Equation Reference Sheet
Bookmark this page

Calculator
Little's Law

Nomenclature:
- Average generic "customers"
  - Average arrival rate
- Average time spent in the system
Notes:
System must be at steady state (e.g. mean arrival rate is not changing over time)
The Unreliable Machine (Single Machine)
Nomenclature: 
 - production time of a reliable machine
 - probability that the machine will go down
 - probability that the machine will remain up
- probability that the machine will be go up
- probability that the machine will remain down
MTTR - mean time to repair
MTTF - mean time to failure
For a completely reliable machine, the production time is given by and the production rate  is
For an unreliable machine, the 2-state system must be modeled in discrete time steps as shown below:

In this system, the following probabilities are true:

The probability that the system is up or down at any given time are given by: Calculator
p y y p yg g y

The MTTR and MTTF are given by:

The max production rate and efficiency are given by:


Max production rate
efficiency
1 Machine Line - Deterministic System
Nomenclature:
- arrival rate (constant)
- operation rate (constant)
- Average number of parts in the system
For a deterministic 1 machine line, the following relationships between arrival rate, operation rate, and number of
parts in the system are true.
When  , then
When  , then
When  , then
When , then
1 Machine Line - Stochastic System
Nomenclature:
- arrival rate (exponentially distributed)
- operation rate (exponentially distributed)
- Average number of parts in the system
- Average time that a part spends in the system
For a stochastic 1 machine line, the following relationships between arrival rate, operation rate, and number of
parts in the system are true.

Multiple Machine Lines 


Nomenclature: Calculator
- rate of production
- operation rate
For a multiple machine line with machines i through K, Buzacott's formula applies:

Discussion Hide Discussion


Topic: Week 8: Manufacturing Systems
/ Equation Sheet
Add a Post
Show all posts by recent activity
There are no posts in this topic yet.

Previous Next

All Rights Reserved

edX
About
Affiliates
edX for Business
Open edX
Careers
News
Legal
Terms of Service & Honor Code
Privacy Policy
Accessibility Policy
Trademark Policy
Sitemap
Connect
Blog
Contact Us Calculator
Help Center
Media Kit

© 2022 edX LLC. All rights reserved.


深圳市恒宇博科技有限公司 粤ICP备17044299号-2

Calculator

You might also like