TP-SVC-005-01
Reviewed
Version Document Name Date Author Change Control
By
V1.0 Material 17/04/2012 Mr. Mr. Manish
Reservation - Sameer Sawant
UPMPL_BPD_MM3A Vaidya
Document Approvals
Highbar technologies
24/04/2012
Consultant Mr. Sameer Vaidya
24/04/2012
Project Manager Mr. Manish Sawant
Reviewed By
Core Team
Process Owner
Table of Contents
1. Executive Summary ................................................................................................ 3
1.1. Background ........................................................................................................ 3
1.2. Business Blueprint Overview......................................................................... 3
2. ORGANIZATION STRUCTURE ................................................................................. 5
3. Master Data .............................................................................................................. 5
4. BUSINESS PROCESS.................................................................................................. 5
5. MODULE INTEGRATION........................................................................................... 5
6. STANDARD INFORMATION SYSTEM ...................................................................... 6
7. DESCRIPTION OF FUNCTIONAL DEFICIT ............................................................. 6
8. DEVELOPMENT CONSIDERATIONS ........................................................................ 6
8.1. Data Conversion Considerations ................................................................... 6
8.2. Interface Considerations ................................................................................ 6
8.3. Reporting Considerations ............................................................................... 7
8.4. Form Considerations ....................................................................................... 7
8.5. Enhancement Considerations........................................................................ 7
9. CHANGE MANAGEMENT .......................................................................................... 7
10. ANNEXURE.............................................................................................................. 7
11. CHECKS & VALIDATIONS ..................................................................................... 7
1. Executive Summary
This document is prepared to give a fair idea to core team members, support team
members and process owners of UPMPL about the TO BE processes mapping with
current AS IS processes based on industry and SAP best practices.
1.1. Background
This Blueprint document is concerned with the process of Reservation for material
for consumption or execution of work on Site. Currently in UPMPL there is no
Reservation process used. When user requires material he gives the Purchase
Requisition (indent).
In a reservation, information is stored that is relevant for the goods issue for a
particular work.
Materials, Spares are issued to equipment for maintenance & repair purpose.
Materials are issued against maintenance, consumption and commissioning orders
which are created in PM module (UPMPL_BPD_PM2B - Unplanned Maintenance).
This reservation will be used where the material to be booked on Cost Center.
This reservation will be created manually with Transaction Code MB21 & Movement
Type 201.
Summary:
1. Making a request to the store to keep materials ready for withdrawal at a later
date and for a certain purpose.
2. ORGANIZATION STRUCTURE
Plant
Storage Location
3. Master Data
Material Master
Maintenance / commissioning Order
Cost Center
4. BUSINESS PROCESS
Responsibility /
Step Activity T. Code Remarks
Authorization
Creating Concerned
1 MB21
Reservation Department
Physical
Reservation
2 Approving authorities - approval (off
Approval
SAP)
Store will
Goods Issue against check physical
3 Store MIGO
Reservation approval and
issue material
5. MODULE INTEGRATION
Plant Maintenance
8. DEVELOPMENT CONSIDERATIONS
Reference Document
Ref Description of Interface
Specification Number
NA
Reference Document
Ref # Description of Report Required
Specification Number
NA
Reference Document
Ref # Description of Form Required
Specification Number
NA
Reference Document
Ref # Description of Enhancement Required
Specification Number
NA
9. CHANGE MANAGEMENT
NA
10. ANNEXURE
NA
NA