Professional Documents
Culture Documents
1. The activity of distinct process which is primarily for the task of goal achievement. (1 pt)
1.1 Management
Quiz 2
1. The contract document whereby the particulars of responsibilities of the contracting parties are
outlined and detailed. (2 pts)
1.1 Matrix of Responsibilities
2. The first construction activity the Contractor will carry-out after receiving the notice-to=proceed
(NTP) letter from the Owner. (2 pts)
2.1 Mobilization
3. Under the terms of the sample contract, the condition a main Contractor may sublet or assign
portion of the Contract to another party. Under what section of the Contract Provision is it
covered? (4 pts)
3.1 When expressed in writing by the Owner.
3.2 CP-4 Assignment
4. Under the terms of the sample contract, what kind of delay the Contractor will be entitled for a
time extension but cannot claim compensation for any losses cause by the delay? Under what
Contract Provision is it covered? (4 pts)
4.1 CP-16 Force Majeure
4.2 Government actions, civil disorder, other delaying events the Owner agree to grant Contractor
time extension only and w/out compensation.
5. Under the terms of the sample contract, the legal grounds for the Contractor to terminate the
contract are: (4 pts)
5.1 Failure of the Owner to settle 45-calendar days after due date of the approved and certified
progress billing; and
5.2 The Owner declares bankruptcy or insolvency and will be unable to meet its financial obligation
or continue to complete the Project.
6. The legal instrument that protects the Owner from any liens against his completed project if the
Contractor fails to pay his subcontractors or suppliers. (2 pts)
6.1 Payment Bond
7. The hand-over of a 360-days, ₱57M government bridge project undertaken by XYZ Construction
Corp was delayed by 32 days. Determine the corresponding penalty amount or liquidated damages
the government will impose upon XYZ Construction Corp using the same terms as the sample
Penalty Calculation. (20 pts)
1. The process considered as the lifeblood of engineering and construction industry. (5 pts)
1.1 The bidding, proposal, and contracting process.
3. Describes, spells out, and details the project to be constructed and delineate the
responsibilities of the Owner and Contractor before the award of Contract. (5 pts)
3.1 Bid/tender package documents
5. The important proposal items the bidder/contractor should submit when bidding. (6 pts)
5.1 The business or commercial proposal
5.2 The technical proposal
5.3 The project-execution proposal
6. Three (3) principal bonds and describe the protection each provides the Owner. (6 pts)
6.1 Bid bond – protection against failure of the contractor to enter into agreement after the contract
has been awarded to the contractor.
6.2 Performance bond – guarantee that the contractor will finish the work. If the contractor fails to
perform the work, the surety will provide the completion of the work according to plans and
specifications.
6.3 Payment bond – guarantee from any liens against the completed project. If the contractor fails to
pay his subcontractors or suppliers the surety protects the owner from any claim.
7. The hand-over of a ₱65M government-owned project contracted by ABC Construction Corp for
250-days was delayed by 45 days. If the government will impose penalty on the same terms set forth
in the Sample Penalty Calculation, what will be the amount? (20 pts)