SCHEDULE OF QUANTITIES
GENERAL NOTES :
1 All items of work under this Contract shall be executed strictly to fulfill the requirements
laid down under “Basis of Design” in the specifications. Type of equipment, material
specification, methods of installation and testing and type of control shall be in
accordance with the specifications, approved shop drawings and the relevant Indian
Standards, however capacity of each component and their quantities shall be such as
to fulfill the above mentioned requirement.
2 The unit rate for all equipment or materials shall include cost in INDIAN RUPEES (INR)
for equipment and materials including all taxes and duties and also including
forwarding, freight, insurance and transport into Contractor’s store at site, storage,
installation, testing, balancing, commissioning and other works required.
3 The rate for each item of work included in the Schedule of Quantities shall, unless
expressly stated otherwise, include cost of :
4 The Contractor shall procure and bring Materials/Equipment to the site only on the
basis of drawings approved for construction and shop drawings and not on the basis of
Bill of Quantities which are approximate only. This also applies to the Contractor’s
requisition for Owner supplied materials.
5 The work shall be carried out in conformity with the HVAC drawings and within the
requirements of architectural, Plumbing, Fire Fighting, Electrical, Structural and other
specialized services drawings.
6 The contractor shall cooperate with all trades and agencies working on the site. He
shall make provision for hangers, sleeves, structural openings and other requirements
well in advance to prevent hold up of progress of the construction schedule. All
supports to the civil structure shall be provided with anchor fasteners.
7 On award of the work, contractor shall submit a schedule of construction in the form of
a PERT chart or BAR chart for approval of the Project Manager.
8 On award of the work the contractor shall be issued two (2) sets of consultant’s
drawings. The drawings shall be the basis of contractor’s shop drawings.
9 Shop drawings are detailed working drawings coordinated with other trading work,
which incorporate the contractor’s details for execution of the work and incorporate
equipment manufacturer’s details and dimensions to ensure that the same can be
installed in the space provided.
10 All shop drawings should detail pipe routing and levels, showing location of other
services at crossings etc., cable runs, route cable trays and all allied works and must
be fully coordinated with other services, before execution of the works.
11 All shop drawings will be made on AutoCAD and colored prints has to be produced for
site work.
12 Any pipe crossing fire rated wall as per fire compartmentation will be provide with
higher size of GI sleeve. All floor crossing pipes will be provided with higher size GI
sleeve.
13 This Schedule shall be fully priced and the extensions and totals duly checked. The
rates for all items shall be filled in INK including NIL items.
15 In the event of an error occurring in the amount of the Schedule, as a result of wrong
extension of the unit rate and quantity, the unit rate quoted by the tenderer shall be
regarded as firm and the extensions shall be amended on the basis of rates.
16 Any error in totaling in the amount column and in carrying forward total shall be
corrected. Any error, in description or in quantity, omission of items from this Schedule
shall not vitiate this Contract but shall be corrected and deemed to be variation
required by the Consultant/Project Manager.
17 Rates have been called for a number of items of works, as alternatives which, for the
present do not form part of the total value of tender. However the rates for these items
shall be quoted, with due care so that in the event of choice of an alternative item of
work, said rate shall form part of the contract and shall not violate the contract any way.
18 The contractor shall , from time to time, clear away all debris and excess materials
accumulated at the site failing which the same shall be done by Project Manager at
contractor’s risk and cost and cost of clean up shall be deducted from the contractors
prorata bill.
19 After the fixtures, equipment and appliances have been installed and commissioned,
contractor shall cleanup the same and remove all plaster, paints, stains, stickers and
other foreign matter or discoloration leaving the same in a ready to use condition.
20 On completion of all works, contractor shall demolish all stores, remove all surplus
materials and leave the site in a broom clean condition, failing which the same shall be
done by the Project Manager at the Contractor'’ risk and cost. Cost of the cleanup
shall be deducted from the contractor’s bills on pro-rata basis in proportion to his
contact value.
2.1 Condensing water pumps (Condenser Water Recirculation for VAM Cooling Tower)
3 Supply, installing, testing and commissioning of horizontal FAN COIL UNITS , blow
thru type, each complete with 3/4 rows deep Chilled Water Coil, one or more centrifugal
fans, cleanable fabric filters, main condensate extended SS drain pans, RA insulated
plenum, as described in specifications, casing, coil piping connections, through copper
pipes, condensate drain connections, wiring,Thermostats, control wiring in conduit upto
thermostat boxes. Fan coil unit shall be factory fitted with valve package comprising of
pressure independent Balancing cum Control Valve with integrated 2 way motorized
actuator in a single body for modulating operation suitable for static pressure of 1600
kPa and actuator shall be capable of withstanding 400 kPa shut off pressure, 24 V AC
incoming power supply, ball valve with Y-strainer at inlet & Ball valve at outlet and
necessary copper coil piping connections. The actuator of modulating valve shall be
provided with interface cards to receive 0-10V or 4-20 mA signal from Digital
Thermostat.
The actuator of the valve shall have necessary torque to overcome pressure differential
of 4 bars rating. All fan coil units shall be suitable for 220±6% volts, 50 cycles, single
phase power supply. Fan coil units shall be of following refrigeration capacities as listed
below :
4 Supplying, installation, testing and commissioning of CHW STORAGE (HOT WELL &
COLD WELL) TANKS fabricated out of 5 mm thk. MS sheet, internal surface duly
lined with Taflon coating & outer surface shall be insulated as per specification
and approved drawing). The storage capacity of the tanks are as listed Below :
4.1 10,000 Liters for chilled water size 4.6x2x1.2 mts( 5mm thick) No. 1
5 Supplying, installing, testing and commissioning of double skin construction draw thru
type Horizontal Floor Mounted AIR HANDLING UNITS with Thermal Break Profile as
per specification, each complete with pre-filter section (90% down to 10 microns), min 6
Row Deep water coil of copper tube & aluminium fins construction , squirrel cage
induction motor, airfoil centrifugal fan belt drive and vibration isolators, coil size shall
be selected for a maximum face velocity of 500 feet/minute and static pressure
shall be as indicated. The motor selected shall be energy efficient having efficiency
(Class I) at full load ranging between 82.5% to 92% in accordance with motor rating as
per specification. Motor shall be suitable for 415±10% volts, 50 cycles, 3 phase AC
supply. Fan motor assembly (as whole) shall be statically and dynamically balanced to
grade G 6.3 as per ISO-1940/AMCA 204-3.All units shall be complete with opposed
blade volume control dampers at oulet, return and fresh air connections. Duct flexible
connector (fire proof) shall be provided at outlets and return connection of AHU. For
AHUs with VFD, complete equipment shall be designed to limit THDi to less than 5%.
9 Supplying, installing, testing and commissioning of INLINE FANS suitable for installing
in any position in vertical or horizontal ducts. The casing shall be double skin, internally
acoustically lined and constructed of galvanised steel. The fan shall be DIDW with
forward curve impeller fitted with maintenance free external rotor motor. The motor
shall be suitable for 220±10% volt single phase 50 cycles AC supply. All units shall be
complete with duct flexible connector and volume control damper.
The fan shall have low sound level exceeding not more than 40 DBA at three metre
distance.
10 Supply, installation, testing and commissioning of AXIAL FANS for return air & exhaust
air suitable for installing in any position in Horizontal or vertical. The motor shall be
suitable for 415 V + 10% volts three phase 50cycle, AC supply and suitable for
operating through VFD. The fan shall be equipped with mounting bracket & outlet core,
Louvers/Cowl as per site condition as required at discharge. The fan shall be low RPM
(less than 1000 RPM) and capacities based on minimum 1.5 inch (4cm WC) static
pressure or to suit the system, shall be as follows:
The fan shall have low sound power level not exceeding 65dBA at three meter distance
at both ends. To achieve these DB levels, sound attenuators of suitable length, at inlet
& outlet of the fans must be included in the cost.
Space CFM
10.1 Basement Plumbing Plant Room Fresh Air 10400 CFM No. 1
10.7 Workshop(Oat Meal) at First Foor Exhaust Air 20 000 CFM Nos. 4
10.8 UPS Room at First floor Fresh Air 15 000 CFM No. 1
10.9 UPS Room at First floor Exhaust Air 15 000 CFM No. 1
11.1 650 TR Cooling tower for Vapor Absorption Chillers ( 500TR) plant having Condenser
Water flow rate of 2000 USGPM inlet temperature of 90 °F and outlet temperature of
100 °F. No. 1
12 Supplying, installing, testing and commissioning of double skin construction draw thru
type CELLULOSE FILL AIR WASHER, giving 90% adiabatic saturation efficiency at
500 FPM air velocity across pads, factory assembled and complete with 24 gauge GI
casing (outer precoated/preplastisized), SS 304 water sump, Mounters/ Glacier Core
fully imported with glued by the orizonal Cellulose fill manufacterer, water distribution
header, GI piping, Audco make butterfly valves, for quick fill; isolation of tank and
pumps, Y strainers fire pumps and necessary fittings. 2 stage filteration : Fine filter
MERV-13 (99% down to 3 microns), Pre-filter section (90% down to 10 microns),
squirrel cage induction motor, airfoil centrifugal fans with belt drive and vibration
isolators, and static pressure shall be as indicated. The motor selected shall be energy
efficient having efficiency (Class I) at full load ranging between 82.5% to 92% in
accordance with motor rating as per specification. Motor shall be suitable for 415±10%
volts, 50 cycles, 3 phase AC supply. Fan motor assembly (as whole) shall be statically
and dynamically balanced to grade G 6.3 as per ISO-1940/AMCA 204-3.All units shall
be complete with opposed blade volume control dampers at oulet & Backdraft
dampers. Duct flexible connector (fire proof) shall be provided at outlet.
The quoted price shall also include GSS louvers with bird-screen fabric filters at inlet
and drift eliminators. The price shall also include horizontal monoblock pumps of
Beaconweir/ KBL make of suitable rating, factory mounted on mild steel channel base
with electric motor for circulation of water . Pumps shall be aligned and suitable for
415±10% volts, 50 cycles 3 phase power supply. One No. 3 phase isolator switch in
weather proof enclosure shall be provided near motor.
The base of the unit shall be of heavy Gauge MS C-channe/ I-Section lincluding all
necessary accessories as required to complete the installation.
12.1 Capacity : 75000 CFM , 60 mmwg SP Nos. 6
Each MCC shall include cost of wiring, control wiring & inter locking between chillers,
primary CHW pumps, condenser water pumps, motorized valves at chillers and
condensers, flow meter & flow switch installed in de-coupler by-pass line, in order to
execute the required sequence of operation.
All outgoing shall be provided with Stop/ Manual/ Auto/ selector switch to facilitate
operation through BAS. All starters shall be provided with potential free Contact for
Connections to Building Automation System.
A separate set of CTs to be provided for BAS and wiring from CT’s and voltage
transducers to be brought on to separate set of terminals.
Incoming-1
i. 1 No. 500 amps 4P microprocessor based MCCB complete with the following :
1 Set
iv. Phase indicating lamps, with toggle switches.
1 Set
v. Digital electronic KWH meter with RS 485 port.
Bus Bar
i. TPN bus bars shall be of aluminium and shall be sleeved. Phase bus bars shall be
rated at 800 amps and neutral bus bar shall be of 50% capacity.
ii. Maximum density of aluminium bus bar for current carrying capacity shall be one amp
per sq.mm.
Outgoing
i. 1 No. 63 amps MCCB, 11 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Chiller (VAM) 500TR, pump. This
compartment shall contain CT operated digital ammeter of 0-60 amps range with
selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/ OFF'
status of pump motor.
ii. 2 Nos. 63 amps MCCB, 9.3 KW VFD and outgoing feeder to 1 no. Cooling Tower
Twin Fan motors. Each of these compartment shall contain CT operated digital
ammeter of 0-60 amps range with selector switch, and an indicating lamp with MCB
and toggle switch for ‘ON/ OFF' status of pump motors.
iii. 1 No. 100 amps MCCB, 37 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Condenser Pump. This compartment
shall contain CT operated digital ammeter of 0-100 amps range with selector switch,
and an indicating lamp with MCB and toggle switch for ‘ON/ OFF' status of pump motor.
iv. 1 No. 63 amps MCCB, 18.5 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Primary Pump Recirculation VAM.
This compartment shall contain CT operated digital ammeter of 0-60 amps range with
selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/ OFF'
status of pump motor.
v. 2 Nos. 100 amps MCCB, 30 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Chilled Water Pump Comfort
Cooing. This compartment shall contain CT operated digital ammeter of 0-100 amps
range with selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/
OFF' status of pump motor.
vi. 1 No. 63 amps MCCB, 11 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Child Water Pump Process Line.
This compartment shall contain CT operated digital ammeter of 0-60 amps range with
selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/ OFF'
status of pump motor.
Bus Coupler :
500 amps 4 pole MCCB with ON/ OFF/ TRIP indicating lamps.
Incoming-2
i. 1 No. 500 amps 4P microprocessor based MCCB complete with the following :
1 Set
iv. Phase indicating lamps, with toggle switches.
1 Set
v. Digital electronic KWH meter with RS 485 port.
1 Set
Bus Bar
i. TPN bus bars shall be of aluminium and shall be sleeved. Phase bus bars shall be
rated at 800 amps and neutral bus bar shall be of 50% capacity.
ii. Maximum density of aluminium bus bar for current carrying capacity shall be one amp
per sq.mm.
Outgoing
i. 2 Nos. 100 amps MCCB, 37 KW star delta starters, over load relay with built in single
phasing protection and outgoing feeders to 1 no. Condenser Pump (Standby) and 1
no. spare. Each of these compartment shall contain CT operated digital ammeter of 0-
100 amps range with selector switch, and an indicating lamp with MCB and toggle
switch for ‘ON/ OFF' status of pump motor.
ii. 1 No. 63 amps MCCB, 18.5 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Primary Pump (Standby)
Recirculation VAM. This compartment shall contain CT operated digital ammeter of 0-
60 amps range with selector switch, and an indicating lamp with MCB and toggle switch
for ‘ON/ OFF' status of pump motor.
iii. 1 No. 100 amps MCCB, 22 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Chilled Water Pump Comfort Cooing
(Standby). This compartment shall contain CT operated digital ammeter of 0-100 amps
range with selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/
OFF' status of pump motor.
iv. 1 No. 63 amps MCCB, 11 KW star delta starter, over load relay with built in single
phasing protection and outgoing feeder to 1 no. Chilled Water Pump Process Line
(Standby). This compartment shall contain CT operated digital ammeter of 0-60 amps
range with selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/
OFF' status of pump motor.
Note: MCCB’s shall be motor duty and suitable for 35 KA (ICS) fault current.
Incoming
i. 1 No. 250 amps 4P microprocessor based MCCB complete with the following :
1 Set
iv. Phase indicating lamps, with toggle switches.
1 Set
v. Digital electronic KWH meter with RS 485 port.
Bus Bar
i. TPN bus bars shall be of aluminium and shall be sleeved. Phase bus bars shall be
rated at 300 amps and neutral bus bar shall be of 50% capacity.
ii. Maximum density of aluminium bus bar for current carrying capacity shall be one amp
per sq.mm.
Outgoing
i. 3 Nos. 40 amps MCCB, 3.7 KW VFD and outgoing feeders to 2 nos. Axial Fan on
Upper Basement and 1 no. spare. Each of these compartment shall contain CT
operated digital ammeter of 0-40 amps range with selector switch, and an indicating
lamp with MCB and toggle switch for ‘ON/ OFF' status of pump motors.
ii. 13 Nos. 63 amps MCCB, 7.5 KW VFD and outgoing feeders to 12 nos. Axial Fan on
Ground Floor and 1 no. spare. Each of these compartment shall contain CT operated
digital ammeter of 0-60 amps range with selector switch, and an indicating lamp with
MCB and toggle switch for ‘ON/ OFF' status of pump motors.
Incoming
1 Set
iv. Phase indicating lamps, with toggle switches.
1 Set
v. Digital electronic KWH meter with RS 485 port.
1 Set
Bus Bar
i. TPN bus bars shall be of aluminium and shall be sleeved. Phase bus bars shall be
rated at 160 amps and neutral bus bar shall be of 50% capacity.
ii. Maximum density of aluminium bus bar for current carrying capacity shall be one amp
per sq.mm.
Outgoing
i. 5 Nos. 63 amps MCCB, 7.5 KW VFD and outgoing feeders to 4 nos. Axial Fan on
First Floor and 1 no. spare. Each of these compartment shall contain CT operated
digital ammeter of 0-60 amps range with selector switch, and an indicating lamp with
MCB and toggle switch for ‘ON/ OFF' status of pump motors.
ii. 3 Nos. 40 amps MCCB, 5.5 KW VFD and outgoing feeders to 2 nos. Axial Fan on
First Floor and 1 no. spare. Each of these compartment shall contain CT operated
digital ammeter of 0-40 amps range with selector switch, and an indicating lamp with
MCB and toggle switch for ‘ON/ OFF' status of pump motors.
Incoming:
1 No. 630 amps 4P microprocessor based MCCB complete with the following :
i. 0-500 volts digital electronic volt meter with selector switch protected by 2 amps TP
MCB's.
1 Set
ii. 0-600 amps digital electronic ammeter with selector switch and 600/ 5 amps 15 VA, CL
1 CTs.
1 Set
iii. Phase indicating light shall be protected by 2 amps SP MCB's.
1 Set
Bus Bars:
i. 800 amps TPN aluminium bus bars with coloured heat shrinkable insulated sleeve.
1 Set
Outgoing:
i. 13 Nos. 63 amps MCCB, 15 KW star delta starters, over load relay with built in single
phasing protection and outgoing feeders to 12 nos. Air washer Fan. Each of these
compartment shall contain CT operated digital ammeter of 0-60 amps range with
selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/ OFF'
status of pump motor.
ii. 4 Nos. 32 amps MCCB, 1.5 KW DOL starters, over load relay with built in single
phasing protection and outgoing feeders to 3 nos. Air Washer Pump. Each of these
compartment shall contain CT operated digital ammeter of 0-30 amps range with
selector switch, and an indicating lamp with MCB and toggle switch for ‘ON/ OFF'
status of pump motors.
iii. 1 No. 40 amps MCCB, 5.5 KW DOL starter, over load relay with built in single phasing
protection and outgoing feeder to 1 no. Exhaust Air fan. This compartment shall
contain CT operated digital ammeter of 0-40 amps range with selector switch, and an
indicating lamp with MCB and toggle switch for ‘ON/ OFF' status of pump motors.
iv. 1 No. 32 amps MCCB, 2.2 KW DOL starter, over load relay with built in single phasing
protection and outgoing feeder to 1 no. Fresh Air Fan. This compartment shall contain
CT operated digital ammeter of 0-30 amps range with selector switch, and an indicating
lamp with MCB and toggle switch for ‘ON/ OFF' status of pump motors.
All internal wiring power cabling and copper earthing of air handling unit motors from
the panel shall be included.
All outgoing shall be provided with Stop/ Manual/ Auto selector switch to facilitate
operation through BAS. All starters shall be provided with potential free Contact for
Connections to Building Automation System.
a. MCCB as per the ratings given below, suitable for motor duty and able to withstand
fault level of 20 KA.
g. Time delay relay for delayed automatic restart of air handling unit motor.
h. Wiring for microswitch for stopping the fan when fire damper closes.
i. For on/ off/ remote and local operation, 3 pole single throw switch shall be provided in
each AHU panel to facilitate override of the automatic operation.
j. All starters shall be provided with suitable potential free contract for connections to the
Building Automation System.
k. 3 Nos of Single Pole MCB's Shall be provided at the incoming section of the starter
panel for DDC Panel, fire damper actuator & as a spare.
l. 220/ 24 V Transformer.
All outgoing shall be provided with Stop/ Manual/ Auto selector switch to facilitate
operation through BAS. All starters shall be provided with potential free Contact for
Connections to Building Automation System.
All internal wiring, power cabling and copper earthing of motors from the panel to VFD
& to the motor shall be included.
a. MCCB as per the ratings given below, suitable for motor duty and able to withstand
fault level of 20 KA.
g. Wiring for microswitch for stopping the fan when fire damper closes.
h. For on/ off/ remote and local operation, 3 pole single throw switch shall be provided in
each panel to facilitate override of the automatic operation.
i. 3 Nos of Single Pole MCB's Shall be provided at the incoming section of the starter
panel for DDC Panel, fire damper actuator & as a spare.
j. All starters shall be provided with suitable potential free contract for connections to the
Building Automation System.
k. 220/ 24 V Transformer
All outgoing shall be provided with Stop/ Manual/ Auto selector switch to facilitate
operation through BAS. All starters shall be provided with potential free Contact for
Connections to Building Automation System.
All wiring and copper earthing of motors from the panel shall be included.
a. MCCB as per the ratings given below, suitable for motor duty and able to withstand
fault level of 20 KA.
i. For on/ off/ remote and local operation, 3 pole single throw switch shall be provided in
each panel to facilitate override of the automatic operation.
j. All starters shall be provided with suitable potential free contract for connections to the
Building Automation System.
13 Providing probe type flow meter to measure the flow in CHW & Nos. RO
CDW pipe lines. The flow meter shall be provided with
necessary fittings & electronic digital read out.
14 Providing and fixing in position SS 304 the industrial dial type Nos. 40
pressure gauges with gun metal valves.
2.2 13 mm thick nitrile rubber insulation for return air ducts. sq.m 900
2.3 19 mm thick nitrile rubber insulation for supply duct (not in RA sq.m 350
path).
2.4 25 mm thick nitrile rubberinsulation for supply & return air ducts sq.m 250
exposed to weather.
3.1 13 mm thick nitrile rubber insulation for supply air ducts in sq.m RO
return air path.
3.2 13 mm thick nitrile rubber insulation for return air ducts. sq.m RO
3.3 19 mm thick nitrile rubber insulation for supply duct (not in RA sq.m 50
path).
3.4 25 mm thick nitrile rubberinsulation for supply & return air ducts sq.m 50
exposed to weather.
SUMMARY OF COST
Sr. Total Price (INR) for
No. Description Supply,
Installation,
Testing and
Commissioning
A. EQUIPMENT
9 IN LINE FANS
10 AXIAL FANS
SUB TOTAL A
D THERMAL INSULATION