Professional Documents
Culture Documents
*
umT CI2Cf '!1'8'!11 C1 ;a (~)
~~~
~ ~- 110105
Quartermaster (jenera( Quartermaster General's Branch
Civ: 01.1-23011508 Integrated· Headquarters of ·
Ascon : 35190 Ministry of Defence (Army)
New Delhi-110 105
FOREWORD
Jai Hind
Anand
... ... -A
~ G'l o1'C!C1 eft <P ~. TRf '(!af, ,,. TRf '(!af
~ ai 'SI IC'Ill
Jvtaj @en YX t_E/iatt, SJvt, YSJvt 'QC5t ~ '!f8"" IC?I"'' (~)
·. Co( Comdt, 'I'fie t_Eom6ay Sayyers <P~~ imRf, ~ \3ft ~
& ~~ - 110011
Quartermaster General's Branch
JtV(jT'E Integrated Headquarters of
Civ: 011-23011812 Ministry of Defence (Army)
Ascon .: 35340 Kashmir House, Rajaji Marg
New Delhi-110 011
PREFACE
TH110~SAY IAPPiAS
llfl>6 ~I
\}t~
Station : New Delhi --TVKBhatt)
Maj Gen
Dated : 12 April 2012 Addl Dir Gen TE
Anand
'{t'1""f~ "iO q ~ I ~ ~ mm 1 -q~"Gfi it~
q:qfe•um-c><
SuruU Chopra xarr li?!IC"'ll
qcCipt:l !j&llw4 ( fl'"ll)
~"@.t 31 tlt (I "'ttl ('F!lffi ~ ~) mx ~. xi\111\Jl) l117f
CE (QS & C) ~~-110011
~~fcl>(~~) Quartermaster General's Branch I ADGTE
Jt. Dir Gen (Tech Exam) Integrated HQ of MoD (Army)
Kashmir House, Rajaji Marg
New Delhi -110 011
Tele: and Fax: 011 -23018995 (0)
INTRODUCTION
1. I had the privilege to serve in this esteemed organisation during 1986 to 1990 as Assistant
Technical Examiner, and now in the present appointment. During last two decades there has been
a sea change in the construction industry and In the aspirations of the users. A need was felt to
revise the inspection procedure of the TE Directorate considering the available manpower, and the
number of contracts which could be effectively handled by this team of officers.
2. The purpose of this organisation is to suggest corrective measures for the deficiencies
and short comings observed in the worl<s dtlring execution. Since project encompasses civil,
electrical, contract and architectural features, the Inspections should ideally be undertal<en by team
of specialist officers in each category to achieve a meaningful and realistic assessment of the work.
3. I am extremely honoured to work under Maj Gen VK Bhatt, SM, VSM Additional
Directorate General Technical Examination, who was the driving force behind this Compendium.
His vast experience in different appointments on works side viz. GE, CE Zone, CE Command has
greatly contributed to the preparation of this document. The Compendium would not have seen the
light of the day without his encouragement and efforts. Chapters on Rain Water Harvesting,
CO'nservation of Electricity and Water, Green Buildings and Heritage Buildings have been Included
for the first time, which shows his deep concern towards the environment and its protection.
4. Lastly, lot of care has been taken to print the contents as accurately as possible but still
there can be some unnoticed errors which may have crept in. In case any such errors are noticed,
these may be intimated to this Directorate for incorporation in errata/future editions.
~
(Sunil Chopra)
CE (QS&C)
Jt DGTE
Anand
POLICY COMPENDIUM (TECHNICAL)-2012
CONTENTS
Anand
ii
List of Appendix
Appendix ' H' Specimen Form for Issuing Case Closing Letter 123
Anand
SECTION -1
ROLE, VISION, MISSION AND KRA OF ADGTE ORGANISATION
1.1 Role
"To carry out quality audit of works to achieve value addition in delivery of end
,
product in respect of works executed for armed forces including works executed by
MFS for agencies such as DGNP, DGQA, DG CG, KVS etc."
1.2 Vision
"Be the premier teclmical audit agency in the country"
1.3 Mission
"To establish transparent, effective and accountable technical examination agency
which can advice and guide based on factual input to enhance value addition and
maximize the return on money spent over the entire life cycle of the infrastructure".
1.4 KRAs
(a) Improvement in quality of wks.
(b) Insist on modernization and professionalism of construction agencies.
(c) Ensure use of skilled manpower & supervisory staff.
(d) Enhance role of PMG & users.
(e) Implement timely defect rectification and settlement of observations.
(f) Improvement of maintenance services.
(g) Enhance user satisfaction.
(h) Conservation of energy & water.
G) Implement measures for eco-friendly & green construction.
(k) Make the organisation approachable, transparent and user friendly.
(1) Enhance and exploit the potential of TB Dte.
(m) Constantly upgrade skills and knowledge of TB staff.
Anand
- 2-
SECTION- 2
UNIVERSAL LAWS OF QUALITY ASSURANCE/AUDIT
2.1. Parameters of Quality Audit. There are certain basic principles which must
be practiced for the effective, transparent and result oriented audit. The guide lines
for audit, general mistakes committed during audit, benefits of quality audit, stages
of audit and barriers to implement quality work are listed below:
Anand
-3-
2.2 SWOT Analysis. A time tested and powerful technique for continuous
improvement is SWOT analysis which stands for Strengths, Weaknesses,
Opportt;tnities and Threats. In ever changing dynamic environment, the
organisations have to keep evolving by harnessing their strength, keeping a check on
weaknesses, exploiting available opportunities and keeping an observant eye on
Anand
-4-
2.3. PDSA. PDSA stands for Plan, Do, Study, Act. This is the basic tool which
needs to be employed for monitoring the process once identified through SWOT
analysis to understand the efficacy and reliability in various conditions and
environments. The stages are as follows;
(a) Plan Identify the problem or issue, gather data.
(b) Do Conduct the ACTION. Make improvement & implement
changes.
(c) Study Review the action, improvement & changes with the aim to see
the positive impact and check negative consequences if any.
(d) Act At the end of cycle, document the improvements and lock in
changes. However, conduct planning process to be conducted again if any
negatives features nohc~d du~ to change in the. \)toce.ss. The diagrammatic
representation as given below:
Act Do
Anand
- 5-
SECTION -3
ORGANISATION, COMMAND AND CONTROL,
CHANNEL OF REPORTING & CHARTER OF DUTIES
3.1. Introduction
70 contracts and 200 Job Orders in one year thus averaging a total of about
26,810 contracts and 76,600 Job Orders. In addition there are 92 CWEs
concluding 40 contracts per CWE and 36 CEs who conclude approximately 30
contracts per CE each year totalling to about 1080 contracts of major value. All
these have to be checked at the execution stage because, checking after
completion serves very little or no purpose.
(d) The above works out to 156 contracts per officer per year even if 10% of
GE's, 25% of CWE's and 100% of CE's contracts are to be checked. In addition
any one officer with an area of specialisation like Contract, B/K E/M or
architect will not be able to do justice and cover all aspects of work viz.
contractual, architectural, electrical and civil. Thus the emphasis hence forth
shall be on joint inspection team consisting of specialist in each category to
achieve a meaningful and realistic assessment of the work.
(e) It is also observed that approx 150 items of SSR are executed in any
major work. The observations on workmanship are generally repetitiv~ in
nature, which leads to accumulation of large no of observations of similar type
which do not serve any useful purpose in improving the quality of work on
ground. h1 view of above emphasis will now be on quality inspections rather
than quantity. Henceforth, intensive inspections will be carried out of
selected works covering all aspects. The methodology and frequency of
inspection has been completely Tevised in this compendium.
(f) The policy Compendium was last revised in the year 1993. Over a
period of 18 years, there has been a sea change in cost 1 size of project, work
load of MES, construction techniques, construction materials used in the work
and aspirations of the users. A large number of policy letters have been issued
during the intervening period. Considering all these factors, a comprehensive,
transparent and easy to follow Policy Compendium - 2012 has been prepared
using experience gained during the past four decades on inspection of works.
The purpose of this compendium is also to apprise and update the inspecting
officers and make the stake holders aware about their responsibilities. While
drafting the compendium, due consideration has also been given to the
Anand
-7-
Organisation
(a) ADGTE heads the organisation, with its HQ situated at Kashmir
House, New Delhi, works under QMG. ADGTE will be assisted by a team of
officers comprising of the following:
(i) Jt DG TB JtDG (QS & C)
(ii) Dir TE Col
(iii) Jt Dir TE LtCol
(iv) TE Lt Col/Maj/EE
(b) The Command STE formations are eo-located with respective
Command HQ except Southern Command which has additional STE
formation at Chennai due larger AOR. Each STF. Command has 3- 4 TEs one
officer each from B/R, E/M, SW, Arch category. Additional STE formations
may be raised if required based on detailed justification i.e. work load,
approachability, traveling time and type of works. The location and break up
of each STE Command is as under:
.
~
Command Location STE TE
(Lt Co]/Ef/EE(QS&C)
.:
Anand
-8-
maintaining unity of Command. ADGTE may change the AOR of STE formation on
Technical/ Adm.hlistrative grounds. The details of AOR for each STE formation are
is-sued {Appendix A) which are as under:-
(a) Northern Command Annexure I
(b) Western Command Annexure 11
(c) South Western Command Annexure Ill
(d) Central Command Annexure IV
(e) Eastern Command Annexure V
(f) Southern Command (Pune) Annexure VI
(g) Southern Command (Chennai) Annexure VII
~
Jt DG TE (QS & C)
~
Dir TE (Col)
~
)t Dir TE (Lt Col)
~
TE (Lt Col/Maj/EE)
~
TE (Lt Col/EE (B/R)/EE(E/M)/EE (QS&C))
Anand
-9-
Appointment 10 RO SRO
O erical Staff so TE
so TE DirTE
TE &JtDirTE DirTE JtDGTE ADGTE
DirTE JtDGTE ADGTE QMG
JtDGTE ADGTE QMG VCOAS
ADGTE QMG VCOAS COAS
Appointment 10 RO SRO
TE STE ADGTE QMG
STE ADGTE QMG VCOAS
CHARTER OF DUTIES
(a) ADG TE Dte (Headquarter).
(i) ADGTE
(aa) Perform the functions of Head of TE Org.
(ab) Site examination of selected works with the team of STE
during progress and after completion
(ac) Submit periodical report to QMG on inspection of works.
(ad) Liaise with three Service HQs, E- in-Cs Branch, DRDO,
DG Coast Guard.
Anand
(ae) Approve tour programs of all officers.
(af) Sanction leave of officers of HQ ADGTE Dte and STEs as
per approved leave program.
(ag) Approve initiation of Draft Para (DP) and Serious Case
(SC).
(ii) It DGTE
(aa) Officiate in the absence of ADG TE.
(ab) Scrutinise selected contracts concluded by the CE Zones.
(ac) Site examination of selected works with the team of STE.
(ad) Tech check of selected final bills.
(ae) Recommend tour programs of all officers of this Dte and
Comd TE formation for approval of ADGTE.
(af) Raise, settlement of Special Obsn, Draft Para & Serious
Cases.
(ag) Advice ADG TE on contract and other policy & technical
matters.
(ah) Countersign on claims on behalf of ADG TE
(aj) Sanction leave of sub ordinate staff.
(ak) Issue advisory to DGW of E in C Br
(iii) Dir TE
(aa) Deal with all technical matters/ correspondence and issue
technical instructions to STE commands
(ab) Budget, grants and procurement
(ac) Recommend leave of officers and staff of this Dte and STE
Comd.
(ad) Inspection of selected works with the team of STE.
(ae) Preparation and issue of Quarterly Report.
(af) Monitor important obsn raised by STE.
(ag) Issue technical instructions and policy letter to STEs on
approval of ADGTE.
Anand
- 11 -
Anand
- 13-
SECTION -4
VISITS AND INSPECTIONS
General.
a) It is not p ossible for the TB organization to check each and every work
fti!!Ctl1ted by the construction agency. Further MES has a system in place to
carry o ut periodic checks by next higher formations. However, the officers of
TE organization inspecting the works will be held responsible to the extent
applicable for any shortcomings observed at a later date. Therefore emphasis
of inspection will be on quality inspections rather than quantity.
Henceforth, intensive inspections will be carried out of selected works
covering all aspects by entire team of STE formation.
(b) It will be the responsibility of the zonal CE to ensure that points observed
by the TE organization during inspections are applied to all other ongoing
\\·arks in their AOR. In case, similar mistakes are found in other works, the
observations will be converted into Serious Cases.
(b) STEs will submit updated list of all ongoing CE Contracts for all CE
Zones in their AOR with latest % of progress.
(c) The Zonal CEs to be inspected shall be proposed by STE, out of which
STE will propose 05 Works/ Stns.
(d) The criteria for selection of proposed wks for insp will be:-
(i) Amount of contract and magnitude of work.
(ii) Based on available input from environment.
(ill) % progress of work:-
(aa)
..
Min 30% to 50% physical progress for first inspection .
(ab) Min 70% physical progress but within DLP for review
inspection.
Anand
- 12-
Anand
- 14-
(e) STE to give preference to Stn which have longest gap since last
inspection.
" (f) In every inspection only one wm·k each of CE, CvVE, GE shall be
inspected.
(g) The draft tour programme will be submitted to ADG TB for approval in
the format given at Appendix B with four Annexure one for each CE Zone.
G) Having inspected all CE Zones in first row1.d, next Stn for inSpection
shall be in the AOR of CWE not inspected in first round.
(k) STE team will cany out review inspection of previously inspected work
while visiting nearby Station.
(1) The details of work as and when due for review inspection, shall be
projected by STE for the approval of ADG TE along with draft tour
programme. The review inspection is applicable to the works inspected after
31 Mar 12.
(m) March and August will be kept for settlement of observations and
during this period no inspection will be undertaken by STE team.
(n) At least one contract apart from building works i.e. furniture, road,
electrification, water supply and periodical services in a station will be
selected for check.
(o) No work shall be checked more than twice. In exceptional and specific
cases prior approval of ADGTE shall be sought before carrying out further
check.
(p) Before and after the inspection STE shall meet the Stn Cdr.
(q) Good quality work, innovative practices & adherence to PDC/ timely
completion will be commented and highlighted in the inspection report.
Anand
- 16-
(a) On arrival at the Stn for inspection, STE Team will meet the Stn Cdr
· along with GE and apprise him about the works proposed to be inspected.
The purpose of this meeting is to obtain the users point of view and in case
any additional feed back is reqttired from the users/ it may be obtained prior
to the inspection.
(b) After obtaining the feed back from the users the STE team will go to the
selected site and the GE will give a presentation to the team bringing out the
salient points of the work/ points of the users and the contractor. This
presentation will be attended by the PMG, site executives/ and the contractor.
Intensive site inspection will be carried out by the team of officers with special
emphasis on the specialization of each officers viz the surveyor officer will
thoroughly scrutinse the contract agreement, E/M officer will check the works
pertaining to the trade and so on. However, if during inspection, any point is
noticed by any officer outside his trade they shall be reflected/ discussed
during the site inspection.
Anand
- 15-
(t) Depending on the nature of the work ADGTE may detail any o_ther
L·fficer from his Dte or any other STE formation to carry out inspection with
the team of STE.
(w) The STE shall forvvard an after inspection report as per the format given
at Appx 'C. In addition STE shall write a DO letter to ADGTE with copy to
Station Cdr, Accepting Officer, Chief Engineer Command & MGOL
Command. This DO shall highlight important observations which require
immediate rectification to stop the execution of defective work and a fate-
accompli situation on completion of the project.
Anand
- 17-
(g) After the arrival of STE and his team to their HQ, shall issue the
observations under the signature of the STE. The visit to next stn shall not be
undertaken before issue of observations of the previous visit. The copy of the
observations shall be forwarded to Stn HQ, CE, CWE, GE. However in case
ADGTE or any officer from his Dte was detailed for the inspection the copy of
observations shall be forwarded to this HQ in draft form for approval before
issue.
(c) If verification reveals that the rectifications as confirmed have not been
carried out, then a Serious Case should be published in the Quarterly Report.
Anand
- 18-
pending and the formation with whom pending. The opportunity should be
utilized by CE Zone to get old observations settled.
(a) ADGTE HQ will carry out annual inspection of STE offices. The annual
inspection will be for the period 01 Apr to 31 Mar.
(b) The Performa for Annual Inspection as per the format at Appendix F
shall be submitted by STE offices duly filled in pencil so as to reach ADGTE
HQ by 30 JUI1 every year.
(c) The annual inspection will normally be carried out in the month of Mar
and Aug. After the inspection, one copy of the report with remarks of the
Inspecting Officer and ADGTE will be forwarded to STE for record and action.
{d) STEs will take prompt action on the points observed in the inspection
report and will ensure compliance in future.
Anand
-19-
SECTION -5
TECHNICAL EXAMINATION
General
a) All inspection of works by the ADGTE Dte and STE shall be carried out
along with the team of STE, hence, the observations raised will be forwarded
to all signatories of the factual notes.
Anand
-20-
Anand
- 21 -
Anand
-22-
E/M items should be available in the library of STEs office and these should
be studied closely.
Anand
-23 -
Anand
-24-
SECTION -6
FORMULATION AND FINALISATION OF OBSERVATIONS
Anand
-25-
o.2. Minor Observations. All single observation with financial effect less than
Rs 10,000/- will be treated as minor observations. With past experience and
occurrence of similar obse1vations in other contracts it should be possible to identify
such observations at the very beginning except in marginal cases. These will be
pointed out to GE to work out financial effect. If the amount is less than 10,000, absn
will be left to the competent authority as laid down to take further action as deems
fit. These shall be included in Factual notes under separate Para. Apart from the first
intimation of the observations, no further correspondence or monitoring/ progressing
will be done by STEs in respect of these minor observations. Once the observation is
declared as minor based on the financial amount worked out by the GE, STE shall in
no way be responsible for the settlement of the observation. However, if STE is of
the opinion that certain observation declared minor by GE is not acceptable, he may
ask the competent authority to forward the reply for his scrutiny. However, such
cases shall be rare and in all such cases the complete correspondence shall be
forwarded to ADGTE HQ with recommendations of STE. Minor observations will
not be considered by the STE in his list of pending observations. The amount at
which the minor observations are settled by the GF/CWF/CE shall not be
considered by the STE in deciding the overpayment for inclusion in Draft Para.
Anand
-26-
Anand
-27 -
Anand
-28-
Anand
-29-
Anand
- 30-
(ii) There is a clear indication that the contractor will get away with
all his payments before the observations are finally settled with MES.
(iii) There is a deliberate delayI neglect on the part of MES executives
to finalise the case.
(iv) Government interest will be seriously jeopardized if CDA is not
informed provisionally.
(v) Such intimation will be given to CDA only with prior permission
of ADG TE. For this purpose, a self-contained note will be sent to ADG
TE HQ bringing out the point at issue and the following main aspects:
(aa) Dated history of the examined final bills/site examination
of works.
(ab) Approxin\ate evaluation of the observations.
(ac) Whether it is suspected that the settlement of observations
is unnecessarily ap.d deliberately being delayed by the MES; how
and why.
(ad) Whether there is likelihood of contractor getting away
with all his payments before the case of
overpayments/ devaluations is finalised.
(ae) Specific efforts that have been made by STE to finalise the
obsns.
(af) Any other relevant point to justify the action proposed.
(ag) After receipt of sanction from ADG TE, while intimating
CDA about provisional amount of overpayment, the reasons for
doing so will be given by STE to CDA in brief and copies shall be
endorsed to all concerned in the MFS up to CE Zone under
intimation to ADGTE HQ. CDA will be requested only to
safeguard the Government interest to the extent of provisional
amounts intimated pending finalisation of the case.
(ah) On finalization of the case, the provisional amounts shall
be replaced with the firm amounts and intimated to CDA, again
under intimation to all the recipients of the previous
information.
Anand
-31 -
Recovery of Overpayment.
a) Condition 67 of IAFW 2249 interalia state that right of Government to
adjust overpayment shall not extend beyond the period of 2 years from date of
payment of final bill. This provision for adjustment must be borne in mind
and all out efforts made to finalise the observation expeditiously, preferably
before expiry of the adjustment period of 2 years from the date of payment of
ftnal bill.
(b) It should be clearly understood that the responsibility of taking
necessary action to enforce the recovery on account of overpayments as a
result of Technical Examination of the work is that of the Garrison Engineer of
the l\tfES.
Anand
-32-
SECTION -7
INTERACTION WITH COMMANDERS/STAFF
.
7.1. STE Interaction with Station Commanders
(a) A copy of tour programme of STE and his team will be sent to Stn HQ
in addition to the concerned MES executives. The GE/CWE would ensure
that meeting is fixed between the Stn Cdr and the visiting team of STE. In the
absence of Sb.1 Cdr, the meeting will be chaired by Offg Stn Cdr.
(b) Briefing by GE. On arrival at the Stn for inspection, STE Team will
interact with Stn Cdr along with AGE(I)/GE/rep of CWE/rep of CE. The STE
will apprise the Stn Cdr regarding the works they propose to inspect and will
obtain the feed back of any of the on going works in the station. In case Stn
Cdr desires that a work not approved by the ADGTE is to be inspected then
the same shall be included for inspection based on a letter from Stn Cdr which
will be forwarded to ADGTE by fax by the STE. ·
(c) De-Briefing bv STE. After inspection, STE shall inform Stn Cdr about
major defects in quality of work and serious lapses if any, observed during the
current inspection. STE will also bring out discrepancies in BP, lack of co-
operation from user and highlight the cases where Stn Cdr' s intervention may
be necessary for expediting completion of the work (e.g. delay in handing over
of the sites by the users). The additional support required by MES/Contractor
to expedite the work and clear bottle neck shall be brought to the notice of Stn
Cdr.
Anand
-33-
-3 STE Presentation to Comd HQ. STEs shall brief CE Comd and COS of
md HQ about state of infrastructure in Comd AOR in every quarter. STE will also
pprise the staff at Comd HQ about details of inspection carried out in recent past
~J. ~~~....~ \\.~~~~~~-
- .4. ADG TE Interaction. ADG TE shall interact with QMG HQ IDS, Service
HQs, E- in-C s Branch, DRDO, DG AWHO, DG Coast Guard, & Command HQ
regarding inspection of work. ADGTE shall keep QMG & E-in-C up dated about the
state of inspection and observations and about short comings in execution of work
and give recommendation for their improvement.
Anand
-34-
SECTION -8
MONITORING OF CASES REPORTED BY TECH EXAMINATION
8.2. Monitoring At Command Level. STE should liaise with Staff at Command
HQ and evolve suitable monitoring system with a view to achieve the desired
results. Bi-Monthly/Quarterly meetings (as may be decided by Comman..J HQs)
with Brig Q, ACE (Wks), Jt DG (Contract) and STE would be useful to monitor and
expedite the following issues:-
(a) No. of observations outstanding for more than one year.
(b) Follow up action on special observation, serious cases and draft paras.
(c) Serious cases observed during current inspections.
(d) Cases in which no replies are forthcoming from Zonal CEs/CsWE/GEs
(e) Progress on implementation of suggestions/recommendations being
made in ADGTE Quarterly Reports.
Anand
-37-
9.2.2 On receipt of above, Draft Para will be issued by ADGTE. The DP will be
allotted number in serial order for inclusion in the Quarterly Reports. For example in
case of STE SC, draft Para number will be DPISC (Pune)lll-1211, DPISC(Pune)ll-
12 12 and so on. The serial order will be maintained in successive draft paragraphs
for the entire financial year of 2011-12.
u.2.3 Immediately, after the draft Para is issued, a letter indicating the short
comings along with the recoveryI rectification cost will be forwarded to respective
Command CE with a copy to DGW.
DGW (E8) shall submit six monthly report on outstanding Draft Para to ADG
Dte.
Serious Cases
ra) The serious cases shall be raised on concerned CE Zone and settled byE
in C s "Branch. The observations of serious {fraudulent nature ines"Qec.ti.ve of
financial effect shall be forwarded to ADG TE for his approval. The following
types of observation will be considered for Serious Case;
(i) Intention to fraud
(ii) Negligence in Execution
(ill) Faulty planning and inadequacies in CA with negligence I
doubtful intention
(iv) Any action causing undue benefit to contractor.
(v) Rectification confirmed by exec but not exec on ground.
(vi) Fake test certificates, vouchers.
(vii) Repeated occurrence of similar obsnsl mistakes in CA or in work
under execution.
Anand
-35-
(f) The STE shall maintain the record of minutes of meetings issued by Stn
HQ after discussion along with response of Stn HQ to the inspection report
and state of rectification. The salient points of discussion shall be incl in the
cbsn sheet.
3.5 No of works sites, final bill and contract agreements checked in the quarter
will be submitted by STE as per the format given in Appendix 'K'
Anand
-36-
SECTION- 9
DRAFT PARA AND SERIOUS CASES
9.1. Draft Paragraphs Draft Para shall be raised by ADGTE and settled by CE
Command. Once all observations are finalized and financial effect arrived at and
agreed by the GE, and if total financial effect of recoveryI rectification/ minus DO in
one contract exceeds the limit given below, a "Draft Para" shall be raised. The
financial effect of minor observation shalJ not be taken into account while deciding
the amount of draft para. The financial limits of DP are as follows;
,----
Value of Work Limit of Draft Para
Up to Rs 15 Lac > ( Rs 25,000 or 5% of CA Amount whichever is less)
-
>Rs 15 Lac but< 50 > (Rs 50,000 or 5% of CA Amount whichever is less)
Lac .
>Rs 50 Lac but < 1 > (Rs 1,00,000 or 5 % of CA Amount whichever is less)
Crore
>Rs 1 Crore but< 5 > (Rs 2,00,000 or 5 % of CA Amount whichever is less)
-
Crore
f-
>Rs 5 Crore but< > (Rs 4,00,000 or 5% of CA Amount whichever is less)
-
>Rs 15 Crore > (Rs 6,00,000 or 5% of CA Amount whichever is less)
9.2. A proposal for Draft Paragraphs as per format given as Appendix 'L' shall be
forwarded by STE to ADGTE along with following d etails;
(a) Observations raised against the work.
(b) Reply I comments forwarded by GE/ CWE/ CE.
(c) Comments of STE on replies indicating amounts of recovery/
rectification and minus DO.
(d) Details of recovery amount arrived at against each observation.Non
receipt of comments from GE/CWE/CE within one month will be treated as
NIL comments.
9.2.1 If Accepting officer in his comments does not agree or suggests any
modifications, the STE will immediately furnish the correct fach1al position and
forward his views/ recommendations to ADG TE HQ for approval.
Anand
-- -- --~------------------------------------------------------~
- 38 -
(b) All serious observation of one Work will be clubbed by STE and a
detailed letter shall be forwarded by STE to CE Zone for comments with the
·· following details with copy to ADGTE:
(i) Observations raised against the work.
(ii) ReplyI comments forwarded by GE/ CWE/ CE.
(ill) Views of STE on replies.
Non receipt of comments within two month will be treated as NIL comments.
After evaluating the entire case, ADGTE will issue the serious case and
forward to DGW for further action.
(c) The Serious Case shall be included in the Quarterly Report. E in C's
Branch will order BOO to pinpoint the responsibly and initiate Disciplinary
action/ Administrative action against responsible executives and contractor.
(e) The monitoring of Serious Case shall be carried out by E-in-C's Brancl1.
The detail of SC case shall be included in the Quarterly report published by
ADG TE Dte. DGW (E8) shall submit six monthly reports on outstanding
serious cases and forward to ADG TB Dte.
Anand
-39-
SECTION -10
RAINWATER HARVESTING
, Introduction. Providing clean water to the forces is one of the major
ponsibilities of MFS. Water is a precious and limited resource and its utilization
d be such as to conserve it for generations to come. In order to achieve this Rain
ter Harvesting (RWH) has been made mandatory by the Ministry of Environment
Forests due to which all major projects are required to cater for provision of rain
ter harvesting for the catchments area of the project under consideration. The term
m \'Vater Harvesting cmmotes collection, storage of rain water and other activities
anned at harvesting surface water. To supplement the ever growing shortage of pure
J. safe water rainwater is an ideal source which can be conserved and used in a
~ful manner by the users. Rain Water Harvesting is merely putting back rain water
the soil where it will be stored in underground reservoirs and rivers so that we can
ral,. it whenever we need it.
? Methods of Rain Water Harvesting
(a) Recharge Well. In this well assemblies of slotted pipes with
diameters varying from 100 mm to 250 mm are lowered throughout the depth.
The annular space around the well assembly may be shrouded with
appropriate size of gravel. This gravel should be washed so that it becomes silt
free. The slotted pipes should be placed against the aquifer or dried up aquifer
encountered in the recharge well.
(b) Recharge Pits. These are suitable in alluvial areas where
permeable rocks are exposed on the land surface, or at very shallow depth,
and the water from the roof tops is collected in these pits. This method is
suitable for buildings having roof area of 100 sqm and the pits are constructed
1 or 2 m wide and 2 to 3 m deep which are back filled with boulders at the
bottom, gravel in between and <;oarse sand at the top. A wire mesh should be
provided at the top so that the leaves or other solid waste is prevented from
entering the pit. The top layer of sand should be cleaned periodically to
maintain the recharge rate.
(c) Recharge Trenches. These are suitable for buildings having roof area
200-300 sqm and where permeable strata are available at shallow depths. The
trench is 0.5 to 1m wide, 1 to 1.5 m deep and 10 to 20 m long depending on the
Anand
-40 -
availability of water to be recharged. These are back filled with boulders at the
bottom, gravel in between and coarse sand at the top. A wire mesh should be
·· provided at the top so that the leaves 0~ other solid waste is prevented from
entering the pit. The top layer of sand should be cleaned periodically to
maintain the recharge rate.
(d) Recharge Through Dry or Operational Dug Wells. These wells, if
exist in the campus may be utilized as recharge structures after cleaning and
de-silting. Recharge water is guided through a pipe from the de-silting
chamber to the bottom of the well or below the water level to avoid scouring
of the bottom. Periodic chlorination should be done for controlling the
bacteriological contamination in the well.
(e) Recharge Through Abandoned/Existing Tube Wells. Abandoned I
existing tube wells should be used as recharge structures. PVC pipes of 10 cm
dia are connected to the roof drain to collect the rain water. Rain water from
roofs is taken to collection/ desilting chambers located on the ground. These
collection chambers are inter connected as well as cmmected to the filter pits
through the pipes.
(f) Recharge Tube Wells. These are used in areas where the aquifers
are over laid by a considerable thickness of impervious layer of soil. In such
situations a new recharge tube well can be constructed for recharging the
harvested rain water. It is also suitable for recharging roof top rain water of
big buildings.
(g) Roof Top Rainwater Harvesting. In areas having rainfall over a large
period of year i.e. in hilly and coastal areas constant and regular rainfall can be
usefully harvested and stored in suitable water tanks. Water is collected
through roof gutters and down take pipes and collected in suitable water
tanks.
10.3 Precautions in Rainwater Harvesting.
(a) No sewage or waste water should be admitted into the rain water
harvesting system.
(b) No waste water from areas likely to have oil, grease or other pollutants
should be connected in to the system.
Anand
- 41 -
Anand
- 43-
Anand
------------------------------------------------~
-42-
(b) Presently the rain/ storm water is collected through inadequate and
poorly maintained storm water road side drains and rain water is not being
harvested. If rain water is localized and channclized by making rain
harvesting struchues, bunds and percolation pits etc, the water could be
collected and stored in a manageable and meaningful way so that the scarce
water could be made to contain within the area which will enrich the water
table and improve the micro climatic condition by facilitating landscape and
plant growth around these structures.
(c) Por implementing RWH schemes, there is a need to review the existing
area drainage system. The existing area drainage systems have been planned
with a view to divert most of surface run off into a natural system/pond/wet
land. However, now this concept is required to be changed. The drainage
system of buildings and catchments area will undergo following changes:-
10.4.1 Modification in Drainage of Roof Top Rainwater. Generally, it is observed
that roof top rain water is allowed to fall freely and goes to unpaved area of further
natural disposal. By providing saucer drains after plinth pro~ection the rainwater
can be diverted to nearby storm water drain for effective use. The saucer drain will
be useful for collecting surface runoff from unpaved area as well as vertical drain, if
any. Therefore saucer drains must be made integral part of building drainage
wherever RWH is envisaged.
10.4.2 Modification to Storm Water Drain. The present trend is to provide standard
storm water drains. However for RWH to be effective, these drains should be
designed to carry, without overflowing, the surface runoff from catchments which
will get generated from 15 to 30 min of peak hourly rainfall.
10.4.3 Modification of Outfalls. As the final step the concept of disposal of R'..Y into
nearby natural body will also get changed. Now, several recharge pits or other
suitable structures approved by CGWB.
10.4.4 Thus, the complete area drainage system should be planned on catchment
basis in totality using following parameters:-
(a) Topography of the area.
(b) Amount of surface run off in each catchment area.
(c) Percolation rate of soil
(d) Locations from where RW can be diverted into grow1d water.
Anand
-44-
(i) Roof or terraces used for harvesting should be clean, free from
dust algal plants etc.
(ii) Roof should not be painted sin.ce most paints contain
toxicsubstances and may peel off.
(iii) Do not store chemicals, rusting iron, manure or detergent on
theroof.
(iv) Nesting of birds on the roof should be prevented.
(v) Terraces should not be used for toilets either by human beings or
by pets.
(vi) Provide gratings at mouth of each drainpipe on terraces to trap
leaves debris and floating materials.
(vii) Provision of first rain separator should be made to flush off first
rains.
(viii) Do not use polluted water to recharge ground water.
(ix) Ground water should only be recharged by rainwater.
(x) Before recharging, suitable arrangements of filtering should be
provided.
(xi) Filter media should be cleaned before every monsoon season.
(xii) During rain season, the whole system (roof catchment, pipes,
screens, first flush, filters, tanks) should be checked before and after
each rain and preferably cleaned after every dry period exceeding a
month.
(xiii) At the end of the dry season and just before the first shower of
rain is anticipated, the storage tank should be scrubbed and flushed off.
Anand
-45 -
SECTIONll
Consen·ation of Electricity
Energy Efficient Fluorescent Lamp (FTL) such as T-5 fittings and CFLs
haYe certification from Bureau of Energy Efficiency (BEE) for its energy
efficiency. Over a periodof time all Street Light Fittings(HPSV/Mercury /FTL)
replaced with LED lighting.
Ensure that the lighting and air conditioning system is not over
ure your fixtures and lan1ps are properly sized for use with one
e'ample T-5 lamps do not work as well in direct fixtures designed
ps and may be too bright for direct lighting solution.
Anand
-46-
(m) Instead of using recessed fixtures to light a work place, use open top
light which will reflect off the ceiling and walls into the task area.
(o) Consider staging multiple AC chillers rather than one large chiller.
Compressors that run near capacity are most efficient. Variable speed drives
can also help chillers operate more efficiently.
(ae) Look for energy star label (BEE rating) for products.
(af) Use task light instead of bright light.
Anand
-47-
(aa) Keep your printer turned off, using switch on the printer.
Anand
~ 48 ~
(i) Taps.
(ii) Kitchen.
(i) Taps
(ac) While brushing and shaving do not leave the tap running.
(ii) Kitchen
(ab) Select proper size pan as large pan require more water for
cooking.
Anand
-49-
(ac) Soak the utensils for some time rather than letting the
water run.
(ab) Arrest all dripping taps and faucets i.e. fix leakage.
(ag) Don't waste water to get cold water from overhead tank
for afternoon bath, instead fill a bucket with water in morning.
Anand
-50-
(ad) vVhen cleaning the fish tank, use the waste water for the
plants.
(ae) Never put water down the drain it will always have some
other use.
(ab) Wash your car/ scooter on grass to use the water for
irrigation of grass.
Anand
-51 -
SECTION12
CitEE.' BUILDING MEASURES: NORMS AND IMPORTANT FEATURES
~ieasures(Nor~s
Anand
-52-
(m) Promote use of rain water harvesting, reduce the quantity of surface
runoff by providing permeable pavement around the building, provide waste
water treatment on site, reuse of h·ealcd waste waler and irrigation demand.
Anand
-53-
SECTION13
HERITAGE BUILDINGS
Introduction
_ -o building is maintenance-free, so every structure, heritage or new, requires
to limit deterioration. ExpoSUie to the elements causes all building materiaJs to
ear down eventually. Periodic inspections can help to find problems early and,
along with regular maintenance, extends the life of building. This also helps to avoid
the need for potentially expensive and disruptive repair work, which may damage
building's heritage value. Heritage buildings are an asset of any organisation and
smce these are generally old buildings they require greater care for maintenance. It is
therefore a good idea to set up a building maintenance schedule to remind of any
mspections or work that needs to be done. It will also help to prioritize maintenance,
preventing avoidable, costly, future repairs.
Anand
- 54-
13.4 Walls
(a) Have the roots of creepers or over-growth penetrated the surface of the
walls? These encourage moisture and insect intrusion. Is there evidence of
moisture penetration? Moisture is the greatest enemy of any ~tructure.
(b) Cracks are the most obvious expression of a failure in a masonry wall.
The level of conce1·n depends on: the size of the crack, the location and
direction of the crack, and the rate of change in the crack.
(c) In masonry walls, check for any evidence of mortar deterioration (eg.no
mortar present in the joint within 4 cm of the wall surface, mortar that can be:_
easily scraped from the joint, mortar that has taken on a sand-like textute anq
crumbles, or morta1· that cleanly separates from the brick).
13.5 Roof
(a) Check the covering over the ridge or hip of a roof to make sure it is
water tight.
(b) Look at flashing for cracks, holes and looseness.
(c) Search roofing materials for deterioration- cracks or blisters or curling.
(d) Inspect soffits and fascia for deterioration (sagging) or openings.
(e) Look for evidence of decay in the rafter ends and for water damage on a
cornice.
(f) Look for signs of clogging, inadequate slopes, or defects in the gutters.
Anand
-55-
Conclusion
Heritage buildings are normally prone to rapid wear and tear since these are
buildings. While every part of building needs ongoing maintenance, some parts
more constant care than others. The exterior of building is subject to constant
. .l!rl,oration due to the rain, sun, wind and snow. The exterior elements often ha:ve
heritage value, so they are likely be the focus of maintenance efforts. A
get needs to be set aside for maintenance of heritage buildings.
Anand
-56-
SECTION 14
14.1 General
(c) GE approves samples of the materials well in advance for any stage.
(d) Work of external wa ter supply, exten1al electrification and furniture are
executed concurrently w ith building work to avoid delay in overall
completion of project.
(e) Proper area drainage is planned and catered for in CA and drains are
planned and sited keeping in view the natural slope of ground.
(i) Cement
(a a) Godown
(ab) Dunnage
(aa) Dunnage
(i) List of equipments required to be kept in site lab shall form part
of contract and all equipments as per CA shall be available at site.
Anand
-57-
Documents
Various stages of Sample Qtr are duly passed by GE and the sample
omplete in all respects within the time fixed for its completion.
General
Anand
-58-
Anand
-59-
(ii) Soil bearing capacity given in soil report shall not be less than
the value given in drawings but not much higher making the
ation uneconomical.
(iv) In pile foundations, casting of test piles and working out the pile
capacity after load test.
c) Concrete
(i) General
Anand
-60-
(ab) Face.
(ac) Throating.
Anand
-- -- - - - - -
~-
- - ~- -
- 61 -
(ab) Size
(ab) Limensions.
Anand
-62 -
(ac) Make
(ad) Pipe sleeve for door bolt.
Anand
-63-
(i) Thickness.
(iv) Handles
Anand
-64-
(i) Reinforcement
(aa) In slabs, chairs between two layers of reinforcement near
supports shall be provided.
Anand
-65-
(ab) Width and thickness of 'Z' section, glazing bars and sash
bars.
(ac) Hinges.
Anand
- 66-
(iv) Cracks.
Anand
- 67-
(m) Flooring
(i) PCC Sub-Base: thickness and size of aggregate.
(ii) PCC Flooring
(aa)
.
Thickness.
(ab) Finish and level and slope of top surface.
(ac) Size of panels.
(ad) Dividing strips, material and size.
(ae) Test for hollowness by tapping.
(ill) Cast-in-situ Terrazzo Flooring
(aa) Thickness
(ab) Type of cement.
(ac) Size of marble chips.
(ad) Spreading of marble chips.
(ae) Cutting and polishing.
(a£) Top level and slope.
(ag) Dividing strips, material and size.
Anand
-68-
Anand
- 69-
(ab) Colour.
(i) Plastering
(aa) Thickness.
Anand
-70-
(p) Painting
(i) Pipes
(ac) Weight.
(ac) Weight.
(v) Plumbin~
(i) Material.
Anand
-72-
(aa) WHB&aurinals
(i) Make: ISI marking and quality.
(ii) Sizes
(iii) Fixing arrangement.
(i) Colour.
(ii) Make and ISI marking.
(ill) Hinges MSCP or brass CP.
(ii) Length.
(ill) Outer dia and wall thickness.
(vii) Testing of plumbing and sanitary fittings.
Anand
- 73-
(ii) Manholes
(aa) Type of cover: RCC or CL
(ae) Handle.
Anand
-74-
(ag) Use separate conduits for audio, video & electric cables.
(iv) Sunken Boxes
(aa) Type: MS or Cl.
(ab) Size and wall thickness and depth.
Anand
-75-
(ix) MCBs
(ab) Rating.
(ac) Wires connected with thimbles.
(x) DBs
(aa) Make..
(ab) Thickness of sheet enclosure.
Anand
-76-
(c) Camber.
(iii) Camber
(v) Compaction.
(vi) Testing of stones.
(vi) Edges.
(vii) Camber.
(viii) Localised depressions.
(f) Bitumen
(i) Source of procurement, Purchase Voucher and test certificate.
Anand
- 77-
(v) Camber.
(a) Location, grid, direction and slopes of drains w.r.t. topography and
slope of natural ground.
(a) Cables
(ii) Voltage 660/1100 Volt or 1100 volt for LT: 6.5.KV /11KV for HT.
(iii) UG armoured or XLPE.
Anand
-78-
(b) Transformers
(c) OCBLACBNCB
(d) MCCB
(e) DG Sets
(i) Specifications: make and rating.
(ii) Various gauges, dampers in outlet smoke pipe.
Anand
-79-
(g) Panels
(v) Earthing.
(a) Cl Pipes
(i) Specifications, class, make and ISI marking.
(vi) Laying.
(viii) Testing.
(b) GI Pipes
(i) Specifications, grade, make and ISI marking.
(vi) Laying.
(viii) Testing.
Anand
- 81 -
(d) Pumps
(v) Noise.
(vi) Earthing.
(vii) Starter.
(vili) Testing.
Anand
-82-
SECTION15
15.1 Roof Treatment. WPT to roof are being considered with APP membrane.
However, with good quality control/ under strict supervision/ leak proof RCC slab
can be casted. WPT with APP membrane not only increases dead load on the slab
but after a lapse of 2/3 years itself become cause of accumulation of water on roof
surface/ thereby leading to avoidable leakage/ seepage. Therefore, water proofing to
roof with APP should not be provided. Also user to ensure ponding test for all roofs.
Wherever there is a case of leakage/ seepage/ necessary repairs to be carried out by
contractor as per specifications/ provisions catered in CA. Executives & users to
ensure that accommodation is handed/taken over only after successful ponding test
has been carried out. Records of all ponding tests to be maintained.
15.2 Quality of Bricks. Quality· of bricks being incorporated in the work was
found to be inferior in terms of shape size/ soundness etc though strength criteria.
Poor quality of bricks leads to efflorescence, cracks and leakage/ seepage. Only class I
bricks to be used in all projects. Amendments to CA/ and SSR be made based on
relevant IS-codes.
15.3 Drainage. Drains of size 45cm X 65cm is being considered in coastal areas,
however/ due to heavy rainfall/ they may get flooded. Therefore, redesign the
drainage system and also connect these to main drainage in the neighboring area.
15.4 Sewage Disposal. Provision of soakage well septic tanks for sewage disposal
is being considered. Instead sewage discharge, direct to nearest manhole of the
sewage system be considered, as clearing of septic tanks is frequently required.
Necessary liaison with municipal authorities be carried out in this regard. Disposal
of sewage be tied with municipal authorities.
15.5 ATI. ATT should be executed through specialist agency which is a member
of PCI and also independent testing of the same be carried out by executives. It must
be confirmed by the GE that the treatment has been done as stated.
Anand
-83-
15.6 Colour Scheme. Colour scheme for the ongoing project be got approved
from the users before commencement to achieve greater user satisfaction.
15.8 Brick Masonry. It is observed that brick wall paneling of ground floor are
being executed before completing of the same on higher floors. Also no space being
left between the top course and soffit of beams. The same is not considered as sound
engineering practice. Wall paneling of higher floors be carried out first so that RCC
members can acjhiever/ desired deflection as per design criteria.
15.9 Sunken Floors. Sunken floors are still being considered in CAs. Concept
of sunken floors is now considered outdated. Provision of direct outlet of sewage be
considered in all future CAs as the same are found to be cheaper and trouble free.
False ceiling be provided under such floors for easy access & quick maintenance.
Also pending test for all sunken floors to be ensured & records maintained.
15.10 Service Tanks. Service tanks black colour be replaced with white/ other
colour for better aesthetics & same be placed over raised platform.
15.13 Alignment of Down Water Pipes. Alignment of down water pipes are
generally not found proper. Also only rust proof fixing clamps be provided at all
places.
Anand
-84-
15.14 Alignment of Parapet Wall. Alignment of parapet wall are generally not
found proper. Executives to take extra care to ensure proper alignment of walls,
jam~~, chajjas etc.
15.15. Drip Course. Provision of drip course should be specified in all CA, the
same be provided over all balconies, chajjas etc.
15.17 Debris Over Chajjas. Cement mortar brick bats etc are mostly observed
over chajjas at places. Executives & Contractor to ensure that top of all chajjas,
projections are properly cleared before H/T over of assets to avoid leakage, seepage
at a later stage.
15.18 Improper Fitting of Tower/Sliding Bolts. Door are often found not to be
closing properly due to poor fitting of tower/sliding bolts, thick plaster near the
bottom rail. Executives to ensure that all such minor defects are rectified for better
user satisfaction, before H/T over of'assets.
15.19 Peg Set in Bathrooms. Provision of peg set in bathrooms are not found
catered in CA. Peg sets be provided in all bathrooms/ toilets.
15.20 Slope in Kitchen Shelves. Executives to ensure that proper slope towards
outside is provided in all shelves located under the kitchen platform for easy
washing/ cleaning.
15.21 SS Bib Cock. Bib cocks of brass found provided in toilet & bathroom. The
same be replaced with SS bib cocks to prevent theft/ pilferage.
15.22 Dado in Toilet/Bathrooms. Dado in toilets & bathrooms found till height of
3 ft. Same be provided to a minimum height of 1.2m as per TI of E-in-C Branch.
Anand
-85-
15.23 Cupboards. Often only shelves have been provided in cupboards. Design
of cupboards be reviewed and hanger rods be included in revised drg.
15.25 Mirror over WHB. Good quality & adequate size mirror to be fixed over
WHB.
15.26 Groove Cutting. Grooves cut at the junctions beam/ coln & brick masonry
are found rough & of irregular depth. Proper size, as per drg, groove be provided at
all places.
15.27 Reinforcement Bars. Rft bars are found projecting out of roof slab in lieu
of being bent in roof beams. The same are required to be cut to prevent leakage in
roof. Executive to ensure no such bars are left uncut over the roof.
15.28 Mixing of Mortar on Roof Slab. Marks indicating cement mortars being
mixed on roof slabs obserired at site. No mixing of mortar directly on slab be
allowed. PGI sheets/ alt arrangements be made for the same as left over mortar shall
hold water and may lead to leakage.
15.31 Plastering. Plastering are found patchy, not smooth at places. Executives to
ensure that all work is executed quality workmanship.
15.32 Road. It is observed that hard core/ soling & WBM are done very late. The
same be done at the earliest to achieve necessary compaction through moving traffic
Anand
-86-
& rains so that there is no settlement of road at a later stage. The minimum road
w1dtll should be 5.5m cUtd prol-·idcd witl1 4Dmm SDAC,IDAC.
15.34 Unpopular Makes. Unpopular maker such as firms like Omtex, Narmada,
Varun etc should be avoided and the mfrs specified should be as per approved list of
E-in-C's Branch. Only reputed firms & makes of items should be specified for
procurement of items under DGS&D Rate Contracts.
15.35 Site Lab. Site lab are not found properly maintained. Charts not found
displayed.
15.36 Test for organic impurities for coarse aggregates are not done. Please
confirm tests have now been conducted.
15.37 Sand found lying on ground, hence lot of impurities are added. No
measures found taken to protect the sand from such impurities.
15.41 Mix Design. RMC is being used in most of the work and concrete is being
manufactured at site in contractor's RMC plant. Though strict supervision is being
ensured during manufacturing RMC and testing at site lab is being carried out
regularly. Independent testing of same be got done intermittently through approved
institutions also.
Anand
-87-
15.43 Flooring. Flooring on various floors of the bldg consists of ceramic tiles,
granite, Katni stone, marble and vitrified tiles. Executives to ensure sample approval
from users before laying of the same. Also architect to supervise the work during
execution to ensure matching of joints, grains of marble etc. User & executives with
architect to consider visiting prestigious buildings for first hand view on the subject
thereby improve quality and also overcome the design/ construction faults found in
the projects.
15.45 Curing. Presently curing on RCC is being carried out for 10 days only. The
same be increased to 28 days. Plastic covers be used for initial 3 to 4 days to improve
curing.
15.46 RCC Valley Gutter. RCC valley gutter are being provided to drain off rain
water. Design of same be revised and FRP jGalvalume sheet valley gutter be
provided in lieu. RCC valley gutter is difficult to maintain/ repair and also not cost
effective.
Anand
-88-
that of external finishes be provided. The plastic cover of the joinery be removed
after all finishes are complete.
15.49 Filler Material in joints. Bitumen mastic filling is specified for joints in hard
standing. The same tends to overflow during summers and hence be replaced with
high density filler boards and Polysulphide/polyurethane.
15.50 Column Out of Plumb. Coh1nms were found to be out of plumb at places.
Defects be rectified and proper steel shuttering with good compaction be ensured in
balance of work.
15.51 Site Engineers. Executives and contractor to ensure that all supervisory
staff of contractor and man power are present at site. In case of further default pay of
this staff be deducted from the RAR of the contractor. Proper entries be made on site
order book and works diary.
15.52 Grubbing of Roots. Contractor and executives to ensure that no root is left in
the ground and all roots are grubbed out.
15.53 Box Type Fittings. Box type fittings are provisioned for internal
electrification in CAs. Same be replaced with modern energy efficient fittings.
15.55 MCBs. It has been observed that oversize/higher capacity MCBs are
installed in internal electrification. The same once installed do not serve the desired
purpose of safeguarding electrical fittings in case of short circuit. Hence MCBs of
only required criteria be provided.
15.56 Earthing Test. Earthing test carried out at number of places in bldgs
revealed that resistance value was coming out to be either open circuit or very high.
Anand
-89-
Earthing test to be canied out frequently & necessa11' repair work be under taken to
prevent any untoward incident, as laid down in Indian Electricity Rules. The
earthing resistance should ideally be 0.2 to 0.3 ohms (-2).
15.57 Cable Trays. Separate cable b·ays for comn and electrical cables be provided.
Executives to ensure that good quality trays are provided. Joints in cables to be
avoided specifically above false ceiling.
15.60 AC Drain Pipes. Condensed water from ACs to be drained out through
pipes upto ground level. Prct>visions for the same be catered accordingly.
15.61 FF Eqpt. Fire fighting equipment's like hose pipes etc. to provided in a
wall mounted cabinet at desired locations and the same be provided with locking
arrangements . Also it is to be ensured that FF extinguishes with environment
friendly chemicals are provided. The brass fittings to be replaced with stainless Steel
(SS) fittings to avoid pilferage/losses.
Anand
-90-
Anand
- 91 -
Anand
-92-
CE (AF) Gandhinagar *
CWE CAF) Jodhpur
24. GE (AF) Jaisalmer
25. GE (AF) Jodhpur
26. GE (AF) Utterlai
27. GE (P) (AF) Jaisalmer
28. GE (AF) Phalodi
Anand
-93-
Anand
-94-
Anand
-95-
Anand
-96-
Anand
Appx 'B' Annexure I
(Refers to Para 4.2)
Mont CE Stn * CWE* GE/* No of Work Load Detail of Last inspection of Total No of visits Proposed Remarks
h Zone CE CE work under the GE so far in last 12 Duration of
AGE(I)* works months (GE Wise) Stay of srE
Date @ Insp by @
team
StnX
CE
Zone
. .
A StnY ;
StnZ
I
I
CE !
CO
I -.J
Zone
I
CE
Zone
c
CE
Zone
D
--·· -··-·· - · · - · - · · - · · · - --- ---······· -·-·-
Note : * AddJ rows may be added if more No of Stations are there in a CE Zone .
@Last Date of visit in the station to check the CE Works should be given.
Anand
Appx 'B' Annexure ll
(Refers to Para 4.2)
ZONE WISE LIST OF CE WKS FOR DRAFT TOUR PROGRAMME- MONTHS &
CEZone:
s MES CA CA Stn CWE GE Date of Physical PDC Status of prevjous checks Remarks
No Fmn No& AmoW1t commenc % Progress Original Extend Out- BY LAST
Name ement PDCas edCA standi SIE/ VISIT BY
of per CA PDC ng TE OFFR
work obsns OF
ADGTE CD
HQ CX>
Date Date&
& %PROG I
I
. %
PRO
G
Anand
Appx 'C'
(Refers to Para 4.2)
GE
Anand
Appx 1 D'
(Refers to Para 4.3)
OFFICER)
I
Anand
Appendix 'E'
(Refers to Para 4.6)
3 4 5 6 7 8 9
1 2
~
0
~
Anand
Appendix 'F' Annex I
(Refers to Para 4.8)
Anand
Appendix 'F' Annex II
(Refers to Para 4.8)
CEWISE RECORD OF TECHNICAL EXAMINATION OF WORKS CARRIED OUT (01 Apr 20 to 31 Mar 20 }
S.No CA No, Name of Date of Date of site check Name of team of STE Jacket No Remarks
Work, & Amount Commencement/ & 1Yo age progress officers inspected
Completion the work
1 2 3 4 5 6 7
CE CONTRACTS
0
w
CWE CONTRACTS
I ::
GE CONTRACTS
I I I I I I l
I :: . I I I I I I I
Anand
Appendix 'F' Almex Ill
(Refers to Para 4.8)
4. 5. 6. 7. 8.
2. 3.
1.
_...
~
Anand
Appendix 'F' Annex IV
(Refers to Para 4.8 )
S.No. Type of Check Obs Nos raised Folio No Details of obs settled Remarks
CA Scrutiny/1st
. with remarks
Recovery/RectI NPF
Check/ Review
From_ _To_ _
Check/ FB Check
1 2 3 4 5 6 I
_..
0
I 0'1
Anand
Appendix 'F~ Aimex V
(Refers to Para 4.8 )
S.No. CA No & Amount Formation Name of officer letter Obs raised from to Remarks
No &date
GE/CWE/CE
1 2 3 4 5 6
I
-loo
0
(J)
Anand
Appendix 'F' Annex VI
(Refers to Para 4.8)
S.No. CA No &Amount Formation Name of officer letter Obs raised from to Remarks
No&date
GE/CWTI/CE
.
1 2 3 4 5 6
........
0
.........
Anand
Appendix 'F' Annex VII
(Refers to Para 4.8 )
1 2 3 4 5 6 7
L.__ ___
---··----
_..
0
00
Anand
Appendix 'F' Annex Vlll
(Refers to Para 4.8)
0
CD
Anand
Appendix 'F' Annex IX
(Refers to Para 4.8)
1 2 3 4 5 6 7
~
~
0
Anand
- 111 -
Appendix 'F'
(Refers to Para 4.8)
ANNUAL INSPECTION OF STE OFFICE
(REVISED 2011)
STE __________________ Conunand Year: 20 -20
1. 2. 3. 4.
Anand
- 112-
Anand
- 113-
Anand
- 114-
Budget Points
Technical Points
Anand
- 116-
Anand
- 117-
Anand
- 118-
Place: _ _ _ _ _ _ __
Date : _ _ _ _ _ _ __
(Signature of STE)
Place : _ _ __ _ __ _
Date : _ __ _ _ _ __
(Signature)
Remarks by ADGTE
Place: _ _ _ _ _ __
Date : _ _ _ __ _ _ _ (Signature)
Anand
- 119-
Appendix JG'
(Refers to Para 6.1)
No: dt
Superintending Technical Examiner
............................... Command
Contract No
Amount of Contract
Name of Work
Name of Contractor
Date of Commencement
Date of Completion as per CA
Extended date of completion
Actual date of completion
Date of expiry of defect liability period
Date of site check
Ph)'sical progress of work as on date
Names of team of officers inspecting the
work
.
Names of MES officers, users, &
contractor present during inspection.
1. The work was inspected by the team of officers on the date mentioned above.
A copy of the factual notes of the observations was signed by all present and was
handed over to all after the site visit. The observations apply to the entire work
(except where otherwise mentioned). Please take suitable further action to get the
defective work rectified. If however the defects are not rectifiable and the defective
work as executed is technically acceptable to you, please forward the details of over
payment involved for such defective work accepted.
Anand
- 120-
2. Please take necessary action to ensure that the defects as detected above are
not allowed or accepted in other works in your area. Remedial action as taken in this
case should be taken in other cases also including any financial recovery.
3. Please furnish your specific replies to the observations within 6 weeks failing
which the matter will be reported to higher authorities.
STE
Anand
- 121 -
Obsn No.-- -- -- - - - -
Obsn No. _ _ __ _ _ _ __ _
Copy to:
Anand
- 123-
Appendix 'H'
(Refers to Para 6.5 )
SPECIMEN FORM FOR ISSUING CASE CLOSING LETTER
REGISTERED
Tele:
Superintending Technical Examiner
_ _ __ _ _ _ Command
No .......................... . .......... 20
Garrison Engineer
~CA No
Name of Work
Anand
. 124 .
Anand
- 125-
Appendix 'K'
(Refer to Para 8.5 of
ADGTE Compendium}
CsWE
GEs
TOTAL
Anand
- 126-
CWE CONTRACTS
GE CONTRACTS
CE CONTRACTS
CWE CONTRACTS
GE CONTRACTS
Anand
- 127-
(Appendix 'L')
(Refer para 9.2)
To
4. Your comments if any regarding wording/ framing the draft para may be
forwarded to Addl Dir Gen TE with a copy to this office within a period of 5 weeks
of receipt of this letter.
Copyto:-
1. Addl Dir Gen TE Together with 2 copies of Annexure I
AHQ, Kashmir House and one copy of Annuxere-II
New Delhi- 110011
2. Garrison Engineer Together with a copy of draft para
Anand
- 128-
STE Command
Notes:-
Anand
- 129-
CA No. _ _ _ _ _ __ _ __ __ _ _ _ _ _ __ _ _ _ _ __ __
No -----------------------------------------------------
Anand