CALCULATIONS OUTPUT
ES
Dr. R. Clarke MD, SPAN = 10.8 x 1.9 = 20.52 kNm
Preliminary ML, SUPPORT = -4.2 x 2.4 = -10.08 kNm
Design of ML, SPAN = 4.2 x 1.9 = 7.98 kNm
Structural
Members
Notes Part D
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part E
Recall:
Beam depth, d = 700mm
Beam width, b = 400 mm
Therefore, I = (400x7003)/12 = 1.14 x 1010 mm4
130
REFERENC
CALCULATIONS OUTPUT
ES
Therefore, As = 1243.8mm2
Use 4 T21 bars = 1385.6mm2
131
REFERENC
CALCULATIONS OUTPUT
ES
ϕMn = 0.9 x 190.06 x 410 x (700 – (190.06 x 410)/ (0.85 x 30 x
400 x 2)) = 190.06 > 48.8kNm
Therefore OK
Summary:
W= 1.2(D+L) = 1.2(10.8+4.2) = 18
kN/m
132
REFERENC
CALCULATIONS OUTPUT
ES
Use T10 at
Therefore OK
100mm c/c
spacing in the
confinement
Summary zone of
1000mm from
the top and
bottom of the
column.
Otherwise, use
T10 at 200 c/c
spacing
133
REFERENC
CALCULATIONS OUTPUT
ES
(ACI Interaction Chart R4 60.6)
1< ρg = 4.3 <6 OK
Column Hoops:
Summary
134
REFERENC
CALCULATIONS OUTPUT
ES
Check Foundation Design:
135
Cost Estimation
CONCRETE
Footings (assume pad footing 2.25 x 2.25 x 0.4) = 8 x 2.252 x0.4 = 16.2 m3
Total= 128.51 m3
REBAR
MASONRY
Consider 400 x 200 x 150 ASTM C90 unreinforced hollow concrete unit
136
GRADE SLAB
137
Three (3) Bedroom Duplex
Sketch:
Figure 30: Sketch of the Three (3) Bedroom Duplex Floor Plan for Reinforced Concrete
Moment Resisting Frame
138
Calculation - Preliminary Structural Design of a Reinforced Concrete Framed for the Three (3)
Bedroom Duplex Building.
PLAN
139
REFERENCES CALCULATIONS OUTPUT
Beams Weight
No. of beams = 7
Maximum span = 9.60 m
Therefore, use beam sizes of 0.4m = b
For d = (9600/26) + 300 = 669.23 = 700mm = 0.7m
Total beam length = (12.64 x 2) + (9.60 x 3) = 54.08 m
No. of floors = 2
Therefore, total beam weight = 24 x 54.08 x 0.7 x 0.4 x 2 =
726.84kN
Columns Weight
Maximum beam span = 9.60 m
Therefore, h = 0.4m
No. of columns = 6
Column height = 3m
No. of floors = 2
Therefore, total column weight = 24 x 0.4 x 0.4 x 3 x 6 x 2 =
138.24 kN
140
REFERENCES CALCULATIONS OUTPUT
Plan
Internal Frame
Dr. R. Clarke
Preliminary Calculating Vertical Distribution of Seismic
Design of Load
Structural
Members Notes Assuming equal spans in the shorter direction
Part A
Seismic Load, V = 0.1W = 0.1 x 2302.09 = 230.21 kN
Also, V = F1 + F2 + F3
Seismic
Load, V =
F2/F1 = 4/1 → F2 = 4F1 230.21 kN
F3/F2 = 7/4 → F3 = 1.75F2
F1 + F2 + F3 = 230.21
141
REFERENCES CALCULATIONS OUTPUT
F1 = 19.2 kN
F2 = 76.7 kN
F3 = 134.2
kN
Dr. R. Clarke
Preliminary
Design of
Structural
Members Notes
Part B 𝑀𝑎𝑐=Σ𝐹𝑖=2, 𝑛×ℎ1 / 2(𝑛𝑐𝑜𝑙−1)
𝑀𝑎𝑑=Σ𝐹𝑖=1, 𝑛×ℎ2 / 2(𝑛𝑐𝑜𝑙−1)
Mab = Mae = ½ (Mac + Mad)
External moment = ½ internal
moment
142
REFERENCES CALCULATIONS OUTPUT
Dr. R. Clarke
Preliminary
Design of
143
REFERENCES CALCULATIONS OUTPUT
Pa = 67.9 kN
Pb = 67.9 kN
Therefore,
MD, SUPPORT = -22.8 x 2.3 = -52.44 kNm
MD, SPAN = 22.8 x 1.8 = 41.04 kNm
ML, SUPPORT = -8.8 x 2.3 = -20.24 kNm
ML, SPAN = 8.8 x 1.8 = 15.84 kNm
144
REFERENCES CALCULATIONS OUTPUT
M D,
Calculate Gravity Moments in Columns support= -
By Moment Distribution of subframes 52.44kNm
MD, span =
41.04kNm
ML,
support = -
20.24kNm
ML, span
=
15.84kN
m
Dr. R. Clarke
Preliminary
Design of
Structural
Members Notes
Recall:
Part F
Beam depth, d = 700mm
Beam width, b = 400 mm
Therefore, I = (400x7003)/12 = 1.14 x 1010 mm4
External Column
145
REFERENCES CALCULATIONS OUTPUT
Therefore, As = 917.5mm2
Use 4 T18 bars = 1018mm2
Span Rebar
82.8 x 106 = 25.8 x 104As – 2.52As2
Therefore, As = 321.9 mm2
Use 3 T13 bars = 339.3mm2
ϕMn = 0.9 x 339.3 x 410 x (700 – (339.3 x 410)/ (0.85 x 30 x 400
x 2)) = 86.8 > 82.8kNm
Therefore OK
146
REFERENCES CALCULATIONS OUTPUT
Summary:
Therefore OK
Summary
147
REFERENCES CALCULATIONS OUTPUT
Use T9 at
External Column, MU = 1.4(90 x 22.8/22.8+ 8.8) + 0.5(90 x 8.8/22.8
+8.8) + 1.4(158.2) = 324.9 kNm 100mm c/c
spacing in
Ultimate Axial Loads: the
External Column, PU = 1.4(170.7) + 0.5(111.1/2) + 1.4(67.9) confineme
= 171.7 kN nt zone of
1000mm
from the
Therefore, Design (PU, MU): top and
bottom of
the
External Column = 171.7, 1.4x324.9= (171.7, 454.86) column.
Otherwise,
3 2
Kn = Pu/(ϕfc’Ag) = 171.7 x10 / (0.8 x30 x 400 ) = 0.04 use T9 at
Rn = MU / (ϕfc’Agh = 454.86 x10 / (0.8 x 30 x 400 ) = 0.30 200
6 3 c/c
spacing
Column Hoops:
148
REFERENCES CALCULATIONS OUTPUT
external column, use 2 legs in each direction with 2 cross ties and
one closed hoop.
Summary
149
COST ESTIMATION
CONCRETE
Total= 79.09 m3
REBAR
MASONRY
Consider 400 x 200 x 150 ASTM C90 unreinforced hollow concrete unit
150
GRADE SLAB
151
Community Centre
Alternative 2: Steel Special Moment Resisting Frame.
Figure 31: Sketch of the Community Centre Floor Plan for Steel Moment Resisting Frame
152
Calculation - Preliminary Structural Design of a Steel Framed for the Community Centre
REFERENC
CALCULATIONS OUTPUT
ES
Community Centre
PLAN
153
REFERENC
CALCULATIONS OUTPUT
ES
Beams Weight
No. of beams = 17
Maximum span = 8.95 m
Therefore, use beam sizes of 0.35m = 350
For d = (8950/26) + 300 = 644= 650mm = 0.650m
Total beam length = (24.49 x 3) + (18.30 x 4) = 134.4 m
No. of floors = 2
Therefore, total beam weight = 24 x 134.4 x 0.650 x 0.35 x 2 =
1467.6kN
Columns Weight
Maximum beam span = 8.95 m
Therefore, h = 0.35m
No. of columns = 12
Column height = 4m
No. of floors = 2
Therefore, total column weight = 24 x 0.35 x 0.35 x 4 x 12 x 2 =
282.24 kN
Plan
154
REFERENC
CALCULATIONS OUTPUT
ES
Internal Frame
F1 + F2 = 600.8
F1 + 1.67F1 = 600.8
2.67F1 = 600.8
F1 = 225.02 kN
Dr. R. Clarke
Preliminary F2 = 375.78 kN
Design of
Structural
Members Calculate Moments Due to Seismic Load in Longer
Notes Part 3 Direction
155
REFERENC
CALCULATIONS OUTPUT
ES
Live
Load= 11.2
kN/m
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part 2
156
REFERENC
CALCULATIONS OUTPUT
ES
Summary
24𝑃𝐴=1702.64 Pe =
𝑃𝐴= (1702.64/24) = 70.94𝑘𝑁 319.25kN
Therefore Pc = 70.94 kN
Therefore, PE = 1702.64 x 3/ (2 x 8) = 319.25
Kn
Dr. R. Clarke
Preliminary
157
REFERENC
CALCULATIONS OUTPUT
ES
Design of
Structural
Members
Notes Part 3
Therefore, M D,
support= -
MD, SUPPORT = -0.133 x 2 x 57.6 x 8 = -122.57 kNm
122.57kNm
MD, SPAN = 0.122 x 2 x 57.6 x 8 = 112.44 kNm MD, span =
ML, SUPPORT = -0.133 x 2 x 22.4 x 8 = -47.67 kNm 112.44kNm
ML, SPAN = 0.122 x 2 x 22.4 x 8 = 43.72 kNm ML, support
= -
Calculate Gravity Moments in Columns 47.67kNm
By Moment Distribution of subframes ML, span =
43.72 kNm
External Column
Dr. R. Clarke
Preliminary Since the subframe analysis requires the beams and column I’s which
Design of are not known yet. The following assumption was made:
Structural Mupper = 60% out-of-balance moment
Members Mlower = 35% out-of-balance moment
Notes Part 4 Therefore,
Mupper = 83.6 x 0.6 = 50.16 kNm
Mupper =
Mlower= 83.6 x 0.35 = 29.26 kNm
50.16 kNm
Mlower =
Calculate Gravity Axial Forces in Columns
29.26 kNm
Dead = 4 x 3.6 x 82 /2= 460.8 kN
Live = 460.8 x (1.4/3.6) =179.2
kN
Beam Size:
Consider U= 1.4D+0.5L+1.4E
Therefore, Mu = 1.4 x 122.57 + 0.5 x 47.67 + 1.4 x 212.83 = 493.4 kNm
For ASTM A992 Grade 50
Therefore, Zrequired = 493.4 x 106 / (0.9 x 345 x 103) = 1589.05 cm3 =
96.97in3
Use
Use W24 x 162 (468 > 96.97 in3: OK)
W24x162
Check Beam Local Buckling instability (i.e., Seismic
Compactness):
158
REFERENC
CALCULATIONS OUTPUT
ES
b/2tf= 5.31; λmax = 0.3√29000/50 = 7.22 > 5.31
159
REFERENC
CALCULATIONS OUTPUT
ES
VG = 2.69/18.3 = 0.15 → =1.15
Therefore, Drift= [5.5 (3 x 1.15-1)62/ (12 x 210 x 106 x 5.49 x10-3) x
(0.1 x 6008.4/2) x 100%= 1.05 <2% which is OK
Non-Seismic Beams:
Dr. R. Clarke
Consider U= (1.2D + 1.6L)
Preliminary
Design of MU= 1.2 x 122.57 + 1.6 x 47.67 = 223.36kNm
Structural Therefore Zrequired = 223.36 x 106 / (0.9 x 345 x 103) = 719.4cm3 = 43.9
Members in3
Notes Part Use W16 x 26 (44.2 >43.9 in3) which is OK
14-15
Non-Seismic Columns: Use
Consider U= (1.2D+1.6L) W14x99
Max moment on internal column, Mu= 1.6 x 29.26 x 2 = 93.63 kNm
Max axial force on internal column, PU = 1.2 x 460.8 x 2 + 1.6 x 179.2
x 2 =839.68kN = 188.77 kips
Effective height= 0.85 x 6000= 6800mm = 22.3ft
160
Cost Estimation
CONCRETE
Concrete for decking for 125mm equivalent thickness= 2 x 24.39 x 18.3 x 0.125 = 112.19 m3
STEEL WORK
Seismic beams = 10 x 8 x 3.28 x 262 x 0.46=31624.45kg
Seismic column =10 x 10 x 3.28 x 183 x 0.46= 27611.04kg
Non-seismic beams = 7 x 2 x 8 x 3.28 x 26 x 0.46= 4393.63kg
Non seismic columns = 2 x 10 x 0.46 x 99 x 3.28= 2987.42kg
Composite beams = 12 x 2 x 8 x 3.28 x 26 x 0.46= 7531.93kg
Total = 74148.47kg
Composite decking, 20 ft long x 25” wide= 2(24.39 x 3.28 x 12/25) 18.3 x 3.28= 4609.8ft
Decking BRC, 610 x 6 x 100= 2x (24.39 x 18.3)/ (30.5x1.8) = 16.26 rolls
161
Polyclinic
Figure 32: Sketch of the Policlinic Floor Plan for Steel Moment Resisting Frame
162
Calculation - Preliminary Structural Design of a Steel Framed for the Policlinic
REFEREN
CALCULATIONS OUTPUT
CES
Policlinic
PLAN
Dead Load = 3.6 kN/m2
Live Load = 1.4 kN/m2
Density of Normal weight concrete = 24 kN/m3
Beams Weight
No. of beams = 17
Maximum span = 8.00 m
Therefore, use beam sizes of 0.35m = 350
For d = (8000/26) + 300 = 607= 625mm = 0.625m
Total beam length = (24.40 x 3) + (15.30 x 4) = 134.4 m
No. of floors = 1
Therefore, total beam weight = 24 x 134.4 x 0.625 x 0.35 x 1 =
705.6kN
163
REFEREN
CALCULATIONS OUTPUT
CES
Columns Weight
Maximum beam span = 8.00 m
Therefore, h = 0.35m
No. of columns = 12
Column height = 3m
No. of floors = 1
Therefore, total column weight = 24 x 0.35 x 0.35 x 3 x 12 x 1
= 105.84 kN
Plan
Internal Frame
164
REFEREN
CALCULATIONS OUTPUT
CES
Dr. R. Clarke
Preliminary Calculating Vertical Distribution of Seismic
Design of Load
Structural
Members Assuming equal spans in the shorter direction
Notes Part 1
Seismic Load, V = 0.1W = 0.1 x 2608.32 = 260.83 kN
Also, V = F1
Seismic Load,
F1 = 260.83 kN V = 260.83kN
Dr. R. Clarke
Preliminary Calculate Moments Due to Seismic Load in Shorter
Design of Direction
Structural
Members Average Tributary width = (8.0+ 8.0 + 8.0)/2=8.0
Notes Part 2 m
Tributary
Dead Load = 3.6 x 8.0 = 28.8 kN/m
width = 8.0 m
Live Load = 1.4 x 8.0 = 11.2 kN/m
Dead
Load=28.8k
N/m
Live Load=
11.2kN/m
F2 = 0
F1 = (260.83) / (4-1) =86.94 kN
Moment of 1st floor internal column
Mac = 0 kNm
165
REFEREN
CALCULATIONS OUTPUT
CES
Summary
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part 3
166
REFEREN
CALCULATIONS OUTPUT
CES
Therefore,
MD, SUPPORT = -0.133 x 2 x 57.6 x 8 = -122.57 kNm
MD, SPAN = 0.122 x 2 x 57.6 x 8 = 112.44 kNm
ML, SUPPORT = -0.133 x 2 x 22.4 x 8 = -47.67 kNm
ML, SPAN = 0.122 x 2 x 22.4 x 8 = 43.72 kNm
MD, support=
Dr. R. Clarke -122.57kNm
Calculate Gravity Moments in Columns
Preliminary MD, span =
By Moment Distribution of subframes
Design of 112.44kNm
Structural ML, support =
External Column
Members -47.67kNm
Notes Part 5 Since the subframe analysis requires the beams and column I’s which ML, span =
are not known yet. The following assumption was made: 43.72kNm
Mupper = 60% out-of-balance moment
Mlower = 35% out-of-balance moment
Therefore,
Mupper = 1165.2 x 0.6 = 699.12 kNm
Mlower= 1165.2 x 0.35 = 407.82 kNm
167
REFEREN
CALCULATIONS OUTPUT
CES
Design of Dead = 4 x 3.6 x 82 /2= 460.8 kN Mupper =
Structural Live = 460.8 x (1.4/3.6) =179.2 0699.12kNm
Members kN Mlower =
Notes Part 6- Beam Size: 407.82kNm
11
Consider U= 1.4D+0.5L+1.4E
Use
Therefore, Mu = 1.4 x 122.57 + 0.5 x 47.67 + 1.4 x 130.25 = 377.78
W24x162
kNm
For ASTM A992 Grade 50
Therefore, Zrequired = 377.78 x 106 / (0.9 x 345 x 103) = 1216.68 cm3 =
74.25in3
Use W24 x 162 (468 > 74.25 in3: OK)
Check Beam Local Buckling instability (i.e., Seismic
Compactness):
168
REFEREN
CALCULATIONS OUTPUT
CES
Mupper = 1165.2 x 0.55 = 640.86 kNm
Dr. R. Clarke Mlower = 1165.2 x 0.38 = 442.78 kNm
Preliminary
Design of Check Column Local Buckling:
Structural
Members b/2tf= 4.92; λmax = 0.3√29000/50 = 7.22> 4.92 which is OK
Notes Part 12 h/w = 52.6; λmax = 2.45√29000/50 = 59> 52.6 which is OK
Check Drift:
For the beam and column sizes selected:
Beam W24 x 262 Ixx = 5170
Column W40 x 183 Ixx = 13200
Consider U=1.4D+0.5L+1.4E
PU= 1.4 x 460.8 + 0.5 x 179.2 + 1.4 x 97.8 = 871.64Kn
λc= 1.1 x 6 x 3.28 x 12 x √ (50/29000)/ (3.14 x 2.49) = 1.4 →
1.96
Fcr = 0.6581.96 x 50 = 22 ksi
Therefore,
ФPn=v0.8FcrA= 0.8 x 22 x 53.3 = 938.1 kip= 4172.9 kN
Dr. R. Clarke PU/ФPn = 871.64/ 4172.9= 0.21 > 0.2
Preliminary As the-out-of-balance load is due to the live load,
Design of MUZ = 0.5 x 407.82 + 1.4 x 260.82= 569.1kNm
Structural Column moment strength, Mnz = ZcFyc = 13200 x 50 = 660000 kip-in =
Members 54999.9 kip-ft
Notes Part Therefore
Use W16x26
14-15 demand factor= 0.21/2 + 8/9(569.1/0.8 x 54999.9 x 1.35) =
0.11< 1 which is OK
Non-Seismic Beams:
Consider U= (1.2D + 1.6L)
MU= 1.2 x 122.57 + 1.6 x 47.67 = 223.36kNm
Therefore Zrequired = 223.36 x 106 / (0.9 x 345 x 103) = 719.4cm3 = 43.9
in3
169
REFEREN
CALCULATIONS OUTPUT
CES
Use W16 x 26 (44.2 >43.9 in3) which is OK Use
W14x145
Non-Seismic Columns:
Consider U= (1.2D+1.6L)
Max moment on internal column, Mu= 1.6 x 407.82 x 2 = 1305 kNm
Max axial force on internal column, PU = 1.2 x 460.8 x 2 + 1.6 x 179.2
x 2 =839.68kN = 188.77 kips
Effective height= 0.85 x 6000= 6800mm = 22.3ft
Therefore, Zrequired= (1305 x 106)/ (0.9 x 345x 103) = 4202.9cm3
= 256.5in3
Use W 14 x 145
170
Cost Estimation
CONCRETE
Concrete for decking for 125mm equivalent thickness= 1 x 24.0 x 14.9 x 0.125 = 44.7 m3
Footings (assume pad footing 2.4 x 2.4 x 0.4) = 12 x 2.42 x 0.4 = 27.65 m3
STEEL WORK
Seismic beams = 10 x 8 x 3.28 x 262 x 0.46=31624.45kg
Seismic column =10 x 6 x 3.28 x 183 x 0.46= 16566.62kg
Non-seismic beams = 7 x 1 x 8 x 3.28 x 26 x 0.46= 2196.8kg
Non seismic columns = 2 x 6 x 0.46 x 145 x 3.28= 2601.3kg
Composite beams = 12 x 1 x 8 x 3.28 x 26 x 0.46= 3765.96kg
Total = 56755.13kg
Composite decking, 20 ft long x 25” wide= 1(24 x 3.28 x 12/25) 14.9 x 3.28= 1846.66ft
Decking BRC, 610 x 6 x 100= 1 x (24 x 14.9)/ (30.5x1.8) = 7 rolls
171
Double Bedroom Apartment Complex
Figure 33: Sketch of the Double Bedroom Apartment Complex Ground, 1st, 2nd&,3rd Floor
Plan for Steel Moment Resisting Frame
172
Calculation - Preliminary Structural Design of a Steel Framed for the Double Bedroom Apartment
Complex Ground, 1st, 2nd ,3rd & 4th Floor Plan
REFERENC
CALCULATIONS OUTPUT
ES
Double Bedroom Apartment Complex
PLAN
Beams Weight
No. of beams = 67
Maximum span = 5.59 m
Therefore, use beam sizes of 0.35m = 350
For d = (5590/26) + 300 = 515 = 550mm = 0.55m
Total beam length = (62.75 x 3) + (10.05 x 14) = 328.9 m
No. of floors = 5
Therefore, total beam weight = 24 x 328.9 x 0.55 x 0.35 x 5 =
7597.6kN
Columns Weight
Maximum beam span = 5.59 m
Therefore, h = 0.5m
No. of columns = 42
Column height = 3m
No. of floors = 5
173
REFERENC
CALCULATIONS OUTPUT
ES
Therefore, total column weight = 24 x 0.5 x 0.5 x 3 x 42 x 5 = 3780
kN
Total
Building Total Weight, W Building
W = 11504 + 7597.6 + 3780 = 22881.6 kN Weight, W
= 27456.72
Connection Preliminary Design kN
Seismic Load:
Increasing building weight by 20% (catering for connections)
22881.6 x (120/100) = 27456.72kN
Plan
Internal Frame
174
REFERENC
CALCULATIONS OUTPUT
ES
F2/F1 = 7/4 → F2 = 1.75F1
F1 + F2 + F3 + F4 + F5= 2745.67
F1 + 1.75F1 + (1.4 x 1.75) F1+(1.3 x 1.4 x 1.75) F1+(1.2 x 1.3 x 1.4 x 1.75) F1
= 2745.67
12.2F1 = 2745.67
F1 = 225.05 kN
F2 = 393.85 kN
F3 = 551.38 kN
F4 = 716.8 kN
F5 = 860.16 kN
Tributary
width = 4.8
Calculate Moments Due to Seismic Load in Shorter Direction m
Dead
Average Tributary width = (4.06+5.59)/2=4.8 Load=17.
m 3 kN/m
Dead Load = 3.6 x 4.8 = 17.3 kN/m Live
Live Load = 1.4 x 4.8 = 6.72 kN/m Load=
6.72kN/m
175
REFERENC
CALCULATIONS OUTPUT
ES
F2 = (393.85+551.38+716.8+860.16) / (3-1)
= 1261.1kN
F1 = (225.05+393.85+551.38+716.8+860.16) / (3-1)
=1373.62 kN
176
REFERENC
CALCULATIONS OUTPUT
ES
Summary
177
REFERENC
CALCULATIONS OUTPUT
ES
MO =
16125.96
kNm
Pa =
1479.45k
Dr. R. Clarke N
Preliminary Pb
Design of =235.85k
Structural N
Members
Notes Part 3
PE
Overturning Moment, Mo = [(225.05 x 4) + (393.85 x 7) + =5039.36
(551.38 x 10) + (716.8 x13) + (860.16 x 16)] / [ 3-1] = 16125.96 kN
kNm
178
REFERENC
CALCULATIONS OUTPUT
ES
M D,
support= -
37.43kNm
Dr. R. Clarke MD, span =
Preliminary 31.06kNm
Design of ML,
Structural support = -
Members 14.62kNm
Notes Part 4 WD = 3.6 x (4.8/2) x (4.8/2) = 20.74 kN ML, span
WL =20.74 x (1.4/3.6) = 8.1 kN =
12.13kN
Therefore, m
MD, SUPPORT = -0.188 x 2 x 20.74 x 4.8 = -37.43 kNm
MD, SPAN = 0.156 x 2 x 20.74 x 4.8 = 31.06 kNm
ML, SUPPORT = -0.188 x 2 x 8.1 x 4.8 = -14.62kNm
ML, SPAN = 0.156 x 2 x 8.1 x 4.8 = 12.13 kNm
179
REFERENC
CALCULATIONS OUTPUT
ES
Therefore, Mu = 1.4 x 37.43 + 0.5 x 14.62 + 1.4 x 1159.72 = 1683.32
Dr. R. Clarke kNm
Preliminary For ASTM A992 Grade 50
Design of Therefore, Zrequired = 1683.32 x 106 / (0.9 x 345 x 103) = 5421.32 cm3 =
Structural 330.83in3
Members Use W30 x 108 (346 > 330.83 in3: OK)
Notes Part 5- Check Beam Local Buckling instability (i.e., Seismic Compactness):
9
180
REFERENC
CALCULATIONS OUTPUT
ES
Check Drift:
For the beam and column sizes selected:
Beam W30 x 108 Ixx = 4470
Column W33 x 354 Ixx = 22000
Consider U=1.4D+0.5L+1.4E
PU= 1.4 x 124.42+ 0.5 x 48.39 + 1.4 x 5039.36 = 7253.49 KN
λc= 1.1 x 4 x 3.28 x 12 x √ (50/29000)/ (3.14 x 3.74) = 0.61 → 0.37
Fcr = 0.6580.37 x 50 = 42.8 ksi
Therefore,
ФPn=v0.8FcrA= 0.8 x 42.8 x 104 = 3569.281 kip= 15876.95 kN
PU/ФPn = 7253.49/ 15876.95= 0.46 > 0.2
As the-out-of-balance load is due to the live load,
MUZ = 0.5 x 4.52 + 1.4 x 1373.62= 1925.33kNm
Column moment strength, Mnz = ZcFyc = 1420 x 50 = 71000 kip-in = 5916.6
kip-ft
Therefore
demand factor= 0.46/2 + 8/9(1925.33/0.8 x 5916.6 x 1.35) = 0.48<
1 which is OK
Non-Seismic Beams:
Consider U= (1.2D + 1.6L)
MU= 1.2 x 37.43 + 1.6 x 14.63 = 68.32kNm
Therefore Zrequired = 68.32 x 106 / (0.9 x 345 x 103) = 220.3 cm3 = 13.44
in3
Use W16 x 26 (44.2>13.44 in3) which is OK
Dr. R. Clarke
Preliminary Non-Seismic Columns: Use
Design of Consider U= (1.2D+1.6L) W10x12
Structural Max moment on internal column, Mu= 1.6 x 4.52 x 2 = 14.46 kNm
Members Max axial force on internal column, PU = 1.2 x 124.42 x 2 + 1.6 x 48.39
Notes Part x 2 =453.46kN = 101.95 kips
13-15 Effective height= 0.85 x 4000= 3400mm = 11.2ft
181
REFERENC
CALCULATIONS OUTPUT
ES
182
Cost Estimation
CONCRETE
Concrete for decking for 125mm equivalent thickness= 5 x 62.75 x 10.05 x 0.125 = 394.15m3
Footings (assume pad footing 2.9 x 2.9 x 0.6) = 42 x 2.92 x 0.6 = 211.93 m3
STEEL WORK
Seismic beams = 30 x 4.8 x 3.28 x 108 x 0.46=23464.86kg
Seismic column =18 x 16 x 3.28 x 354 x 0.46= 153825.2kg
Non-seismic beams = 37 x 5 x 4.8 x 3.28 x 26 x 0.46= 34835.17kg
Non seismic columns = 24 x 16 x 0.46 x 12 x 3.28= 6952.55kg
Composite beams = 52 x 5 x 4.8 x 3.28 x 26 x 0.46= 48957.54kg
Total = 268035.32kg
Composite decking, 20 ft long x 25” wide= 5(62.75 x 3.28 x 12/25) 10.05 x 3.28= 17012.26ft
Decking BRC, 610 x 6 x 100= 5 x (62.75 x 10.05)/ (30.5x1.8) = 57.44 rolls
183
Single Bedroom Apartment Complex
Figure 34: Sketch of the Single Bedroom Apartment Complex Ground, 1st & 2nd Floor Plan
for Steel Moment Resisting Frame
184
Calculation - Preliminary Structural Design of a Reinforced Concrete Framed for the Single
Bedroom Apartment Complex Ground, 1st & 2nd Floor Plan
REFERENC OUTPU
CALCULATIONS
ES T
Single Bedroom Apartment Complex
PLAN
Dead Load = 3.6 kN/m2
Live Load = 1.4 kN/m2
Density of Normal weight concrete = 24 kN/m3
Columns Weight
Maximum beam span = 6.86 m
Therefore, h = 0.4m
No. of columns = 30
Column height = 3m
No. of floors = 3
185
REFERENC OUTPU
CALCULATIONS
ES T
Therefore, total column weight = 24 x 0.4 x 0.4 x 3 x 30 x 3 = 1036.8
kN Total
Building
Weight,
Building Total Weight, W W
W = 7080 + 3487.1 + 1036.8 = 11604kN =13924.8
kN
Connection Preliminary Design
Seismic Load:
Increasing building weight by 20% (catering for connections)
11604 x (120/100) = 13924.8kN
Plan
Internal Frame
186
REFERENC OUTPU
CALCULATIONS
ES T
F3/F2 = 10/7 → F3 = 1.4F2
F1 + F2 + F3 = 1392.48
F1 + 1.75F1 + (1.75 x 1.4) F1 =
1392.48
5.2F1 = 1392.48
F1 = 267.78 kN
F2 = 468.62 kN
F3 = 656.07 kN
Dr. R. Clarke
Calculate Moments Due to Seismic Load in Shorter
Preliminary
Direction
Design of
Structural Tributar
Average Tributary width = (4.11+6.17)/2=5.14
Members y width =
m
Notes Part 2 5.14 m
Dead Load = 3.6 x 5.14 = 18.5 kN/m
Dead
Live Load = 1.4 x 5.14 = 7.2 kN/m
Load=18
.5 kN/m
Live
Load=
7.2kN/m
187
REFERENC OUTPU
CALCULATIONS
ES T
Summary
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part 3
188
REFERENC OUTPU
CALCULATIONS
ES T
189
REFERENC OUTPU
CALCULATIONS
ES T
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part 5
Dr. R. Clarke
Preliminary MD,
Therefore, support=
Design of
Structural -
MD, SUPPORT = -0.188 x 2 x 23.78 x 5.14 = -45.96 kNm 45.96kN
Members
MD, SPAN = 0.156 x 2 x 23.78 x 5.14 = 38.14 kNm m
Notes Part 6- MD, span
11 =
ML, SUPPORT = -0.188 x 2 x 9.25 x 5.14 = -17.88 kNm
38.14kN
ML, SPAN = 0.156 x 2 x 9.25 x 5.14 = 14.83 kNm m
ML ,
support =
-
17.88kN
m
ML,
span =
14.83kN
m
190
REFERENC OUTPU
CALCULATIONS
ES T
191
REFERENC OUTPU
CALCULATIONS
ES T
Dr. R. Clarke Beam plastic moment strength, Mp= FyZ= 50 x 346/12= 1441.67 kip-
Preliminary ft
Design of Beam depth = 29.8 in
Structural Therefore,
Members Shear force in plastic hinge, Vp = 2 x 1441.67/ (5.14 x 3.28-2 x 1.6 x
Notes Part 13 29.8/12) + 1.2(18.5 + 7.2) x 0.74(5.14 x 3.28 – 2 x 1.6 x 29.8/12)/2 =
517.61 kip = 2302.44kN
Consider U=1.4D+0.5L+1.4E
PU= 1.4 x 142.67 + 0.5 x 55.48 + 1.4 x 1592.24 = 2456.6 kN
λc= 1.1 x 4 x 3.28 x 12 x √ (50/29000)/ (3.14 x 3.32) = 0.69 → 0.48
Fcr = 0.6580.48 x 50 = 40.9 ksi
Therefore,
192
REFERENC OUTPU
CALCULATIONS
ES T
ФPn=v0.8FcrA= 0.8 x 40.9 x 63.9 = 2090.81 kip= 9300.39 kN
PU/ФPn = 2456.6/ 9300.39= 0.26 > 0.2
As the-out-of-balance load is due to the live load,
MUZ = 0.5 x 9.87 + 1.4 x 696.24= 979.67kNm
Column moment strength, Mnz = ZcFyc = 711 x 50 = 35550 kip-in = 2962.5
kip-ft
Therefore
Non-Seismic Columns:
Consider U= (1.2D+1.6L)
Max moment on internal column, Mu= 1.6 x 9.87 x 2 = 31.58 kNm
Max axial force on internal column, PU = 1.2 x 142.67 x 2 + 1.6 x
55.48 x 2 =259.97kN = 58.44 kips
Effective height= 0.85 x 4000= 3400mm = 11.2ft
193
REFERENC OUTPU
CALCULATIONS
ES T
Use
W10x12
194
Cost Estimation
CONCRETE
Concrete for decking for 125mm equivalent thickness= 3 x 59.80 x 10.28 x 0.125 = 280.32m3
Footings (assume pad footing 2.4 x 2.4 x 0.5) = 30 x 2.42 x 0.5 = 86.3 m3
STEEL WORK
Seismic beams = 22 x 5.14 x 3.28 x 108 x 0.46=18426.43kg
Seismic column = 14 x 10 x 3.28 x 217 x 0.46= 45837.34kg
Non-seismic beams = 21 x 3 x 5.14 x 3.28 x 31 x 0.46= 15145.97kg
Non seismic columns = 16 x 10 x 0.46 x 12 x 3.28= 2896.9kg
Composite beams = 36 x 3 x 5.14 x 3.28 x 31 x 0.46= 25964.52kg
Total =108271.16kg
Composite decking, 20 ft long x 25” wide= 3(59.78 x 3.28 x 12/25) 10.28 x 3.28= 9520.49ft
Decking BRC, 610 x 6 x 100= 3 x (59.78 x 10.28)/ (30.5x1.8) = 33.58 rolls
ITEM AMOUNT UNIT RATE (TT$) TOTAL (TT$)
Conc. for decking 366.62 m3 1380.00 505,935.60
Decking 9520.49 ft 22 209,450.78
BRC for decking 33.58 Nr. rolls 598.2 20,087.56
Steelwork 108271.16 kg 21.1 2,284,521.48
Accessories (end plates, bolts,
571130.37
etc. @ 25%
Blocks (inc. mortar) 491029.10
Labour for blocks @ 65% 319168.91
Grade slab 166,467.30
TOTAL STRUCTURAL 4,567,791.09
TOTAL SERVICES 2,283,895.55
TOTAL ARCHITECTURAL 12,789,815.05
TOTAL STR, SERV, ARCH 19,641,501.69
Preliminaries @ %5 982075.08
Contingency @ 15% 3,093,536.52
CONSTRUCTION COST 23,717,113.29
Overhead & Profit @ 30% 7,115,133.99
GRAND TOTAL TT$
30,832,247.28
Therefore, Total Cost= Grand Total x No. of Structure=$ 30,832,247.28 x 4
=$123,328,989.10
195
Two (2) Bedroom Triplex
Figure 35: Sketch of the Two (2) Bedroom Triplex Floor Plan for Steel Moment Resisting
Frame
196
Calculation – Preliminary Structural Design of a Steel Framed for the Two (2) Bedroom Triplex
Building.
REFERENCE
CALCULATIONS OUTPUT
S
Three (3) Bedroom Duplex
PLAN
Dr. R. Clarke Dead Load = 3.6 kN/m2
Preliminary Live Load = 1.4 kN/m2
Design of Density of Normal weight concrete = 24 kN/m3
Structural
Members Notes Calculating Building Weight
Part 1
Floor Slabs Weight
Floor slab area = 188.7 m2
Thickness, h=6in = 0.153 m
Density of concrete = 24 kN/m3
Floor slab weight = 24 x 188.7 x 0.153 = 692.9kN
No. of floor slabs = 2
Therefore, total floor slab weight = 692.9 x 2 = 1385.8
kN
Beams Weight
No. of beams = 10
Maximum span = 9.69 m
Therefore, use beam sizes of 0.4m = b
For d = (9690/26) + 300 = 679.7 = 700mm = 0.7m
Total beam length = (29.07 x 2) + (6.00 x 4) = 82.14 m
No. of floors = 2
Therefore, total beam weight = 24 x 82.14 x 0.7 x 0.4 x 2 =
1104kN
Columns Weight
Maximum beam span = 9.69 m
Therefore, h = 0.4m
No. of columns = 8
Column height = 3m
No. of floors = 2
197
REFERENCE
CALCULATIONS OUTPUT
S
Therefore, total column weight = 24 x 0.4 x 0.4 x 3 x 8 x 2
= 184.32 kN
Plan
Internal Frame
F1 + F2 = 320.89
F1 + 1.75F1 = 32.89
198
REFERENCE
CALCULATIONS OUTPUT
S
2.75F1 = 320.89
F1 = 116.69kN
F2 = 204.20kN
199
REFERENCE
CALCULATIONS OUTPUT
S
Moment of 1st floor internal column
Mac = [(80.06) x 3] / 2(4-1) = 40.03 kNm
Summary
Dr. R. Clarke
Preliminary
Design of
Structural Calculate Axial Loads Due to Seismic Loads
Members Notes
Part 3
200
REFERENCE
CALCULATIONS OUTPUT
S
Overturning Moment, Mo = [(116.69 x 4) + (204.20 x 7)] /
MO = 632.1
[ 4-1] = 632.1 kNm
kNm
Pa = 65.23 kN
Pa = Pb
Pb = 65.23 Kn
Taking moments about Centreline:
9.69Pa = Mo PE = 98 Kn
Pa = 632.1/9.69
Pa = 65.23 kN
Pb = 65.23 kN
Dr. R. Clarke
Preliminary Calculate Gravity Moments in Beams
Design of
Structural Consider as a continuous beam and use standard
tables
Members Notes
Part 4
Therefore,
MD, SUPPORT = -0.133 x 2 x 84.52 x 9.69 = -217.85 kNm
MD, SPAN = 0.122 x 2 x 84.52 x 9.69 = 199.84 kNm MD, support=
ML, SUPPORT = -0.133 x 2 x 32.76 x 9.69 = -84.44 kNm 217.85kNm
ML, SPAN = 0.122 x 2 x 32.76 x 9.69 = 77.46 kNm MD, span =
199.84kNm
Calculate Gravity Moments in Columns ML, support =
84.44kNm
Dr. R. Clarke By Moment Distribution of subframes
Preliminary
201
REFERENCE
CALCULATIONS OUTPUT
S
Design of External Column ML, span =
Structural 77.46kNm
Members Notes Since the subframe analysis requires the beams and column I’s
Part 5 which are not known yet. The following assumption was made:
Mupper = 60% out-of-balance moment
Mlower = 35% out-of-balance moment
Therefore,
Mupper = 84.5 x 0.6 = 50.7 kNm
Mlower= 84.5 x 0.35 = 29.58 kNm
Mupper =
Calculate Gravity Axial Forces in Columns 50.7 kNm
Mlower =
Dead = 4 x 3.6 x 9.692 /2= 676.05 kN 29.58 kNm
Live = 676.05x (1.4/3.6) =262.90 kN
Beam Size:
Dr. R. Clarke Consider U= 1.4D+0.5L+1.4E
Preliminary Therefore, Mu = 1.4 x 217.85 + 0.5 x 84.44 + 1.4 x 65.1= 438.35
Design of kNm
Structural For ASTM A992 Grade 50
Members Notes Therefore, Zrequired = 438.35 x 106 / (0.9 x 345 x 103) = 1411.76
Part 6-11
cm3 =86.15in3
Use W14 x 132 (234 >86.15 in3: OK)
Check Beam Local Buckling instability (i.e., Seismic
Compactness): Use W14x132
202
REFERENCE
CALCULATIONS OUTPUT
S
Shear force in plastic hinge, Vp = 2 x 975/ (9.69 x 3.28-2 x 1.6 x
14.7/12) + 1.2(34.88 + 13.57) x 0.74(9.69 x 3.28 – 2 x 1.6 x
14.7/12)/2 = 751.73 kip =3343.86kN
OK
Dr. R. Clarke
Preliminary
Design of
Check Drift:
Structural
Members Notes For the beam and column sizes selected:
Part 12 Beam W14 x 132 Ixx = 1530
Column W24 x 176 Ixx = 5680
203
REFERENCE
CALCULATIONS OUTPUT
S
Members Notes λc= 1.1 x 4 x 3.28 x 12 x √ (50/29000)/ (3.14 x 3.76) = 0.6
Part 13
→ 0.36
Fcr = 0.6580.36 x 50 = 43 ksi
Therefore,
ФPn=v0.8FcrA= 0.8 x 43 x 51.7 = 1778.48 kip= 7911 kN
PU/ФPn = 1346.6/ 7911= 0.2 =0.2
As the-out-of-balance load is due to the live load,
MUZ = 0.5 x 29.58 + 1.4 x 110.5= 169.49kNm
Column moment strength, Mnz = ZcFyc = 511x 50 = 25550 kip-in =
2129.17 kip-ft
Therefore
demand factor= 0.2/2 + 8/9(169.49/0.8 x 2129.17 x 1.35) = Use W16x45
0.16 < 1 which is OK
Dr. R. Clarke Non-Seismic Beams:
Preliminary Consider U=1.2D + 1.6L
Design of MU= 1.2 x 217.85 + 1.6 x 84.44 = 396.52kNm
Structural Therefore Zrequired = 396.52 x 106 / (0.9 x 345 x 103) = 1277.04
Members Notes cm3 = 77.9 in3
Part 14-15 Use W16 x 45 (82.3 >77.9 in3) which is OK
Non-Seismic Columns:
Consider U= (1.2D+1.6L)
Use W12x16
Max moment on internal column, Mu= 1.6 x 29.58 x 2 = 94.66
kNm
Max axial force on internal column, PU = 1.2 x 676.05 x 2 + 1.6
x 265.90 x 2 =2473.4kN = 556.04 kips
Effective height= 0.85 x 4000= 3400mm = 11.2ft
204
Cost Estimation
CONCRETE
Concrete for decking for 125mm equivalent thickness= 2 x 29.07 x 6.0 x 0.125 =43.61m3
Footings (assume pad footing 2.25 x 2.25 x 0.4) = 8 x 2.252 x0.4 = 16.2 m3
STEEL WORK
Seismic beams = 8 x 9.69 x 3.28 x 132 x 0.46= 15439kg
Seismic column = 4 x 7 x 3.28 x 176 x 0.46= 7562.11kg
Non-seismic beams = 2 x 2 x 9.69 x 3.28 x 45 x 0.46= 2631.65kg
Non seismic columns =4 x 7 x 0.46 x 16 x 3.28= 657.94kg
Composite beams = 6 x 2 x 9.69 x 3.28 x 45 x 0.46= 7894.95kg
Total =34185.65kg
Composite decking, 20 ft long x 25” wide= 2(29.07 x 3.28 x 12/25) 6 x 3.28= 1801.421ft
Decking BRC, 610 x 6 x 100=2 x (29.07 x 6)/ (30.5x1.8) = 6.35 rolls
205
Calculation - Preliminary Structural Design of a Steel Framed Three (3) Bedroom Building.
REFERENC OUTPU
CALCULATIONS
ES T
Three (3) Bedroom
PLAN
206
REFERENC OUTPU
CALCULATIONS
ES T
Beams Weight
No. of beams = 7
Maximum span = 9.60 m
Therefore, use beam sizes of 0.4m = b
For d = (9600/26) + 300 = 669.23 = 700mm = 0.7m
Total beam length = (12.64 x 2) + (9.60 x 3) = 54.08 m
No. of floors = 1
Therefore, total beam weight = 24 x 54.08 x 0.7 x 0.4 x 1 =
368.42kN
Columns Weight
Maximum beam span = 9.60 m
Therefore, h = 0.4m
No. of columns = 6
Column height = 3m
No. of floors = 1
Therefore, total column weight = 24 x 0.4 x 0.4 x 3 x 6 x 1 = 69.12
kN
Total
Building Total Weight, W
Building
W = 958.02 + 368.42 + 69.12 = 1395.6kN Weight,
W =
Connection Preliminary Design 1674.72
Seismic Load: kN
Increasing building weight by 20% (catering for
connections)
1395.6 x (120/100) =1674.72kN
207
REFERENC OUTPU
CALCULATIONS
ES T
Plan
Internal Frame
208
REFERENC OUTPU
CALCULATIONS
ES T
Dr. R. Clarke Dead
Preliminary Load=22
Design of .8 kN/m
Structural Live
Members Load=
Notes Part 2 8.8kN/m
F1 = (167.5) / (3-1)
=83.8 kN
Therefore,
MAC= 0 kNm
MAD= (167.6 x 4)/2= 335.2 kNm
209
REFERENC OUTPU
CALCULATIONS
ES T
Summary
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part 3
210
REFERENC OUTPU
CALCULATIONS
ES T
Pa = Pb MO =
335kNm
Taking moments about Centreline: Pa =
34.89 kN
9.6Pa = Mo Pb =
34.89 Kn
Pa = 335/9.6
Pa = 34.89 kN PE = 69.8
Kn
Pb = 34.89 kN
Dr. R. Clarke
Preliminary
Design of
Structural
Members
Notes Part 4
Therefore,
MD, SUPPORT = -0.188 x 1 x 35.95 x 6.32 = - 42.71
KNm
MD, SPAN = 0.156 x 2 x 35.95 x 6.32 = 17.54 kNm
ML, SUPPORT = -0.188 x 1 x 13.98 x 6.32 = -16.61 kNm
211
REFERENC OUTPU
CALCULATIONS
ES T
ML, SPAN = 0.156 x 2 x 13.98 x 6.32 = 27.57 kNm
MD,
Calculate Gravity Moments in Columns support=
By Moment Distribution of subframes -
42.71kN
External Column m
Since the subframe analysis requires the beams and column I’s which are MD, span
not known yet. The following assumption was made: =
Mupper = 60% out-of-balance moment 17.54kN
Mlower = 35% out-of-balance moment m
Therefore, ML ,
Mupper = 175.1 x 0.6 = 106.06 kNm support =
-
Mlower= 175.1 x 0.35 = 61.29 kNm
16.61kN
m
Calculate Gravity Axial Forces in Columns ML,
span =
Dead = 3.6 x 4 x 9.62 /2= 663.6 kN 27.57kN
Live = 662.6 x (1.4/3.6) =258.1 m
kN
Dr. R. Clarke Beam Size: Mupper =
Preliminary Consider U= 1.4D+0.5L+1.4E 106.06
Design of Therefore, Mu = 1.4 x 42.71 + 0.5 x 16.61 + 1.4 x 82.50= 183.60 kNm
Structural kNm Mlower =
Members For ASTM A992 Grade 50 61.29
Notes Part 5 kNm
Therefore, Zrequired = 183.60 x 106 / (0.9 x 345 x 103) = 591.30 cm3
=36.08in3
Use W18 x 130 (198 >36.08 in3: OK)
212
REFERENC OUTPU
CALCULATIONS
ES T
Beam plastic moment strength, Mp= FyZ= 50 x 290/12= 1208.3kip-
Dr. R. Clarke ft
Preliminary Beam depth = 19.3in
Design of Therefore,
Structural Shear force in plastic hinge, Vp = 2 x 1208.3/ (6.32 x 3.28-2 x 1.6 x
Members 19.3/12) + 1.2(22.8 + 8.8) x 0.74(6.32 x 3.28 – 2 x 1.6 x
Notes Part 7- 19.3/12)/2=373.67 kip =1662.17kN
11
Moment due to Vp= 373.67 x 1.6 x 19.3/12= 961.58-kip ft
Σ𝑀𝑝𝑏= 1.1 x 1.1 x 1208.9 +961.58 = 2424.35 kip-ft
Σ𝑀𝑝𝑐= 2Zcx50
Therefore 2Zcx50= 1.5x 2424.35 x 12 →436.4in3
Use W24x 162 (468>436.4 in3)
Check:
Mupper = 55% out-of-balance moment
Mlower = 38% out-of- balance moment
Therefore,
Dr. R. Clarke Mupper = 175.1 x 0.55 = 96.31kNm Use
Preliminary Mlower = 175.1 x 0.38 = 66.58 kNm W24x162
Design of
Structural Check Column Local Buckling:
Members b/2tf= 5.31; λmax = 0.3√29000/50 = 7.22> 5.31 which is
Notes Part 12 OK
Mupper =
h/w = 30.6; λmax = 2.45√29000/50 = 59> 30.6 which is OK 96.31
kNm
Check Drift:
Mlower =
For the beam and column sizes selected:
66.58
Beam W18 x 130 Ixx = 2460 kNm
Column W24 x 162 Ixx = 5170
Dr. R. Clarke
Ib */L = 2460 x 0.02544/9.60 = 1.07 x 10-4.
Preliminary
Ic */h = 2 x 5170 x 0.02544/4 = 1.08 x 10-3
Design of
VG = 1.07/10.8=0.1 → =1.39
Structural
Members Therefore, Drift= [5.5 (3 x 1.39-1)42/ (12 x 210 x 106 x 2.15 x 10-3)
Notes Part 13 x (0.1 x 1099.86/2) x 100%= 0.28 <2% which is OK
Consider U=1.4D+0.5L+1.4E
PU= 1.4 x 663.6 + 0.5 x 258.1 + 1.4 x 69.8 = 1155.81Kn
λc= 1.1 x 4 x 3.28 x 12 x √ (50/29000)/ (3.14 x 2.7) = 0.85 → 0.72
213
REFERENC OUTPU
CALCULATIONS
ES T
Fcr = 0.6580.72 x 50 = 37 ksi
Therefore,
ФPn= 0.8 x 37 x 38.3 = 1133.7 kip=5042.9 kN
PU/ФPn = 1155.81/5042.9= 0.23>0.2
As the-out-of-balance load is due to the live load,
MUZ = 0.5 x 61.29 + 1.4 x 83.75= 147.9kNm
Column moment strength, Mnz = ZcFyc = 100x50 = 5000 kip-in =416.7 kip-
Dr. R. Clarke ft
Preliminary Therefore
Design of
Structural demand factor= 0.23/2 + 8/9(147.7/0.8 x 416.7 x 1.35) = 0.40
Members < 1 which is OK
Notes Part 14-
15
Non-Seismic Beams:
Consider U=1.2D + 1.6L
MU= 1.2 x 42.71 + 1.6 x 16.61 = 77.83kNm
Therefore Zrequired = 77.83 x 106 / (0.9 x 345 x 103) = 244.29cm3 =
14.9 in3
Use W10 x 15 (16 >14.9 in3) which is OK
Non-Seismic Columns:
Consider U= (1.2D+1.6L)
Max moment on internal column, Mu= 1.6 x 61.29 x 2 =
196.13kNm
Max axial force on internal column, PU = 1.2 x 663.6 x 2 + 1.6 x
258.1 x 2 =2418.56kN = 543.71 kips
Effective height= 0.85 x 4000= 3400mm = 11.2ft Use
W10x15
Therefore, Zrequired= (196.13 x 106)/ (0.9 x 345x 103) = 631.66cm3 =
38.55in3
Use W 8x35
Use
W8x35
214
COST ESTIMATION
CONCRETE
Concrete for decking for 125mm equivalent thickness= 1 x 10 x 13.05 x 0.125 =16.31 m3
STEEL WORK
Seismic beams = 6 x 4.8 x 3.28 x 130 x 0.46=5648.95kg
Seismic column = 4 x 4 x 3.28 x 162 x 0.46= 3910.81 kg
Non-seismic beams = 1 x 1 x 4.8 x 3.28 x 15 x 0.46= 108.63kg
Non seismic columns =2 x 4 x 0.46 x 35 x 3.28= 422.46kg
Composite beams = 4 x 1 x 4.8 x 3.28 x 15 x 0.46= 434.53kg
Total =10525.38kg
Composite decking, 20 ft long x 25” wide= 1(12.64 x 3.28 x 12/25) 9.6 x 3.28=626.62ft
Decking BRC, 610 x 6 x 100=1 x (12.64 x 9.6)/ (30.5x1.8) = 2.21 rolls
215
3.3.2 Pavement Design
This section focuses on the pavement design within the community. Pavement design is a
principal factor to consider when creating developments. These road networks help with ease of
access in and around the site. Major factors that need to be considered when designing the road
network within a residential community include the ease of accessibility to and around homes
and other structures, and the flow of traffic (in order to avoid congestion). The main aim of the
structural design of pavements is to determine the material constituents, and the number and
thickness of varying layers within the structure, that can carry a given loading.
216
The figures below provide a comparison to the two main types of pavements.
217
Proposed Road Layout
Due to the steep slopes of the land, the traditional grid system would not be the best fit for the
road network. Therefore, the road system adopted was the curvilinear road system. This system
caters more to the sensitive topography of the site area, allowing for more flexibility in the road
design. The road network established was designed for allowance of two-way traffic within the
community. The two types of roads considered for this site were collector streets and access
roads (see Figures 3 and 4 below. Source: Town and Country Planning Division: “Guide to
Developers and Applicants for Planning Permission”).
218
The access roads had a carriageway width of 5 metres, and a right-of-way width of 8 metres.
Allowances for sidewalks on both sides (1.045m) and drain (0.91m) were accommodated within
the total width of the access road. The road had a minimum allowable slope of 2.5% to assist
with drainage runoff.
The collector roads had a carriageway width of 7 metres (inclusive of kerb and slipper), and a
right-of-way width of 12 metres. Allowances for sidewalks (1.59m) and drains (0.91m) on both
sides were accommodated within the total width of the collector road.
219
Figure 41. Proposed Collector Road cross section
Due to the limited access to the site amid the ongoing pandemic, some assumptions based on our
engineering judgement needed to be made. The information gathered was mostly from secondary
sources, including persons involved in the current project and from manuals such as the
AASHTO and Town and Country Manuals including the Town and Country Planning Division:
“Guide to Developers and Applicants for Planning Permission”. These calculations were based
on the worst-case scenario.
To determine the thickness of a road pavement, we must consider the number, weight, and speed
of loading iterations/ repetitions from the tyres of the vehicles travelling on the structure. The
standard axle during the design life of the structure is composed of four factors. These include:
● The number of vehicles per lane per day
● The vehicle wear factor (standard axles per vehicle)
● The design life of the structure and
● The estimated growth factor in vehicles, over the design life.
220
Calculating the AADT
To get an estimation of the AADT value for the community, the trip generation rates were used for each
building type (Sourced: Institute of Transportation Engineering 2018).
221
DU = Dwelling Unit
ksf = square feet (*1000)
(N.B. AADT values used here are the total for both directions)
222
Vehicle Ni FEi fd Gjt Days AADT AADTi ESAL
classification
Passenger Car 2 0.0001 1.0 22.019 365 2431.94 63% 2462.713
SUV 2 0.0011 1.0 22.019 365 2431.94 22% 9459.46
Pickup 2 0.0023 1.0 22.019 365 2431.94 14% 12,587.20
Vans 2 0.0106 1.0 22.019 365 2431.94 0.30% 1243.084
Small trucks 2 0.0748 1.0 22.019 365 2431.94 0.02% 584.7967
Medium trucks 2 0.4759 1.0 22.019 365 2431.94 0.05% 9301.629
Bus 3 2.2444 1.0 22.019 365 2431.94 0.23% 302,686.20
Small maxi taxi 2 0.0066 1.0 22.019 365 2431.94 0.20% 515.9971
Large maxi taxi 2 0.0511 1.0 22.019 365 2431.94 0.20% 3995.068
Total 342,836.70
6
The total ESAL value was estimated to be 342,836.70 = 0.342x10 million
Table 14. Calculated ESAL values for each vehicle type.
223
Structural Design
Flexible Design:
To estimate the thicknesses of the pavement layers, the structural number must be calculated.
Structural number, SN = a1m1D1 + a2m2D2 + a3m3D3 …....
SN = flexible pavement structural number
a, = layer strength coefficient (structural)
m, = drainage coefficient
D = thickness of layer in inches
1, 2, 3 = pavement layers
224
Reference Calculations Output
Asphalt Layer:
Structural Layer Coefficient, a1:
Source:
Garber and Hoel,
pg. 1043
Source:
Garber and Hoel,
pg. 1042
225
a2 = 0.133 = 0.13 a2 = 0.13
CBR = 80% (AASHTO recommended value)
Mr = 28,000 psi Mr = 28 ksi
Subbase Layer:
Structural Layer Coefficient, a3:
Source:
Garber and Hoel,
pg. 1041
To find the Effective Modulus of the Subgrade soil the below equation
was used:
Source:
Garber and Hoel,
pg. 1040
226
Mr = 1500 (2%) = 3000 lb/in2 Mr = 3 ksi
Source:
Garber and Hoel,
pg. 1052
ESAL = 342,836.70
This value lies within the range that corresponds to row 3 in the figure
above, with a minimum asphalt layer thickness of 2.5” and minimum
base of thickness 4”.
Source:
Garber and Hoel,
pg. 1049
SN1 = 1.75
227
Calculating for Layer Thickness (Asphalt Layer):
SN1 = a1m1D1; assuming m1 = 1.0 (assuming layer impermeable)
i.e., 1.75 = (0.44) (1.0) (D1)
:. D1 = 1.75/ ((0.44) (1.0)) = 3.98 inches ≈ 4 in.
Use D1* = 4 in.
SN1 = a1m1D1* = (0.44) (1.0) (4.0) = 1.76
SN1 = 1.75
SN2 = 2.15
D1 = 4 in.
228
Garber and Hoel,
pg. 1049 SN2 = 2.15
D2 = 4 in.
SN3 = 3.49
SN3 = 3.49
229
D3 = 15 in.
230
Rigid Pavement Design
To calculate the layer thicknesses for the rigid pavement design, the data below was used:
● Total ESAL = 342,836.70 = 0.342x106 million
● AADT = 2431.94
● So = 0.35 (range for rigid pavements = 0.30 - 0.40; Garber and Hoel, pg. 1047)
● R = 90%
● ΔPSI:
Initial Serviceability Index, Po = 4.25
Terminal Serviceability Index, Pt = 2.0 (assumed value)
(For rigid pavements-AASHTO; Source Garber and Hoel, pg. 1094)
Therefore, ΔPSI = Po – Pt = 4.5 - 2.0 = 2.5
231
Mr = 1500(2%) = 3000 lb/in2 (psi)
From graph, the composite modulus of subgrade reaction k∞= 200 psi
Source:
AASHTO 1993,
pg. 131
k∞ = 200 pci
232
Source:
AASHTO 1993,
pg. 116
For jointed pavements without load transfer devices at joints the Load
Transfer value (J-value) range = 3.8 to 4.4. Using J-value = 4.1
U = 130
Source:
AASHTO 1993,
pg. 116
233
Determining the loss of support (LS):
Source:
AASHTO 1993,
pg. 117
Cd = 0.8
Source:
AASHTO 1993,
pg. 118
Grade 60 steel rebar ¾” with a steel working stress of 45,000 psi, was
the chosen reinforcement.
(Recommended from AASHTO 1993 Manual)
234
Source:
AASHTO 1993,
pg. 118
Source:
AASHTO 1993,
pg. 132
Grade 60 steel
chosen
k = 200 pci
LS = 2.5
:. From graph, k (corrected) = 17 (Ls corrected)
235
Source:
AASHTO 1993,
pg. 134
F = 0.9
In cases where the slab is placed on the subgrade without any
subbase, the composite modulus of subgrade reaction was determined
using the equation below:
[Mr value for subgrade = 1500*CBR = 1500(2%) = 3000 psi]
k = Mr/19.4
i.e.
k = 3000/19.4
Source:
AASHTO 1993,
pg. 134
k (corrected) = 17
236
Using the nomograph below, the required slab thickness can be found:
Source:
AASHTO 1993,
pg. 135
237
Source:
AASHTO 1993,
pg. 136
238
Determining the percentage of steel required:
Source:
AASHTO 1993,
pg. 141
239
Source:
AASHTO 1993,
pg. 142
From the graph, the percentage of steel, Ps = 0.035% (transverse and Ps = 0.035%
longitudinal bars)
240
Cost Estimations for Pavement Designs:
Collector Roads:
Road width = 7m
Asphalt Layer thickness = 0.1016 m
Base Layer thickness = 0.1016 m
Subbase Layer thickness = 0.381 m
Total Pavement thickness = 0.5842 m
Subgrade preparation depth = 0.5842 m
Sample length = 100m
241
Excavation cost:
Volume of Excavation = thickness * road width * sample length
= (0.5842) (7) (100) = 408.94 m3
Cost per m3 = $ 156.95
Cost of Excavation = volume * cost/m3
= (408.94) (156.95) = $ 64,183.13
Total cost of a 100m sample of road = Asphalt layer cost + Base layer cost + Subbase layer cost
+ Excavation cost
= $ (128,442.72 + 14,263.83 + 146,685.00 + 64,183.13)
= $ 353,574.68
Access Roads:
Road width = 5 m
Asphalt Layer thickness = 0.1016 m
Base Layer thickness = 0.1016 m
Subbase Layer thickness = 0.381 m
Total Pavement thickness = 0.5842 m
Subgrade preparation depth = 0.5842 m
Sample length = 100m
242
Asphalt Concrete Layer Cost:
Volume of Asphalt layer = thickness * road width * sample length
= (0.1016) (5) (100) = 50.8 m3
Cost per m3 = $ 1806
Cost of Asphalt = volume * cost/m3
= (50.8) (1806) = $ 91,744.80
Base Layer Cost:
Volume of Base layer = thickness * road width * sample length
= (0.1016) (5) (100) = 50.8 m3
Cost per m3 = $ 200.56
Cost of Base = volume * cost/m3
= (50.8) (200.56) = $ 10,188.45
Subbase Layer Cost:
Volume of Subbase layer = thickness * road width * sample length
= (0.381) (5) (100) = 190.5 m3
Cost per m3 = $ 550.00
Cost of Subbase = volume * cost/m3
= (190.5) (550.00) = $ 104,775.00
Excavation cost:
Volume of Excavation = thickness * road width * sample length
= (0.5842) (5) (100) = 292.1 m3
Cost per m3 = $ 156.95
Cost of Excavation = volume * cost/m3
= (292.10) (156.95) = $ 45,845.10
Total cost of a 100m sample of road = Asphalt layer cost + Base layer cost + Subbase layer cost
+
Excavation cost
= $ (91,744.80 + 10,188.45 + 104,775.00+ 45,845.10)
= $ 252,553.35
243
Cost of Asphalt Concrete Pavement
Item Quantity Units Rate ($/unit) Total Cost ($)
Surface Course 50.8 m3 1806.00 91,744.80
Total cost of Asphalt Pavement per 100m sample length = Cost of Collector + Access Road
= $ (353,574.68+ 252,553.35) = $ 606,128.03
244
Costing for Concrete Pavement (rigid design):
Collector Road:
Road width = 7m
Concrete Layer thickness = 0.2286 m
Subbase Layer thickness = 0.1778 m
Total Pavement thickness = 0.4064 m
Subgrade preparation depth = 0.4064 m
Sample length = 100m
Concrete Layer Cost:
Volume of Concrete layer = thickness * road width * sample length
= (0.2286) (7) (100) = 160.02 m3
Cost per m3 = $ 1694.98
Cost of Concrete = volume * cost/m3
= (160.02) (1694.98) = $ 271,230.70
Subbase Layer Cost:
Volume of Subbase layer = thickness * road width * sample length
= (0.1778) (7) (100) = 124.46 m3
Cost per m3 = $ 550.00
Cost of Subbase = volume * cost/m3
= (124.46) (550.00) = $ 68,453.00
Excavation cost:
Volume of Excavation = thickness * road width * sample length
= (0.4064) (7) (100) = 284.48 m3
Cost per m3 = $ 156.95
Cost of Excavation = volume * cost/m3
= (284.48) (156.95) = $ 44,649.14
Steel cost:
Amount of reinforcement required is expressed as a percentage of the cross-sectional area of
concrete. (Source: AASHTO 1993 Manual, pg.141)
Amount of reinforcement required = 0.035% of the C.S.A of Concrete
= (0.035%) (7*0.2286) = 0.00056 m3
245
Volume of steel for a 100m sample length = (0.00056) (100) = 0.056m3)
Density of steel = 7850 kg/m3
Weight of steel = volume * density = (0.056) (7850) = 439.60 kg = 0.4396 tons (kg to ton divide
by 1000)
Cost of Grade 60 steel rebar (3/4”) = $ 9800.00/ton
Accounting for transverse rebars, weight of steel = 2(0.4396) tons = 0.8792
Cost of Steel per 100m length = weight * cost/ton
= (0.8792) (9800.00) = $ 8616.16
Total cost of a 100m sample of road = Concrete layer cost + Subbase layer cost + Excavation
cost + Steel
= $ (271,230.70+ 68,453.00 + 44,649.14+ 8616.16)
= $ 392,949.00
Cost of Portland Cement Concrete Pavement
Item Quantity Units Rate ($/unit) Total Cost ($)
Surface Course 151.13 m3 1694.98 271,230.70
Access Road:
Road width = 5m
Concrete Layer thickness = 0.2286 m
Subbase Layer thickness = 0.1778 m
Total Pavement thickness = 0.4064 m
Subgrade preparation depth = 0.4064 m
Sample length = 100m
246
Concrete Layer Cost:
Volume of Concrete layer = thickness * road width * sample length
= (0.2286) (5) (100) = 114.30 m3
Cost per m3 = $ 1694.98
Cost of Concrete = volume * cost/m3
= (114.30) (1694.98) = $ 193,736.21
Subbase Layer Cost:
Volume of Subbase layer = thickness * road width * sample length
= (0.1778) (5) (100) = 88.9 m3
Cost per m3 = $ 550.00
Cost of Subbase = volume * cost/m3
= (88.9) (550.00) = $ 48,895.00
Excavation cost:
Volume of Excavation = thickness * road width * sample length
= (0.4064) (5) (100) = 203.2 m3
Cost per m3 = $ 156.95
Cost of Excavation = volume * cost/m3
= (203.2) (156.95) = $ 31,892.24
Steel cost:
Amount of reinforcement required is expressed as a percentage of the cross-sectional area of
concrete. (Source: AASHTO 1993 Manual, pg.141)
Amount of reinforcement required = 0.035% of the C.S.A of Concrete
= (0.035%) (5*0.2286) = 0.00040 m3
Volume of steel for a 100m sample length = (0.00038) (100) = 0.040m3)
Density of steel = 7850 kg/m3
Weight of steel = volume * density = (0.040) (7850) = 314 kg = 0.314 tons (kg to ton divide by
1000)
Cost of Grade 60 steel rebar (3/4”) = $ 9800.00/ton
Accounting for transverse rebars, weight of steel = 2(0.314) tons = 0.628
Cost of Steel per 100m length = weight * cost/ton
= (0.628) (9800.00) = $ 6154.40
247
Total cost of a 100m sample of road = Concrete layer cost + Subbase layer cost + Excavation
cost + Steel
= $ (193,736.21 + 48,895.00 + 31,892.24 + 6154.40)
= $ 280,677.85
Cost of Portland Cement Concrete Pavement
Item Quantity Units Rate ($TTD/unit) Total Cost ($)
Surface Course 107.95 m3 1694.98 193,736.21
Total cost of PPC Pavement per 100m sample length = Cost of Collector + Access Road
= $ (392,948.86+ 280,677.85)
= $ 673,626.85
248
Calculating costs for Alternatives
249
● Access Road = 621.29m
For a 100m length sample, the cost of the access road = $ 280,677.85
Therefore, for a length of 621.29m, the cost = (621.29/100) * (cost)
= $ 1,743,823.41
Classification Width (m) Length(m) Cost ($)
Collector 7 1983.55 7,794,339.89
Access 5 621.29 1,743,823.41
Total 2604.84 9,538,163.30
Table 20. Summary Table showing Capital cost of PPC roadworks for Alternative # 1.
Site Layout # 2:
Using the cost of a sample length of 100m for the roads, the actual cost of the collector and
access roads for Layout #2 can also be determined.
Asphalt (flexible pavement)
Calculating costs of roads using Total lengths:
● Collector Road = 2306.65m
For a 100m length sample, the cost of the collector road = $ 353,574.68
Therefore, for a length of 2306.65m, the cost = (2306.65/100) * cost
= $ 8,155,730.36
● Access Road = 734.90m
For a 100m length sample, the cost of the access road = $ 252,553.35
Therefore, for a length of 734.90m, the cost = (734.90/100) * cost
= $ 1,856,014.57
Classification Width (m) Length(m) Cost ($)
Collector 7 2306.65 8,155,730.36
Access 5 734.90 1,856,014.57
Total 3041.55 10,011,744.93
Table 21. Summary Table showing Capital cost of roadworks for Alternative # 2.
250
Concrete (rigid pavement)
Total lengths and areas:
● Collector Road = 2306.65m
For a 100m length sample, the cost of the collector road = $ 392,949.00
Therefore, for a length of 2306.65m, the cost = (2306.65/100) * cost
= $ 9,063,958.11
● Access Road = 734.90m
For a 100m length sample, the cost of the access road = $ 280,677.85
Therefore, for a length of 734.90m, the cost = (734.90/100) * cost
= $ 2,062,701.52
251
Multi-criteria Analysis:
A multi-criteria analysis will be performed to determine the feasibility of each pavement design
and decide which will be the better option. The analysis will be based on the following criteria:
● Construction costs (per 100m sample length)
● Constructability
● Sustainability
● Durability
● Pavement Service Life
● Maintenance
● Aesthetics
The rating system below was used to perform the assessment.
5 Ideal
4 Very Good
3 Moderate
2 Poor
1 Very Poor
Table 23. Rating System for Multicriteria Analysis.
252
Analysis of Flexible versus Rigid Pavement:
Durability 3 5 3 5
Sustainability 4 3 4 3
Constructability 4 4 4 4
Service Life 4 5 4 5
Aesthetics 5 3 5 3
Table 24. Table showing Measure of Effectiveness of the Proposed Alternatives.
253
The measures of effectiveness are then ranked, weighted, and allotted a score.
Total 36 100
Table 25. Table showing Calculated Weighting Factor for each Criteria.
From the analysis, the pavement option for Site Layout #1 was determined to be the better of the
two sites. This was mainly due to Construction costs, as the roads for Site Layout #1 were
shorter than those for Site Layout #2.
254
Determining the Present Worth Cost of the Road Design:
The Present Worth Factor, PWF is determined using the formula below:
PWF = (1+i) n – 1/ i (1+i) n
Road user
Operation Daily cost ($) Days Annual cost ($)
Fuel cost 14.00 365 5110
Tyres 14.00 365 5110
Brake cost 6.00 365 2190
Depreciation 40.00 365 14,600
Total 27,010
Table 27. Summary Table showing Estimated Road User Cost.
The Total Present Worth Cost (TPWC) = Agency Cost + User Cost
= 14,414,173.13 + 27,010
= $ 14,441,183.13
255
Car Parking
In both residential and commercial developments, consideration must be made for car parking
areas. These car parks will be accessible to both the residents and visitors that access the site.
Parking areas should be such that they are durable, easy to manoeuvre, of low maintenance and
allows for proper runoff during and after rainfall events. One factor that should be considered
apart from cost and sustainability when choosing the type of material to construct the car park, is
the aesthetics. The more visually pleasing elements there are, the more it will help to attract
consumers and potential homeowners to the development. The car park layout used was one that
provided a 90° angle to allow for two-way traffic, as seen in the figure below (Source: obtained
from the Town and Country Planning Division: “Guide to Developers and Applicants for
Planning Permission”).
Some types of materials that may be used when constructing a parking lot include:
Concrete pavement:
One of the more traditional options, concrete is proven as a durable and long-lasting solution for
parking areas. It is also one of the easier solutions to maintain and makes for easy marking for
256
layouts of parking bays and is also recyclable. There is also a more diverse range of colours to
choose from when selecting your pavement. Some things that must be considered when choosing
concrete as the driveway material, is:
i. The process of installation, as concrete needs time to cure. This may have an impact
on the functionality/ operations of businesses.
ii. Drainage: concrete is impermeable, therefore allowance for drainage must be taken
into consideration to prevent flooding of areas.
Tarmac:
Modern designs now allow for various colours of tarmac to be used as paving materials. Tarmac
is made by combining crushed stone and bound together with tar. This choice of material is both
durable and visually appealing. One factor to consider is that diesel can stain/mar this type of
pavement, and if gaps are present, it will need to be maintained to remove any weeds present.
257
Figure 44. showing Tarmac Car Parking Driveway and damage caused due to oil spill on
surface
These pavers are a more environmentally friendly alternative to using the traditional paving
materials. They can be made of concrete or recyclable plastic, with open cells that allow for the
growth of grass (when grass is the fill material) or they can be filled with gravel. These types of
pavers are suitable for driveways, parking areas and also walkways. They are porous and good
for areas of sloping land, where erosion can be problematic. Below is a table that lists the
possible pros and cons of using this type of material as paving.
258
Pros Cons
● They assist in reducing stormwater ● They will need to be properly
runoff, which can pose a major maintained especially if they are filled
problem in terms of water pollution. with grass. They may need to be
In storm events, water that is flowing over watered at times (especially in long
the asphalt or concrete pavement may periods of hot weather), fertilized, and
collect chemical pollutants (oils, diesel mowed as necessary, as the grass
etc.) and other debris which then is carried grows and weeds sprout.
away to nearby rivers and streams.
These help with infiltration of the water
thus helping to prevent erosion. ● They are usually more expensive as
compared to other alternatives.
● They help in recharging the
groundwater. As they absorb water ● Their durability is not as good as
from rainfall etc., it filters out compared to say asphalt or concrete
pollutants and allows for that water to pavements, which need to be repaired
be put back into aquifers. This is of every 20-30 years. In residential
great consideration where areas are driveways, these may need to be
more depleted in water supply. replaced every 10 -15 years, and in
commercial driveways, that time
● These pavers are porous and due to period is even more so reduced.
their makeup allow for the air in and
around the area to be cooler (as ● These pavers due to their nature, may
compared to some other paving be less conducive to assisted access,
alternatives) in warmer weather, due to where persons with disabilities may
transpiration. find manoeuvring challenging, as
compared to the standard asphalt or
● They are aesthetically pleasing as concrete surfaces.
compared to concrete or asphalt
pavements, thus improving its overall
value.
Table 25. Potential Environmental Impacts on environmental resources of proposed Paving
Material.
259
Figure 45. showing Grass Block Pavers for a driveway.
(Sources: https://www.tremron.com/pavers/turf-block; https://westerninterlock.com/products/turf-stone/)
Gravel:
Gravel is a fast and easy alternative to paving. It is easy to install and is suitable for projects that
need to adhere to a strict budget. This material offers a great variety of colours and textures as
well, and easily conforms to the contours of the surface. However, this type of paver is more
high maintenance as compared to others and will require more weeding to maintain its
appearance. This can prove tedious especially when dealing with large areas.
260
Asphalt:
This, like concrete, is one of the standard options when considering paving materials. It is
durable, low maintenance and impermeable (waterproof). It provides a classic clean, smooth
finish to paving areas, and is more time efficient to use as compared to say concrete, that requires
more time to cure. It is also easy to repair when the surface is damaged and can come in many
varieties of mixtures.
Figure 47. showing Asphalt paving for a residential driveway and commercial car parking lot.
(Sources: https://masticasphaltcontractor.co.uk/asphalt-car-parks/;
https://masticasphaltcontractor.co.uk/asphalt-car-parks/)
Resin Bound:
This type of surface paving definitely enhances the visual appeal to surrounding areas. It is made
up of a mixture of aggregate ad resin, that results in a smooth, clean finish. Another upside to
using resin bound as paving material is that it is low maintenance and also porous. It allows for
water to infiltrate through the aggregates back into the ground. It is durable, resistant to cracking
and chipping, and provides adequate traction. It is provided in a variety of colours and textures to
suit the consumers’ specific preference.
261
Figure 48. showing Resin bound driveway on the left, and on the right, a variety of textures
and colours for this type of paving material.
(Sources: https://www.simonslandscaping.co.uk/2018/12/01/resin-bound-driveway-norfolk/;
https://www.hazellj.co.uk/why-opt-for-a-resin-bound-driveway)
Brick Pavers:
In many residential settings, brick pavers are still considered as one of the popular choices. It
allows for flexibility in terms of their layout and design (varying sizes, colours, and shapes), thus
allowing for a more customized/ personalized touch. It is cost effective as well, however, with
this type of pavement, care must be taken to maintain its appearance and structure (where blocks
may become loose). Regular weeding and washing may be required to keep the aesthetic quality
up to par.
262
Proposed Paving Materials:
In comparing the types of materials mentioned above, the three materials chosen for the car
parking design were asphalt, brick pavers and porous (gravel or grass) block pavers. These were
chosen as:
● Asphalt is a proven car parking material that is both reliable and feasible in terms of
the areas of commercial parking lots to be paved.
● Brick driveways also aid in enhancing visual appearance and are durable.
● Porous block pavers aid in creating a more environmentally friendly and aesthetically
pleasing visual, while allowing adequate drainage of runoff.
Alternative 1: a combination of asphalt paving for commercial buildings and (15.5”x15.5”) grass
pavers for residential housing areas.
Alternative 2: asphalt paving for commercial buildings and clay brick for residential housing
areas.
Asphalt Car Parking Lots:
In determining Asphalt as the paving material, the ESAL will need to be determined for these
carparks. As the car parks will be traversed mainly by the residents (particularly the apartment
parking lots) and some small commercial businesses (health centre and clinic), a design ESAL
was calculated considering the following class/ types of vehicles:
● Passenger cars
● SUVs
● Pickups
● Vans
● Small trucks
263
Vehicle Ni FEi fd Gjt Days AADT AADTi ESAL
classification
Passenger Car 2 0.0001 1.0 22.019 365 2431.94 60% 2345.44
SUV 2 0.0011 1.0 22.019 365 2431.94 23.2% 9975.94
Pickup 2 0.0023 1.0 22.019 365 2431.94 16% 14,385.37
Vans 2 0.0106 1.0 22.019 365 2431.94 0.30% 1243.08
Small trucks 2 0.0748 1.0 22.019 365 2431.94 0.50% 14,619.92
Total ESAL = 42,569.75
The total ESAL value was estimated to be 42,569.75 = 0.043x106 million
Table 28. Calculated ESAL value for Car Parking lots.
Asphalt Layer:
Source:
Garber and Hoel,
pg. 1043
264
a1 = 0.44 (recommended range 0.40 to 0.44) a1 = 0.44
E = 450,000 psi E = 450 ksi
265
a2 = 0.133 = 0.13
Mr = 28 ksi
Source:
266
Garber and Hoel,
pg. 1041
Subbase Layer:
CBR = 30%
Mr = 14,500 psi
To find the Effective Modulus of the Subgrade soil the below equation
Source:
was used:
Garber and Hoel,
pg. 1040
267
CBR = 30%
Mr = 14.5 ksi
Source:
Garber and Hoel,
pg. 1052
Source:
Garber and Hoel,
pg. 1049
268
269
Cost Estimate for Car Parking Lots:
Costing for Asphalt Concrete Parking lot:
270
Cost of Asphalt Concrete Paved Car Parks
Table 29. Summary Table showing total cost of Asphalt Pavement for Proposed Car Parks.
271
Figure 50. showing Grass Block paving layout.
(Source: adapted from Google images, https://www.nitterhousemasonry.com/resource-
center/installation-guides/turfstone-installation/)
Figure 51. showing the layout of Gravel and Grass Block Pavers.
(Source: adapted from Google Images, https://www.abg-
geosynthetics.com/products/truckcell.html)
272
Cost Estimate for Porous Paved Driveways:
Sample Area = 1 m2
Gravel Base thickness = 6” = 0.1524m
Volume of gravel = area * thickness = (1) (0.1524) = 0.1524m3
Cost per m3 = $ 200.56
Cost of gravel = (volume x cost)
= (0.1524) (200.56) = $30.57
Total Cost per sq. m. (excluding preparation work) = $ (30.57 + 2.92 + 245.00)
= $ 278.49
273
Clay Brick Paved Driveways:
The alternative to using porous blocks for the driveways, was the use of clay brick pavers. These
bricks are also aesthetically pleasing, low maintenance and recyclable. They allow little
infiltration to the soil beneath and can also be laid in various patterns according to the users’
preference. Below, some of the types of various patterns in brick paving can be seen:
Although bonded patterns such as herringbone bone and basket weave can be used, it is
recommended that patterns for these bricks be laid in more suitable patterns such as running
bond, 45° running bond, 45° chevron or herringbone, or a stacked bond. As these bricks allow
for little infiltration, they should be sloped appropriately to allow for proper drainage
(approximately a minimum of 1 in. drop for every 4 ft. or a 2% slope).
These pavers are installed by first excavating the area to the required depth (approximately 7 in.
minimum), removing any material such as roots and weeds that may cause issues (such as
ingrown roots and uneven driveways) later in the service life of the driveway. After excavation,
the subgrade should be compacted and an appropriate base (such as loose bedding sand), placed
over it and compacted as well.
274
This base material should be laid in two separate layers (approximately 3 in. each) and if
necessary, a geotextile fabric placed in between (to help if there is movement in the soil below).
This layering of material is done to allow for proper stability (settling of underlying soil) and to
remove excess moisture. The area should then be checked to determine if it is levelled and
sloped appropriately. If any voids are present, they should be filled and compacted where
necessary. More base is then added and compacted before laying of the bricks. The compacted
layers should be approximately 1” to 2” thick.
Before laying the bricks, a barrier or edging must be laid to keep the bricks in place so there is no
shifting. Devices such as metal barriers or an application of PCC can be used. It should be noted
that when laying the bricks, using a suitable pattern (e.g., the 45° herringbone pattern), they
should have a gap (about 1/8”) between each brick. In cases where there are voids within the
pattern, then the bricks should be cut to an appropriate size and inserted in the space. After the
bricks are laid out in the desired design, a layer of filler sand is placed over the area and swept
into the joints. The bricks are then compacted, and the process repeated. After compaction, any
excess material should be swept away.
275
Total Cost per sq. m. (excluding preparation work) = $ (14.40 + 48.65 + 151.20)
= $ 214.25
Item Quantity Units Total Cost ($)
Table 28. Summary Table showing cost of various alternatives for the Proposed Car Parks.
5 Ideal
4 Very Good
3 Moderate
2 Poor
1 Very Poor
276
Table 30. Rating System for Multicriteria Analysis.
Analysis of Alternatives:
Analysis of Porous Block vs Brick Block Pavers:
Criteria Measure of Effectiveness of Alternatives
Durability 4 4
Sustainability 5 3
Constructability 4 4
Aesthetics 5 4
Table 31. Table showing Measure of Effectiveness for the Proposed Paved Driveways.
277
The measures of effectiveness are then ranked, weighted, and allotted a score.
Table 32. Table showing total score of each Alternative for the Proposed Car Parks.
From the analysis, the porous block pavers were determined to be the better pavement alternative
for the residential driveways.
278
Costing for Car Parks and Driveways Site Layout #1:
To perform the previous multi-criteria analysis, a sample area of 1m2 was used to cost the
driveways. Similarly, a sample area of 1000m2 was used to cost the Asphalt car parking lots.
Using these values, the actual cost of the driveways for the selected Layout #1 can be
determined.
● Car Parking lots (Apartments and Commercial Buildings) = 7809.45m2
For a 1000m2 sample area of parking lot, the Asphalt surface costs = $ 86,181.95
Therefore, the cost for the commercial parking lots = (area*cost)
= (7809.45/1000) (86,181.95) = $ 673,033.63
● Residential Driveways = 2448.6m2
For a 1m2 sample area of driveway, the porous pavers costs = $ 278.49
Therefore, the cost for the residential driveways = (2448.6) (278.49) = $ 681, 910.61
Table 33. Summary Table showing Total cost of Car Parks for Alternative # 1.
279
3.3.3 Storm Water Management
Storm water, also known as rainwater runoff, is precipitation that travels over a surface from the
area where it initially fell with minimal infiltration of said precipitation occurring on the surface
it travels over (EPA, 2021). In urban areas, where there is high impervious cover, water cannot
penetrate surfaces such as roofs, driveways, concrete, and roads, making it even harder for
infiltration/seepage to occur in these environments (EPA, 2021). High impervious cover in these
urban areas also led to increased runoff volumes and higher peak flows of runoff. Adequate
stormwater management practises are therefore employed to deal with the issues of stormwater
runoff as if this isn’t catered for, the issue of flooding, health hazards, contamination of receiving
waters and other indirect consequences and threats to human health, property and safety can
arise. Stormwater management can simply be defined as the knowledge used to understand and
manage water in its different forms within the hydrological cycle (Larry W. Mays, 2010).
Stormwater is usually transported by a series of pipes known as the stormwater drainage network
to our natural water bodies, i.e., rivers, mangroves, and the sea (EPA, 2021). which generate
more runoff and lead to higher stormwater volumes and discharges.
280
Figure 53 shows the comparison between stormwater runoff on natural vs impervious
environments
281
Figure 54 shows the comparison between stormwater runoff on natural vs impervious
environments
Drainage Alternatives
Alternatives to be considered for the drainage systems include a HDPE storm sewer system,
along with a manhole/catchment basin with slump, and rain gardens for alternative 1. Alternative
2 includes a box drain system combined with curb and slipper drains with grate inlets, along with
tree box filters and infiltration trenches. Other stormwater management practises such as
domestic rainwater harvesters and detention basins will also be considered in both alternatives to
further aid in stormwater runoff reduction whilst also conserving water, encouraging water
savings, reducing strain on the central water supply system, and adhering to
regulations/guidelines laid out by the Ministry of Works and Transport. These alternatives have
subsurface and surface drainage accounted for and will be assessed via a multiple criteria
analysis in which both alternatives will be ranked and scored according to a number of objectives
to be met to determine which alternative is more feasible than the other.
These objectives include and consider the economic, social, sustainable, and environmental
impacts that both drainage alternatives will have on the environment if they are to be chosen.
282
Double Wall Corrugated HDPE Pipes
HDPE Pipes have largely grown in popularity and are now one of the most efficient and cost-
effective ways of transporting stormwater. HDPE corrugated pipe is strong, economical,
lightweight, and easy to install which makes it a more favourable subsurface drainage alternative
to reinforced concrete pipe. The corrugated exterior of HDPE pipes allows for increased
structural strength while the smooth interior wall provides smooth flow. Double Wall Corrugated
Pipe has been tested to have a 100-year service life and they are able to withstand and prevent
corrosion, chemical abrasion, pollution to groundwater, root ingression and the tough demands
of heavy construction.
283
Figure 57: Image showing section of typical storm sewer manhole/catch basin with slump
Source: https://www.jtv-cipp.com/storm-drain-cleaning-florida.html
HDPE manholes are prefab manholes made of HDPE and can be easily connected to HDPE
pipes. These manholes, given that they are made of the same materials as the corrugated pipes
have the same properties and characteristics in terms of strength, longevity, chemical resistance,
root ingression and the ability to prevent groundwater from being polluted.
Rain Garden
A rain garden is a garden of shrubs and flowers planted in a small depression or along road
verges. It is designed to temporarily store and allow rainwater runoff that flows from roofs,
driveways, lawns etc to infiltrate into the ground and recharge aquifers/water tables. Rain
gardens are effective in removing up to 90% of nutrients and chemicals and up to 80% of
284
sediments from the rainwater runoff. Compared to lawns, rain gardens can allow for 30% more
water to infiltrate into the ground.
285
Figure 60: Image showing box drain
The gutter portion of the curb creates a channel that directs run-off into specified collection
points such as sewers and storm drains as mentioned prior. Sitting water on the surface of an
asphalt or concrete road can damage pavement material, causing it to crack and separate and
even potholes. Therefore, proper water redirection using gutters is important in order to protect
the surface and maintain longevity of road surfaces.
286
Figure 61: Image showing curb and gutters
Source: https://www.civilconcept.com/curb-and-gutter/
287
Figure 62: Image showing Tree well
Source: http://www.ladstudios.com/ladsites/sustainability/strategies/Strategies_TreeWell.shtml
Infiltration trenches
An infiltration trench is a Low Impact Development (LID) technique in which a trench is filled
with gravel or other aggregate lined with geotextiles and covered with topsoil. Stormwater is
directed to the trench and is stored in the voids between the stone temporarily. Over time, the
stormwater infiltrates into the natural soil around the infiltration trench, recharging underground
water tables. These trenches can be placed around areas of parking, road verges and even yards
since they take up minimal space, it must also be said that infiltration trenches act as storage
reservoirs which facilitate flood reduction and reduction of peak flows.
288
Figure 63: Image showing infiltration trench
289
Figure 64: Image showing Tree well
Rainwater Harvesting systems can also be equipped with water treatment devices to improve the
quality of potable water.
Detention Basins
Detention basins provide flow control through attenuation of stormwater runoff and facilitate
some settling of particulate pollutants. The purposes of the detention basin on site will be to
allow for water to be stored for a period of time and then be discharged into both tributaries at a
slower controlled manner using an outlet control structure to control the flow rate and to protect
against flooding and downstream erosion lower down the Arouca catchment. During the dry
season, both detention ponds can be designed in such a way to be used as parks for recreation
and leisure and habitats for fauna in the area.
290
Figure 65: Image showing section of detention basin
Source: CVNG 3016 Design of Environmental Systems; Stormwater Systems 1; Detention Basin
Design
Figure 66: Image showing detention basin being used as a green area when empty.
Source: https://www.susdrain.org/delivering-suds/using-suds/suds-
components/retention_and_detention/Detention_basins.html
291
Reference Calculations Output
Water
Resources River Flow Calculations
Engineering,
Second Area of catchment in hectares = 24 hectares
Edition,
Chapter 15. Therefore, the rational method can be used to river analysis
(Larry W.
Mays)
Figure 67 showing entire catchment of proposed site with the left sub
catchment in blue and the right sub catchment in green
The Rational formula can be used to estimate the storm runoff peak.
Q= kCiA
292
Where in SI Units K = 0.0028
A- Area in hectares
i = 190mm/hr
293
Length = approx. 712.811m
70𝑚 − 40𝑚
= 0.0421m —> 4.21%
712.811𝑚
i = 180mm/hr
Calculating Q
Using c = 0.40 for Undeveloped; Good Condition (Grass cover larger than 75%) of
area; Average 2% - 7%
Q = kCiA
Therefore, the peak flows occurring in both tributaries left and right Good
Condition
respectively are Q(left) = 2.42m3/s & Q(right) = 2.55m3/s
(Grass cover
larger than
Analysing the peak flow for both tributaries on the left and right of the
75%) of area;
294
proposed site and examining the sections along the tributaries upstream since Average 2% -
they are expected to be smallest to determine whether it can handle a peak 7%
flow of 2.42m3/s coming from the left sub-catchment and 2.55 m3/s coming
from the right sub-catchment.
Assuming that the smallest sections of the river would be higher upstream of
both tributaries
Using the manning equation and assuming the river as a trapezoidal channel
(Right Tributary):
295
b =7.506m - 6.435m = 1.071m
Finding for z
B = b + 2zy
𝐵𝐵 − 𝑏𝑏
—> =z
2∗𝑦𝑦
296
2.145𝑚𝑚 − 1.07𝑚1𝑚
z= = 0.94
2∗0.57𝑚𝑚
Finding for P
P = b + 2y √1+z2
𝐴𝐴 0.92𝑚𝑚2
R= = = 0.35 m
𝑃𝑃 2.64𝑚𝑚
Q = 3.45 m3/s
Given the peak flow the tributary can accommodate is 3.45m3/s and the peak
flow of the tributary currently is calculated to be 2.55 m3/s. The tributary will
not overflow and cause flooding on site.
Using the manning equation and assuming the river as a trapezoidal channel
(Left Tributary):
297
(𝐴𝐴𝑅𝑅 2/3 𝑆𝑆 1/2 )
Q=
𝑛𝑛
Finding for z
B = b + 2zy
298
𝐵4.655𝑚 −2.323 𝑚𝑏
—> =z
2∗𝑦1.08
4.655𝑚𝑚 − 2.323𝑚𝑚
z= = 1.08
2∗1.08𝑚𝑚
Finding for P
P = b + 2y √1+z2
𝐴𝐴 3.77𝑚𝑚2
R= = = 0.69 m
𝑃𝑃 5.44𝑚𝑚
Q = 17.30 m3/s
Given the peak flow the tributary can accommodate is 17.30m3/s and the peak
flow of the tributary currently was calculated to be 2.42 m3/s. The tributary
will not overflow and cause flooding on site.
299
Alternative 1
Note the same calculations for determining river flows will be applied to
obtain pre-development flows on site using the rational method given that
both catchments are the same.
Water
The Rational formula can be used to estimate the storm runoff peak.
Resources Capacity >
Engineering, Flow OK!
By the rational formula:
Second
Edition,
Q= kCiA
Chapter 15.
(Larry W.
Where in SI Units K = 0.0028
Mays)
A- Area in hectares
300
Elevation Upstream = 90m
90𝑚𝑚 − 40𝑚𝑚
= 0.0698m —> 6.98%
716.738𝑚𝑚
i = 190mm/hr
70𝑚𝑚 − 40𝑚𝑚
= 0.0421m —> 4.21%
712.811𝑚𝑚
301
From IDF Curve listed in Appendix
i = 180mm/hr
Given tc(left) is larger than tc(right), use tc = 10mins and i = 180mm/hr for both
tributaries.
Calculating Q
Q = kCiA
Q = 0.0028*0.40*180mm/hr*12ha = 2.42m3/s
Given tc; i; A and C are the same for both tributaries Q value is the same.
Therefore, pre-development peak flow = 2.42 m3/s
302
larger than 75%) of
area; Average 2% - 7%
Calculating Composite C
18.9 5.7 76
[0.86( 100 )24] + [0.88(100)24] + [0.39(100)24]
C= = 0.51
24
Calculating Q
Q = kCiA
Q = 0.0028*0.51*180mm/hr*24ha = 6.17m3/s
Therefore, peak flows post-development = 6.17m3/s Given peak
flow pre-
development
not less than
peak flow
post-
development
Detention
basins must
303
be designed
to reduce
peak flows
post-
development
according to
regulations.
Sum CA = 0.75
304
𝐿𝐿0.77
Inlet time(min) = 0.0195
𝑆𝑆0.385
44.720.77
Inlet time(min) = 0.0195( )= 12.6mins
0.00010.385
Water flows into sewer 3.1 from catchment 2.1 & 2.2 therefore upstream
sewer times are 2.91 and 3.43 for catchment 2.1 and 2.2 respectively.
Time of concentration (tc) & rainfall duration (td) is taken as the longest of the
different times of concentration from sub catchments 2.1, 2.2, 3.1 + the sum
of upstream sewer times from sewer 2.1 and 2.2.
Therefore
Intensity (i) is obtained from the IDF curve from the appendix and multiplied
by a factor of 1.2 to account for climate change.
305
n is Manning’s Roughness Coefficient. For a HDPE pipe n = 0.011
3.21∗0.28∗0.011 3/8 From Pipe
D=( √0.0001
)
Chart in
References
D = 0.99m = 990mm
= 2.1 min
This entire process was repeated for the other sewers in order to obtain
the sizes below:
306
307
Figure 70 showing pipe sizes and flow velocity layout 1
Assuming Cd = 0.61
Orifice Diameter = 1m
308
(Requirement × A × √2gh = 0.61*(0.5) *(√2(9.81) *3 = 2.3 m3/s
s for drainage
design Given 2.3 m3/s < 2.42m3/s, the orifice design is OK.
approval-
#18)
Calculating Storage of Basin
CVNG 3016
Design of
Environment
al Systems;
Stormwater
Systems 1;
Detention
Basin Design
Figure 71 showing the effect the detention basin has on the post-
development peak discharge.
309
Qa is the allowable outflow from the detention basin
Let L = 3W
V = (3W x W x 3) = 2250m3
2250 0.5
Therefore Width (W) = ( )
9
310
Method used
AASHTO when inflow
(1991)
hydrographs
equation #1
are not
Procedure for
available
Volume
storage
CVNG 3016
Design of
Environment
al Systems;
Stormwater
Systems 1;
Detention
Basin Design
311
Figure 72. Sketch showing plan view of the detention basin on site for layout 1
312
Figure 73. Sketch showing sectional view of the detention basin on site for layout 1
Note: Basins for layout 2 is designed the same but with differing dimensions
313
Water
Resources Alternative 2
Engineering
, Second
Pre-development Peak Flow
Edition,
Chapter 15.
Given the site is unchanged pre-development, the
(Larry W.
predevelopment flow for alternative 2 = predevelopment flow
Mays)
alternative 1 = 2.43m3/s
314
For 25 Year Return Period
Calculating Composite C
Calculating Q
Q = kCiA
Q = 0.0028*0.53*180mm/hr*24ha = 6.41m3/s
315
width of drain and n is manning's roughness number.
See
𝑦𝑦
Let b =2y; P = 4y and R = for rectangular channels Appendix
2
Note
Taking A as A = by
Substituting b into A
1 1⅔
6.41 = 0.015 * 2y2* * y2 /3 *(0.02)1/2
2
6.41 = 66.667*2y2*0.629960524*y2/3*0.141421356
Finding for y
316
0.539620933 = y2 * y2/3
—> 0.539620933 = y2 + ⅔
—> y = 0.5396209333/8
1 0.9⅔ *
Q= * (0.9*1.6) * (0.02) ½
0.015 2
Q = 8m3/s
317
Transport
Assuming Cd = 0.61
Orifice Diameter = 1m
318
Basin
Design Given 2.3 m3/s < 2.42m3/s, the orifice design is OK.
Figure 74 showing the effect the detention basin has on the post-
development peak discharge.
319
Qa is the allowable outflow from the detention basin
2394 0.5
Therefore Width (W) = ( )
9
320
Costing
Maintenance cost and Installation costs were assumed to be 5% and 30% respectively.
Layout 1 costing
321
Sum of Sewer System = Total for Pipes + Total Cost for HDPE Manholes = $8,923,325 TTD
Therefore, Total Cost of Sum of Sewer System = Sum of Sewer System + Maintenance cost +
Installation Cost
Detention Basin = Volume of detention basin * rate per m3 = (2309*1500) = $3,463,500 TTD
Therefore, Total Cost of Detention Basin = Detention Basin Sum + Maintenance cost +
Installation Cost
Therefore, Total Cost of Alternative 1 = Cost of Sewer System + Cost of 2 Detention Basins
322
—> Cost of Alternative 1 = $21,397,938.75 approx. $21,397,939 TTD
Layout 2 Costing
Box Drain System = Total Length of Box Drain * Rate of Box Drain per m = (5612.51m*$700)
= $3,928,757 TTD
Therefore, Total Cost of Box Drain System = Sum of Box Drain System + Maintenance cost +
Installation Cost
Detention Basin = Volume of detention basin * rate per m3 = (2601*1500) = $3,901,500 TTD
323
Therefore, Total Cost of Detention Basin = Sum of Detention Basin + Maintenance cost +
Installation Cost
Therefore, Total Cost of Alternative 2 = Cost of Box Drain System + Cost of 2 Detention Basins
324
Multi-Criteria Analysis
A multicriteria analysis will be performed to assess the feasibility of both drainage alternatives.
Alternative 1; A HDPE pipe storm sewer system will be compared to alternative 2; concrete box
drains. Both alternatives will be assessed on measures of effectiveness: Capital Costs,
Environmental impact, Social Impact and Performance.
5 Ideal
4 Very Good
3 Moderate
2 Poor
1 Very Poor
I II
Storm Sewer Box Drains
2 Environmental ● Impact on 3 4 3
impact Environment
● Sustainability of
325
Design
4 Performance ● Efficiency of 2 5 4
drainage system
2 3 3: (n - 2) 3/14*100 = 21.43
4 2 4: (n - 1) 4/14*100 = 28.57
Total 14 100
Objective
Alternatives
I II
Storm Sewer Box Drains
326
2 21.43 ¾*21.43 = 16.07
Total 85.37
91.07
The results obtained from conducting the Multiple Criteria Analysis shows that the Storm Sewer
system is the best option as it achieved the highest value, that of 91.07 points.
327
3.3.4 Environmental Design
Water is vital in many domestic needs such as cooking, washing, drinking potable water, and
flushing wastes, hence the proposed housing development requires a consistent water supply
system to satisfy the needs of the community.
The objective of designing a water supply system for any project is to ensure that the residents of
the development always have consistent water supply at an adequate pressure to all their fixtures,
and to obtain the most economical pipe size. There are several important reasons why designing
proper water distribution systems is essential, the most notable being that inadequate sizing can
result in pressure decreases in some parts of the piping system, which can lead to contamination
of the water supply due to backflow and siphonage, adversely affecting the health of individuals
who use the system.
In Trinidad and Tobago, the Water and Sewerage Authority (WASA) is responsible for
delivering potable water to all residents. In the Arouca area specifically, the water supply comes
from the Hollis Reservoir and the Caroni Arena Reservoir. For the proposed settlement, the
Hollis Reservoir will be considered as the settlement’s source of water. To determine the
required water demand, pipe sizes, and storage tank capacities for the project, the WASA’s
Guidelines for Design and Construction of Water and Wastewater Systems in Trinidad and
Tobago was used. Using the water supply from the Hollis Reservoir through a WASA main, the
method to manage and distribute the water within the development must be evaluated.
The two alternatives considered are the Grid/Looped Distribution System with one emergency
storage tank and the other is the Branched Distribution System with two emergency storage
tanks. The emergency storage tanks would be situated in a location where the pipe networks can
be utilised to meet the water demand for the site in the event of a water shortage. The WASA
main will also be connected to the storage tanks without distributing its contents to the
community to allow for the tank to be filled when required. A bypass water line would be
designed to allow for direct water flow to the development. During periods of water shortage or
emergencies, the stored water from the tanks will be distributed with the use of a booster pump
328
to ensure the required water supply reaches the units. A pressure sustaining valve would be
applied to achieve a reasonable supply pressure for the network when the bypass line is in use,
and when the storage tanks are being filled. To prevent backflow into the storage tanks when
they are being used, a non-return flow valve is implemented to the supply lines connected to the
tanks.
There are two main water distribution systems considered when designing a water supply to a
community, the Grid Distribution System, and the Branched Distribution System. These systems
provide the water to the residential and commercial buildings in the area and must be able to
cater for the increases in water demand due to climate change and population growth.
Grid/Looped System
The Grid distribution system is one of the more desirable distribution system layouts as they can
provide water to all consumers from multiple areas and directions. This configuration allows the
water to circulate throughout the entire system with little to no ends in its layout design,
providing better water quality, flow rates and pressures. These types of systems are usually
implemented in large urban areas. The system consists of a continuous looped main pipe
bordering the area and is connected to the secondary mains and then travels along the
distribution pipes.
● Minimal disruptions during maintenance as the surrounding areas will receive water from
another direction in the system.
● Water reaches all connections of the system with minimal head loss.
● Stagnant water rarely occurs since the water is free to flow in multiple directions.
● The water supply can be controlled and conveyed to certain areas during firefighting
events or emergencies where there is a short supply of water.
The two main disadvantages for this system are that the materials and installation costs may be
costly when compared to the branched distribution system and that the calculations required are
more complex.
329
Figure 79. Image of a Grid/Looped Distribution System
Branched System
The Branched Distribution System is the least desirable design. The system is also known as the
Tree system since its layout is similar to that of a tree branch. This system typically starts with
the main water source pipe entering the development, which then connects to the secondary
mains which travel along the main roads of the community. The secondary mains then connect to
the distribution pipes and “branches” off to their respective buildings.
However, as shown in the figure below, most of the distribution pipes' paths end and are referred
to as “dead ends”. These dead ends typically occur when a water main’s path stops at the end of
a cul-de-sac or other areas where the pipe cannot connect to another distribution main. As a
result, dead ends produce reduced water quality, pressure, and flows. If a dead-end distribution
main is too large, the water in the main can become stagnant and result in undesirable taste,
odour, and colour water quality concerns.
Therefore, when using this system, undersize the dead-end water mains so as to reduce the
pressures and flows of the water demand.
● This is a very straightforward system, and the required calculations are simple.
330
● The pipe dimensions used are affordable and economical.
● Less cut-off valves are needed.
● During maintenance, the water supply for that area would be very limited or cut off until
the repairs are completed.
● Stagnation occurs at the dead-ends resulting in bacterial growth and sedimentation
lowering the quality of the water supply.
● For firefighting purposes, the water supply may be limited due to the existence of a single
water main and limited directions the supply can travel through.
331
Reference Calculations Outp
s ut
332
Total 354 557.5 1593
5
Average
No. of Consumption
Facility Description Flow
Units (lpd)
(m^3/d)
Waiting
Area
56 Seat 12 0.67
(Assembly
Hall)
Community Toilet
16 2083 33.33
Centre / Room
Admin
Office 20 Employee 38 0.76
333
Laundry 19 Machine 2083 39.58
Mart (in
CC/AO) 75 Wash 158 11.85
Showers
8 Person 95 0.76
(in CC/AO)
Total 106.45
Wastewat
Volume of Tank = 664m3 * 264 gal/m3 = 175, 300 gal
er Systems
in
Trinidad
334
and Using Glass Lined Steel (GSL) Storage Tanks,
Tobago –
The storage tanks will be placed above ground.
Design
Guidelines Referencing the Aquastore Tank Capacity Chart – AWWA Seismic 0, 1
for Water English Units,
System
(Section Using Model Diameter 20ft,
2.2.2
Volume of Tank ~ 177, 000 gal
Storage
Facilities) Diameter of Tank = 19.58 ft ~ 20 ft
No. of Sheets = 7
er Systems
Using the minimum velocity of 0.91m/s and Q = 1596.33 m3/d to design
in
the pipe sizes,
335
Trinidad 1
Q = 1596.33 m3/d * 86400 𝑠/𝑑 = 18.48 x 10-3 m3/s
and
Tobago – Recall Q=Av
Design
Where: Q – flow, A – area, v – velocity
Guidelines
for Water 𝜋𝐷 2
Recall A = 4
System
(Section ∴ A = Q/v
2.2.1.3)
𝜋𝐷 2
∴ = Q/v
4
⇒ D2 = 4Q/πv
(Section
2.2.1.4)
To produce the same flow (Q) and maintain the minimum allowable
velocity, let:
336
According to WASA, the minimum size of any distribution pipeline shall
be 100mm (4 inches).
Cost Estimation
For the purposes of this project, it is assumed that the installation and maintenance costs of the
water tanks are 30% and 5% of the capital costs respectively. The average price of a water tank
with the required size was obtained online as well as the average cost per meter of a 6-inch PVC
Schedule 40 pipe. Guidance and estimations on the costing of the materials were also given by
Mr. Derek Outridge. These pricings obtained were used to acquire a rough estimate for the cost
of the water distribution system.
Average Tank Cost (Capital Cost) = $75.00 per gal * 177, 000 = $13, 275, 000 (TTD)
Total Tank Cost = $13, 275, 000 + $3, 982, 500 + $663, 750 = $17, 921, 250 (TTD)
Total Distribution System Cost (Alternative 1) = $17, 921, 250 + $2, 473, 750 = $20, 395,
000 (TTD)
337
Alternative 2
Tobago –
Peak Flow Rate = 1596.33 m3/d
Design
Guidelines
for Water
According to WASA Guidelines, pipes shall be designed to
System
accommodate this Peak Flow Rate.
(Section
2.2.1.2 Water
Consumption)
338
Wastewater Volume of Tank = 664m^3 *264gal/m^3 = 175, 300 gal
Systems in
Trinidad and
Tobago – Using Glass Lined Steel (GLS) Storage Tanks,
Design
Guidelines The storage tanks will be placed above ground.
for Water
Using 2 GLS tanks,
System
(Section 2.2.2 Volume of one Tank = 175300 = 87, 650 gal
2
Storage
Facilities)
Capacity
Volume of Tank ~ 88, 000 gal
Chart (2020)
Diameter of Tank = 25.17 ft ~ 25 ft
No. of Sheets = 9
339
and Since the demand flow (Q) and the required velocity are the same
Construction for both alternatives and following WASA regulations where the
of Water and velocity flows fall within the range of 0.91m/s and 1.52m/s.
Wastewater
Thus, the calculation for determining the required pipe sizing and
Systems in
diameter would also be the same.
Trinidad and
Tobago – Taking water from the WASA Main supplied by the Hollis
Design Reservoir.
Guidelines
for Water
System
WASA Distribution Line – Storage Tank
(Section
2.2.1.3) Using the minimum velocity of 0.91m/s and Q to design the pipe
sizes,
Recall Q = Av
(Section
2.2.1.4) ⇒ D = 0.16m = 0.52 ft = 6.24 inches approx. 6 inches
To produce the same flow (Q) and maintain the minimum allowable
velocity, let:
340
According to WASA, the minimum size of any distribution pipeline
shall be 100mm (4 inches).
Cost estimation
For the purposes of this project, it is also assumed that the installation and maintenance costs of
the water tanks are 30% and 5% of the capital cost respectively. The average prices for a water
tank with the required size and the average cost per metre of a 6-inch PVC Schedule 40 pipe
were also obtained online, with reference to the cost estimates given by Mr. Outridge and used to
acquire a rough cost estimate for the water distribution system.
Average Tank Cost (Capital Cost) = 2($75 per gal * 88000) = $13, 200, 000 (TTD)
Total Tank Cost = $13, 200, 000 + $3, 960, 000 + $660, 000 = $17, 820, 000 (TTD)
Total Distribution System Cost (Alternative 2) = $17, 820, 000 + $2, 435, 500 = $20, 255, 500
(TTD)
341
Multi-Criteria Analysis
This multicriteria analysis will be performed to assess the feasibility of both water distribution
alternatives. Where Alternative 1 is a grid distribution system with one above ground water
storage tank against Alternative 2 which is a branched distribution system with two above
ground water tanks.
Both alternatives will be assessed on the following measures of effectiveness: Capital Costs for
Piping and Tanks, Performance, and Maintenance Costs.
Rank Description of
Rating
5 Ideal
4 Very Good
3 Moderate
2 Poor
1 Very Poor
Alternative 1 Alternative 2
Criteria
Water Quality 5 3
Efficiency (%) 5 3
Maintenance 4 3
342
Ease of Implementation and
4 4
Installation
Construction Cost
2 n-1=4 4/17*100 = 23.52
($TTD)
Ease of Implementation
4 n-3=2 2/17*100 = 11.76
and Installation
Total 17 100
Alternative 1 Alternative 2
Construction Costs
23.52 23.52 23.35
(STTD)
343
Ease of Implementation
11.76 11.76 11.76
and Installation
The results obtained from conducting the Multiple Criteria Analysis show that the Grid Water
Distribution System is the better option as it achieved the higher value of 99.99.
344
3.3.5 Wastewater Management
A Package Plant will be considered as one alternative and the other will consider connecting the
wastewater flows to a nearby wastewater treatment plant, Bon Air West Wastewater Treatment
Plant. According to the EPA, “Package plants are pre-manufactured treatment facilities used to
treat wastewater in small communities or on individual properties”. Manufacturers highlight that
package plants are appropriate for treating flows ranging from 0.002MGD and 0.5MGD.
Common types of package plants are Extended Aeration Plants, Sequencing Batch Reactors, and
Oxidation Ditches.
345
Alternative 1
3 Storey
142.5
Single 120 Person 4.5 264 540
6
Apartme
346
(Sections nts
3.1 –
3.1.6) 424.8
Total 354 1593
7
Average
No. of Consumption
Facility Description Flow
Units (lpd)
(m^3/d)
Community Toilet
16 2000 32
Centre / Room
Admin
Office 20 Employee 40 0.80
Showers (in
8 Person 96 0.77
CC/AO)
Total 106.61
347
Table 45. Commercial and Institutional Wastewater Flows
= 5 m3/ha/d * 24 ha
= 120 m3/d
United
Wastewater Management System
States
Environme Extended Aeration Package Plant
ntal
The aeration process in treating wastewater is one variation to the
Protection
activation sludge process where biological treatment is used to remove
Agency
biodegradable organic wastes under aerobic conditions. To maintain the
(EPA 832-
aerobic conditions, air is typically supplied using mechanical means or
F-00-016,
by diffusing air into the chamber. Mixing the contents is essential to
September
ensure the microbial bacteria bonds with dissolved organics (waste
2000) –
organisms) and is generally maintained by the aeration mechanisms
Wastewate
mentioned previously.
r
Technolog The figure below summarises and portrays the process for an Extended
y Fact Aeration Treatment.
Sheet
348
Figure 81. Extended Aeration Treatment Process
This package treatment plant will be located at the Southern end of the
proposed settlement, near the lower entry/exit access road.
349
Cost estimation
For the purposes of this project, it is also assumed that the installation and maintenance costs of
the water tanks are 30% and 5% of the capital cost respectively. The average prices for a water
tank with the required size and the average cost per meter of a 6-inch PVC Schedule 40 pipe
were also obtained online, with reference to the cost estimates given by Mr. Outridge and used to
acquire a rough cost estimate for the water distribution system.
Average Tank Cost (Capital Cost) = 2($75 per gal * 88000) = $13, 200, 000 (TTD)
Total Tank Cost = $13, 200, 000 + $3, 960, 000 + $660, 000 = $17, 820, 000 (TTD)
Total Distribution System Cost (Alternative 1) = $17, 820, 000 + $2, 435, 500 = $20, 255, 500
(TTD)
350
Alternative 2
Tobago –
Average Flow (Residential, Commercial, Institutional) = 424.87 +
Design
106.61 = 531.48 m3/d
Guidelines
for Peak Flow Rate = (3*Average Flow) + Infiltration = 3(531.48) + 120
Wastewater = 1714.44 m3/d ÷ 4546.09 = 0.38MGD
System
(Table 3.1
Wastewater According to WASA Guidelines, pipes shall be designed to
Flow) & accommodate this Peak Flow Rate.
(Sections
3.1 – 3.1.6)
351
and According to WASA, the velocity flow in any pipeline for either
Construction average or peak flow, the velocity shall normally be between 0.6m/s
of Water to 3.0m/s.
and
Using the minimum velocity of 0.6m/s and Q = 1714.44 m3/d to
Wastewater
design the pipe sizes,
Systems in
Trinidad and 1
Q = 1714.44 m3/d * = 19.84 x 10-3 m3/s
Tobago– 86400 𝑠/𝑑
Design
Recall Q = Av
Guidelines
for Where: Q – flow, A – area, v – velocity
Wastewater
𝜋𝐷 2
System Recall A =
4
352
This alternative follows the sewer system shown in the Sewer System
Design and will be connected to the Bon Air West Wastewater
Treatment Plant.
Cost Estimation
For this alternative, the installation and maintenance costs of the wastewater collection piping
system are 30% and 5% of the capital cost respectively. The average cost per metre of an 8-inch
PVC Schedule 40 pipe was obtained online and used to determine a rough estimate of the
wastewater piping system on the site.
Wastewater Piping System Costs = $350 per metre of PVC Schedule 40 pipes
Total Piping System Cost (Alternative 2) = $595, 000 + $178, 500 + $29, 750 = $803, 250
(TTD)
353
Multi-Criteria Analysis
This multi-criteria analysis will compare the wastewater treatment processes stated in Alternative
1 with connecting the wastewater flows to the nearby Bon Air West Wastewater Treatment Plant
in Alternative 2, assuming that the plant will be upgraded and can cater for the flows from the
proposed site. The alternatives and both treatment processes will be compared based on its
applicability, performance, total costs and their operation and maintenance.
Rank Description of
Rating
5 Ideal
4 Very Good
3 Moderate
2 Poor
1 Very Poor
Alternative 1 Alternative 2
Criteria
Connecting Wastewater Flows
Extended Aeration Treatment
to Bon Air West Wastewater
Process
Treatment Plant
Maintenance 4 4
354
Applicability (min. flow rate
3 4
MGD)
Installation Time 3 5
Construction Costs
2 n-1=4 4/18*100 = 22.22
($TTD)
Total 18 100
355
Maintenance 16.67 16.67 16.67
The results obtained from conducting the Multiple Criteria Analysis show that the Extended
Aeration Treatment Process is the better option as it achieved a higher value of 90.01.
356
4. Sustainability
Sustainable development is defined as development that meets the needs of the present, without
compromising the ability of future generations to meet their own needs (Sustainable Development
Commission, 2022).
In the Bon Air North affordable development, natural ventilation and lighting were the first
alternatives explored throughout the design phase since it is less expensive to create, run, and
maintain than mechanical ventilation. The passive design approach was used to maximise the use
of natural ventilation and natural lighting. Building ventilation is required to remove 'stale' air and
replace it with 'fresh' air: Helping to moderate internal temperatures. Creating air movement which
improves the comfort of occupants. Also, the glass in the windows incorporated in the design
would be tinted or coated with a glazing compound that would limit the amount of solar energy
that enters the house. This not only minimises glare, but it also increases the Solar Heat Gain
Coefficient (SHGC) of the windows, which is a measurement of how well the windows prevent
sunlight from boosting the internal temperature of the residence. Natural ventilation and natural
lighting reduce the energy consumption by extension making the units more affordable. The roof
was designed as a concrete slab to cater for water tanks on the roof or solar panels to allow for
directly harness the sun’s radiation to be converted into reusable energy, by doing so reduces the
unbearable temperatures during the day.
Another factor that must be considered in regard to sustainability when designing for developments
such as these, are the type of materials used in the infrastructure. It is important to consider the
effects these materials have on the environment, whether during the construction phase (i.e., CO2
emissions) or during their service life. For example, environmentally friendly options that can be
used in pavement designs include elements such as natural aggregates and recyclable materials,
and the use of green alternatives to driveways and parking areas. These are not only vital in moving
towards an eco-friendlier environment, but they can also enhance the visual appeal of housing
developments, thus attracting more consumers.
357
The structural alternative which was chosen was layout one where the material selection was
reinforced concrete. Portland Cement Concrete is the most often used concrete nowadays. Cement
is one of the key components of concrete, and it is wreaking havoc on the environment at an
alarming rate. For every ton of cement produced, approximately 0.9 tons of carbon dioxide is
discharged into the atmosphere. Carbon dioxide is a greenhouse gas that is responsible for much
of the world's warming. Cement replacement materials are materials that can be used to substitute
cement in the production of concrete and will be incorporated in this development and a deep
consideration was made to incorporate Premium Plus Cement (Type IP) which is locally produced
by Trinidad Cement Limited. Premium Plus was designed to reduce greenhouse gas emissions into
the environment, consequently reducing our carbon footprint and with additional properties such
as decreased permeability, durability and longevity, increased workability along other properties.
This would decrease the carbon footprint significantly and cost since it is locally produced making
it ideal in the construction of the development.
Solar Panels
Solar Panels will be equipped on an average of 1.6 hectares of roof area within the proposed
development and this number represents all rooftops of buildings within the proposed Bon Air
North Development. Solar panels are being used to harness solar energy to reduce energy usage,
energy costs, strain on centralised systems, the amount fossil fuel that would have been burnt to
completely supply the development with power, to promote sustainability and to add to the
excess power generated to the national grid and receive points which may further reduce energy
costs for the development.
Solar Heater
Solar heaters, just like solar panels, use solar energy to heat water rather than electricity and will
be equipped on roofs of the buildings in the Bon Air North Development, this would provide the
same benefits that the solar panels provide with an exception for sending power back to the
national grid.
358
LED Lights
LED streetlights equipped with photocells will be used throughout the community for lighting
along streets and green areas as they are more energy efficient than traditional streetlights and
are much brighter. LED bulbs will also be used in households for the same reason rather than
traditional CFL and Incandescent bulbs.
As mentioned prior, rainwater gardens and or infiltration wells will be used in the proposed
layouts for stormwater runoff reduction and bioretention. Rain gardens in particular absorb
runoff 30% - 40% more efficiently than normal yards, they reduce mosquito breeding, they are
aesthetically pleasing, self-sustaining, they can recharge water tables and conserve water.
(NRCS, 2022).
Trees will be planted about the site to deal with the issue of the heat island effect as well as tree
wells along roadway verges, these trees will provide shade keeping the community cool and
benches can also be placed under said trees so that residence and visitors of the community can
have some leisure time and also sit and socialise.
Domestic rainwater harvesters will be equipped to homes and shared among some in an effort to
capture and reuse water for both potable and non - potable purposes, promoting water savings,
promoting water recycling and conservation, and also reducing the strain on centralised water
systems, these domestic rainwater harvesters will also be equipped with solar pumps making
them even more sustainable.
359
5. Health & Safety
Health and Safety can simply be defined as the laws, rules, and principles that are intended to
keep people safe from injury or disease at work and in public places according to Cambridge
Dictionary (2022). As a result, countries tend to have a regulatory body which enforces these
laws, rules, and principles in said nation. In Trinidad and Tobago, the Occupational Health and
Safety Agency, (OSHA) is a regulatory agency that ensures these laws are enforced and safe,
risk free, clean working conditions are provided for and by employers for employees and the
general public using the rules and laws outlined by the Occupational Health and Safety (OSH)
Act as minimum standard (OSHA, 2022). As a result, in accordance with the OSH Act of 2004,
amended 2006 consideration and attention will be paid to the aforementioned act to ensure that
the safety of all personnel on and around the proposed site in neighbouring environs are always
safe and out of harm's way. Enforcing the laws and rules of this Act will be the responsibility of
the “employer” of the proposed site whether or not workers or civilians have a personal
responsibility to ensure their own safety. As a result, the issue of health and safety at all phases,
Pre- Construction, Construction and Post - Construction of the proposed site will be discussed,
along with special considerations for COVID 19.
360
Pre - Construction Phase
Phase 1, the Pre - Construction Phase of the project is the phase in which the site is inspected,
cleared, prepared and all relevant earthworks i.e., grading and stabilisation of soils along with all
relevant engineering tests and analysis will be performed. As a result, there will be the issue of
noise and movement of heavy vehicles and equipment on and off site. Therefore, it is imperative
to notify residences and businesses in neighbouring environs in advance ahead of the
commencement of works on the proposed site. Large signs alerting the public of construction in
the area and heavy vehicle traffic are to be placed at reasonable distances from the site before the
commencement of works. The proposed construction site should also be fenced and signs which
read, “Construction site; Restricted access; PPE required on entry” etc should be placed on
fencing at the entrances to the sites as to keep the project and site safe from trespassers,
interruptions and to keep civilians from entering site and getting injured. When preparation of
the site has started and earthworks, clearing, grading etc has begun works are to be conducted
during the day within reasonable hours as to not discomfort surrounding residence and
businesses, the site should also be constantly wetted to minimize large concentrations of dusts
getting into the atmosphere and affecting neighbouring environs. While these works are being
done, guidelines according to the Occupational Safety and Health Act, 2004, PART IV: Safety,
No. 24. “Removal of dust and fumes” and PART VI: Health, No. 32. “Respiratory protection” is
to be followed and PART VII: Welfare is to also be followed in preparing the site for the
construction phase.
361
Construction Phase
The construction phase of any project can be the most risky and dangerous phase of construction
and as a result good health and safety practices must be employed and enforced. Risks such as
being electrocuted, falling objects, trips, and falls, inhaling dust, noise, punctures, structures
collapsing, retaining walls collapsing, being buried under soil and dehydration can all occur
along with others. Hence, the reason that all personnel on site should always wear appropriate
PPE as risks can range from minor to fatal and only by using PPE can these risks be substantially
minimized. One measure that can be taken to identify and plan for risk reduction on site is by
having safety officers on site who regularly inspect the site for risks and ensure the proper PPE is
always being worn, as well as said safety officers performing regular risk assessments on site. If
an assessment of risks is conducted before the construction phase even begins, as mentioned
prior, risks can be reduced and by wearing PPE can be brought to a minimum. Another important
personnel on site will be a security guard to prevent the unauthorised access of persons on site.
Muster points and signs should also be placed on site to alert workers and visitors of the dangers
onsite and where to go in an emergency. All visitors to the site should be briefed on where the
muster points are and on what to do in the case of an emergency, this is also applied to works as
regular briefings and emergency evacuations will be performed so that workers know what to do
in the event of an emergency.
Post - Construction Phase is the phase in construction where the health and safety aspects of
designs for the residence of the development will be implemented. Therefore, this includes clean
and well-maintained facilities. Health and safety plans such as an evacuation plan for the site in
the event of natural disasters, fires, or security breach of the site perimeter and briefing of
emergency response and where the various muster points are located on site will also be
developed. Devices such as fire sprinklers and early warning systems will be placed on site.
362
Given that there are two tributaries in close proximity to the proposed site, even though it is
believed that both tributaries will not break their banks, river calculations were performed to
ensure that there will be no instance where this happens, and the tributaries flood our site. In
addition to this 10m setbacks from the rivers were taken to ensure that there is enough distance
between the site and the river in the event this happens. A lot of green spaces and storm water
mitigation strategies which use the process of bioretention, recycling and infiltration were also
implemented on site to deal with the issue and risk of onsite flooding and to reduce flooding and
peak flows downstream. The site was also graded in such a way to allow for water to run to
drains and sewer outlets to prevent the issue of water ponding on site as this facilitates
mosquitoes which can transfer various diseases and sicknesses.
Proper traffic signage as well as speed bumps will be implemented into the traffic and pavement
design to avoid speeding within the community and possible crashes which can cause loss of life.
Rules and regulations in accordance with THE PUBLIC HEALTH ORDINANCE, CH. 12 NO. 4
will be implemented during all construction phases and will be considered in design. Few
considerations of COVID 19 will include; Encouraging workers to stay home if sick, reminding
persons of social distancing and having signs placed in the community, fully functional poli
clinic on site, development and implement a social distancing plan for maintaining at least 6 feet
of separation, cleaning and disinfect frequently touched objects, encouraging the use of face
coverings in addition to social and physical distancing, designate a COVID-19 health and safety
officer responsible for responding to COVID-19 concerns, restricting access and capacity in
enclosed areas such as elevators, small spaces and break areas and lastly, keep temperature logs
and contacts of everyone on site during all phases to facilitate contact tracing if necessary.
363
6. Selected Alternative
The highest scoring alternative in terms of the multicriteria analysis will be the winning
alternative.
Won Fail
Alternative 1 Alternative 2
According to the table above, alternative 1 won all out of the 5 categories assessed via multi-
criteria analysis and therefore will be the chosen alternative to be developed.
364
7. Conclusion
Factors such as Sustainability, Design life, Capital Costs and Aesthetics were all taken into
consideration when selecting the most feasible alternative. Based on the feasibility analysis and
the multi criteria analysis performed. Overall, alternative Layout 1 was deemed the better option
of the two proposed layouts. This layout comprises the Asphalt Road networks, subsurface
HDPE storm sewer pipe system, Reinforced Concrete moment resisting frame buildings and a
package Wastewater treatment plant (WWTP). An Environmental Impact Analysis was
performed to assess how the development of the community would affect environs within and in
close proximity to the site and during the entire life cycle of the project.
The total cost of the alternative selected was $519,256,931.10 and an infrastructural cost
breakdown is shown in the table below.
Total $519,256,931
365
8. References
American Association of State Highway and Transportation Officials. 1993. AASHTO Guide for
Design of Pavement Structures. 444 N Capitol Street N. W. Suite 249 Washington D.C.
(https://bestcosurfacing.co.uk/services/coloured-tarmac-driveways)
Boral Limited. Guide to Laying Pavers. 2017. Accessed January 12, 2022. PDF File.
(https://www.boral.com.au/sites/default/files/media/field_document/14654_How_to_Lay
_Pavers_LR.pdf)
6005. 019-2020 v2, 2019. UWI, St. Augustine, Civil Engineering Department
Clarke, Richard. PRELIMINARY DRIFT ANALYSIS, n.d. UWI, St. Augustine, Civil Engineering
Department
“Climate.” Climate | Trinidad & Tobago Meteorological Service. Accessed December 2, 2021.
(https://www.metoffice.gov.tt/Climate#:~:text=The%20dry%20season%20which%20occ
urs,showers%20due%20to%20daytime%20convection).
Direct Colors LLC. Resurfacing and Staining a Faded Concrete Driveway. Photograph.
Accessed January 19, 2022. (https://directcolors.com/diy/wp-
content/uploads/2018/07/Concrete-Stain-Driveway-1-940x705.jpg)
Encyclopædia Britannica Inc. Trinidad and Tobago. Accessed December 17, 2021.
(https://www.ttconnect.gov.tt/gortt/portal/ttconnect/!ut/p/a1/jdDBCoJAEAbgp_HqjIqR3
TxYqUFoVLqX0NhWY90VNe3xM29iWXOb4fvhZ4BABEQkbc6SJpci4e-dLC5-
oKPpWgbuA7RQD13NQdM3NqHWg3gEws26B46pbf2TgYj_5fHL2D_zByrgDGSWeT
gB05oDmOnhAWFcpsNPYlukxpIBqeiNVrRSH1V_zpqmrFcKKth1ncqkZJyqV1ko-
366
CmSybqBaCyhLI7R072bvN3ZL9sCR6M!/dl5/d5/L2dBISEvZ0FBIS9nQSEh/?WCM_G
LOBAL_CONTEXT=/gortt/wcm/connect/GorTT%20Web%20Content/ttconnect/home/a
bout+t+and+t/general+information/geography).
(https://www.bobvila.com/articles/asphalt-driveway-cost/)
Fredine, Elle. Backyard Renovations - How to Build a Patio. Photograph. October 27, 2015.
Pinterest. (https://www.pinterest.com/pin/486881409698424571/)
Garber, Nicholas J., and Lester A. Hoel. Traffic and Highway Engineering. Pacific Grove Calif.
Hazell and Jefferies Ltd. Why opt for a Resin Bound Driveway. December 9, 2019.
(https://www.hazellj.co.uk/why-opt-for-a-resin-bound-driveway)
“HDPE Pipe Dimensions and Weights - pe100 PN10 SDR 17.” 2022. Piping Engineering and
Heritage Asphalt. Asphalt Car Park Repairs and Car Park Waterproofing Systems. Accessed
(https://odpm.gov.tt/node/21)
Jordan, Peter. 2017. Rainbow coloured oil spill on wet Tarmac Road surface. Photograph.
Alamy.
367
4834-B634-
98378D947DC0&p=18776&n=0&orientation=0&pn=1&searchtype=0&IsFromSearch=1
&srch=foo%3dbar%26st%3d0%26pn%3d1%26ps%3d100%26sortby%3d2%26resultvie
w%3dsortbyPopular%26npgs%3d0%26qt%3dpetrol%2520diesel%2520tarmac%26qt_ra
w%3dpetrol%2520diesel%2520tarmac%26lic%3d3%26mr%3d0%26pr%3d0%26ot%3d0
%26creative%3d%26ag%3d0%26hc%3d0%26pc%3d%26blackwhite%3d%26cutout%3d
%26tbar%3d1%26et%3d0x000000000000000000000%26vp%3d0%26loc%3d0%26imgt
%3d0%26dtfr%3d%26dtto%3d%26size%3d0xFF%26archive%3d1%26groupid%3d%26
pseudoid%3d%26a%3d%26cdid%3d%26cdsrt%3d%26name%3d%26qn%3d%26apalib
%3d%26apalic%3d%26lightbox%3d%26gname%3d%26gtype%3d%26xstx%3d0%26si
mid%3d%26saveQry%3d%26editorial%3d1%26nu%3d%26t%3d%26edoptin%3d%26cu
stomgeoip%3d%26cap%3d1%26cbstore%3d1%26vd%3d0%26lb%3d%26fi%3d2%26ed
rf%3d%26ispremium%3d1%26flip%3d0%26pl%3d)
Killian Masonry and Concrete Inc. 2010. Decorative Concrete. Photograph. Accessed January
“Landslides.” Trinidad and Tobago Weather Centre. (2019, November 20). Accessed January
19,
Leon, Lee. Pavement Materials Characterisation. Lecture Course CVNG 3009. 2021. The
Mays, Larry W. 2011. Water resources engineering / Larry W. Mays. 2nd ed. ed. Hoboken, NJ:
368
Merrill Paving. Gravel Driveway Installations. Photograph. Accessed January 19, 2022.
(https://merrillpaving.com/gravel-driveway-installation/)
NDS Inc. Tufftrack grass paver. Accessed January 10, 2022. PDF File.
(https://www.ndspro.com/PDFs/Tech-Spec-Guides/Grassroad-Pavers-Tufftrack.pdf)
Simons Landscaping Ltd. Resin Bound Driveway - Norfolk. Accessed January 19, 2022.
(https://www.simonslandscaping.co.uk/2018/12/01/resin-bound-driveway-norfolk/)
369
Town and Country Planning Division. Guide to Developers and Applicants for Planning
Permission. n.d. PDF File.
(https://tcpd.gov.tt/wp-content/uploads/2018/11/Guide-to-Developers-and-Applicants-
for-Planning-Permission-1988.pdf)
(https://www.epa.sa.gov.au/environmental_info/water_quality/programs/stormwater/unde
rstanding_stormwater#:~:text=Stormwater%2C%20or%20rainwater%20runoff%2C%20i
s,as%20roofs%2C%20driveways%20and%20roads).
Western Interlock Inc. Turf Stone. Photograph. Accessed January 19, 2022.
(https://westerninterlock.com/products/turf-stone/)
(https://oceanservice.noaa.gov/facts/hurricane.html)
370
9. Appendix
371
372
373
374
375
N
W E
LAYOUT ONE
SCALE: 1:1500
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
LAYOUT PLAN ONE DATE: 17/01/2022
W E
LAYOUT TWO
SCALE: 1:1500
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
LAYOUT PLAN TWO DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
SEWER SYSTEM DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
BOX DRAIN SYSTEM DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
WATER SUPPLY DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
SEWER SYSTEM DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
COLUMN GRID FOR
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
COMMUNITY CENTER DATE: 17/01/2022
DRAWN BY:
CIV-A01
GROUP 1
LAYOUT PLAN 2 DATE: 31/10/2021
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
COMMUNITY CENTER
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
GROUND FLOOR DATE: 31/10/2021
SIDE ELEVATION
SCALE: 1:60
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
GROUND FLOOR
SCALE: 1:90
NOTES:
CIVIL ENGINEERING DEPT.
DO
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1 AP
SCALE: 1:90
SIDE ELEVATION
SCALE: 1:100
FRONT ELEVATION
SCALE: 1:85
NOTES:
CIVIL ENGINEERING DEPT. DOUBLE COMPLEX DRAWN BY: GROUP 1
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER: CIV-A01 ELEVATION DATE: 17/01/2022
DRAWN BY: GROUP 1
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
COLUMN GRID FOR
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
DUPLEX & POLICLINIC DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
DUPLEX DATE: 31/10/2021
SIDE ELEVATION
SCALE: 1:40
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
THREE-BEDROOM
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
DUPLEX DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
POLICLINIC DATE: 31/10/2021
SIDE ELEVATION
SCALE: 1:40
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
POLICLINIC ELEVATION
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
DATE: 17/01/2022
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
LAYOUT PLAN 2 DATE: 17/01/2022
GROUND FLOOR
SCALE: 1:85
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
SINGLE ROOM
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
APARTMENT COMPLEX DATE: 31/10/2021
FRONT ELEVATION
SCALE: 1:85
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
SINGLE COMPLEX
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER:
DRAWN BY:
CIV-A01
GROUP 1
ELEVATION DATE: 17/01/2022
SIDE ELEVATION
SCALE: 1:30
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
TOWN-HOUSE
CIVIL ENGINEERING DESIGN PROJECT PROJECT NUMBER: CIV-A01
ELEVATION DATE: 17/01/2022
DRAWN BY: GROUP 1
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
TRIPLEX COLUMN GRID DATE: 17/01/2022
GROUND FLOOR
SCALE: 1:50
NOTES:
CIVIL ENGINEERING DEPT. DRAWN BY: GROUP 1
DRAWN BY:
CIV-A01
GROUP 1
TRIPLEX DATE: 31/10/2021