1.1 PREPARED BY
Company: Bespoke Landscape Architects
Postal Address: PO Box 38319, Howick, Auckland, 2145
Street Address: Level 2, 6 Leek Street, Newmarket, Auckland 1020
Telephone: 09 520 2164
Email: studio@bespokelandscape.co.nz
1220 PROJECT
1 GENERAL
Site
1.5 SITE
The site consists Open lawn and terraced planting, timber decking
of: areas, concrete footpaths and stairs, general amenity
planting, tree planting and internal access courtyards
As shown on KP-100 and GA plan series
drawing:
Archaeological discovery
Pre-1900, items or evidence of human activity on the site, come under the
Heritage New Zealand Pouhere Taonga Act 2014. If such items or evidence is
discovered work must stop immediately and the Contract Administrator must be
notified immediately. The site may be classified as an Archaeological Site
under the Act, and the Contract Administrator or Owner must contact the
Heritage New Zealand for authority to proceed.
Post-1900 items remain the property of the owner, pre-1900 items may remain
the property of the owner or the Crown subject to what is found.
This general section relates to definitions and interpretation that are used in
this specification.
Definitions
1.1 DEFINITIONS
Hold point: A stage of the construction where the contract
administrator and any other nominated person
requires notice to be given that particular work is to
be carried out. Work may not proceed on that
particular part until the contract administrator and
any other nominated person has advised that work
can continue. A notice period of 2 Working Days is
required unless stated otherwise.
Notification point: A stage of the construction where the contract
administrator and any other nominated person
requires notice to be given that particular work is to
be carried out. Work may continue and the contract
administrator and any other nominated person may
choose whether or not they wish to witness the
particular work being carried out. A notice period of
2 Working Days is required unless stated otherwise.
Product: A thing or substance produced by natural process or
manufacture.
Proprietary: Identifiable by naming the manufacturer, supplier,
installer, trade name, brand name, catalogue or
reference number.
Provide and fix: "Provide" or "fix" or "supply" or "fix" if used
separately mean provide and fix unless explicitly
stated otherwise.
Required: Required by the documents, the New Zealand
Building Code or by a statutory authority.
Review: Review by the contract administrator and other
consultants is for general compliance only. Review
does not remove the need for the contractor to
comply with the stated requirements, details and
specifications of the manufacturers and suppliers of
individual components, materials and finishes.
Neither can the review be construed as authorising
departures from the contract documents.
Working day: Working day means a calendar day other than any
Saturday, Sunday, public holiday or any day falling
within the period from 24 December to 5 January,
both days inclusive, irrespective of the days on
which work is actually carried out.
Workplace: Workplace means the place where work is being
carried out, or is customarily carried out, for a
business or undertaking including any place where a
worker goes, or is likely to be, while at work (under
Health and Safety at Work Act 2015).
1.2 PERSONNEL
Principal:
© CIL Masterspec Mar 2023 1232 INTERPRETATION & DEFINITIONS Page 6
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
1.3 ABBREVIATIONS
The following abbreviations are used throughout the specification:
AAMA American Architectural Manufacturers Association
AS Australian Standard
AS/NZS Joint Australian/New Zealand Standard
ASTM American Society for Testing and Materials
AWCINZ Association of Wall and Ceiling Industries of New
Zealand Inc.
BCA Building Consent Authority
BRANZ Building Research Association of New Zealand
BS British Standard
COP Code of practice
CSIRO Commonwealth Scientific and Industrial Research
Organisation
HERA Heavy Engineering Research Association
LBP Licensed Building Practitioner
MBIE Ministry of Business, Innovation and Employment
MPNZA Master Painters New Zealand Association Inc
NZBC New Zealand Building Code
NZS New Zealand Standard
NZS/AS Joint New Zealand/Australian Standard
NZTA New Zealand Transport Agency
NUO Network Utility Operator
OSH Occupational Safety and Health
PCBU Person Conducting a Business or Undertaking
(under Health and Safety at Work Act 2015)
RBW Restricted Building Work
SARNZ Scaffolding and Rigging New Zealand Inc
SED Specific Engineering Design
TA Territorial Authority
TNZ Transit New Zealand
(Transit New Zealand is now New Zealand Transport
Agency NZTA - some specifications are still prefixed
TNZ)
Some schedule sections are identified by the 4 digit CBI (Co-ordinated Building
Information) number of the general section that they relate to, followed by the
letter "S" followed by a numeral (1-9). The numeral allows for multiple
schedule sections to be associated with the same general section.
Other schedule sections that do not share a common CBI number with a
general section, have their own unique 4 digit CBI number, followed by the
letter "S" followed by a numeral. These schedule sections contain additional
subject content relating to the schedules and the identified work sections.
Documents cited both directly and within other cited publications are deemed to
form part of this specification. However, this specification takes precedence in
the event of it being at variance with the cited documents.
1.2 DOCUMENTS
Documents referred to in the GENERAL sections are:
1234 DOCUMENTATION
1 GENERAL
Compliance information
Refer to the general sections for the requirements for compliance information to
be provided by the contractor.
Refer to the building consent for the requirements for compliance information to
be provided by the contractor.
Obtain required documents from the relevant parties for delivery to the contract
administrator after the final inspection has been carried out by the BCA.
Substitutions
1.7 NO SUBSTITUTIONS
Substitutions are not permitted to any of the specified products and systems
listed in a section unless specified otherwise. If a product is not available then
immediately contact the contract administrator for direction.
and if requested:
All current manufacturer's literature on the product
© CIL Masterspec Mar 2023 1234 DOCUMENTATION Page 12
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Manufacturer's documents
The Contract Administrator will advise whether such documents shall be:
delivered to the Contract Administrator/Owner; or
disposed of by normal waste disposal methods; or
disposed of by secure document disposal methods.
Confidentiality of documents
2 SELECTIONS
1.8 RESPONSIBILITY
Review of shop drawings does not relieve the contractor of responsibility for the
correctness of the shop drawings, site dimensions, the overall design,
coordination and performance, or for ensuring the work is carried out in
compliance with the contract documents. It does not remove the need for the
contractor to comply with the stated requirements, details and specifications of
the manufacturers and suppliers of individual components, materials and
finishes. Review cannot be construed as authorising departures from the
contract documents.
2 SELECTIONS
This schedule section identifies work sections in the specification that have
requirements for the preparation, submission and review of shop drawings.
Shop drawings
Refer to drawings.
1237 WARRANTIES
1 GENERAL
Warranties
Provide warranties in favour of the principal. The terms and conditions of such
warranties in no case negate the minimum remedies available under common
law as if no warranty had been offered. Failure to provide the warranty does
not reduce liability for execution and materials for that part of the work.
Provide warranties in favour of the principal. The terms and conditions of such
warranties in no case negate the minimum remedies available under common
law as if no warranty had been offered. Failure to provide the warranty does
not reduce liability for execution and materials for that part of the work.
Submission
2 SELECTIONS
This schedule section identifies work sections in the specification that have
requirements for warranties.
Warranties
1.2 WARRANTIES
Refer to the following sections:
6614TT Total Tactilez Nosings & Trim
6745R Resene Protective Coatings - Steelwork
7451AL Allproof Level Threshold Drainage Systems
8255 Synthetic Turf
8281TT Total Tactilez Exterior Tactile Indicators
8432BF Boundaryline Fencing & Gates
8461 Street & Landscape Furniture
8465 Playground Equipment & Surfacing
Principal: ~
.............................................................................................................
Contractor: ~
.............................................................................................................
Warrantor: ~
.............................................................................................................
1.2 BACKGROUND
The principal has entered into a contract with the contractor for carrying out the
contract works. The warranted works / materials are part of the contract works.
The contractor has agreed to arrange for the provision of a warranty in respect
of the warranted works / materials for the warranty period on the terms set out
in this warranty. The warrantor has agreed to provide a warranty in respect of
the warranted Works / materials for the warranty period on the terms set out in
this warranty agreement.
1.3 LOCATION
Project ~
name:
.............................................................................................................
Project ~
address:
.............................................................................................................
Warranted ~
works:
.............................................................................................................
Warranty ~ years from the date of practical completion of the contract
period: works.
Warranted ~
materials:
.............................................................................................................
Warranty ~ years from the date of practical completion of the contract
period: works.
2 WARRANTY TERMS
The warrantor warrants to the principal that the warranted work performed
/materials supplied shall be as required in the contract. If not otherwise
specified the work shall be of good trade practice with materials and fittings of
merchantable quality.
The principal shall first give the warrantor 10 working days notice, or such other
reasonable time as agreed by the principal, to carry out and complete the
remedial work / supply replacement materials. If the warrantor does not
complete this work / supply replacement materials within the time, the principal
shall then advise the warrantor in writing that the work will be carried out /
materials will be supplied by others.
In such an event the warrantor is not released from obligations under this
warranty, which continues in full force and effect, except in respect of the defect
remedied / materials supplied by the principal or by another person contracted
by the principal. The reasonable cost of the remedial work carried out by such
other persons including all reasonable costs of the principal is to be paid to the
principal by the warrantor on demand.
2.10 DISPUTES
Any dispute between the principal and the warrantor arising out of this warranty
is to be referred to arbitration before a sole arbitrator. If within 15 Working
Days of notice of dispute, the principal and the warrantor cannot agree upon a
single arbitrator, either party may request the president of the Arbitrators and
Mediators Institute of New Zealand Incorporated (AMINZ) to appoint an
arbitrator.
3 SIGNATORIES
..................................................................................................
..................................
Signed Date
......................................................................................................................................
Print name of person(s) authorised to sign
© CIL Masterspec Mar 2023 1237WA WARRANTY AGREEMENT Page 24
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
..................................................................................................
..................................
Signed by witness, include occupation and address Date
..................................................................................................
..................................
Signed Date
......................................................................................................................................
Print name of person(s) authorised to sign
..................................................................................................
..................................
Signed by witness, include occupation and address Date
3.3 NOTE
The warranty shall be executed by the warrantor and the principal in the
manner required for execution of a deed. In the case of a natural person, the
person shall sign and their signature shall be witnessed by another person, a
witness must not be a party to the deed.
Sign the warranty on behalf of a company by having 2 or more directors sign,
or if there is only 1 director, by that director whose signature must be
witnessed, or if the constitution of the company so provides, a director, or other
person or class of person(s) whose signature(s) must be witnessed, or by 1 or
more attorneys appointed by the company in accordance with section 181 of
the Companies Act 1993.
Execute the warranty on behalf of a body corporate (other than a company) by
affixing its seal, which shall be attested in the manner provided for in the rules
of, or applicable to, the body corporate. If signing for another type of entity for
example an incorporated society, trust, school board etc. follow the protocol
required for the execution of a deed.
Documentation format
O&M review indicates only that the reviewer is satisfied that the documents are
legible. The review is not a check of the accuracy of the documents, however
the reviewer may comment on any aspect of the documentation and require the
documents to be revised and resubmitted. Review of operation and
maintenance documentation does not relieve the contractor of responsibility for
the correctness of the documentation.
Final documentation
© CIL Masterspec Mar 2023 1239 OPERATION & MAINTENANCE Page 27
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Provide a title on the binder edge "Operation and maintenance instructions for
(project name)". If more than one binder is required identify each binder by
number and ranking (e.g. Volume 2 of 3) and group information logically
between the binders for ease of reference.
Provide operation and maintenance manuals clearly and neatly marked on the
spine or front cover so as to identify the project name. Where operation and
maintenance manuals are a collection of loose leaf documentation, provide
documentation in a loose-leaf binder as described above.
2 SELECTIONS
O&M Documentation
This schedule section identifies work sections in the specification that have
requirements for the submission of:
Information for operation and maintenance
Operation and maintenance manuals
Maintenance contract proposals
Additional Items
© CIL Masterspec Mar 2023 1239S1 SCHEDULE OF OPERATION & MAINTENANCE INFO Page 30
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
1240 ESTABLISHMENT
1 GENERAL
Inspections
Site preparation
Temporary construction
First aid
This general section relates to temporary works and services required for the
construction of the contract works. It includes
Temporary works and services including temporary fencing
General care and protection
Rubbish removal
Temporary works
Pump water from trenches and other areas of the site using methods to prevent
sediment entering any drain or watercourse. Filter dirty water before
discharging into drainage system.
Small project with relatively large exposed ground areas - prevent run off by:
directing small amounts of washwater onto the area of ground closest
to the work.
for larger amounts provide run off channels, and small soak pits
very small amounts of washwater with no aggregate and only a small
amount of sand may be spread over existing lawns.
Large project and those without suitable ground area - prevent run off by:
plan and implement washwater control measures based on the
expected volumes, allow for the timely removal and safe disposal of
liquids and solids.
Limit the volume of water used for washing down to the extent
required.
Control the flow of washwater so that it is directed to proper
catchments.
providing watertight bunds, pits or tanks, filtered washwater is not to
be discharged to drains.
Temporary services
1.9 WATER
Provide clean, fresh water for the works and make arrangements for
distributing about the site.
1.10 ELECTRICITY
To AS/NZS 3012.
© CIL Masterspec Mar 2023 1250 TEMPORARY WORKS & SERVICES Page 34
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Nominate the person to install and be responsible for the complete temporary
electrical installation. The name and designation of the person responsible is
to be displayed prominently and close to the main switch or circuit breaker.
Inspect and overhaul the installation at such intervals as are prescribed by the
network utility operator but not more than three monthly intervals.
1.11 TELEPHONE
Provide on-site temporary telephone facilities.
1.13 PRINTER
Provide on-site temporary printing facilities capable of printing A4 and A3
colour prints.
1.14 IMAGING
Keep available devices able to take and send quality printable digital
photographs.
© CIL Masterspec Mar 2023 1250 TEMPORARY WORKS & SERVICES Page 35
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Rubbish removal
© CIL Masterspec Mar 2023 1250 TEMPORARY WORKS & SERVICES Page 36
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
1270 CONSTRUCTION
1 GENERAL
Record keeping
The level of documentation for signing off the contract works as
complete
Procedures to ensure that all persons engaged in undertaking the
contract works are qualified, experienced and trained for the work
they are undertaking
Inspection and testing required by the contract
Auditing the quality plan
Review by the contract administrator of the quality plan does not make the
quality plan a contract document. The contractor at all times remains
responsible for the construction of the Works. If resubmission of a quality plan
is required, the contract administrator will give their reasons. The contractor
shall take account of the reasons and resubmit a revised quality plan within a
period of 5 working days.
1.6 NOTICE
Give notice to the contract administrator and any other nominated person of
hold points and notification points. Refer to work sections and 1260 PROJECT
MANAGEMENT for hold points and notification points required.
Provide information to neighbours of any noise generation from the site liable to
constitute a problem. Explain to them the means being used to minimise
excessive noise and establish with them the timings most suitable for the noise
generating work to be carried on.
Discuss with any complainant the measures being used to minimise noise.
Where possible modify these measures to accommodate particular
circumstances. Finally, determine the sound level at the location under
discussion using methods and observation reporting as laid down in NZS 6803.
If the noise level is above the upper limits of NZS 6803, table 2 and table 3,
cease the noise generating operation and remedy the problem.
1.18 RESTRICTIONS
Do not:
light rubbish fires on the site.
bring dogs on to or near the site.
bring radios/audio players on to the site.
1.20 DATUM
Establish a permanent site datum to confirm the proposed levels and their
relationship to all other existing and new levels.
1.21 SET-OUT
Set out the work to conform with the drawings.
Provide the certificate to the local authority. Provide a copy of the certificate to
the contract administrator.
1.26 TOLERANCES
All work to be level, plumb, and true to line and face. Unless otherwise
specified in specific work sections of this specification, tolerances for structural
work shall comply with the following:
Execution
Where there is more than one method or detail appropriate to the part of the
work in question, refer the options to the Contract Administrator for direction as
to which detail or method to use.
Qualifications
Ensure that the replacement person takes responsibility for the work they carry
out and that they are able to provide such records of work, producer
statements, warranties and the like required as a condition of the contract and
the building consent.
Products
Samples
Samples for review may be described as a portable sample for review, portable
control sample, fixed sample for review or fixed control sample. A portable
sample refers to a sample that is easily movable, convenient for carrying. A
fixed sample refers to a sample that is not portable. If the location of a fixed
sample is not defined in the work section, obtain direction from the contract
administrator.
For samples that are located on site, or by agreement with the contract
administrator are located off site, notify the reviewer and contract administrator
of their location and availability for review.
Timing for the provision and review of samples is to be included in the contract
programme. Where no time is stated in a work section allow 10 working days
for each review. Allow for such resubmission and further review as may be
required. No extension of time will be allowed for resubmission and further
review.
Control samples that are to remain on site, or otherwise in the care of the
contractor, are to be maintained in original condition.
Prototypes
Collect, protect, package, label and store safely all spares and maintenance
products specified in the work sections. Give the contract administrator an
inventory of all spares and maintenance products.
If no instruction is given within a work section for the location of spares and
maintenance products, then deliver to the owner.
If no instruction is given within a work section for timing in relation to the
provision of spares and maintenance products, then provide at practical
completion.
Remove protection
Completion
Commissioning
Completion submissions
This schedule section identifies work sections in the specification that have
requirements for:
The submission of samples
The submission of prototypes for review
The provision and testing of prototypes
Samples
1.2 SAMPLES
Refer to the following sections:
3124 Finishes to Wet Concrete
4383 Timber Decking
4924 Stainless Steel Metalwork
6745R Resene Protective Coatings - Steelwork
8226 Gravel & Stone Paving
8332 Planting
8333 Turf Laying & Lawn Seeding
8335 Tree Planting & Transplanting
© CIL Masterspec Mar 2023 1270S1 SCHEDULE OF SAMPLES & PROTOTYPES Page 49
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This schedule section identifies work sections in the specification that have
requirements for spares and maintenance products.
© CIL Masterspec Mar 2023 1270S2 SCHEDULE OF SPARES & MAINTENANCE PRODUCTS Page 50
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC D1/AS1 Access routes
AS 4586 Slip resistance classification of new pedestrian
surface materials
© CIL Masterspec Mar 2023 1278SR SCHEDULE OF SLIP RESISTANCE TESTING Page 51
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Sloping access wet - minimum test values required for a given slope
Minimum test value Maximum Maximum slope in
required (SDV) gradient degrees
42 BPN 1 in 39 1.5°
43 BPN 1 in 29 2.0°
44 BPN 1 in 23 2.5°
45 BPN 1 in 20 3.0°
45 BPN 1 in 17 3.5°
46 BPN 1 in 15 4.0°
47 BPN 1 in 13 4.5°
© CIL Masterspec Mar 2023 1278SR SCHEDULE OF SLIP RESISTANCE TESTING Page 52
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
48 BPN 1 in 12 5.0°
49 BPN 1 in 11 5.5°
50 BPN 1 in 10 6.0°
Sloping access dry - minimum test values required for a given slope
Minimum test value Maximum Maximum slope in
required (COF) gradient degrees
0.433 1 in 39 1.5°
0.444 1 in 29 2.0°
0.455 1 in 23 2.5°
0.466 1 in 20 3.0°
0.477 1 in 17 3.5°
0.488 1 in 15 4.0°
0.499 1 in 13 4.5°
0.504 1 in 12 4.76°
0.521 1 in 11 5.5°
0.525 1 in 10 5.7°
0.543 1 in 9 6.5°
0.557 1 in 8 7.125°
© CIL Masterspec Mar 2023 1278SR SCHEDULE OF SLIP RESISTANCE TESTING Page 53
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the clearance, excavation and backfilling of the site area
in preparation for:
footings and floor slabs
backfilling behind retaining walls
Documents
1.1 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 3604 Timber-framed buildings
WorkSafe Good Practice Guidelines - Excavation Safety
2 PRODUCTS
3 EXECUTION
Place fill in layers of not more than 150mm and compact to achieve 95% of
maximum dry density. For granular fill material, the fill shall be compacted to
80% of saturated dry density.
2241 EXCAVATION
1 GENERAL
This section relates to the excavating required for the building works, removing
surface soils and the disposal of excavated material.
Related work
Documents
Documents listed above and cited in the clauses that follow are part of this
specification. However, this specification takes precedence in the event of it
being at variance with the cited document.
Requirements
Performance
1.8 INSPECTION
© CIL Masterspec Mar 2023 2241 EXCAVATION Page 57
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Arrange for inspections and before placing any new work. If bearing becomes
inadequate due to any cause then stop work and request further instructions.
2 PRODUCTS
Materials
2.1 TOPSOIL
Weathered soil, with organic inclusions capable of supporting the growth of
vegetation.
2.3 ROCK
Defined as material encountered in excavations which because of its size or
position can be removed only by breaking up by explosives or mechanical plant
such as jack hammers or percussion drills.
3 EXECUTION
Conditions
3.1 REPORT
Report any survey pegs, bench marks, and the like on any features, leaving
them undisturbed until approval is given for removal.
3.3 COMPLY
Comply with the requirements of WorkSafe, Good Practice Guidelines -
Excavation Safety.
© CIL Masterspec Mar 2023 2241 EXCAVATION Page 58
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Application
Take special care when working close to retained trees and shrubs.
Finishing
Completion
3.20 LEAVE
Leave work to the standard required by following procedures.
4 SELECTIONS
This section relates to timber pile foundations and subfloor bracing supporting
timber framed floor construction.
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC B1/VM4 Structure Foundations
NZS 3109 Concrete construction
NZS 3602 Timber and wood-based products for use in building
NZS 3603 Timber structures standard
NZS 3604 Timber-framed buildings
NZS 3605 Timber piles and poles for use in buildings
NZS 3640 Chemical preservation of round and sawn timber
Requirements
1.3 CO-ORDINATION
Refer to all drawings and calculations to ensure details and fixings required are
provided for in the installation of the piles and bracing work structure.
Performance
2 PRODUCTS
Materials
Radiata pine, treated H5 CCA (preservative code 01 or 02) to NZS 3602, table
1A to design data assigned in NZS 3603, section 7 and complying with NZS
3605.4 Round or square house piles, for cross-section, length, straightness,
grade, growth rings, durability, strength, and branding.
Components
2.3 CONCRETE
For pile footings 17.5 MPa ordinary grade concrete (normal concrete) to NZS
3109, and NZS 3604, section 6.4.5, Pile footings.
2.5 BOLTS
Stainless steel and or hot dipped galvanized steel to NZS 3604, Section 4
Durability, clause 4.4 Steel fixings and fastenings.
3 EXECUTION
Conditions
3.1 GENERALLY
Comply with NZS 3602 and NZS 3604 except as varied by this specification.
Execution to include those methods, practices and processes contained in the
unit standards for the National Certificate in Carpentry.
3.2 EXCAVATION
Comply with NZS 3604 section 3, Site requirements, and section 6,
Foundations and subfloor framing. Excavate for pile footings as detailed on
the drawings.
Application - General
Completion
3.6 LEAVE
Leave work to the standard required by following procedures.
4 SELECTIONS
This section relates to the supply and installation of concrete strip footings of
non-specific design to NZS 3604 and NZS 4229, including;
formwork, reinforcement, concrete mixes and the placing of concrete
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 3104 Specification for concrete production
NZS 3109 Concrete construction
NZS 3121 Water and aggregate for concrete
NZS 3604 Timber-framed buildings
NZS 4229 Concrete masonry buildings not requiring specific
engineering design
NZS 4431 Code of practice for earth fill for residential
development
AS/NZS 4671 Steel reinforcing materials
NZCMM NZ Concrete Masonry Manual section 6.1 Masonry
Retaining Walls
Requirements
1.3 QUALIFICATIONS
Concrete workers to be experienced, competent and familiar in the fabrication
and erection of formwork and with the materials and the techniques specified.
All work to be installed or supervised by a Registered Mason or licensed
building practitioner (LBP): Licensed for Bricklaying and Blocklaying 2:
Structural Masonry. RBW must be supervised by an LBP.
2 PRODUCTS
2.2 REINFORCEMENT
To AS/NZS 4671 Grade 300E deformed mild steel except for ties in plain round
mild steel and as detailed.
2.4 WATER
To NZS 3121. Water from a territorial authority/NUO water supply is
acceptable.
3 EXECUTION
3.1 STORAGE
Handle and store reinforcing steel and accessories without damage or
contamination. Store on timber fillets on hard ground in a secure area clear of
any building operation. Lay steel fabric flat.
Ensure reinforcement is clean and remains clean so that at the time of placing
concrete it is free of all loose mill scale, loose rust and any other contamination
that may reduce bonding capacity.
3.6 FORMWORK
Use formwork of sufficient strength to retain and support the wet concrete to
the required profiles and tolerances. Select formwork finish to produce the
specified finished quality. Water blast to clean formwork. Keep formwork wet
before concrete is placed.
3.7 REINFORCEMENT
Cut and bend bars using proper bending tools to avoid notching and to the
requirements of NZS 3109. Do not rebend bars. Where rebending is
approved, use a purpose built tool, proper preparation and preheating.
Longitudinal reinforcing and ties, refer to SELECTIONS for size and quantity.
Stepped footings to NZS 4229, at least 50% of the lower footing reinforcement
shall be turned up the step to a minimum of 450mm beyond the rebar
intersection, and at least 50% of the upper footing reinforcement shall be carry
on into the lower foundation wall to a minimum of 450mm (350 with hook)
beyond the rebar intersection.
3.10 COVER
Minimum cover 75mm.
3.11 OPENINGS
Footings to be continuous under openings unless shown otherwise.
Completion
3.16 REMOVE
Remove from the site materials not used.
4 SELECTIONS
This section relates to formwork, reinforcement, concrete mixes and the placing
of concrete.
Documents
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC B1/AS1 Structure
NZBC E2/AS3 External moisture
AS 1366.3 Rigid cellular plastics for thermal insulation - Rigid
cellular polystyrene - Moulded (RC/PS - M)
NZS 3101.1 Concrete structures standard
NZS 3104 Specification for concrete production
NZS 3109 Concrete construction
NZS 3114 Specification for concrete surface finishes
NZS 3604 Timber-framed buildings
NZS 4229 Concrete masonry buildings not requiring specific
engineering design
AS/NZS 4671 Steel reinforcing materials
AS/NZS 4858 Wet area membranes
CCANZ CP 01 Code of practice for weathertight concrete and
concrete masonry construction
Requirements
1.4 QUALIFICATIONS
Workers to be experienced, competent trades people familiar with the materials
and techniques specified.
2 PRODUCTS
2.3 REINFORCEMENT
Bars to AS/NZS 4671. Grade 300E deformed, other than for ties, stirrups and
spirals, unless shown otherwise on the drawings. Welded reinforcing mesh
Class E to AS/NZS 4671, and 500E mesh to AS/NZS 4671 as modified by NZS
B1/VM1.
3 EXECUTION
Ensure reinforcement is clean and remains clean so that at the time of placing
concrete it is free of all loose mill scale, loose rust and any other contamination
that may reduce bonding capacity.
Securely fix and brace formwork sufficiently to support loads and with joints
and linings tight enough to prevent water loss. Do not use tie wires or rods
unless approved in writing by the Contract Administrator. Unless detailed
otherwise, provide a 19mm chamfer or fillet strip at all interior and exterior
angles of beam and column forms. Mitre at intersections.
Water blast to clean formwork. Keep formwork wet before concrete is placed.
Unless detailed otherwise, set up soffit boxing for beams and slabs to provide a
camber when forms are stripped, of 3mm rise for every 3 metres of total clear
span.
Cut and bend bars using proper bending tools to avoid notching and to the
requirements of NZS 3109: 3.3 Hooks and bends. Minimum radii of
reinforcement bends to NZS 3109, table 3.1, Minimum radii of reinforcement
bends. Do not rebend bars. Where rebending is approved, use a purpose built
tool, proper preparation and preheating.
3.4 ADJUSTMENTS
Use a purpose built tool for on site bending and to deal with minor adjustments
to steel reinforcement.
3.9 CASTING IN
Build in all grounds, bolts and fixings for wall plates and bracing elements,
holding down bolts, pipes, sleeves and fixings as required by all trades and as
shown on the drawings, prior to pouring the concrete.
Form all pockets, chases and flashing grooves as required by all trades and as
shown on the drawings.
Wrap all pipes embedded in concrete with tape to break the bond and to
accommodate expansion. Do not embed pipes for conveying liquids exceeding
a temperature of 50°C in concrete.
3.16 COMPACTION
Use power operated vibrators on foundations, vertical constructions and
beams.
3.21 REMOVE
Remove all unused materials and all concrete and reinforcing debris from the
site.
4 SELECTIONS
© CIL Masterspec Mar 2023 3101 CONCRETE WORK - BASIC Page 70
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC D1/AS1 Access routes
NZS 3114 Specification for concrete surface finishes
NZS 3121 Water and aggregate for concrete
Requirements
1.3 QUALIFICATIONS
Workers to be experienced, competent and familiar with the materials and
techniques specified.
1.4 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed and how instructions to proceed will be given. Before casting
the sample panel arrange a meeting with the reviewer to confirm the method of
preparing the sample. Provide the following samples for review:
Sample A Sample B
Sample PV1.a Concrete: in situ PV1.b Concrete: in situ
description: concrete with standard concrete with standard
10mm aggregate chip, 10mm aggregate chip,
Peter Fell [675] pigment Peter Fell [675] pigment
oxide and U5E medium oxide and acid etched
exposed aggregate finish surface finish
Sample type: Portable control sample Portable control sample
Sample size: 500mm x 500mm 500mm x 500mm
Number: Two (one sandblasted and One
one exposed with retarder
and wash)
Location: TBA TBA
Supporting N/A N/A
documentation:
Reviewer: Landscape Architect Landscape Architect
Time for 10 working days 10 working days
review:
Review Appearance (texture, Appearance (texture,
criteria: colour) and level of colour) and level of
exposure exposure
2 PRODUCTS
2.4 SEALERS
Proprietary penetrating or surface sealers. Refer to SELECTIONS for brand
and type.
3 EXECUTION
Conditions
3.1 RESPONSIBILITY
Take responsibility for determining the method of producing the specified
finished surface.
3.2 PROTECTION
Protect and maintain the specified finish where necessary during any handling,
erection or subsequent construction operation to ensure a clean undamaged
surface at completion of the contract works.
3.3 GENERAL
Except where noted otherwise on the drawings or in the specification,
tolerances in regard to colour and surface to the requirements of NZS 3114 for
each finish specified.
Application
Finishing
3.8 GENERAL
© CIL Masterspec Mar 2023 3124 FINISHES TO WET CONCRETE Page 75
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Achieve the standard of the specified finish required, direct from the formwork
with a minimum of attention to the stripped surface.
Exposed aggregate
Colour concrete
Sealer
3.15 SEALER
Apply selected sealer to the manufacturers recommendations.
Special effects
Acid washing
4 SELECTIONS
4.4 SEALER
Location: All in situ concrete pavement
Manufacturer/type: Peter Fell
System: PFL Natural Sealer. Two coats
This section relates to the supply and installation of hollow concrete masonry to
NZS 4229, as modified by NZBC E2/AS3, including;
concrete masonry, mortar, reinforcement and grouting
self insulating concrete masonry
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC B1/AS1 Structure
NZBC E2/AS3 External moisture
AS/NZS 2699 Built-in components for masonry
NZS 3103 Sands for mortars and plasters
NZS 3109 Concrete construction
NZS 3121 Water and aggregate for concrete
NZS 3604 Timber-framed buildings
NZS 4210 Masonry construction: Materials and workmanship
NZS 4229 Concrete masonry buildings not requiring specific
engineering design
NZS 4230 Design of reinforced concrete masonry structures
AS/NZS 4455.1 Masonry units, pavers, flags, and segmental
retaining wall units - Masonry units
AS/NZS 4671 Steel reinforcing materials
AS/NZS 4858 Wet area membranes
CCANZ CP 01 Code of practice for weathertight concrete and
concrete masonry construction
NZCMM NZ Concrete Masonry Manual section 6.1 Masonry
Retaining Walls
Requirements
1.4 QUALIFICATIONS
Carry out all masonry work with people competent and experienced in this type
of work, under the supervision of a suitably qualified tradesperson as required
in NZS 4229 and NZS 4210.
1.7 TESTS
Carry out all required tests in accordance with NZS 4210: appendix 2A,
Compressive strength tests for mortar and grout.
Performance
1.9 DURABILITY
To NZS 4210, Table 2.E1 - Masonry durability requirements. Refer to
SELECTIONS.
2 PRODUCTS
2.2 REINFORCEMENT
Grade 500E to AS/NZS 4671 deformed mild steel except for ties in plain round
mild steel and as detailed.
Refer to the Concrete section for reinforcing and mesh for slabs.
2.3 MORTAR
Sand to NZS 3103. Chloride levels to not exceed 0.04% by dry weight of sand.
Mortar to NZS 4210: section 2.2, Mortar. Compressive strength minimum 12.5
MPa at 28 days
2.4 GROUT
To NZS 4210: section 2.3, Grout, with minimum compressive strength of 17.5
MPa.
2.5 WATER
To NZS 3121. Water from a territorial authority/NUO water supply is
acceptable.
3 EXECUTION
3.2 STORAGE
Store masonry units clear of the ground, under cover and well ventilated until
placed in the work.
Handle and store reinforcing steel and accessories without damage or
contamination. Store on timber fillets on hard ground in a secure area clear of
any building operation. Lay steel fabric flat.
Ensure reinforcement is clean and remains clean so that at the time of placing
concrete it is free of all loose mill scale, loose rust and any other contamination
that may reduce bonding capacity.
3.6 REINFORCEMENT
Reinforcement to NZS 4229 and NZS 4210: 2.6, Reinforcing details.
© CIL Masterspec Mar 2023 3320 CONCRETE MASONRY Page 80
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Cut and bend bars using proper bending tools to avoid notching and to the
requirements of NZS 3109. Do not rebend bars. Where rebending is
approved, use a purpose built tool, proper preparation and preheating.
3.8 COVER
Cover to NZS 4210, Table 2.E1 - Masonry durability requirements, refer to
DURABILITY clause in SELECTIONS.
3.9 TOLERANCES
Construct within the tolerances set out in NZS 4210: clause 2.6.5, Tolerances,
and clause 2.7.1, General. Lay masonry units with bedding of consistent
thickness throughout.
Reinforcement to NZS 3109: 3.9 Tolerances for reinforcement.
3.10 PROTECTION
Protect fair-faced masonry walls, keeping them clear of mortar droppings, grout
splashes, or stains of any kind.
3.14 BRACING
Provide sufficient temporary lateral bracing to ensure stability until the final
supporting construction is in place.
Inspect walls prior to grouting. Ensure cells are clean and reinforcement is
correctly placed. Where "high lift" (to NZS 4210) grouting is used, seal the
clean out holes and brace to prevent blow outs.
3.21 BUILD-IN
Build-in plugs, bolts, ties, metal flashings, dowels, fastenings and fixings as
required by all trades and as shown on the drawings.
3.24 REMOVE
Remove from the site materials not used.
4 SELECTIONS
Width: 200mm
Bond: stretcher
4.3 GROUT
Design strength: 20 MPa at 28 days
Aggregate size: 13.2mm maximum
Note: if expansive agents are used the minimum strength must be 20 MPa or
the design strength whichever is greater.
Related work
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC D1/AS1 Access routes
NZS 3602 Timber and wood-based products for use in building
NZS 3604 Timber-framed buildings
BRANZ BU 497 Stair construction
Requirements
1.6 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed and how instructions to proceed will be given.
Sample Notes:
All samples are to be fixed control samples
Location is to be confirmed by contractor prior to commencement.
Refer to Selections for specification of timber
Slip resistance test results to be provided for all samples.
All samples to be reviewed by Landscape Architect
Allow 10 workings days for completion of sample review. Review of
samples will only be undertaken once completion of all surface
finishes and sealants are applied.
All samples are to be provided in tandem for comparison and located
within contractor's yard or other agreed location for reference during
construction.
Approved samples are to be retained until final works have been done
and approved by the Landscape Architect.
2 PRODUCTS
Materials
3 EXECUTION
Conditions
3.1 GENERALLY
Execution to include those methods, practices and processes contained in the
current syllabus for the National Certificate in Carpentry and the National
Certificate in Joinery (cabinetry, exterior joinery, stairs).
Application
Completion
3.9 LEAVE
Leave work to the standard required by following procedures.
3.10 REMOVE
Remove all debris, unused materials and elements from the site.
4 SELECTIONS
This section relates to the fabrication and installation of exterior handrails and
timber balustrades.
Related work
Documents
2 PRODUCTS
2.3 HARDWARE
Handrail brackets, metal supports, angles and sundry fittings, all as shown and
described on the drawings.
3 EXECUTION
Conditions
3.1 GENERALLY
© CIL Masterspec Mar 2023 4851 EXTERIOR HANDRAILS & TIMBER BALUSTRADES Page 88
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Application
3.2 HANDRAILS
Fabricate and install the handrails and balustrading as detailed, complete with
all associated metal componentry and hardware. Unless otherwise detailed
construct to comply with NZBC F4/AS1 and NZBC D1/AS1: Access routes.
Completion
3.3 LEAVE
Leave work to the standard required by following procedures.
3.4 REMOVE
Remove all debris, unused materials and elements from the site.
4 SELECTIONS
© CIL Masterspec Mar 2023 4851 EXTERIOR HANDRAILS & TIMBER BALUSTRADES Page 89
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the fabrication and installation of steel items, including:
Fabricated items
Circular hollow sections
Steel plate
Documents
Documents listed above and cited in the clauses that follow are part of this
specification. However, this specification takes precedence in the event of it
being at variance with the cited document.
© CIL Masterspec Mar 2023 4911 STEEL METALWORK Page 90
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Requirements
1.3 QUALIFICATIONS
Refer to 1270 CONSTRUCTION for requirements relating to qualifications.
Metalworkers to be qualified as welders and experienced in working with steel
and the techniques specified.
2 PRODUCTS
Materials
Components
2.4 BOLTS
Similar composition and mechanical properties to the parent metal, selecting
type and size to suit the work and its location.
2.5 NAILS
Spiral rolled flat-head/clout type, with similar composition and mechanical
properties to the parent metal. Select length and gauge to suit the work and its
location.
3 EXECUTION
Conditions
3.5 PREPARATION
Ensure location and substrate is ready to receive the elements and will allow
work of the required standard.
3.6 FLASHINGS
Select and use sheet metals suited to the element, process or finish specified,
jointing them as necessary to allow full development of their expected durability
with a minimising of corrosion and to BRANZ BU 567.
Assembly
3.7 PROTECTION
During fabrication protect all surfaces which will be visible in completed work.
3.9 CORNERS
Unless specified otherwise, mitre junctions of identical sections.
3.10 HOLES
Form without distortion of surrounding metal.
3.12 CLEANING
Remove all burrs and sharp arrises which would be visible after fixing, or a
hazard to the user.
Assembly - Welding
3.15 PREPARATION
Remove grease, dirt, moisture and oxide from edges being welded. Remove
scale and residue from arc and power cutting by machining or hand grinding.
3.16 ACCURACY
Ensure accurate fit using clamps and jigs where practical. Use tack welds for
temporary attachment where jigging is not practical.
3.18 WELDS
Make joints with parent and weld metal fully fused throughout with no
inclusions, holes, porosity or cracks.
3.19 SPATTER
Prevent weld spatter falling on surfaces of materials which will be self finished
and/or visible in completed work.
3.20 RESIDUES
Ensure complete removal of flux residues and slag.
Application
3.24 INSTALLATION
Locate plugs accurately and use in accordance with the manufacturer's
requirements. Fix plumb, level and true to line. Comply with the specified
standards, the reviewed shop drawings and installation details, including
brackets, bolts, fixings, grout, bedding compounds and sealants.
3.25 LOADING
Elements must not carry any structural load unless designed to do so. Do not
use as strutting or support when in place.
3.26 FABRICATE
Fabricate and assemble in a workshop wherever practicable.
Mark out the work accurately, square and true to line allowing for correct radius
folds and laps to give the dimensions required for neat, close fits when in place.
Use marking methods that do not damage, deface or cause future corrosive
attack to the sheet metal being worked. Do not use carbon-based pencils with
aluminium/zinc alloy coated metals.
3.29 FORMING
Use mechanical methods wherever possible and form and fold sheets square
and true to line and face free of all deformation and defects. Minimise
cold-working and stress build-up and their effects by limiting the amount of
working and avoiding sharp radius bends (minimum 1 x sheet thickness).
3.30 PRE-ASSEMBLE
Pre-assemble in the workshop and match mark items for assembly or erection
on site. Do not strain, twist, bend or open such items to force them into the
correct position while assembling or erecting.
3.31 SEPARATION
Isolate dissimilar materials (metal and non-metal) in close proximity as
necessary by painting the surfaces or fitting separator strips. Place isolators
between metals and treated timber and cement-based materials. Do not use
unpainted lead sheet in contact with or allow water run-off onto zinc-coated and
aluminium/zinc alloy coated metals. Refer also to BRANZ BU 567.
3.34 INSTALLATION
Locate fixings accurately and use in accordance with the manufacturer's
requirements. Fix plumb, level and true to line. Comply with the installation
details and complete with bedding compounds and sealants.
3.35 LOADING
Ensure elements are fully supported unless designed to be self-supporting.
Finishing
3.37 GALVANIZING
After fabrication clean surface and hot-dip galvanize to AS/NZS 4680 and
AS/NZS 4792.
Completion
4 SELECTIONS
This section relates to the fabrication and installation of stainless steel items
used in exterior applications.
It includes:
stainless steel handrails and balustrades
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC F4/AS1. Safety from falling
AS/NZS 1554.6 Structural steel welding - Welding stainless steel for
structural purposes
ASTM A240 Standard specification for chromium and chromium-
nickel stainless steel plate, sheet and strip for
pressure vessels and for general applications
ASTM A276 Standard specification for stainless steel bars and
shapes
ASTM A480 Standard specification for general requirements for
flat-rolled stainless steel and heat-resisting steel
plate, sheet and strip
ASTM A1016 Standard specification for general requirements for
ferritic alloy steel, austenitic alloy steel, and stainless
steel tubes
BS EN 1011-3 Welding. Recommendations for welding of metallic
materials. Arc welding of stainless steels
BRANZ BU 567 E2/AS1 Flashing Requirements
Documents listed above and cited in the clauses that follow are part of this
specification. However, this specification takes precedence in the event of it
being at variance with the cited document.
Requirements
1.3 QUALIFICATIONS
Refer to 1270 CONSTRUCTION for requirements relating to qualifications.
Metalworkers to be experienced, competent trades people familiar with the
materials and techniques specified.
1.4 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed and how instructions to proceed will be given. Provide the
following samples for review:
Sample A
Sample SST handrail including end cap and tactile handrail
description: indicator
Sample type: Portable control sample
© CIL Masterspec Mar 2023 4924 STAINLESS STEEL METALWORK Page 96
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Provide shop drawings to show the general arrangement including, but not be
limited to:
Handrail dimensions, gradient (angle), staunching number and dimensions,
locations and types of fittings and fixtures.
2 PRODUCTS
Fabricated items
2.1 ITEMS
Refer to SELECTIONS.
Materials
Components
2.3 SCREWS
Grade 316 stainless steel self-tapping with the type of head, length, gauge and
thread to suit the work and its location.
2.4 BOLTS
Grade 316 stainless steel, type and size to suit the work and its location.
2.6 NAILS
3 EXECUTION
Conditions
3.4 FLASHINGS
Form to BRANZ BU 567. Ensure the location and the substrate is ready to
receive the fabrication and will allow work of the required standard.
Fabrication general
3.6 PROTECTION
During fabrication protect all surfaces which will be visible in completed work.
3.8 CORNERS
Unless specified otherwise, mitre junctions of identical sections.
3.9 HOLES
Form without distortion of surrounding metal.
3.11 CLEANING
Remove all burrs and sharp arrises which would be visible after fixing, or a
hazard to the user.
3.13 BONDING
Prepare surfaces of metals to receive adhesives by degreasing and abrading
mechanically or chemically. Use adhesives in accordance with the
manufacturer's requirements. Form bond under pressure.
Fabrication - welding
3.20 ACCURACY
Ensure accurate fit using clamps and jigs where practical. Use tack welds for
temporary attachment where jigging is not practical.
3.21 WELDS
Make joints with parent and weld metal fully fused throughout with no
inclusions, holes, porosity or cracks.
3.23 SPATTER
Prevent weld spatter falling on surfaces of materials which will be self finished
and visible in completed work.
3.24 RESIDUES
Ensure complete removal of flux residues and slag.
Completion
3.33 PROTECTION
Provide the following temporary protection of the finished work:
Protective film
© CIL Masterspec Mar 2023 4924 STAINLESS STEEL METALWORK Page 100
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
4 SELECTIONS
Fabricated items
Location/item: Midrail
Manufacturer: TBC
Brand/type: N/A
Profile: CHS
Grade: 316
Dimensions: 50.8mm ∅ x 3mm
Finish: Satin No4 brushed
Hardware
© CIL Masterspec Mar 2023 4924 STAINLESS STEEL METALWORK Page 101
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
4.2 HARDWARE
SST 316 threaded rods
SST 316 socket coachscrews
SST 316 decking screws
SST 316 socket screws
SST 316 bolts
SST 304 nails
© CIL Masterspec Mar 2023 4924 STAINLESS STEEL METALWORK Page 102
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the supply and installation of Total Tactilez products
including:
Nosings
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC D1/AS1 Access Routes
AS 4586 Slip resistance classification of new pedestrian
surface materials
NZS 4121 Design for Access and Mobility - Buildings and
Associated Facilities
Warranties
© CIL Masterspec Mar 2023 6614TT TOTAL TACTILEZ NOSINGS & TRIM Page 103
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Requirements
1.6 NO SUBSTITUTIONS
Substitutions are not permitted to any specified system, or associated
components and products.
1.7 QUALIFICATIONS
Nosing, traction bar, floor trim, transition bar and expansion joint cover
installers to be competent, experienced workers familiar with the materials and
techniques specified.
Performance
2 PRODUCTS
Materials - nosings
Components
Accessories
2.5 CLEANER
Acetone, solvent wipes or spray cleaner suitable for the cleaning of aluminium
surfaces prior to the application of double sided tape and contact with
adhesive.
© CIL Masterspec Mar 2023 6614TT TOTAL TACTILEZ NOSINGS & TRIM Page 104
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3 EXECUTION
Conditions
3.1 INSPECTION
Before starting work inspect the substrate to ensure that it will allow work of the
required standard.
3.2 PROTECTION
Protect adjoining work surfaces and finishes during the installation.
3.3 LAYOUT
Plan the general layout to conform to size and orientation requirements.
3.4 TEMPERATURE
Do not apply Sikaflex® 11FC adhesive in temperatures above 40°C or below
5°C.
3.8 CLEAN
Clean aluminium profiles prior to contact with adhesive or double sided tape, in
accordance with Total Tactilez requirements.
Installation - nosings
Completion
3.10 REPLACE
Replace damaged or marked materials.
3.11 LEAVE
On completion of the installation thoroughly clean the finished products. Leave
surfaces, edges and visible joints free of adhesive, dirt and debris and to the
standard required by following procedures.
© CIL Masterspec Mar 2023 6614TT TOTAL TACTILEZ NOSINGS & TRIM Page 105
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.12 REMOVE
Remove debris, unused materials and elements from the site.
3.13 PROTECT
Protect completed work from damage for the period between completion of
installation and completion of the contract works.
4 SELECTIONS
For further details on selections go to www.totaltactilez.co.nz
Substitutions are not permitted to the following, unless stated otherwise.
© CIL Masterspec Mar 2023 6614TT TOTAL TACTILEZ NOSINGS & TRIM Page 106
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This painting specification assumes that the applicator has the necessary skill,
experience and equipment to undertake the work. The applicator remains
responsible for ensuring proper completion of the work.
Documents
1.1 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
AS 1627 Metal finishing - Preparation and pre-treatment of
surfaces, Parts 1-10
AS/NZS 2312.1 Guide to the protection of structural steel against
atmospheric corrosion by the use of protective
coatings - Part 1: Paint coatings
AS/NZS 2312.2 Guide to the protection of structural steel against
atmospheric corrosion by the use of protective
coatings - Part 2: Hot dip galvanizing
AS/NZS 5131 Structural Steelwork - Fabrication and Erection
AS/NZS ISO Quality management systems - requirements
9001
MPNZA Health and Safety Program
Health and Safety at Work Act 2015
Warranties
Requirements
1.5 QUALIFICATIONS
Painters to be experienced competent workers, familiar with the materials and
the techniques specified.
1.6 NO SUBSTITUTIONS
Substitutions are not permitted to any specified Resene system, or associated
components and products.
1.7 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed and how instructions to proceed will be given. Provide the
following samples for review:
Sample A
Sample Resene System '5D', colour TBC
description:
Sample type: Portable sample for review
Number: One
Location: TBA
Supporting N/A
documentation:
Reviewer: Contract administrator
Time for review: 10 working days
Review criteria: Colour, appearance
Performance
© CIL Masterspec Mar 2023 6745R RESENE PROTECTIVE COATINGS - STEELWORK Page 108
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
2 PRODUCTS
Materials
2.2 PRIMER
Refer to SELECTIONS for type.
2.3 THINNERS/ADDITIVES
Use only if and when expressly directed by Resene for their particular product
in a particular application.
Accessories
2.4 ACCESSORIES
Contact your local Resene ColorShop, if required, for a full range of
accessories and usage advice.
3 EXECUTION
Conditions
Ensure prepared and painted surfaces are clean and dry. Do not carry out
preparation or painting when the ambient relative humidity exceeds 85%. The
temperature of the substrate to be 3°C above Dew Point.
© CIL Masterspec Mar 2023 6745R RESENE PROTECTIVE COATINGS - STEELWORK Page 109
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.3 COMPATIBILITY
Ensure that materials are as required by their manufacturers for the particular
surface and conditions of exposure, and that materials used within each
painting system are compatible with each other and are from the same
manufacturer.
Where steel is only partly encased, then extend priming 100mm maximum into
and above the concrete encasement area.
© CIL Masterspec Mar 2023 6745R RESENE PROTECTIVE COATINGS - STEELWORK Page 110
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Application - general
Completion
3.15 LEAVE
Leave the whole of this work uniform in gloss, texture and colour, free from
painting defects, clean and unmarked, and to the standard required by
following procedures.
4 SELECTIONS
For further details on selections go to www.resene.co.nz.
Substitutions are not permitted to the following, unless stated otherwise.
© CIL Masterspec Mar 2023 6745R RESENE PROTECTIVE COATINGS - STEELWORK Page 111
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
© CIL Masterspec Mar 2023 6745R RESENE PROTECTIVE COATINGS - STEELWORK Page 112
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to hot dip galvanizing of structural steel framing, general
steel articles and fabricated steel assemblies.
Related work
Documents
Requirements
1.3 QUALIFICATIONS
Galvanizers to be experienced, competent workers, and familiar with the
materials and techniques specified.
© CIL Masterspec Mar 2023 6781 HOT DIP GALVANIZING Page 113
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Performance
2 PRODUCTS
Materials
3 EXECUTION
Conditions
3.1 GENERALLY
The galvanized coating on all steel articles shall conform to the requirements of
AS/NZS 4680 and AS/NZS 2312.2, as specified.
3.2 SUPERVISION
All galvanising operations to be supervised by a competent person.
3.3 DEFECTS
Discard any material or fabricated items showing defects affecting its structural
integrity.
Galvanizing
© CIL Masterspec Mar 2023 6781 HOT DIP GALVANIZING Page 114
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Ensure that tolerances in screw cutting have made allowance for galvanizing.
Degrease and sweep abrasive blast using a non metallic media galvanized
steelwork to be painted to NZS 4680, Appendix I, Information on the use of
sweep (brush) blast cleaning of galvanized steel prior to painting
3.6 INSPECTION
Integrity of the coating to be determined by visual inspection and coating
thickness measurement, to AS/NZS 4680.
For critical locations, with exposed or painted finish, all spikes to be removed
and all edges free from lumps and runs.
Repairs
Priming
Completion
3.10 ENSURE
Ensure all elements are free of marks or blemishes.
3.11 REPLACE
Replace damaged, cracked or marked elements.
© CIL Masterspec Mar 2023 6781 HOT DIP GALVANIZING Page 115
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.12 LEAVE
Leave work to the standard required by following procedures.
4 SELECTIONS
© CIL Masterspec Mar 2023 6781 HOT DIP GALVANIZING Page 116
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC E1/AS1 Surface water
NZBC E2/AS1 External moisture
AS/NZS 3500.3: Plumbing and drainage - Stormwater drainage
2018
Plumbers, Gasfitters and Drainlayers Act 2006
Warranties
Requirements
© CIL Masterspec Mar 2023 7451AL ALLPROOF LEVEL THRESHOLD DRAINAGE SYSTEMS Page 117
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
1.5 QUALIFICATIONS
Drainlayers / contractors to be experienced, competent and familiar with the
materials and techniques specified. Carry out all work under the direct
supervision of a certifying drainlayer under the Plumbers, Gasfitters and
Drainlayers Act 2006.
1.9 NO SUBSTITUTIONS
Substitutions are not permitted to any of the specified Allproof Industries
systems, components and associated products listed in this section.
Performance
2 PRODUCTS
3 EXECUTION
Conditions
© CIL Masterspec Mar 2023 7451AL ALLPROOF LEVEL THRESHOLD DRAINAGE SYSTEMS Page 118
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Installation
3.2 GENERAL
All work to NZBC E2/AS1: Level Threshold, 7.3.2.1 system materials and
construction, NZBC E1/AS2 as modified by AS/NZS 3500.3: 2018 Plumbing
and drainage - Stormwater drainage and Allproof Industries Installation Details.
Installation - connection
3.5 CLEAN
Clean and flush out the whole installation and remove all silt and debris before
handing over.
Completion
3.6 REPLACE
Replace damaged or marked elements.
3.7 LEAVE
Leave the whole of this work free of all debris. Leave work to the standard
required by following procedures.
3.8 REMOVE
Remove debris, unused materials and elements from the site.
© CIL Masterspec Mar 2023 7451AL ALLPROOF LEVEL THRESHOLD DRAINAGE SYSTEMS Page 119
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
4 SELECTIONS
For further details on selections go to www.allproof.co.nz.
Substitutions are not permitted to the following, unless stated otherwise.
© CIL Masterspec Mar 2023 7451AL ALLPROOF LEVEL THRESHOLD DRAINAGE SYSTEMS Page 120
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Related work
Documents
Documents listed above and cited in the clauses that follow are part of this
specification. However, this specification takes precedence in the event of it
being at variance with the cited document.
Performance
1.3 TESTING
Before metalling test subgrade and on completion of metalling test sub base to
NZS 4402, test 6.1.1. Take one test every 100 m².
No more than 5% of the test shall be less than the minimum allowable
CBR.
No single test shall be less than 75% of the minimum allowable CBR.
2 PRODUCTS
Materials
2.1 HARDCORE
Scoria or crushed rock to GAP (General All Passing) 40 grading.
3 EXECUTION
Conditions
3.6 COMPACTION
Do not use earthmoving equipment for compaction.
Application
Alternative compaction plant may be used provided it can be shown that the
density requirement can be achieved.
© CIL Masterspec Mar 2023 8212 SUB BASES TO SEALING & PAVING Page 122
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Spread and level in layers of not more than 150mm loose depth where required
to make up from subgrade to the underside of sub base or to where shown on
the drawings. Compact as described under GRANULAR FILL.
Completion
3.14 LEAVE
Leave work to the standard required by following trades.
3.15 REMOVE
Remove debris and unused materials from the site.
© CIL Masterspec Mar 2023 8212 SUB BASES TO SEALING & PAVING Page 123
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the installation of loose aggregate and stone paving for
driveway, carpark and footpath areas.
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 4407 Methods of Sampling and Testing Roading
Aggregates
TNZ B/02 Specification for Construction of Unbound Granular
Pavement Layers
Requirements
1.3 QUALIFICATIONS
Workers to be experienced, competent trades people familiar with the materials
and techniques specified.
1.4 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed and how instructions to proceed will be given. Provide the
following samples for review:
Sample A
Sample Aggregate footpath sample
description:
Sample type: Sample bag of hoggin
Number: Two
Location: One off site to Landscape Architect, one to be kept
on site
Supporting Confirmation of hoggin specification from supplier
documentation:
Reviewer: Landscape Architect
Time for review: 10 working days
Review criteria: Appearance, texture and colour
2 PRODUCTS
Materials
2.2 HOGGIN
© CIL Masterspec Mar 2023 8226 GRAVEL & STONE PAVING Page 124
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
1.5 to 3.75mm Finer Grade Limestone Chip, GAP 7 aggregate and cement
mixed in the following proportions;
Limestone: 50%
GAP 7: 45%
Cement: 5%
Mix Hoggin in rotary mixers prior to placing onto the prepared base.
3 EXECUTION
Conditions
3.4 EDGING
Install on completion of the preparation of the subgrade, true to line and grade
to match the design levels or surrounding ground levels.
3.5 BASECOURSE
To TNZ B/02. Lay basecourse on the prepared subgrade, free of loose
material or surface water. Lay in layers to achieve the design depth and
compacted in layers not exceeding 100mm.
Compact with no less than 4 passes of a vibrating pedestrian roller or plate
compactor. Leave the surface fully compacted with a tight surface with no
loose aggregate stones.
3.7 BACKFILL
© CIL Masterspec Mar 2023 8226 GRAVEL & STONE PAVING Page 125
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Where paths are constructed in grassed areas, respread and compact topsoil
adjacent to the paving edging to fill all depressions and voids and provide a
compact and free draining surface, and re-grass. Re-use topsoil from stripping
operations.
3.8 CLEAN UP
Clean up as the work proceeds.
3.9 LEAVE
Leave the whole of this work in a sound, coherent, voidless and level to grade
condition, free of any defects.
3.10 REMOVE
Remove debris, unused materials and elements from the site.
4 SELECTIONS
4.2 HOGGIN
Location: As shown in the drawings
Limestone chip: LAP6 hoggin with 3mm high grade oxide or quick
lime additive
Bed thickness: 80mm
© CIL Masterspec Mar 2023 8226 GRAVEL & STONE PAVING Page 126
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the design, supply and installation of a synthetic turf
system and sub-base, to meet the requirements of various outdoor applications
including;
Landscaping
Commercial, Domestic
Educational Establishments
All weather multi-use playing surfaces, Kindergartens, playgrounds.
Documents
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 5828 Playground equipment and surfacing
Warranties
contract works.
Requirements
1.7 QUALIFICATIONS
Fitters to be experienced, competent trades people familiar with the materials
and techniques specified.
1.8 NO SUBSTITUTIONS
Substitutions are not permitted to any of the specified systems, components
and associated products listed in this section.
1.11 INSPECTIONS
- Review final base course compaction and profiling
- Review edge fixing points
- Review seam locations and direction
- Review final installed product
2 PRODUCTS
Pile height maximum variation ± 15% of the mean height, with pile distribution
uniform over the whole surface.
Components
Accessories
2.4 DRAINAGE
Drainage laid to manufacturer's specification.
3 EXECUTION
Conditions
Sports surfacing:
no ridges, bumps or hollows to cause a hazard or to deflect a ball
from its true path
gradients not greater than 1:100 in any direction
deviation from the finished plane, on a 10m grid the difference in level
between adjacent grid points, after taking design gradients into
account, must not exceed 25mm
Refer to SELECTIONS for Profile Falls and Surface Regularity.
Playground surfaces:
deviation from the finished plane, on a 10m grid the difference in level
between adjacent grid points, after taking design gradients into
account, must not exceed 25mm
Installation/application
© CIL Masterspec Mar 2023 8255 SYNTHETIC TURF Page 129
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Completion
3.10 PROTECTION
Keep traffic off finished work for 48 hours after installation.
Provide the following temporary protection of the finished work:
Temporary fencing
Commissioning
At Practical Completion
3.12 HANDOVER
At Final Completion
4 SELECTIONS
Substitutions are not permitted to the following, unless stated otherwise.
Materials
Item: Shockpad
Quantity: 1% of installed quantity
Location: Refer to 1270 CONSTRUCTION
This section relates to the supply and external installation of Total Tactilez
products including:
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
AS/NZS Design for access and mobility - Means to assist the
1428.4.1 orientation of people with vision impairment - Tactile
ground surface indicators
Warranties
© CIL Masterspec Mar 2023 8281TT TOTAL TACTILEZ EXTERIOR TACTILE INDICATORS Page 132
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Requirements
1.7 NO SUBSTITUTIONS
Substitutions are not permitted to any specified system, or associated
components and products.
1.8 QUALIFICATIONS
Product installers to be competent, experienced workers familiar with the
materials and techniques specified.
Performance
2 PRODUCTS
Components
2.2 ADHESIVE
Refer to SELECTIONS.
3 EXECUTION
Conditions
3.1 INSPECTION
Before starting work inspect the substrate to ensure that it will allow work of the
required standard.
3.2 PROTECTION
Protect adjoining work surfaces and finishes during the installation.
© CIL Masterspec Mar 2023 8281TT TOTAL TACTILEZ EXTERIOR TACTILE INDICATORS Page 133
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.3 LAYOUT
Plan the general layout to conform to size and orientation requirements.
Completion
3.7 REPLACE
Replace damaged or marked materials.
3.8 LEAVE
On completion of the installation thoroughly clean the materials. Leave
surfaces, edges and visible joints free of adhesive, dirt and debris and to the
standard required by following procedures.
3.9 REMOVE
Remove debris, unused materials and elements from the site.
3.10 PROTECT
Protect completed work from damage for the period between completion of
installation and completion of the contract works.
4 SELECTIONS
For further details on selections go to www.totaltactilez.co.nz
Substitutions are not permitted to the following, unless stated otherwise.
© CIL Masterspec Mar 2023 8281TT TOTAL TACTILEZ EXTERIOR TACTILE INDICATORS Page 134
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
© CIL Masterspec Mar 2023 8281TT TOTAL TACTILEZ EXTERIOR TACTILE INDICATORS Page 135
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 8409 Management of Agrichemicals
TNZ F/01 Specification for Earthworks construction
Requirements
1.4 QUALIFICATIONS
Workers to be experienced, competent trades people familiar with the materials
and techniques specified. Construction plant and equipment shall only be
operated by licensed or experienced operators as appropriate.
© CIL Masterspec Mar 2023 8310 LANDSCAPE SITE PREPARATION Page 136
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Any suspected myrtle rust finds must be reported immediately to the Project
Administrator. On direction of the Project Administrator immediately notify the
Ministry for Primary Industries (MPI) Exotic Pest and Disease Hotline on 0800
80 99 66
1.8 INSPECTIONS
Notify the Contract Administrator for inspection of the works following:
Identification of unsuitable materials requiring removal
Prior to the placement of any fill material
At the completion of the Site preparation
2 PRODUCTS
Materials
2.2 HERBICIDES
Post-emergence selective chemical to control broadleaf weeds and/or a
non-selective chemical. Submit for review the proposed chemical and area of
use.
3 EXECUTION
Conditions
3.1 DELIVERY
Only deliver material to the site that can be immediately placed in its final
location from the delivery vehicle.
3.2 REPORT
Report any survey pegs, bench marks, and the like on any features, leaving
them undisturbed until approval is given for removal.
© CIL Masterspec Mar 2023 8310 LANDSCAPE SITE PREPARATION Page 137
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Undertake regular inspections and maintain the erosion and sediment control
measures in operational order.
On stabilisation of disturbed soil or upon sufficient ground cover, remove
control measures including the disposal of silt off site.
Installation/application
3.6 TOLERANCES
All cut and fill work shall be free draining and be constructed to the design
levels and shapes to ±100mm. Ensure NZ Building Code ground clearances
are maintained against buildings. Ensure all surfaces are graded to shed water
and maintain overland flow paths.
The clearing of hardstand surfaces shall include saw cutting where necessary,
breaking and excavation of bedding materials and disposal off site. Store on
site cleared materials for re-use.
All grass weed species stolons to be racked out and removed prior to re use on
site.
Unless otherwise specified, do not remove topsoil from the site, and surplus
topsoil shall remain on site.
Place and compact the material to be used for general landscape shaping in
layers not exceeding 150mm, and compact by track rolling in 4 passes with
equipment in excess of 10 tonnes weight or other approved methods to prevent
undue settlement.
Fill material placed adjacent to pipes, walls and other structures shall be
compacted by hand held vibrating plate compaction equipment. Heavy
equipment shall not be operated within one metre of any pipes or structures.
Ensure that all batters are maintained in a stable condition at all times.
Completion
4 SELECTIONS
© CIL Masterspec Mar 2023 8310 LANDSCAPE SITE PREPARATION Page 139
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the supply, preparation and placement of soil and plant
mix for the planting of:
trees
shrubs
lawns
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 4402 Methods of testing soils for civil engineering
purposes
NZS 4454 Composts, soil conditioners and mulches
NZS 8409 Management of Agrichemicals
TNZ F/1 Specification for Earthworks construction
Requirements
1.3 QUALIFICATIONS
Landscapers to be experienced competent workers, familiar with the materials
and the techniques specified.
2 PRODUCTS
Materials
2.1 TOPSOIL
To NZS 4402 and NZS 4454. Top quality screened topsoil stripped from its
original location to a maximum depth of 200mm:
free of pernicious weeds, straw, stones, sticks, clay lumps
free of foreign matter exceeding 25mm dimension.
pH value between 6.5 and 7.5
humus content greater than 50%.
2.3 COMPOST
Organic compost of a friable texture without excessive moisture, free of all
stones and other solids over 20mm in diameter. Compost shall be free of weed
propagules and other physical or chemical contaminants. The compost shall
contain no substances toxic to plants and posess no objectionable odours.
2.4 BACKFILLING
© CIL Masterspec Mar 2023 8321 SOIL & SOIL PREPARATION FOR PLANTING Page 140
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
2.5 HERBICIDES
Post-emergence selective chemical to control broadleaf weeds and/or a
non-selective chemical. Submit for review the proposed chemical and area of
use.
2.6 CHEMICALS
Where chemicals are to be used, work generally to NZS 8409.
Only certified applicators shall be responsible for the application of herbicides.
3 EXECUTION
Conditions
Excavation of existing ground shall be required to form tree pits and new
garden beds. Excavate to required formation levels. All excavations for tree
transplants shall be protected from collapse by shoring as necessary and kept
clear of all loose debris before planting takes place
Should the Contractor excavate to a greater depth than called for by the
drawings or the Landscape Architect written instructions he shall at his own
cost fill to the proper level with compacted hardfill or subsoil as the Landscape
Architect sees fit.
Where excavations extending into sub grade are required to achieve desired
levels and drainage gradients in areas to be planted; the entire subgrade
surface shall be scarified / tilled in two directions to a minimum depth of
100mm. Scarification shall be executed in dry soil conditions and machinery
selected to minimise disturbance, trafficking and compaction of sub grade.
Note that areas located within the dripline of existing trees to be retained shall
not be scarified.
All grass areas to receive planting (and/or associated topsoil buildup) shall be
sprayed in accordance with the specification to prevent weed/grass regrowth
prior to planting (and/or installation of bark soft fall)
3.3 DELIVERY
Only deliver material to the site that can be immediately placed in its final
location from the delivery vehicle. Should the topsoil or other planting material
be left on site long enough for weed growth to occur it is the Contractor’s
responsibility to remove all weed material prior to placement.
© CIL Masterspec Mar 2023 8321 SOIL & SOIL PREPARATION FOR PLANTING Page 141
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
When moving topsoil within the site, select and use plant to minimise
disturbance, trafficking and compaction. Avoid contamination by subsoil,
basecourse, rubbish or material from demolition and/or building work. Minimise
multiple handling of topsoil. Handle topsoil in the driest condition reasonably
possible. Do not handle topsoil during or after heavy rainfall. Do not compact
topsoil. Preserve a friable texture of separate visible crumbs.
3.4 SERVICES
Check for services in the area of this work. Avoid interference or damage to
them. Ensure that all new services are in place before commencing work.
3.5 ENSURE
Ensure that all areas are clean, ready to be worked and clear of any continuing
work by others.
Application
Thoroughly spray grass areas which contain weed growth with a non-selective
herbicide. Apply using protective clothing, in dry, still-air conditions to the spray
manufacturer's requirements.
Carry out final grading of the top 100 - 150mm to ensure a true specified level
and slope and to avoid hollows or other depressions where water may collect.
Loosen unduly compacted areas (such as in traffic routes) by ripping or discing
prior to final levelling.
The final grade shall allow for subsidence so that after settlement the levels
shall be the final specified levels.
All grass weed species stolons to be racked out and removed prior to re use on
site
© CIL Masterspec Mar 2023 8321 SOIL & SOIL PREPARATION FOR PLANTING Page 142
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Grades not otherwise indicated on the plans shall be generally even, flowing
slopes between paths, kerbs, mowing strips and other points of specified
finished level.
Completion
3.10 CLEAN UP
Clean up and remove surplus soil from the site.
3.11 REMOVE
Remove debris, unused materials and elements from the site.
4 SELECTIONS
© CIL Masterspec Mar 2023 8321 SOIL & SOIL PREPARATION FOR PLANTING Page 143
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
8332 PLANTING
1 GENERAL
Documents
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 4454 Composts, Soil Conditioners and Mulches
Requirements
1.4 QUALIFICATIONS
Landscape contractors to be experienced, competent landscapers familiar with
the materials and techniques specified.
1.6 NO SUBSTITUTIONS
Substitutions are not permitted to any of the products listed in this section.
1.7 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed.
Shrub & tree samples – photos may be accepted if clearly show scale
and health of specimens
1.8 INSPECTIONS
Contract Administrator to inspect all plants before planting. They shall be
inspected on delivery to site or at the contractor's depot in a single batch. Any
plant not approved by the Contract Administrator shall be replaced.
Plants to be first class specimens of nursery stock, true to name and type with
well developed and well shaped trunk or stem and head. They shall be well
hardened off to cope with the climatic conditions of the site, and free from pests
and disease.
The roots shall have a high percentage of fibrous roots that are just touching
the edge of their containers. Plants with roots that are wound round their
containers in circular fashion shall be rejected.
Plants shall be free from disfiguring knots, bark abrasions, wind, or freezing
injury or other disfigurements and shall bear evidence of proper pruning.
Where several specimens of the same species are to be selected, evenness of
shape and size is required within the size range specified.
1.9 IDENTITY
Plants to be good and true representatives of their species, cultivar or variety
and each batch shall be labelled.
1.10 LABELLING
Attach legible labels to each plant delivered to site as a separate unit, or to
each box, bundle or bale containing plants. The labels shall give the approved
botanical name, size, age and quantity and other information required to
identify the plant or plants.
Substitutions are not permitted to any of the products listed in this section.
Contractor must notify and gain approval from the Landscape Architect if they
wish to substitute PB for L / L for PB
1.12 HEALTH
Ensure plants are free of pests, diseases, disorders, disfiguring knots damage
or pruning injury.
Replace any plants which die, are significantly damaged, or which show signs
of significant stress or declining health during the contract and maintenance
period. Plants destroyed by vandalism by others or theft once planted are
excluded from this condition.
Ensure:
Plants from a commercial nursery have the appropriate completed
copies of the NZPPI Nursery Management Declaration form and Plant
Transport Declaration form.
Treatment records are provided for non-commercially sourced plants
Myrtaceous plants are within the effective period of cover for the
treatment used at time of dispatch (different treatments and cover
periods are on the NZPPI website).
Any suspected myrtle rust finds must be reported immediately to the Project
Administrator. On direction of the Project Administrator immediately notify the
Ministry for Primary Industries (MPI) Exotic Pest and Disease Hotline on 0800
80 99 66.
Weed Control
All chemical herbicides used are to be non-toxic to human beings, birds and
animals under normal use and only those chemical herbicides registered under
the Pesticides Act may be used.
Where a translocated herbicide such as glyphosate is used around plants in
leaf, an adequate guard must be used for all spraying.
Do not apply herbicide to water plants emerging from water and do not apply
herbicide to plants in the flowing water of streams.
Cultivation
2 PRODUCTS
Materials
Plant material shall be consistent in size and quality, of good nursery stock,
true to name and type with well developed and well shaped trunk or stem and
head.
All plant material shall be available for inspection by the Landscape Architect,
prior to planting.
2.3 TREES
Tree species to have a single well defined leader of 2.5 - 3 meters unless
otherwise specified and a reasonably straight main stem which is sturdy
enough to easily support the crown of the tree under the environmental and
climatic conditions of the planting site.
© CIL Masterspec Mar 2023 8332 PLANTING Page 147
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
2.7 HARDINESS
Plants to be fully hardy having been acclimatized in the nursery to sun,
exposure and cold. Plants which have not been hardened off, drawn plants
with soft growth or plants requiring additional support to that specified will not
be accepted.
2.9 SIZES
For acceptable sizes of plants refer to SELECTIONS. Plants which are larger
than the maximum size may be accepted at the discretion of the Contract
Administrator who may require oversize plants to be pruned. Where plants
have been recently "bagged on" from a smaller nursery grade they will be
deemed to only fulfil the size requirements of the smaller grade.
All plants of the same species to be of similar height and stature (±10%). Plants
supplied later in the contract to replace defective plants are to match the
current size of those previously planted.
Components
2.13 COMPOST
3 EXECUTION
Conditions
3.2 APPROVAL
Do not start preparation or planting until the setting out has been inspected and
approved by the Contract Administrator.
3.7 TOPSOIL
Supply and install topsoil to planting areas to achieve finished surface levels,
and to ensure specified topsoil depths are achieved. Remove existing earth
where necessary to accommodate topsoil and soil conditioner in planters to
achieve finished surface levels.
Installation/application
If planting is carried out without prior approval, realignment and re-siting may
be necessary and shall be at the Contractor’s expense.
Apply approved slow release fertiliser with plants as they are planted. Apply
quantities as recommended by the manufacturer, varying amount as
recommended to suit the size of specimen.
Pierce the bottom of each hole to a depth of 200mm with the tines of a fork or
similar implement to ensure root penetration and free drainage. Roughen the
sides of pits dug by rotary augers.
The base of each hole shall be provided with a 25mm layer of proprietary
compost. Apply fertiliser to the base of the dug hole.
Set plants in their final positions with main stem vertical and at such a depth
that the soil, when firmed down is at the same height as the nursery earth
marks on the stem or the container soil level. Spread out loose roots in a
natural fashion, carefully place the soil under and amongst them to fill all voids
and firmed in.
3.18 PRUNING
Prune any damaged or diseased roots and branches.
The base of each hole shall be provided with a 25mm layer of proprietary
compost. Apply fertiliser to the base of the dug hole.
3.20 BACKFILL
Back fill with finely broken down topsoil free from clay lumps and large clods
and thoroughly mixed with slow release planting fertiliser. Spreading of
planting fertiliser on the soil surface after planting will not be accepted.
3.22 HEELING IN
Heel the soil firmly after planting and thoroughly water.
3.25 PRUNING
Pruning (unless the plant is rejected) shall remove all injured twigs and
branches.
Operations are to be carried out using sharp clean implements to give a clean
sloping cut with one flat face.
All pruning shall be carried out in accordance with the best horticultural
practise, and all pruning operations to trees shall be finished with an approved
protective paint to prevent disease.
3.26 MULCHING
Dress all planter areas with a minimum 100mm depth of mulch.
Apply mulch following planting. Level the soil surface prior to mulch being
applied. Ensure that soil is not mixed with the mulch.
Spread mulch to a generally even level but in particular grade away from plant
stems to avoid the possibility of collar rot.
Ensure mulch is graded away from the paths and kerbs in a way that avoids
mulch spilling from planters.
Completion
All plants shall be maintained for two full growing seasons after planting.
Replace damaged or marked plants during this period.
3.29 REMOVE
The Contractor shall remove all rubbish, excess stakes, planter bags and
undesirable debris, resulting from planting operations from the site, and make
good any damage to existing hard works resulting from the landscape works.
3.30 GRASSING
Contractor shall make good any damage or compaction marks to grassed
areas incurred as a result of landscape works. Damaged areas shall be lightly
cultivated and re sown as necessary to remedy damage and ensure complete
grass coverage over the affected area(s).
3.33 PROTECTION
Provide the following temporary protection of the finished work:
Protective fencing. Ensure full protection of planted areas during the
completion of immediate or adjacent building works, including protection from
dust, water and general damage due to site traffic (pedestrian & vehicular) or
construction activities.
Commissioning
3.35 HANDOVER
Meeting with Landscape Architect / Client representative
4 SELECTIONS
Materials
Components
4.2 MULCH
Mulch type Location Depth
Living Earth More Than All Garden Areas 100mm
Mulch
4.3 FERTILISER
Fertiliser type Location Application rate
Osmocote Exect 8-9 All Planting 5.5kg per cubic metre of
month standard Areas growing garden
© CIL Masterspec Mar 2023 8332 PLANTING Page 153
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Requirements
1.2 QUALIFICATIONS
Workers to be experienced, competent trades people familiar with the materials
and techniques specified.
1.4 NO SUBSTITUTIONS
Substitutions are not permitted to any of the specified systems, components
and associated products listed in this section.
1.5 SAMPLES
Supply a sample of the turf for the approval of the Contract Administrator.
Ensure that all the turfs are similar to the approved sample.
1.6 INSPECTIONS
Contract Administrator to inspect the works following:
cultivation and preparatory work prior to turfing
cultivation and preparatory work prior to seeding
completion of respreading topsoil prior to final levelling and seeding
completion of turf establishment
2 PRODUCTS
Materials - Seed
© CIL Masterspec Mar 2023 8333 TURF LAYING & LAWN SEEDING Page 154
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
All seed label analysis data shall comply with trade standards. Germination
tests must have occurred within the past six months. The germination capacity
of each constituent of the mixture should be not less than 80%, and the purity
of the mixture not less than 90%.
3 EXECUTION
Conditions
Installation/application
Lawn Seeding
3.4 SOWING
Sow the seed mix by broadcasting in two directions, in suitable calm weather,
at a rate of 30 gm/m² using a mechanical spreader.
Lightly brush soil to cover seeds, and lightly roll to ensure a good moisture
content.
Water immediately after sowing and then as often as necessary to keep it moist
until germination and grass is well established.
3.5 TIMING
© CIL Masterspec Mar 2023 8333 TURF LAYING & LAWN SEEDING Page 155
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Carry out sowing from 1st April to 31st May, or from 1st September to 30th
November. When sowing takes place outside this period, when the weather
changes, or when silt control requires its use, mulch the seeding area using
hay.
3.6 FERTILISER
Apply a dressing of fertiliser and work into the top 50mm of soil immediately
prior to sowing.
Refer to SELECTIONS.
3.7 FENCING
Install "Pigs Tails" and warning tape fencing around the perimeter of the sown
area to prevent damage from unauthorised access.
3.10 MOWING
Mow the grass when it has reached a height of 100mm. Cut to 50mm high.
Mow only one third grass length at one mowing. Mow in dry conditions with
sharp mower blades and remove clippings. Use only reel mowers on fine
grasses.
For subsequent mowings, the mowing frequency shall be governed by growth
rate.
Grass height at the completion of the contract to be, 15mm to 20mm for fine
grasses like Fescue/Browntop etc, 20mm to 25mm for coarser grasses like
Ryegrass etc.
Generally
3.13 PROTECTION
Provide the following temporary protection of the finished work:
Protective fencing. Ensure full protection of planted areas during the
completion of immediate or adjacent building works, including protection from
dust, water and general damage due to site traffic (pedestrian & vehicular) or
construction activities.
3.14 MAINTENANCE
© CIL Masterspec Mar 2023 8333 TURF LAYING & LAWN SEEDING Page 156
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
The contractor shall be required to maintain the surface of all grassed areas,
and to cut the grass at intervals throughout the period of the contract works,
including the defects notification/liability period. A final cut shall be made just
prior to the expiration of the defects notification/liability period, and ground
surfaces shall present a uniform, dense continuous surface free from bare
patches.
4 SELECTIONS
Materials
4.1 SEED
Location: Make good all lawn areas damaged or disturbed
during construction works
Mix/Brand PGG Wrightson 'Traditional' Mix
4.2 FERTILISER
Location: Lawn
reinstatement/disturbed
areas
Rate: As below
Rate (kg/ha):
Fertiliser type: 30% Potassic 500
Superphosphate Dolomite Lime 500
© CIL Masterspec Mar 2023 8333 TURF LAYING & LAWN SEEDING Page 157
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 4454 Composts, soil conditioners and mulches.
Requirements
1.4 QUALIFICATIONS
Workers to be experienced, competent landscape people familiar with the
materials and techniques specified. All works shall be undertaken under the
supervision of a qualified arborist in accordance with the best arboricultural
practice. The Contractor shall supply evidence of experience and competence
on request.
1.6 NO SUBSTITUTIONS
Substitutions are not permitted to any of the products listed in this section.
1.7 SAMPLES
Refer to the general section 1270 CONSTRUCTION for details of how samples
will be reviewed.
© CIL Masterspec Mar 2023 8335 TREE PLANTING & TRANSPLANTING Page 158
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Dacrydium cupressinum
Hoheria sexstylosa
Knightia excelsa
Podocarpus totara
Sophora microphylla
1.8 INSPECTIONS
Contract Administrator to inspect all trees before planting. They shall be
inspected on delivery to site or at the contractor's depot in a single batch.
Replace any tree not approved by the Contract Administrator.
Trees to be first class specimens of nursery stock, true to name and type with
well developed and well shaped trunk or stem and head. They shall be well
hardened off to cope with the climatic conditions of the site, and free from pests
and disease.
The roots shall have a high percentage of fibrous roots that are just touching
the edge of their containers. Trees with roots that are wound round their
containers in circular fashion shall be rejected.
Trees shall be free from disfiguring knots, bark abrasions, wind, or freezing
injury or other disfigurements and shall bear evidence of proper pruning.
Where several specimens of the same species are to be selected, evenness of
shape and size is required within the size range specified.
1.9 LABELLING
Attach labels to each tree delivered to site as a separate unit, or to each box,
bundle or bale containing trees. The labels to show the approved botanical
name, size, age and quantity and other information required to identify the
trees.
Substitutions are not permitted to any of the products listed in this section.
Contractor must notify and gain approval from the Landscape Architect if they
wish to substitute PB for L / L for PB
1.11 HEALTH
© CIL Masterspec Mar 2023 8335 TREE PLANTING & TRANSPLANTING Page 159
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Ensure trees are free of pests, diseases, disorders, disfiguring knots damage
or pruning injury.
2 PRODUCTS
Ensure:
Plants from a commercial nursery have the appropriate completed
copies of the NZPPI Nursery Management Declaration form and Plant
Transport Declaration form.
Treatment records are provided for non-commercially sourced plants.
Myrtaceous plants are within the effective period of cover for the
treatment used at time of dispatch (different treatments and cover
periods are on the NZPPI website).
Any suspected myrtle rust finds must be reported immediately to the Project
Administrator. On direction of the Project Administrator immediately notify the
Ministry for Primary Industries (MPI) Exotic Pest and Disease Hotline on 0800
80 99 66.
Materials
Plant material shall be consistent in size and quality, of good nursery stock,
true to name and type with well developed and well shaped trunk or stem and
head.
All plant material shall be available for inspection by the Landscape Architect,
prior to planting.
2.3 TREES
Tree species to have a single well defined leader and a reasonably straight
main stem which is sturdy enough to easily support the crown of the tree under
the environmental and climatic conditions of the planting site.
© CIL Masterspec Mar 2023 8335 TREE PLANTING & TRANSPLANTING Page 160
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Trees shall have well developed vigorous branch systems of normal habit,
dimensions and density for a well grown nursery plant of their species. Trees
which have 'leggy', narrow or thin branch systems will not be accepted.
2.7 HARDINESS
Trees to be fully hardy having been acclimatized in the nursery to sun,
exposure and cold. Trees which have not been hardened off and drawn plants
with soft growth or plants requiring additional support to that specified will not
be accepted.
2.8 COMPOST
Proprietary top quality compost to NZS 4454 Composts, Soil Conditioners and
Mulches.
2.9 MULCH
To NZS 4454 Composts, Soil Conditioners and Mulches. Grade 3 Bark Mulch.
2.10 SIZES
For acceptable sizes of plants refer to SELECTIONS. Plants which are larger
than the maximum size may be accepted at the discretion of the Contract
Administrator who may require oversize plants to be pruned. Where plants
have been recently "bagged on" from a smaller nursery grade they will be
deemed to only fulfil the size requirements of the smaller grade.
All plants of the same species to be of similar height and stature (&plus minus
10%). Plants supplied later in the contract to replace defective plants are to
match the current size of those previously planted
Components
2.12 STAKING
All staking timber is to be treated as follows:
2.15 FERTILISERS
All plants shall be planted with controlled, slow release fertiliser of composition
6:15:3 N:P:K. (Nitrogen, Phosphorus and Potassium).
The fertiliser shall be mixed with the soil placed as backfill around the sides of
the root ball - not on the base of the pit or on top of the existing root ball.
© CIL Masterspec Mar 2023 8335 TREE PLANTING & TRANSPLANTING Page 161
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3 EXECUTION
Planting Generally
3.2 SERVICES
It is the Contractor’s responsibility to check for services in the area of work and
avoid interference or damage to them
3.4 DRAINAGE
Install 100mm scoria drainage layer to base of tree pits in areas of poor natural
drainage.
3.5 LIFTING
Protect all tree limbs at contact points with lifting equipment.
Lift trees by strops under the root ball of the tree. Lifting by the bole of the
trunk is not permitted.
Lift in one action from the transportation vehicle to the prepared tree pit.
3.7 ENSURE
Ensure that areas for planting are clean, ready to be worked and clear of any
continuing work by other trades. Do not start until work area is ready
© CIL Masterspec Mar 2023 8335 TREE PLANTING & TRANSPLANTING Page 162
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Planting positions shall be laid out in accordance with the planting plans and
approved by the Landscape Architect prior to planting. The Contractor shall
contact the Landscape Architect 48 hours before planting each stage to
arrange a meeting for sample plant layout to be approved.
If planting is carried out without prior approval, realignment and re-siting may
be necessary and shall be at the Contractors expense
Apply approved slow release fertiliser with trees as they are planted. Apply
quantities as recommended by the manufacturer, varying amount as
recommended to suit the size of specimen.
Backfill in 150 mm layers using rod or fingers to evenly firm without compaction
to a level that will allow the top of the root ball to finish flush with surrounding
ground. The soil shall be lightly consolidated, without compaction, heeling each
plant firmly round the root collar.
Tie plants at 2/3 the height of the main stem leaving enough play for a small
amount of natural movement. Allow to prune any damaged limbs as per
clause. (unless the plant is damaged so badly that it is rejected). Water in
immediately after planting to saturation level in surrounding soil. Spread mulch
over newly planted areas as per clause
3.11 STAKING
Drive two stakes in plumb, position perpendicular (at 90 deg) to the prevailing
wind and locate to avoid wind contact with the tree or shrub at opposite sides of
the planting hole. Drive two stakes into the ground parallel and at 800mm
centres to stand 1200mm min. above ground level and min. 600mm below.
Ensure all stakes are at the same height and orientation to provide visual
consistency across the scheme.
3.12 TYING
Tie the stem firmly and without slack in the belt to avoid movement in high
winds. Cut the strap so that 75mm exceeds the spacer on each side. Tree ties
to be installed to approved sample.
3.13 MULCHING
Cover the surface of the tree root ball with mulch to a depth of 100mm, under
the drip line of the tree.
3.14 WATERING
Keep the root ball well watered immediately after planting and during the tree's
establishment phase. Provide additional watering during the summer season.
Monitor the soil's moisture content on a daily basis and apply water as
necessary until any initial leaf wilt /drop has stopped and the transplant has
become acclimatised to the new position.
© CIL Masterspec Mar 2023 8335 TREE PLANTING & TRANSPLANTING Page 163
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.15 TOLERANCES
The maximum period roots exposed and un-watered shall be 1 hour.
Plant trees facing north.
Plant single leadered trunks as vertically as possible.
Place Multi-leadered trunks without a noticeable lean.
Completion
3.16 REINSTATEMENT
On completion of the work, ensure all surfaces affected by the works are
reinstated to pre-construction condition unless specified otherwise.
Tree guy wires shall be taut on completion and re-tightened through the defects
notification/liability period.
Remove all rubbish and spoil from the site on completion of the works, leaving
the site in a clean and tidy condition.
3.18 PROTECTION
Provide the following temporary protection of the finished work:
Protective fencing. Ensure full protection of planted areas during the
completion of immediate or adjacent building works, including protection from
dust, water and general damage due to site traffic (pedestrian & vehicular) or
construction activities.
4 SELECTIONS
Components
4.3 MULCH
4.4 FERTILIZER
Requirements
1.3 QUALIFICATIONS
Workers to be experienced, competent landscape people familiar with the
materials and techniques specified.
1.4 PERIOD
Undertake maintenance of the landscaping works regularly for:
12 months From Practical completion of the Landscape Work.
2 MAINTENANCE
2.1 GENERAL
Maintenance shall include watering, weed removal, plant trimming, cultivation,
insect and disease control, checking stakes and ties, pruning and other
accepted horticultural operations to ensure normal and healthy plant
establishment and growth.
Ensure that the plants installed will survive and grow. Water the plants
installed as frequently as necessary.
© CIL Masterspec Mar 2023 8380 LANDSCAPE MAINTENANCE Page 165
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Inspect the landscaping works no less than monthly to confirm the health of the
plants, existence of pests, diseases, or vandalism.
3 EXECUTION
3.1 WATERING
Where planter beds and trees are watered by an automatic irrigation system,
operate and manage the system to ensure that all beds receive adequate water
at all times.
Adjust the watering periods as necessary to accommodate seasonal
fluctuations.
Monitor Trees planted into paved areas for symptoms of water stress and
provide additional watering as necessary.
Carefully monitor transplanted trees for symptoms of water stress and provide
additional watering as necessary.
3.4 FERTILISER
Apply slow release fertiliser to the bedding soil of plants at the time of plant
installation.
Apply further applications of approved, NPK balanced, slow-release fertiliser in
accordance with the maintenance programme. Refer to SELECTIONS.
Application rates shall be as recommended by the fertiliser manufacturer with
regard to the size of plant.
© CIL Masterspec Mar 2023 8380 LANDSCAPE MAINTENANCE Page 166
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.5 MULCH
Supply and install additional mulch and/or bark (the same material as existing)
to ensure all mulch areas have a minimum depth of 75mm.
Specimen Trees
3.10 STAKING
Repair or replace staking as required.
Check ties every two months, to ensure that they have not broken or become
too tight around the trunk. Ties should be maintained firm but not so tight as to
cause damage to the bark. They should be adjusted accordingly over the initial
three growing seasons for planted trees, after which time the majority of stakes
can be removed.
3.11 PRUNING
Undertake regular light pruning of specimen trees over a period of time to avoid
one severe pruning. Excessive foliage removal should be avoided which may
result in wind damage or sun scalding and loss of the tree's aesthetic
appearance. Remove broken or dangerously overhanging branches.
Prune back overhanging branches to a minimum clearance of 2.3m above the
ground. Remove dead and broken branches. Care must be taken when
removing branches to prevent further damage to the tree.
Prune back to a sound healthy branch with a clean cut, in accordance with
good arboricultural practice. Final cuts shall be made as close as possible to
the branch collar without damaging the collar, and apply wound treatment
where necessary.
Dispose of all pruning waste off site.
3.12 FORKING
© CIL Masterspec Mar 2023 8380 LANDSCAPE MAINTENANCE Page 167
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Regularly fork tree pits within paved areas to loosen the ground in order to
avoid compaction, which can reduce the infiltration of water into the ground.
3.14 TRIMMING
Undertake regular trimming of shrubs to maintain the following aspects:
Removal of dead heads after flowering
Removal of dead or old weak growth
Cutting back to encourage growth vigour
Thinning out mass planted areas to allow stronger plants to dominate
3.15 CLIMBERS
Train climbing shrubs to grow over the climbing frame and wires. Adjust
vegetation and tie to wires to encourage even spread over the structure where
necessary.
3.16 HEDGES
Trim hedge shrubs to form low hedges to the height, shape and form shown on
the drawings.
Grass
If necessary top dress the turf with clean screened soil to eliminate minor
hollows. Applications shall be less than 15mm at any one time, preferably
applied in spring or autumn.
Protect and maintain all grassed areas by watering, mowing and spraying to
maintain a good quality turf with a neat appearance.
Completion
Carry out routine trade cleaning of this part of the work including periodic
removal of all cuttings, trimmings, debris and elements from the site.
3.20 PROTECTION
Provide the following temporary protection of the finished work:
Fencing - Refer 1250 TEMPORARY WORKS AND SERVICES
4 SELECTIONS
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 3104 Specification for concrete production
NZS 3109 Concrete construction
NZS 3602 Timber and wood based products for use in building
2 PRODUCTS
Materials
Materials
2.2 STAKES
50 x 50 x 500mm long timber pegs to NZS 3602. Treated to H5.
3 EXECUTION
Conditions
3.1 STORAGE
Take delivery of materials undamaged and dry. Store on level hard standings,
protect from damage and keep materials dry until laid.
3.2 INSPECTION
Before starting work inspect the area to ensure that the preliminary works are
in place to correct falls, and all services completed, to allow work of the
required standard.
3.3 ALIGNMENT
Lay edging true and straight to grade, alignment and level. Curves to sweep
evenly around bends without kinks, flats or angles. Form bends with
purpose-made corner blocks.
3.4 TOLERANCES
Application
Completion
3.6 REPLACE
Replace damaged, cracked or marked elements.
3.7 LEAVE
Leave work to the standard required by following procedures.
3.8 REMOVE
Remove debris, unused materials and components from the site.
4 SELECTIONS
Materials
This section relates to the supply and erection of exterior light timber framing
and decking.
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC B2/AS1 Durability
NZBC D1/AS1 Access routes
NZBC E2/AS1 External Moisture
AS/NZS 1328.1 Glued laminated structural timber - Performance
requirements and minimum production requirements
AS/NZS 1748.1 Timber - Solid - Stress graded for structural purposes
- General requirements
AS/NZS 2269.0 Plywood - Structural - Specification
AS/NZS 2904 Damp-proof courses and flashings
NZS 3602 Timber and wood-based products for use in building
NZS 3603 Timber structures standard
NZS 3604 Timber-framed buildings
NZS 3622 Verification of timber properties
NZS 3640 Chemical preservation of round and sawn timber
NZS 4121 Design for access and mobility - Buildings and
associated facilities
AS/NZS 4347.0 Damp-proof courses and flashings - Methods of test -
General introduction, list of methods and test
specimen requirements
Performance
1.3 DIMENSIONS
All timber sizes are actual minimum dried sizes.
Requirements
2 PRODUCTS
2.5 NAILS
Type to NZS 3604, section 4: Durability, and of the size and number for each
particular types of joint as laid down in the nailing schedules of NZS 3604,
sections 6-10.
2.6 SCREWS
Wood screws to the requirements of NZS 3604, 2.4 Fastenings and
Fabrication, and section 4, Durability, and of the type, number and form
required for each screw application to NZS 3604, sections 6 - 10.
2.9 CONNECTORS
© CIL Masterspec Mar 2023 8422 TIMBER STRUCTURES, DECKS & PERGOLAS Page 173
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Comply with the requirements of NZS 3604, section 4: Durability, and of the
number and form required for each particular junction to NZS 3604, sections
6-10. Connectors and structural brackets to the connector manufacturer's
design for particular locations shown on drawings.
For exterior timber, timber in damp areas and timber subject to occasional
wetting, use only stainless steel (or equivalent) fixings and connectors, when
the timber is treated with; Copper Azole (CuAz, Preservative code 58), Alkaline
Copper Quaternary (ACQ, Preservative code 90), Micronise Copper Azole
(code 88) or Micronised Copper Quaternary (code 89).
2.13 CONCRETE
For piles and footings, 17.5 MPa prescribed mix concrete to NZS 3104, section
3, Provisions for prescribed mix concrete, and NZS 3604, section 6.4.5, Pile
footings.
3 EXECUTION
Conditions
Installation
3.3 SEPARATION
Separate all timber framing timbers, except H4 and H5, from concrete,
masonry and brick by;
a full length DPC overlapping timber by at least 6mm; or
a 12mm minimum free draining air space
Separate H3.2 structural timber, with a DPC, from H4 or H5 ground contact
timber, if the junction is within 300mm of the ground.
© CIL Masterspec Mar 2023 8422 TIMBER STRUCTURES, DECKS & PERGOLAS Page 174
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.4 SET-OUT
Set out framing in accordance with the requirements of NZS 3604. When
necessary provide framing to suit any required cladding/lining control joints.
3.6 FRAMING
Frame to required loading and bracing complete with trimmers and nogs, all
fabricated and fastened to NZS 3604.
Completion
4 SELECTIONS
4.3 DECKING
Refer to 4383 TIMBER DECKING for exterior timber board decks
4.4 DPC
Brand/type: To be proposed by the Contractor for approval.
4.5 NAILS
Location Type Material Finish
© CIL Masterspec Mar 2023 8422 TIMBER STRUCTURES, DECKS & PERGOLAS Page 175
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
4.6 SCREWS
Refer to 4383 TIMBER DECKING for decking screws
4.8 CONNECTORS
Location Type Material Finish
Timber step transition Joist hanger 316 SST -
Timber step transition Angle bracket 316 SST -
© CIL Masterspec Mar 2023 8422 TIMBER STRUCTURES, DECKS & PERGOLAS Page 176
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.3 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZBC F4/AS1 Safety from falling
NZBC F9/AS1 Residential Pool Barriers
AS/NZS 2728 Prefinished/prepainted sheet metal products for
interior/exterior building applications - Performance
requirements
NZS 6806 Acoustics - Road-traffic noise - new and altered
roads
NZS 8500 Safety barriers and fences around swimming pools,
spas and hot tubs
© CIL Masterspec Mar 2023 8432BF BOUNDARYLINE FENCING & GATES Page 177
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Warranties
Requirements
1.7 NO SUBSTITUTIONS
Substitutions are not permitted to any of the specified systems, components
and associated products listed in this section.
2 PRODUCTS
Materials
© CIL Masterspec Mar 2023 8432BF BOUNDARYLINE FENCING & GATES Page 178
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
2.3 CONCRETE
Concrete to NZS 3104 for cast-in post footings, minimum compressive strength
of 17.5 MPa.
3 EXECUTION
Conditions
Installation/application
3.5 SETOUT
Property boundaries are to be defined by legal survey pegs. Check location of
underground services prior to digging. Measure out fence line using string line
or laser level, and mark post centres. If the length of the fence line does not
work out as multiples of the standard panel length, adjust the length of the last
section, or the last few sections to suit and cut fence panels to fit. Any cut
edges of steel or aluminium must be coated with zinc rich paint.
© CIL Masterspec Mar 2023 8432BF BOUNDARYLINE FENCING & GATES Page 179
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
4 SELECTIONS
For further details on selections go to www.boundaryline.co.nz
Substitutions are not permitted to the following, unless stated otherwise.
© CIL Masterspec Mar 2023 8432BF BOUNDARYLINE FENCING & GATES Page 180
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
© CIL Masterspec Mar 2023 8432BF BOUNDARYLINE FENCING & GATES Page 181
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
This section relates to the supply and installation of exterior fixtures including;
Benches
Seats
Picnic tables
Fixed sport equipment
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 3104 Specification for concrete production
NZS 3124 Specification for concrete construction for minor
works
Warranties
contract works.
Requirements
1.6 NO SUBSTITUTIONS
Substitutions are not permitted to any specified system, or associated
components and products.
1.7 QUALIFICATIONS
Work to be carried out by trades people experienced, competent and familiar
with the materials and installation requirements specified.
1.8 INSPECTIONS
Carry out inspections of the following:
Custom built fixtures fabricated and ready to be delivered to the site.
Furniture items delivered to site before installation.
Locations or footings prepared to receive furniture or fixtures before
installation.
Services - prior to installation of Street Furniture.
2 PRODUCTS
2.1 PRODUCTS
Refer to SELECTIONS
© CIL Masterspec Mar 2023 8461 STREET & LANDSCAPE FURNITURE Page 183
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
2.3 CONCRETE
Normal concrete or prescribed mix concrete, maximum aggregate size 19mm
to NZS 3104. Refer to the appropriate concrete section(s) for concrete to
furniture bases.
2.7 FIXINGS
To suit application including corrosion resistance.
3 EXECUTION
Conditions
Installation
© CIL Masterspec Mar 2023 8461 STREET & LANDSCAPE FURNITURE Page 184
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
3.6 SERVICES
Allow for installation and connection of services.
Completion
3.10 PROTECTION
Provide the following temporary protection of the finished work:
Protective polythene sheeting
4 SELECTIONS
© CIL Masterspec Mar 2023 8461 STREET & LANDSCAPE FURNITURE Page 186
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
© CIL Masterspec Mar 2023 8461 STREET & LANDSCAPE FURNITURE Page 187
Bespoke Landscape Architects Mauri Ora Mental Health Building 270343
Documents
1.2 DOCUMENTS
Refer to the general section 1233 REFERENCED DOCUMENTS. The
following documents are specifically referred to in this section:
NZS 5828 Playground equipment and surfacing
Playtop NZ
0800752986
ww.playtopnz.co.nz
Warranties
Requirements
1.6 NO SUBSTITUTIONS
Substitutions are not permitted to any specified system, or associated
components and products.
1.7 QUALIFICATIONS
Work to be carried out by trades people experienced, competent and familiar
with the equipment, materials and installation requirements specified.
2 PRODUCTS
Materials
3 EXECUTION
Conditions
Installation
Completion
3.6 PROTECTION
Provide the following temporary protection of the finished work:
Protective polythene sheeting
4 SELECTIONS
© CIL Masterspec Mar 2023 8465 PLAYGROUND EQUIPMENT & SURFACING Page 190