Driven Pile Rig Inspection Checklist

1.0 MTPA Alumina Refinery, Project Stream-5, NALCO-DAMANJODI, ODISHA

Name of Site: Make:


Capacity: Date:
Name of contractor:

Sl.no Inspection points Yes No NA Remarks

1 Operator competent and with having valid license.


2 Third party inspection certificate is available.
3 Condition of sling, wire rope D-shackle in good
condition and third party certificates is available.
4 Suitable ground Access prepared for marching to
required location.
5 Condition of the boom with lock pins.
6 Boom angle indicator is available.
7 Boom back stopper and cut-off switches is
available.
8 All lights, indicators, horn, brakes are in working
condition
9 Wire ropes and drum is in healthy condition.
10 Load chart is available.
11 Fire extinguisher available inside the cabin.
12 All rotating parts are guarded.
13 Clear view between operator and signalman
14 Daily inspection log is available.
15 Condition of hydraulic pipe and is free from oil
spillage
16 Engine without leakage.
17 Condition of guide plate is ok.
18 Cat head and pulleys are in healthy condition.
19 Casing, lugs and helmet casing in good condition
20 Pulling link / cat eye is in good condition
21 Additional safety sling provided at cat eye/pulling
link
22 Hammer is in good condition with valid test
certificate.
23 Sufficient no of U/dogged clamps fixed properly.
24 Ladders are in healthy condition with alignment and
free from oil/ slippery condition.
25 Pneumatic hose is in healthy condition and
approved in quality.
26 Pneumatic Hose with whip arrestor is available.
27 No unwanted and combustible materials lying in the
operator cabin.
28 Available of Swing alarm with flash light.
29 No loose materials are lying on the rig.
30 If any other points?

Name & Signature of Supervisor/Operator/HSE

Accepted /Rejected

NAL/tkIS-HSE-CHECKLIST-Pile rig-FORMAT-17, Dated-11.6.2022,Rev-0.0