Document Front Sheet TOMBIM SERVICES LIMITED

QIT POWER DISTRIBUTION UPGRADE PROJECT


CIVIL WORK
Contractor Name: PSL / NETCO

Contractor NGAA-TL-KPCEP-AD39672 Contractor Document A


Document No: Revision

Document Title: LIFT MANAGEMENT PLAN (TRANSFORMER LIFT AND INSTALLATION PLAN)

Document Number

Contract No:A2120351

Document No:NGAA-TL-KPCEP-AD39672

Rev Description Date Orig Chk’d App’d

A Issued for Client Review 15-12-2017 HS IA SE

Approval of Contractor document

Code Description of code PSL NETCO


Date
Approval Approval
1 Not Approved

2 Approved Subject To Comments

3 Approved

4 For Information Only


TOMBIMSERVICES LIMITED

Project Title:

QIT POWER DISTRIBUTION UPGRADE PROJECT CIVIL WORK

Document Title:

LIFT MANAGEMENT PLAN (TRANSFORMER LIFT AND INSTALLATION PLAN)

Document Number:
Documen
Equipment / Sequential
Country and Originato t Document
Discipline Component Document
Facility Code r Type Sub-Type
Location Code Number
Code
NG AA TL K P CEP AD 39672

A 15/12/2017 Issued for Client Review HS IA SE


Rev Date Description Prepared Reviewed Approved Accepted
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

AUTHORIZATION PAGE

APPROVED BY:
PERSON
DESIGNATION SIGNATURE DATE

HALIDU SULE INSTALLATION ENGINEER Prepared by 12/07/2017

PROJECT ENGINEER Reviewed by 12/07/2017


ITUA AIGBOJE

EGBERI STEVENS PROJECT MANAGER Approved by 12/07/2017


MPN Accepted by

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

3 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

REVISION MODIFICATION LOG

Revision Section Description

A All Issued for Client Review/Comments

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

4 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

TABLE OF CONTENTS

1.0 INTRODUCTION......................................................................................................... 6
1.1 Purpose....................................................................................................................6
1.2 List of Abbreviations and Definitions........................................................................6
1.3 References...............................................................................................................6
2.0 MANPOWER AND EQUIPMENT LIST........................................................................6
2.1 Roles & Responsibility.............................................................................................6
2.2 Equipment List.........................................................................................................6
3.0 SAFETY PRECAUTION..............................................................................................7
3.1 Pre-lift Activities........................................................................................................7
3.2 Lift Guides................................................................................................................ 8
3.3 Lift & Installation Steps.............................................................................................8
4.0 LIFTING EQUIPMENT DATABASE/REGISTER..........................................................9
5.0 EMERGENCIES.......................................................................................................... 9
6.0 APPENDIX 1: SUMMARY OF LIFT ARRANGEMENT...............................................10
7.0 APPENDIX 2: 30T GROOVE CRANE CHART..........................................................11
7.0 APPENDIX 3: THIRD PARTY CERTIFICATION RECORD.......................................13

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

5 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

1.0 INTRODUCTION
1.1 Purpose
This plan specifies steps to be taken by Tombim to safely carryout lifting and
positioning of 6no transformer. The lifting shall be done by a 30T crane with
SAW 17.5T and will be carried out one after the other.
1.2 List of Abbreviations and Definitions
DPICL Designated Person In Charge of Lift
GP ExxonMobil Global Practices guide
JSA Job Safety Analysis
MPN Mobil Producing Nigeria
QIT Qua Iboe Terminal
QPDUP QIT Power Distribution Upgrade Project
SWL Safe Working Load
SWP Safe Work Practices
WMS Work Management System UN Upstream Nigeria
1.3 References
a) ExxonMobil Upstream Nigeria Work Management System – WMS April
2013.
b) MPN Safe Work Practices Manual chapter 1.20 Lifting Operations – SWP
2014.
c) MPN Safe Work Practices Manual chapter 1.21 Cranes and Rigging –
SWP 2014.
d) Emergency Preparedness & Response Plan
e) Method Statement for Installation of Concrete Batching Plant
f) GP 04-14-01 Equipment Lifts by Cranes

2.0 MANPOWER AND EQUIPMENT LIST


2.1 Roles & Responsibility
a) DPICL – Assess, plan and oversee the safe execution of the lifting
operation
b) Crane Operator – Control the Crane Operations as per approved lift plan
c) Riggers – Inspect, install, remove rigging gear and support during lift
operation per approved lift plan
d) Banks-man - Co-ordinate the lifting movements and maintains radio
and/or visual communication with crane operator
e) Safety Officer – Shall ensure involved personnel observe all safety
precautions
2.2 Equipment List
The following are the list of equipment and have passed required pre-mob
inspection/ certification. Each lift shall be drawn from the under listed
equipment as required. All equipment shall be kept within valid certificated
pre-mob status at all times to minimize potential delays when required.

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

6 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

Lifting Equipment
Third Party Pre-Mob
S/
Equipment ID/ Tag SWL Qty Certificatio Inspection
N
n Date date
1 4x4 Mobile Grove Crane RT 530 E 17.5T 1 28/11/2017 13/12/2017

2 4 Legged Sling Wire with N/A 6T 1 28/11/2017 10/04/2017


master link each

3 CS Shackle N/A 6T 1 28/11/2017 6/07/2017

Table 1: Lifting Equipment

3.0 SAFETY PRECAUTION


3.1 Pre-lift Activities
The DPICL must ensure the following activities are carried out prior to lift.
a) Conduct risk assessment for tagline usage prior to lifting operation.
b) The rigging configuration set up checklist must be completed and signed
off prior to lifting activities.(DPICL)
c) The crane operator shall carry out crane checks with the mobile crane
pre-use inspection checklist, with oversight check from the Designated
Person In charge of Lift. (DPICL).
d) Ensure all certifications for crane, personnel; equipment and tools are
present and current. All rigging equipment must be inspected, colour-
coded and certified by an approved third party vendor before use.(DPICL)
e) Pre use inspection/ certification verification shall be carried out by
specialized personnel.
f) Ensure crane footprints are clear and free from obstructions (including
access/egress).
g) Identify and confirm to all parties access and egress path of trucks with
transformers.
h) Confirm crane operator knows where to position the crane, where loads
will be located prior to lifting, as well as the location to lift/set the loads.
i) Pre-lift meeting/walkthrough must be conducted with truck driver to
determine how truck will approach lift area
j) Confirm the correct weight and size of the load (length, width, height).
k) Confirm center of gravity of the load.
l) Confirm pad eyes on transformer are fit for use
m) Identify appropriate lifting and rigging materials (Crane, hook block, slings,
shackles, etc.).
n) Confirm working radius for pick up and final location radii is free from
obstruction
o) Confirm transformer plinth is capable of carrying load i.e., verify strength
from result of “crush test”.
p) Ensure weather conditions and wind speed are within working parameters

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

7 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

q) Inspect ground stability/ condition to determine the load bearing capability


of the ground with fully extended outriggers, including potential
obstructions to outriggers.
r) Site access control during lifting operation to be in place. Barriers to be in
position after cranes/truck positioned and prior to lifting.
s) Hold JSA review and Toolbox talk with all persons involved with task.
Banks-man to be identified to all personnel involved in the lifting
operations
3.2 Lift Guides
The documents listed here must be in place to facilitate a safe lift.
a) Permit to work
b) Job Safety Analysis
c) Approved Diagram/Sketches of operation (appendix 1)
d) Approved Method statement
e) Crane Charts (appendix 2)
f) Third party certification of the lifting equipment and accessories (appendix
3)
3.3 Lift & Installation Steps
The transformers to be lifted are as seen in the table 2. During lift, the crane
shall be placed at approximately 12m away from the load and the following
steps shall be followed.
a) Check transformer for any damage (do not lift where substantial damage is
observed)
b) Position lowbed truck at minimum distance away from crane
c) Connect sling with shackle to each pad eye of the tranformer (the slinge
shall be 4 legged and connected together by master link).
d) Ensure all 4 lift points are positively locked
e) Connect master link to crane hook (30T crane)
f) Ensure that the crane hook is approximatly centered parpendicularly to the
top of the transformer. Tension the sling to verify so.
g) Lift few inchs away from the ground to confirm stability and the capability
of lifting aids. If any abnormality is observed; terminate lift, resolve
anomally and repeat everything fresh
h) Else, lift, swing and drop while the load is guided by 2 riggers with 2 marine
ropes ties to either ends of the base of the tranformer
i) While lowering, install anchor bolts as follows;
i. Suspend the lifted transformer at 0.8m away from the plinth
ii. Insert anchor bolts in the 4 no. transformer hold down plates
iii. Guide transformer such that the installed bolts penetrates the plinth
provided anchor holes
j) Lower transformer gradually to position while ensuring that the installed
bolts are centered
k) Verify that the tranformer is centered properly
l) Sag the 4 legged sling connection, remove shackle and transfer the 4
legged slings to laydown area

S/ TRANSFORMER CAPACITY WEIGHT

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

8 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

N
1 3750KVA 10.9T
2 1000KVA 5T
3 750KVA 4T
4 500KVA 3.2T
5 300KVA 2.6T
6 150KVA 1.8T
Table 2: Transformers to be Lifted for Installation

4.0 LIFTING EQUIPMENT DATABASE/REGISTER


A lifting equipment database/register will be maintained on the site with details of
all lifting equipment. The lifting equipment database / register will be compiled and
maintained by the DPICL and will show both the identification and certification status
of the equipment. Files shall also be maintained of all current certification for lifting
gear on the site.

5.0 EMERGENCIES
All lifting operations must cease immediately in the event of any emergency alarm
signals. The Operators shall make the Side Boom/Crane and any load safe, with
loads lowered into a safe area.
During thunderstorms, operations involving crane must cease immediately and the
equipment powered down.

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

9 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

6.0 APPENDIX 1: SUMMARY OF LIFT ARRANGEMENT

Crane hook

Master Link

6T Sling Wire

6T Shackle

Transformer Pad eye

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the Company.

10 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

7.0 APPENDIX 2: 30T GROOVE CRANE CHART

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

11 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

12 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

7.0 APPENDIX 3: THIRD PARTY CERTIFICATION RECORD

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

13 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

14 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

15 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

16 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

17 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

18 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

19 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

20 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

21 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

22 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

23 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

24 of 25
QIT POWER DISTRIBUTION UPGRADE MPN DOC NO:NGAA-TL-
PROJECT CIVIL WORK KPCEP-AD39672
TOMBIMSERVICES
LIMITED LIFT MANAGEMENT PLAN
(TRANSFORMER LIFT AND
INSTALLATION PLAN) REV. A

This document is the property of COMPANY, it must not be stored, reproduced or disclosed to others without written authorization from the
Company.

25 of 25