COST ESTIMATION PROCEDURE

COST ESTIMATION PERFORMANCE


MEASURMENT

NEOM-NCC-PRC-002 Rev 02.00, October 2022

©NEOM [2022]. All rights reserved.


Document History

Revision code Description of changes Purpose of issue Date

Rev 01.00 First Issue Issued for Implementation 13.05.2020

Rev 02.00 Revised Version Issued for Implementation 26.10.2022

Document Approval

Prepared by Reviewed by Approved by


Name Ammar Alhaddad Haashiem Tayob Ian Hawkes

Job Title Cost & Planning Analyst Senior Manager (A), Cost Cost Estimation Director
Estimation, ETSD, NEOM ETSD, NEOM
ETSD, NEOM

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 2 OF 38

©NEOM [2022]. All rights reserved.


Contents

1 PURPOSE ..................................................................................................................4
2 SCOPE .......................................................................................................................4
3 LIST OF DEFINITIONS AND ABBREVIATIONS .......................................................4
3.1 Definitions .................................................................................................................. 4
3.2 Abbreviations ............................................................................................................. 6
4 RELATED NEOM DOCUMENTS ...............................................................................6
5 ROLES AND RESPONSIBILITIES ............................................................................7
6 PROCEDURE .............................................................................................................8
6.1 Cost estimating as a functional area.......................................................................... 8
6.2 The need for KPIs ...................................................................................................... 8
6.3 KPI groups ................................................................................................................. 8
6.4 Cost estimating KPIs ................................................................................................. 8
6.5 Cost Estimator performance measurement ............................................................... 9
6.6 Cost Estimator performance ratings ........................................................................ 10
6.7 Reporting KPIs......................................................................................................... 11
7 FORMS AND TEMPLATES .....................................................................................11
8 APPENDICES ..........................................................................................................11
APPENDIX A - COST ESTIMATING KEY PERFORMANCE INDICATORS ........................12
APPENDIX B - EXAMPLE KPI CALCULATIONS ................................................................20
APPENDIX C - COST ESTIMATE REPORT CHECKLIST ...................................................24
APPENDIX D- COST ESTIMATE REPORT SCORECARD (MS EXCEL SPREADSHEET) 29
APPENDIX E- COST ESTIMATOR PERFORMANCE REPORT FORM ..............................31
APPENDIX F - COST ESTIMATOR PERFORMANCE SCORECARD (MS EXCEL
SPREADSHEET)......................................................................................................35
APPENDIX G - COST ESTIMATOR KPI RESULTS RECORD (MS EXCEL
SPREADSHEET)......................................................................................................37

List of Tables

Table 1: Table of Definitions ................................................................................................... 4


Table 2: Table of Abbreviations .............................................................................................. 6
Table 3: Related NEOM Documents ....................................................................................... 6
Table 4: Roles and Responsibilities ........................................................................................ 7
Table 5: Cost Estimating KPIs ................................................................................................ 8
Table 6: Cost Estimator Performance Ratings Definitions .................................................... 10

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 3 OF 38

©NEOM [2022]. All rights reserved.


Purpose
This procedure establishes the NEOM Cost Estimation Division’s framework for measuring the performance
of Cost Estimators and the quality of their deliverables (e.g., Cost Estimates and Cost Estimate Reports).
The framework comprises key performance indicators (“KPI’s”) that matter the most to NEOM in terms of
cost estimation. They provide the key targets for Cost Estimators to achieve in terms of “Time,” “Quality,
and “Customer Satisfaction.”

From NEOM Cost Estimation Division’s perspective, the purpose of Time KPIs is to monitor if Cost
Estimators are submitting their Cost Estimate Reports within the agreed time parameters. Whereas the aim
of the Quality KPIs is to improve visibility of quality relating to Cost Estimates and Cost Estimate Reports
through the measurement of “Quality Issues”. The objective of the Customer Satisfaction KPIs is to assess
NEOM’s satisfaction with its Cost Estimator’s services.

KPIs give NEOM Cost Estimation Division a realistic look at the quality of Cost Estimates, Cost Estimate
Reports, and the service provided by Cost Estimators engaged for cost estimation services. They help
identify issues and inform the corrective measures required to resolve them, so that NEOM can rely on the
Cost Estimates and Cost Estimate Reports received.

Scope
These Procedures relate to NEOM’s cost estimation function (i.e., the NEOM Cost Estimation Division).
They apply to all cost estimating services provided by both NEOM’s cost estimators (internal) and NEOM’s
external cost estimating service providers (external).

List of Definitions and Abbreviations


3.1 Definitions

Several terms used for performance measurement are used interchangeably, often within the same
organization, NEOM has adopted the following definitions of these terms:

Table 1: Table of Definitions

Term Definition

Cost Estimate(s) Collective term for an Order of Cost Estimate and/or an Elemental Cost
Plan.

Cost Estimator/ Cost The organisation contracted by NEOM Cost Estimation Division (or a
Consultant NEOM Proponent) to provide cost estimating services to NEOM.

Indicator(s) A qualitative or quantitative factor or variable that provides a simple and


reliable means to measure achievement.

Key Performance Indicator A selected indicator considered key for monitoring the performance of a
(“KPI”) strategic objective or a key result area important to the success of an
activity and growth of an organisation overall. KPIs make objectives
quantifiable, providing visibility into the performance of individuals, teams,
departments, and organisations and enabling decision-makers to act in
achieving desired outcomes. KPIs will be communicated through
dashboards, scorecards, and other forms of performance reports.

Major Quality Issue The Quality Issue results in NEOM rejecting the Cost Estimate Report.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 4 OF 38

©NEOM [2022]. All rights reserved.


Term Definition

Minor Quality Issue The Quality Issue results in NEOM returning the Cost Estimate Report to
the Cost Estimator or NEOM accepts the Cost Estimate Report although it
is below the agreed standard (compromises).

Measure A number or a quantity that records a directly observable value. All


measures are composed of a number and unit of measure. The number
provides the magnitude (how much) for the measure, while the unit gives
the number a meaning (what). Examples of units are percentage, number,

Metric, Performance The quantitative basis by which objectives are established and
measure, or Performance performance is assessed. It helps quantify the achievement of a result, the
indicator quantifiable component of the cost estimator’s performance.
Note:

In the context of measuring and managing performance these terms can be used
interchangeably.

NEOM Cost Estimation Reviews and endorses cost estimates submitted by Cost Estimators/Cost
Division Consultants, NEOM Sectors, NEOM Departments and NEOM Proponents.
Currently a division of “Engineering & Technical Services Department”.

NEOM Cost Estimation The representative of NEOM Cost Estimation Division who is responsible
Division Representative or for liaising with the Cost Estimator/Cost Consultant about service
NEOM Representative deliverables (i.e., the Cost Estimate and Cost Estimate Report).

NEOM Head of Cost The head of NEOM Cost Estimation Division who has overall responsibility
Estimation for delivering accurate and timely Cost Estimates to NEOM

NEOM Plan of Work The objectives and activities during project implementation through
business case, master planning, design, construction, and operation and
maintenance stages.

NEOM Proponent The NEOM Region, Sector or Department.

Project The development and delivery of a NEOM asset or a group of NEOM


assets.

(Project) cash flow The cash flow forecast of a particular project


forecast

Project Brief, Project The project brief is the key document upon which design of a project will
Requirements, Statement be based.
of Need, Scope of Work
Note:

In the context of cost estimating, the terms can be used interchangeably.

Quality The degree to which a requirement meets, fails to meet, or exceeds


NEOM’s requirements.

Quality Issue An issue that affects the Cost Estimate or Cost Estimate Report so that
work needs to be redone, modified, or compromised to a lower standard
than originally agreed.

Risk allowance The sum included within a cost estimate for an unknown condition, or yet-
to-be-specified product.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 5 OF 38

©NEOM [2022]. All rights reserved.


Term Definition

Risk allowance estimate The amount added to the base cost estimate for items that cannot be
precisely predicted.

Service Improvement Plan A documented strategy for improving service delivery. The Plan identifies
the areas in which improvement is required and what actions the Cost
Estimator is to take to achieve the improvements. The Plan is produced by
the Cost Estimator and agreed by NEOM. Improvement actions by the
Cost Estimator are monitored by NEOM.

Significant cost item(s) Major cost items, such as concrete, structural steelwork, reinforcement,
cladding, excavation, groundworks, piled foundations, etc.

3.2 Abbreviations

Definitions and abbreviations in this document follow NEOM-NEN-SCH-006. Additional definitions and
abbreviations covered by this procedure are found below:

Table 2: Table of Abbreviations

Abbreviation Description

CE Cost Estimator

DIFOT Delivery in full, on time

KPI Key Performance Indicator.

Related NEOM Documents


Other NEOM documents that relate to this Performance Measurement and Reporting procedure are listed in
Table 3 below:

Table 3: Related NEOM Documents

Document Code Document Name

NEOM-NCC-MAN-001 Cost Estimation Manual: Cost Estimation Policies and Guidelines

NEOM-NCC-PRC-001 Cost Procedures: Cost Estimation Procedures

NEOM-NCC-PRC-003 Company Bid Procedure

NEOM-NEN-PRC-029 NEOM Plan of Work

NEOM-NEN-MAN-001 Quality Management System Manual

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 6 OF 38

©NEOM [2022]. All rights reserved.


Roles and Responsibilities
The roles and responsibilities under this procedure are set out in Table 4:

Table 4: Roles and Responsibilities

Role Responsibilities

Cost Estimator Cost Estimate Report review:


• Receives notification of rework or rejected Cost Estimate Report
from NEOM Cost Estimation Division.
• Completes rework of Cost Estimate Report requested by NEOM
Cost Estimation Division.
• Resubmits corrected or new Cost Estimate Report to NEOM Cost
Estimation Department.
Cost Estimator service:
• Receives Cost Estimator Performance Report Form” from NEOM
Cost Estimation Division.
• Completes Part 3 of the “Cost Estimator Performance Report
Form” and returns to NEOM Cost Estimation Division within three
(3) working days.

NEOM Cost Estimation Cost Estimate Report review (for all Cost Estimate Reports):
Division
• Receives Cost Estimate Report, including Cost Estimate, from
Cost Estimator.
• Reviews Cost Estimate Report.
• Completes “Cost Estimate Report Checklist” by:
- Confirming if requirements have been met.
- Scoring each requirement.
- Identifying and recording the number of “Quality Issues”.
• Completes “Cost Estimate Report Scorecard”, which generates
“Ratings”, and the total number of Quality Issues.
• Notifies Cost Estimator of any rework required, together with
resubmission date.
• Notifies Cost Estimator if Cost Estimated Report rejected,
together with resubmission date.
Cost Estimator service (Quarterly):
• Completes Parts 1 and 2 of “Cost Estimate Performance Report
Form”.
• Issues “Cost Estimate Performance Report Form” to Cost
Estimator for feedback.
• Completes “Cost Estimator Performance Scorecard”, which
generates performance “Ratings” for the Cost Estimator.
• Records KPI measurements on “Cost Estimator KPI Results
Record”.
• Reappraises the Cost Estimator’s “Rating” if instructed to do so
by the NEOM Head of Cost Estimation following review of the
Cost Estimator’s feedback.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 7 OF 38

©NEOM [2022]. All rights reserved.


Role Responsibilities
Record management:
• Retains copies of all completed “Cost Estimate Report
Checklists”, “Cost Estimate Report Scorecards”, “Cost Estimator
Performance Report Forms”, “Cost Estimator Performance
Scorecards”, and all other KPI records. (Records Management).
Reporting KPIs:
• Reports KPIs to the NEOM Head of Cost Estimation at the agreed
frequency (i.e., monthly, quarterly, six monthly, yearly).

NEOM Head of Cost Cost Estimator service:


Estimation
• Receives completed Cost Estimator Performance Report Form”
from Cost Estimator.
• Completes Part 4 of the “Cost Estimator Performance Report
Form”, including specifying any actions to be taken by the NEOM
Cost Estimation Division.
• Communicates actions to be taken to the appropriate person(s) in
NEOM Cost Estimation Division.

Procedure
6.1 Cost estimating as a functional area

These Procedures apply to all cost estimating services provided by Cost Estimators.

6.2 The need for KPIs

NEOM undertakes verification activities, which include checking that cost Estimating service providers have
provided the services specified in their contract with NEOM and meet quality requirements.

6.3 KPI groups

The KPI framework for cost estimating services consists of three main groups:

• Time.
• Quality.
• Client satisfaction.

Within these KPI groups, a range of indicators has been developed to analyze either cost estimator or
NEOM performance, or both.

6.4 Cost estimating KPIs

NEOM has established Cost Estimating KPIs to measure the performance of both NEOM’s cost estimators
(internal) and external cost estimating service providers (external). The Cost Estimating KPIs are reflective
of the Cost Estimating Function and are presented in ‘Table 5: Cost Estimating KPIs’ below. Table 5 shows
the ‘Indicator’ (i.e., the KPI), the ‘KPI Group’, and the ‘KPI Definition’.

Table 5: Cost Estimating KPIs

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 8 OF 38

©NEOM [2022]. All rights reserved.


Indicator KPI Group KPI Definition

1.01 Delivery in full, on time (DIFOT) Time Measures the percentage of fully compliant
rate Cost Estimate Reports delivered on time by the
Cost Estimator.

2.01 Quality of Cost Estimate Quality Measures the quality of Cost Estimate Reports
Reports against predetermined criteria using the 1 to 10
scale set out in Appendix C: Cost Estimate
Report Checklist.

2.02 Quality Issues Quality Measures the number of “Quality Issues”


identified within Cost Estimate Reports.

2.03 Rework Quality Measures the number of Cost Estimate


Reports returned to the Cost Estimator for
rework by NEOM.

2.04 Rejection Quality Measures the number of Cost Estimate


Reports rejected by NEOM.

2.05 Compromise Quality Measures the number of Cost Estimate


Reports below the agreed standard that are
accepted by NEOM without rework.

3.01 Cost Estimator service Client Measures the overall NEOM satisfaction with
Satisfaction the cost Estimating services provided against
predetermined criteria using the following
performance ratings: Unacceptable; Marginal;
Acceptable; Very Good; and Exceptional.
See Appendix D: Cost Estimator Performance
Report Form.

The purpose of each of the above KPIs are explained in Appendix A (Cost Estimation KPIs), together with
the method of measurement, the data collection method, the calculation formula, the frequency of
measurement, the source of data, the target rating, the required trend, and the reporting period.

Example calculations of KPIs are contained in Appendix B (Example KPI Calculations).

6.5 Cost Estimator performance measurement

Cost Estimator’s performance shall be monitored by NEOM. Each Cost Estimators’ performance is to be
measured and analyzed quarterly, or more frequently in cases of mediocre or deficient performance.

Metrics are to be gathered by way of performance reports (using the Cost Estimator Performance Report at
Appendix D), which shall be completed by the NEOM Representative responsible for procuring the Cost
Estimate Report on completion of service delivery.

The NEOM Representative inserts the metrics recorded on the Cost Estimator Performance Report on to
the Cost Estimator Performance Scorecard, which will automatically calculate the Cost Estimator’s overall
rating, as well as ratings for each performance criteria.

Cost Estimators are to be given an opportunity to comment on the performance ratings given by NEOM.
This is achieved by the NEOM Representative sending a copy of the Cost Estimator Performance Report to
the Cost Estimator. The Cost Estimator is invited to comment on the ratings given by the NEOM
Representative.

The Cost Estimator returns the completed Cost Estimator Performance Report to the NEOM Head of Cost
Estimation, who assesses the Report and the ratings and informs the NEOM Cost Estimation Division of
any actions to be taken by them in connection with the Cost Estimator’s performance.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 9 OF 38

©NEOM [2022]. All rights reserved.


If there is poor or downward trend in Cost Estimator performance, it is important to act quickly. Quick action
can reduce the risk of future performance issues and gives the NEOM Cost Estimation Division and the
Cost Estimator the ability to take steps to prevent poor outcomes.

Cost Estimators whose performance falls below requirements shall be required to provide the NEOM Cost
Estimation Division with a Cost Estimation Service Improvement Plan, which NEOM will monitor.

The NEOM Head of Cost Estimation may instruct the removal of Cost Estimators from the NEOM Approved
Supplier List where performance consistently falls below expectations and where Cost Estimation Service
Improvement Plans are not achieved.

6.6 Cost Estimator performance ratings

Definitions of the ratings used to rate the Cost Estimator’s performance are given in Table 6 (Cost Estimator
Performance Ratings Definitions) below.

Where a performance criterion is not applicable, insert “Not Applicable” for performance criteria that are not
applicable.

Table 6: Cost Estimator Performance Ratings Definitions

Rating Definition
Quality of Service Cost Timeliness Business
Relations
Unacceptable: Non-conformances There were significant Delays significantly Responses to
compromised issues in connection compromised the enquiries/technical
achievement of with fees and/or time achievement of service and
contract records, which required programme/delivery administrative issues
requirements despite major help from NEOM schedule, despite was/is neither
help from NEOM resources to resolve help by NEOM effective nor
resources resources responsive

Marginal: Non-conformances There were Delays required Responses to


required major considerable issues in help by NEOM enquiries/technical
involvement of connection with fees resources to ensure service and
NEOM resources to and/or time records, achievement of administrative issues
enable achievement which required some programme/delivery was/is occasionally
of contract help from NEOM schedule effective and
requirements resources to resolve responsive

Acceptable: Non-conformances There were minor Delays impacted on Responses to


required minor issues in connection achievement of enquiries/technical
involvement of with fees and/or time programme/delivery service and
NEOM resources to records, which required schedule administrative issues
enable achievement some help from NEOM was/is often effective
of contract resources to resolve and responsive
requirements

Very Good: Non-conformances There were minimal Delays did not Responses to
did not impact the issues in connection impact on enquiries/technical
achievement of with fees and/or time achievement of the service and
contract records programme/delivery administrative issues
requirements schedule was/is mostly
effective and
responsive

Exceptional: There were no quality There were no issues There were/are no Responses to
problems in connection with fees delays enquiries/technical
and/or time records service and
administrative issues
was/is always
effective and
responsive

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 10 OF 38

©NEOM [2022]. All rights reserved.


6.7 Reporting KPIs

The NEOM Cost Estimation Division records the KPI metrics on the “Cost Estimator KPI Results Record.

Divisional Heads are responsible for developing the Quality Objectives of the department and transforming
them into team members.

The NEOM Cost Estimation Division presents or reports the KPI metrics at agreed frequencies to the
NEOM Head of Cost Estimation.

The NEOM Head of Cost Estimation shares the final KPIs results with the Cost Estimation team members,
the Consultants, and ETSD Management.

Email, meetings, and memos should be maintained as communication means of the KPIs objectives &
Performance Results with the interested parties and teams.

Forms and Templates

Form No. Title


NEOM-NCC-PRC-002_FRM01 Cost Estimate Report Checklist
NEOM-NCC-PRC-002_FRM02 Cost Estimate Report Scorecard (MS Excel spreadsheet)
NEOM-NCC-PRC-002_FRM03 Cost Estimator Performance Report Form
NEOM-NCC-PRC-002_FRM04 Cost Estimator Performance Scorecard (MS Excel spreadsheet)
NEOM-NCC-PRC-002_FRM05 Cost Estimator KPI Results Record (MS Excel spreadsheet)

Appendices
Appendix A: Cost Estimating Key Performance Indicators

Appendix B: Example KPI Calculations

Appendix C: Cost Estimate Report Checklist

Appendix D: Cost Estimate Report Scorecard

Appendix E: Cost Estimator Performance Report Form

Appendix F: Cost Estimator Performance Scorecard

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 11 OF 38

©NEOM [2022]. All rights reserved.


Appendix A - Cost Estimating Key Performance Indicators

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 12 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 1.01

Delivery in full, on time (DIFOT) rate

Purpose
Key performance question this indicator helps to answer:
To what extent are we are getting what we want by the time we want it?
Was the Cost Estimate delivered on time? Were there reasons for slippage?

Definition
Measures the percentage of fully compliant Cost Estimate Reports delivered in full and on time by the Cost Estimator.

How is it measured?
DIFOT is simply calculated as the number of Cost Estimates delivered in full and on time verses the total number of Cost
Estimate Reports commissioned.
Data collection method
Data for the DIFOT KPI are collected through comparing the number of Cost Estimate Reports received from the Cost
Estimator that are delivered in full and on time with the total number of Cost Estimate Reports received from the Cost
Estimator in a defined period.
Calculation formula
(A/B) x 100
Where:
A = Number of Cost Estimate Reports delivered in full, on time by Cost Estimator
B = Total number of Cost Estimate Reports delivered by Cost Estimator
Frequency
Continuously - Every time Cost Estimate Report delivered.
Source of the data
Required by date stated in contract and actual submission date of Cost Estimate Report by Cost Estimator.

Target
100% - Action required if DIFOT slips below 95%.

Required trend
Increasing or Static if target achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 13 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 2.01

Quality of Cost Estimate Reports

Purpose
Key performance question this indicator helps to answer:
Do Cost Estimate Reports meet NEOM’s requirements (i.e., estimating formats, grouping costs under the right work
breakdown structure)?

Definition
Measures the quality of Cost Estimate Reports against predetermined criteria.

How is it measured?
Data collection method
Checking Cost Estimate Reports against predetermined criteria.
Calculation formula
1 to 10 scale set out in the Cost Estimate Report Checklist.
Frequency
Continuously - Every time Cost Estimate Report delivered.
Source of the data
Cost Estimate Report.

Target
“Very Good” - Action required if “Unacceptable” or “Marginal”

Required trend
Increasing or Static if target achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 14 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 2.02

Quality Issues

Purpose
Key performance question this indicator helps to answer:
To what extent can we rely on the Cost Estimator’s Cost Estimate Report?
Does the Cost Estimate Report include errors?

Definition
Measures the total number of “Quality Issues” identified within Cost Estimator’s Cost Estimating Report.

How is it measured?
Data collection method
Derived from Cost Estimate Report Scorecard.
• Arithmetical errors:
• Quantity measures:
• Rate/Price errors:
• Omissions:
• Duplication:
• Unassessed risks:
• Transparency deficiency
Calculation formula
A= B1+B2+B3+B4+B5+B6+B7 (or A = ∑B1, B2, B3, B4, B5, B6, B7)
Where:
A= Total number of Quality Issues
B1 = Number of Arithmetical errors
B2 = Quantity measures
B3 = Rate/Price errors
B4 = Omissions
B5 = Duplication
B6 = Unassessed risks
B7 = Transparency deficiency
Frequency
Continuously - Every time Cost Estimate Report delivered.
Source of the data
Cost Estimate Report.

Target
0 – Service Improvement Plan required if “Major Quality Issue” found, or more than seven (7) “Minor Quality Issues” found.

Required trend
Decreasing or Static if target achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 15 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 2.03

Rework

Purpose
Key performance question this indicator helps to answer:
To what extent can we rely on the Cost Estimator’s Cost Estimate Report?
Does the Cost Estimator’s Cost Estimate Report include errors?

Definition
Measures the number of Cost Estimate Reports returned to the Cost Estimator for rework.

How is it measured?
Data collection method
Through review of Cost Estimate Report.
Calculation formula
A
Where:
A = Number of Cost Estimate Reports returned to Cost Estimator for rework.
Frequency
Continuously - Every time Cost Estimate Report delivered.
Source of the data
Cost Estimate Report.

Target
0 - Action required if greater than five (5) in a reporting period (e.g., Q1, Q2, etc.).

Required trend
Decreasing or Static if target achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 16 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 2.04

Rejection

Purpose
Key performance question this indicator helps to answer:
To what extent can we rely on the Cost Estimator’s Cost Estimate Report?
Does the Cost Estimator’s Cost Estimate Report include numerous and/or significant errors?

Definition
Measures the number of Cost Estimate Reports rejected by NEOM.

How is it measured?
Data collection method
Through review of Cost Estimate Report.
Calculation formula
A
Where:
A = Number of Cost Estimate Reports rejected by NEOM.
Frequency
Continuously - Every time Cost Estimate Report delivered.
Source of the data
Cost Estimate Report.

Target
0 – Service Improvement Plan required is more than three (3) in a reporting period (e.g., Q1, Q2, etc.)..

Required trend
Decreasing or Static if target achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 17 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 2.05

Compromise

Purpose
Key performance question this indicator helps to answer:
To what extent can we rely on the Cost Estimator’s Cost Estimate Report?

Definition
Measures the number of Cost Estimate Reports below the agreed standard that are accepted by NEOM (i.e., Quality Issues
accepted without the need for rework).

How is it measured?
Data collection method
Through review of Cost Estimate Report.
Calculation formula
A
Where:
A = Number of Cost Estimate Reports below the agreed standard that are accepted by NEOM.
Frequency
Continuously - Every time Cost Estimate Report delivered
Source of the data
Cost Estimate Reports.

Target
0 - Action required if more than three (3) Cost Estimate Reports are below the agreed standard that is accepted by NEOM in
any a reporting period (e.g., Q1, Q2, etc.).

Required trend/target
Decreasing or Static if target achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 18 OF 38

©NEOM [2022]. All rights reserved.


Ref: CE KPI 3.01

Cost Estimator service

Purpose
Key performance question this indicator helps to answer:
Are we satisfied with the performance of our Cost Estimators?

Definition
Measures the performance of Cost Estimators against predetermined criteria.
How is it measured?
Data collection method
Through Cost Estimator Performance Report (refer to Appendix D: Cost Estimator Performance Report Form).
Calculation formula
Derived from Cost Estimator Performance Scorecard.
Ratings:
• Unacceptable
• Marginal
• Acceptable
• Very Good
• Exceptional
Frequency
Continuously - Every time Cost Estimate Report delivered.
Source of the data
Cost Estimator Performance Evaluation Report and Cost Estimator Performance Scorecard.

Target
Very Good - Action required if rating is ‘Unacceptable’ or ‘Marginal’.

Required trend/target
Increasing or Static if maximum measure achieved.

Reporting period
Quarterly.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 19 OF 38

©NEOM [2022]. All rights reserved.


Appendix B - Example KPI Calculations

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 20 OF 38

©NEOM [2022]. All rights reserved.


Time

Data
• Total number of Cost Estimate Reports delivered by the Cost Estimator to
NEOM: 8
• Total number of fully compliant Cost Estimate Reports delivered by the Cost
Estimator to NEOM on or before the due date: 6

Indicator 1.01 – Delivery in full, on time (DIFOT) rate

Total number of Cost Estimate Reports delivered in full, on


time by Cost Estimator
DIFOT = x 100 = __%
Total number of Cost Estimate Reports delivered by Cost
Estimator

6
DIFOT = x 100 = 75%
8

Quality

Data obtained from Cost Estimate Checklist Form


• Arithmetical errors: 2
• Quantity measures: 3
• Rate/Price errors: 2
• Omissions: 1
• Duplication: 2
• Unassessed risks: 6
• Transparency deficiency:
2
• Total number of compliant Cost Estimate Reports received from the Cost
Estimator by NEOM in measurement period: 8
• Number of Cost Estimate Reports returned to Cost Estimator for “Rework”: 2
• Total number of Cost Estimate Reports “Rejected” by NEOM in measurement 1
period:
• Number of Cost Estimate Reports below the agreed standard accepted by 3
NEOM in measurement period:

Indicator 2.01 – Quality of Cost Estimate Reports

Scores input into Cost Estimate Report Scorecard, which automatically ascertains “Rating” for each Cost
Estimate Report requirement.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 21 OF 38

©NEOM [2022]. All rights reserved.


Indicator 2.02 – Quality Issues

Quality Issue No.


Arithmetical errors: 2
Quantity measures: 3
Rate/Price errors: 2
Omissions: 1
Duplication: 2
Unassessed risks: 6
Transparency deficiency: 2

Total number of “Quality Issues”: 18

Indicator 2.03 – Rework

Number of Cost Estimate Reports returned to Cost Estimator for rework = 2

Note:

The percentage of Cost Estimate Reports returned to Cost Estimator for rework can also be measured using the
following calculation and recorded:

Total number of Cost Estimate reports returned” to the Cost


Estimator for “Rework”
Rework = x 100 = __%
Total number of Cost Estimate Reports delivered by Cost
Estimator

2
Rework = x 100 = 25%
8

Indicator 2.04 – Rejection

Number of Cost Estimate Reports rejected by NEOM = 1

Note:

The percentage of Cost Estimate Reports rejected can also be measured using the following calculation and
recorded:

Total number of Cost Estimate Reports returned to the Cost


Estimator as “Rejected”
Rejection = x 100 = __%
Total number of Cost Estimate Reports delivered by Cost
Estimator

1
Rejection = x 100 = 12.5%
8

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 22 OF 38

©NEOM [2022]. All rights reserved.


Indicator 2.05 – Compromise

Number of Cost Estimate Reports below the agreed standard that are accepted by NEOM = 4

Note:

The percentage of Cost Estimate below the agreed standard that are accepted by NEOM can also be measured
using the following calculation and recorded:

Total number of Cost Estimate Reports below the agreed


standard that are accepted by NEOM (“Compromised”)
Compromise = x 100 = __%
Total number of Cost Estimate Reports delivered by Cost
Estimator

4
Compromise = x 100 = 50%
8

Customer Satisfaction

Indicator 3.01 – Cost Estimator performance

Ratings input into Cost Estimator Performance Scorecard, which automatically calculates Cost Estimates overall
performance rating.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 23 OF 38

©NEOM [2022]. All rights reserved.


Appendix C - Cost Estimate Report Checklist

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 24 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM01

Guidance

The Quality of Cost Estimate Report KPI is recorded using the following scoring system:

5 = Satisfactory – appears to meet all NEOM’s requirements.

4 = Minor errors – errors contained in Cost Estimate Report which have no significant impact on NEOM.
Rework not required (compromise).

3 = Some rework - some modifications/changes required to Cost Estimate Report to meet the required
standard.

2 = Extensive rework – extensive modifications/changes required to Cost Estimate Report to meet the
required standard.

1 = Rejected – completely unacceptable, considered unusable. Cost Estimate Report to be restarted and
resubmitted.

The aim of this quality KPI is to improve the visibility of quality issues pertaining to Cost Estimate Reports through
the measurement of “Quality Issues”. Therefore, this measure is to record all quality issues on all elements of
Cost Estimate Reports received by NEOM.

In the context of Cost Estimation, a “Quality Issue” is defined as:

“An issue that affects the Cost Estimate or Cost Estimate Report so that work needs to be redone, modified,
or compromised to a lower standard than originally agreed.”

As a result, a “Quality Issue” will encompass errors, but it is also a much wider measure which covers issues
such as incorrect information, missing information, inappropriate rates and prices, duplicate items, use of
incorrect measurement convention, arithmetical errors, unclear statements, and unstructured Cost Estimate
Reports.

Definitions of the three types of “Quality Issue” are:

Rejected: When a “Quality Issue” involves the work being completely restarted and all previous work
deemed unusable, then the “Quality Issue” will be classified as rejected.

Reworked: When a “Quality Issue” involves the work that requires modification/correction to meet the
required NEOM standard, then the “Quality Issue” will be classified as reworked.

Compromised: If NEOM accept the work below the agreed standard this will be classified as
compromised.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 25 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM01

Cost Estimate Report Checklist

Project title: Click or tap here to enter text.


Cost Estimator: Click or tap here to enter text.
Date Checklist Completed: Click or tap to enter a date.

Item Requirement Requirement Score/Rating


met
1.01 Cost Estimate Report "Delivery in full, on time (DIFOT): Insert Insert

2.01.01 Structure of Cost Estimate Report Insert Score/Rating


The Cost Estimate Report is structure in accordance with Table 9 of
the Cost Estimation Procedure:
• Executive Summary. Choose an item.
• Introduction. Choose an item.
• Statement of Cost. Choose an item.
• Project Description. Choose an item.
• General Pricing Notes and Assumptions. Choose an item.
• Information Provided (list of information on which cost estimate Choose an item.
has been based).
• List of Exclusions. Choose an item.
• Cost Estimate Summary Page. Choose an item.
• Cost Estimate Summary Reconciliation Page (if applicable). Choose an item.
• Detailed Breakdown of Cost Estimate. Choose an item.
• (Project) Cash Flow Forecast (if applicable). Choose an item.
2.01.02 Understanding project requirements: Choose an item. Insert Score/Rating
The Cost Estimate Report contains satisfactory narrative to confirm
that the Cost Estimator has fully understood NEOM’s project
requirements/Project Brief.
2.01.03 Correct scope: Choose an item. Insert Score/Rating
The correct project scope has been captured in the Cost Estimate
Report?
2.01.04 Quality/Specification: Choose an item. Insert Score/Rating
The Cost Estimate Report contain a satisfactory narrative to confirm
that the Cost Estimator has allowed for the appropriate level of
quality (specification) in the cost estimate.
2.01.05 Collaboration: Choose an item. Insert Score/Rating
The Cost Estimate Report contains satisfactory narrative to confirm
that the Cost Estimator has collaborated with the with Designers and
other Project Team members to ensure understanding of NEOM’s
project requirements/Project Brief.
2.01.06 Basis of Estimate Choose an item. Insert Score/Rating
All exclusions, assumptions, and other qualifications are clearly
communicated in the Cost Estimate Report.
2.01.07 Method of measurement: Choose an item. Insert Score/Rating
The correct method of measurement (e.g., NRM1, NRM2, NRM3 or
CESMM) has been used by the Cost Estimator.
2.01.08 Appropriateness of unit rates and prices Choose an item. Insert Score/Rating
Unit rates and prices used to determine significant cost items (see
definition) are considered appropriate for the project.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 26 OF 38

©NEOM [2022]. All rights reserved.


Item Requirement Requirement Score/Rating
met
2.01.09 Contractors/Sub-Contractors Estimates Choose an item. Insert Score/Rating
Contractor’s and Sub-Contractors estimates included in the Cost
Estimate have been checked by the Cost Estimator.
2.01.10 Cost drivers Choose an item. Insert Score/Rating
Key cost drivers have been identified and recorded in the Cost
Estimate Report.
2.01.11 Estimate base date: Choose an item. Insert Score/Rating
The date from which tender inflation is estimated is clearly stated in
the Cost Estimate Report.
2.01.12 Inflation: Choose an item. Insert Score/Rating
Appropriate allowances for tender inflation (estimate base date to
start of construction) and construction inflation (tender return date to
mid-point of construction period) have been included in the Cost
Estimate.
2.01.13 Risks - Inclusion: Choose an item. Insert Score/Rating
All appropriate risks identified in the Risk Register have been
addressed in the Cost Estimate.
2.01.14 Risk allowance estimates - Inclusion: Choose an item. Insert Score/Rating
Appropriate risk allowances have been included in the Cost
Estimate.
2.01.15 Risk allowance estimates - Justification: Choose an item. Insert Score/Rating
Justification has been given for risk allowances.
2.01.16 Value engineering/Value improvements: Choose an item. Insert Score/Rating
Value engineering options/value improvement suggestions are
included in the Cost Estimate Report.
2.01.17 Arithmetical checks: Choose an item. Insert Score/Rating
The Cost Estimate has been independently arithmetically checked
by the Cost Estimator (i.e., by an individual not involved in compiling
the Cost Estimate).
2.01.18 Cost Estimate Sign-Off Form: Choose an item. Insert Score/Rating
Completed ‘Cost Estimate Sign-off Form’ (NEOM-NCC-PRC-
001_FRM01) included within Cost Estimate Report.
2.01.19 Cost Estimate Summary Form: Choose an item. Insert Score/Rating
Completed ‘Cost Estimate Summary Form’ (NEOM-NCC-PRC-
001_FRM02) included within Cost Estimate Report.
2.02 Quality Issue Quantity Unit
2.02.01 • Arithmetical errors. Insert nr
Quantity
2.02.02 • Quantity errors (due to inaccurate measurement) Insert nr
Quantity
2.02.03 • Rate/Price errors Insert nr
Quantity
2.02.04 • Omissions. Insert nr
Quantity
2.02.05 • Duplication. Insert nr
Quantity

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 27 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM01

Item Requirement Requirement Score/Rating


met
2.02.06 • Unassessed risks (i.e., no risk allowance included in Cost Estimate for Insert nr
items on Risk Register which would have a cost and/or time impact on Quantity
project if they materialize).
2.02.07 • Transparency deficiency (lack of or unclear explanations included in Cost Insert nr
Estimate Report). Quantity

☐ Sent back for re-work

☐ Rejected

☐ Compromise

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 28 OF 38

©NEOM [2022]. All rights reserved.


Appendix D- Cost Estimate Report Scorecard (MS Excel
spreadsheet)

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 29 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM02

Cost Estimate Report Scorecard

NEOM-NEN-PRC-002_FRM02A

Project: Enter text.

Name of Cost Estimator (Company) Enter text.

Date: Insert Date of Cost Estimate Report Review

Item Requirement Score RATING

1.01 Cost Estimate Report "Delivery in f ull, on time (DIFOT): Insert Score FALSE

2.01.01 Structure of Cost Estimate Report: Insert Score FALSE


2.01.02 Understanding project requirements: Insert Score FALSE
2.01.03 Correct scope: Insert Score FALSE
2.01.04 Quality/Specif ication: Insert Score FALSE
2.01.05 Collaboration: Insert Score FALSE
2.01.06 Basis of Estimate: Insert Score FALSE
2.01.07 Method of measurement: Insert Score FALSE
2.01.08 Appropriateness of unit rates and prices: Insert Score FALSE
2.01.09 Contractors/Sub-Contractors Estimates: Insert Score FALSE
2.01.10 Cost drivers: Insert Score FALSE
2.01.11 Estimate base date: Insert Score FALSE
2.01.12 Inf lation: Insert Score FALSE
2.01.13 Risks - Inclusion: Insert Score FALSE
2.01.14 Risk allow ance estimates - Inclusion: Insert Score FALSE
2.01.15 Risk allow ance estimates - Justif ication: Insert Score FALSE
2.01.16 Value engineering/Value improvements: Insert Score FALSE
2.01.17 Arithmetical checks: Insert Score FALSE
2.01.18 Cost Estimate Sign-Of f Form: Insert Score FALSE
2.01.19 Cost Estimate Summary Form: Insert Score FALSE

Total Score/Overall Rating: 0 UNACCEPTABLE

Overall Score: 1

Item Quality Issue Number of


Errors
2.02.01 Arithmetical errors: Insert
2.02.02 Quantity errors (due to inaccurate measurement): Insert
2.02.03 Rate/Price errors: Insert
2.02.04 Omissions: Insert
2.02.05 Duplication: Insert
2.02.06 Unassessed risks: Insert
2.02.07 Transparency def iciency: Insert

Total number of errors: 0

☐ Sent back f or re-w ork


☐ Rejected
☐ Compromise

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 30 OF 38

©NEOM [2022]. All rights reserved.


Appendix E- Cost Estimator Performance Report Form

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 31 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM03

Guidance

Parts 1 to 3 of this report are to be completed by the NEOM Representative responsible for monitoring the Cost
Estimator’s performance. Definitions of performance ratings are set out in section 6.6 (Cost Estimator
performance ratings) of the Performance Measurement and Reporting Procedure. The reasons for giving
‘Marginal’ or ‘Unacceptable’ ratings must be given by the NEOM Representative in Part 3 of the report.

The Evaluator submits the Cost Estimator Performance Report to the Cost Estimator for comment. The Cost
Estimator provides feedback by completing Part 4 and returns the completed report to the NEOM Head of Cost
Estimation via email.

The NEOM Head of Cost Estimation reviews the report (including the Cost Estimator’s comments), records any
actions to be taken and by whom, and closes out the report by completing Part 5.

The NEOM Representative inserts the ratings into the Cost Estimator Performance Scorecard and records the
overall scores in the Cost Estimator Performance Record.

Figure 1: Cost Estimator performance measurement

Flowchart for Performance Measurement Process


Assesment

NEOM CED (Representative) NEOM Cost


Estimating Division Cost Estimator
Complete Parts 1 and 2 of Cost (Representative)
Start
Estimator Performance Review Send Form to Cost Complete Part 3 of Form
Form Estimator via email

NEOM CED (Representative) NEOM CED (Representative)


Rating

Enter ratings from Review Form to Cost Record KPI metrics ascertained from
Estimator Performance Scorecard to Scorecard on Cost Estimator s KPI Results
ascertain KPI metrics Record
Review

NEOM Head of Cost Estimation Cost Estimator


NEOM Head of Cost Estimation
Review ratings and comments of both Send Form to
Complete Part 4 of Form NEOM Representative and Cost Estimator NEOM Head of Cost
recorded on Form Estimation via email
Evaluation

NEOM CED (Representative)


Finalizing

NEOM Head of Cost Estimation NEOM Head of Cost


Estimation
Send completed Form to Update ratings on Scorecard if instructed to do so
Communicate actions to be taken to by NEOM Head of Estimation; ascertain revised
appropriate person(s) in NEOM Cost NEOM Cost Estimating rating; and update Cost Estimator s KPI Results
Estimating Division Division via email Record

NEOM Cost Estimating Division


Archive

(Representative)
End
Store completed Form in Cost
Estimator Performance Review File

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 32 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM03

Cost Estimator Performance Report

Part 1: General information


NEOM Project No.: Click here to enter text.
Project Title: Click here to enter text.
Name of Cost Estimator Click here to enter text.

Part 2: Performance evaluation

Performance criteria Rating


Refer to “Rating Guidelines” at end of Report Form.
1. Quality of service
1.1 Professionalism Choose Rating
1.2 Technical skills Choose Rating
1.3 Co-operation Choose Rating
1.4 Contract compliance Choose Rating
1.5 Accuracy of work completed Choose Rating
1.6 Responsiveness to problems Choose Rating
1.7 Service recovery (i.e., following corrective action or rework) Choose Rating
2. Cost
2.1 On time billing (Applications for payment submitted on time) Choose Rating
2.2 Billing accuracy (complies with Cost Estimator’s contract) Choose Rating
3. Timeliness
3.1 On-time delivery (i.e., adherence to programme/delivery schedule) Choose Rating
4. Business relations
4.1 Effective management Choose Rating
4.2 Accessibility to Director/Senior manager Choose Rating
4.3 Prompt notification of problems/issues Choose Rating

Part 3: NEOM Representative’s comments


Click here to enter text.
Would you use this Cost Estimator again? Choose
Evaluated by: Click here to enter name. Date of Report: Click here to enter a date.

☐ Sent back for re-work

☐ Rejected

☐ Compromise

Submit completed report via email to Cost Estimator for response, stating when response is required by.

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 33 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM03

Part 4: Cost Estimator’s comments


Click here to enter text.
Reviewed by: Click here to enter text. Date: Click here to enter a date.

Submit completed report via email to:

NEOM Cost Estimation (costestimation@neom.com)

Part 5: NEOM Head of Cost Estimation Review


Actions: Click here to enter text.
Reviewed by NEOM Head of Cost Estimation: Click here to enter text.
Date: Click here to enter a date.

File: [Insert file/folder location]

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 34 OF 38

©NEOM [2022]. All rights reserved.


Appendix F - Cost Estimator Performance Scorecard (MS Excel
spreadsheet)

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 35 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM04

Cost Estimator Performance Scorecard

NEOM-NEN-PRC-00_FRM04A

Name of Cost Estimator (Company) Enter text.

Date: Insert Date of Performance Review

Criteria Rating Maximum Achieved Category Sub-Category Weighted SCORE RATING


Score Score Weighting Weighting Score

1 Quality of Service 65.00% 100.00% 0.00% 0.00% UNACCEPTABLE

1.1.1 Professionalism of people Insert Rating 4 0 15.00% 0.00%

1.1.2 Technical skills of people Insert Rating 4 0 20.00% 0.00%

1.1.3 Co-operation Insert Rating 4 0 15.00% 0.00%

1.1.4 Contract compliance Insert Rating 4 0 15.00% 0.00%

1.1.5 Accuracy of work completed Insert Rating 4 0 20.00% 0.00%

1.1.6 Responsiveness to problems Insert Rating 4 0 10.00% 0.00%

1.1.7 Service recovery (following corrective/rework) Insert Rating 4 0 5.00% 0.00%

2 Cost 10.00% 100.00% 0.00% 0.00% UNACCEPTABLE

On time billing (Applications for payment


2.1 Insert Rating 4 0 35.00% 0.00%
submitted on time)
Billing accuracy (complies with Cost
2.2 Insert Rating 4 0 65.00% 0.00%
Estimator’s contract)

3 Time 15.00% 100.00% 0.00% 0.00% UNACCEPTABLE

3.1 On-time delivery Insert Rating 4 0 100.00% 0.00%

4 Business Relations 10.00% 100.00% 0.00% 0.00% UNACCEPTABLE

4.1 Effective management Insert Rating 4 0 50.00% 0.00%

4.2 Accessibility of senior people/management Insert Rating 4 0 25.00% 0.00%

4.3 Prompt notification of problems Insert Rating 4 0 25.00% 0.00%

100.00% TOTAL SCORE: 0.00%

OVERALL RATING: UNACCEPTABLE

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 36 OF 38

©NEOM [2022]. All rights reserved.


Appendix G - Cost Estimator KPI Results Record (MS Excel
spreadsheet)

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 37 OF 38

©NEOM [2022]. All rights reserved.


NEOM-NEN-PRC-002_FRM05

Cost Estimator KPI Results Record

NEOM-NEN-PRC-002_FRM05A

Name of Cost Estimator (Company) Enter text.

Item Indicator Cost Estimator Performance Report


Date of Report Date of Report Date of Report Date of Report Date of Report Date of Report Date of Report
[Insert] [Insert] [Insert] [Insert] [Insert] [Insert] [Insert] Trend

Score/Rating Score/Rating Score/Rating Score/Rating Score/Rating Score/Rating Score/Rating

Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall
X Overall Performance Rating Insert
Rating Rating Rating Rating Rating Rating Rating
Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall
1 Quality of Service Insert
Rating Rating Rating Rating Rating Rating Rating
1.1 Professionalism of people Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
1.1 Technical skills of people Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
1.1 Co-operation Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
1.1 Contract compliance Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
1.1 Accuracy of work completed Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
1.1 Responsiveness to problems Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
1.1
Service recovery (following corrective/rework) Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert

Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall
2 Cost Insert
Rating Rating Rating Rating Rating Rating Rating
2.1 On time invoicing Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
2.2 Invoice accuracy Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall
3 Time Insert
Rating Rating Rating Rating Rating Rating Rating
3.1 On-time delivery Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall Insert Overall
4 Business Relations Insert
Rating Rating Rating Rating Rating Rating Rating
4.1 Effective management Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
4.2 Accessibility of senior people/management Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert
4.3 Prompt notification of problems Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert Rating Insert

DOCUMENT CODE : NEOM-NCC-PRC-002 REVISION CODE: 02.00 P AGE 38 OF 38