INSPECTION OF STEEL PIPE RECEPTION

8.ago.2022 PBOJV-CON-FT-043 V2

CONSTRUCTION SITE: PUERTO BOLIVAR PORT EXPANSION - EPC PHASE 1


RECEPTION DATE: 27/12/2021 PILE ID: CC G 26 INSPECTION SITE
INSPECTION DATE: 8/9/2022 DRAWINGS: SNR-TEC-DB-122-V3 PILE STOCKYARD: X QUAY:
Nominal

Total length: 46600 mm Diameter ext.: 914 mm Top Wall Thk: 19 mm


Values

**Coating length: 15000 mm **Dry film thk: 450 µm Bottom Wall Thk: 14,3 mm

PILE LENGHT AND WALL THICKNESS


UTM EQUIPMENT UD 04279 LAST CALIBRATION 6/8/2022

Total Length: 46680 mm

Section A* Section B* Section C*


*Pile Graphic
Coating Length

TOP tt1: 19,1 tb1: 14,2 BOTTOM

tt2: 18,9 tb2: 14,1

tt6: 19 tt3: 18,8 tb6: 14,3 tb3: 12,3

tt5: 18,9 tb5: 14,2


tt4: 18,9 tb4: 14,1

*The sections A,B and C reffer to the coating inspection area.


The length and the wall thickness is measured in millimeters.
PILE DIAMETER OUTSIDE

TOP D3: 904 D3: 910 BOTTOM


D1: 916 D1: 910

D2: 912 D2: 912

*The diameter is measured in millimeters.


COATING INSPECTION
COATING EQUIPMENT WK 07764 LAST CALIBRATION 6/8/2022

Coating length: 15100 mm

Section A* (µm) Section B* (µm) Section C* (µm)


1 2 3 1 2 3 1 2 3
1 841 739 674 726 663 670 643 679 697
2 765 768 625 634 721 623 620 781 669
3 783 723 679 607 633 687 850 698 773
4 866 717 727 585 558 668 682 747 705
5 733 842 629 632 698 630 698 730 1261
*Section A,B and C, are distributed in the pile total coating length(according to the pile graphic)
** The values of coating length and dry film inspection corresponding to the minimum project requirements, to the values according each tube please refer to the PBOJV-CAL-INF-001

INSPECTIONS
By: CPBO X Sub-Contr
APPROVED REJECTED
1. The pile´s material certificate was received and checked X
Acceptance Criteria

2. Steel pipe pile diameter ± 1% D nominal (max. ± 8 mm) X


3. Roundness < 2% D internal nominal (max 15 mm) X
4. The coating length ≥ Minimum Design Coating length X
5. Total length pile ± 100 mm X
6. Coating inspection ≥ 80% nominal dry film thickness (NDFT) X
7. Wall thickness ± 1,5 mm X
Non-conformances

Non-conformances Remedied?
Description Date
Yes No
Remarks

Site Engineer QA/QC Engineer

Signature

Name A. Rodríguez / J. Vergara J. Novillo


Page 1/2
INSPECTION OF STEEL PIPE RECEPTION

8.ago.2022 PBOJV-CON-FT-043 V2

CONSTRUCTION SITE: PUERTO BOLIVAR PORT EXPANSION - EPC PHASE 1


DATE: 8/9/2022 PILE ID: CC G26 DRAWINGS: SNR-TEC-DB-122-V3

PHOTOGRAPHIC RECORD

Measurement of total length of piles. Measurement of external diameter of pile.

Thickness measurement of base material in pile. Pile mark inspection.

Site Engineer QA/QC Inspector

Signature

Name A. Rodríguez / J. Vergara J. Novillo


Page 2/2