Professional Documents
Culture Documents
_
3u limits
120 __
Wl140I Xis
z N
ow
_30 0
w Figure 2 (right).
D-c overpoten-
tial test of a large
turbine generator
IL~ ~ ~ -I 0
~LOG SECONDS -i- weeding out defective insulation that may
result in coil failures during final test. A
TIME LOG10 H10H d-c test voltage is required that has equal
or greater destructive effect than the final
L
10
REARS 1-minute a-c test voltage to adequately
insure that any coils with weak insulation
thickness and dielectric constant of the 2. Lower voltage rectifiers which use lad- are detected before the final test. Table I
components, thus stressing the binding der circuits in cascade to produce the re- indicates some of the test voltages that
materials more than the mica because of quired output voltage. are applied during winding of high-volt-
the lower dielectric constant of usual Adequate d-c insulation test equipment age machines. At these high direct volt-
binding materials. With d-c tests, the utilizing each method is in use. ages, little attempt has been made to cor-
stress distribution through the material The variation in the d-c and a-c peak relate leakage and dielectric strength;
will be determined by the volume re- breakdown voltages of solid insulations the primary use of the leakage is an in-
sistivity of its components and the major is a very controversial subject and prob- dication to the tester of impending trouble
components of the insulation regarding ably will prevent utilizing the advantages indicated by current runaway. Another
dielectric strength (the mica) will be sub- of d-c testing until more information on factor preventing correlation between
jected to the greatest stress. specific insulation systems can be deter- leakage and insulation strength during d-c
Even early investigations were quick mined. It is doubtful that an absolute test is that momentary or 1-minute tests
to note advantages of applying a direct equivalent ratio of d-c to a-c peak volt- are used and no steady-state leakage is
voltage which was considerably less than age can be determined for solid insula- reached in these time intervals; the rate
the normal operating alternating volt- tion. However, and this is important, d-c at which the voltage is applied is an im-
age. The majority of insulation failures tests can be used to give assurance of the
in service are due to the presence of mois- absence of specific types of insulation 60
ture, which gives rise to conducting paths faults.
on the internal or external surfaces of the 7
30 +30
insulation. A d-c test is a very sensitive Shop D-C Overpotential Testing
detector of moisture penetration. In-
sulation resistance measurements have The advantages of d-c testing were ap-
provided a relatively simple criterion of plied to d-c armature coils long before its
the condition of insulation for many use was extended to high-voltage insula-
years. tion. In connection with turn insulation
Recent improvements in the last dec- failures on a certain type motor, d-c test-
ade in high-voltage rectifying tubes have ing was distinctly advantageous in the de- VOLTAGE DOUBLER CIRCUIT
largely eliminated the problem of equip- tection of copper slivers and similar
ment. Several manufacturers are able to faults. D-c testing of turn insulation on
supply d-c test apparatus with the volt- low-voltage equipment during coil manu-
age range and portability required. Three facture has given excellent results during
conventional circuits for d-c test equip- the past 4 years.
ment are shown in Figure 3. These Preliminary winding tests have been
testers usually use one of two basic cir- made with direct as well as with alternat-
cuits with slight modifications. ing current on high-voltage windings for LADDER TYPE TRPLER CIRCUIT, 45KV POWER SUPPLY
1. Single high-voltage rectifier circuits- the last year. Manufacturers' prelimi- Figure 3. Conventional d-c high-voltage
full or half wave. nary winding tests are directed toward test circuits
No Discussion
Rapid Measurement of the Thermal than is the case with the older concrete
duct types.
In the autumn of 1949, plans of Thle
Resistivity of Soil Hydro-Electric Power Commission of
Ontario to install some 25,000 feet of
underground high-voltage cable necessi-
V. V. MASON M. KURTZ tated the immediate determination of the
ASSOCIATE MEMBER AIEE ASSOCIATE MEMBER AIEE thermal resistivity of the soil along the
proposed route with a reasonable degree
of accuracy.
Synopsis: Following a method due origi- duration of a typical determination. Re- There are two possible procedures to be
nally to Stalhane and Pyk,1 the thermal sistivity values obtained agree with those followed in making such measurements.
resistivity of soil may be measured in situ obtained by the steady-state method. A Samples of the soil may be conveyed to
by thrusting a long heated needle into the crew of three can make determinations at the
ground to the required depth and measuring rate of one to three per hour. the laboratorv or the measurements max'
its temperature every 30 seconds for 15 to 30
minutes. The slope of the resulting tem-
perature versus time curve on semilog paper
is proportional to the thermal resistivity of THE effect of the thermal resistivity Paper 52-158, recommended by the AIEE Insulated
Conductors Committee and approved by the AIEE
the soil, and the constant of proportionality of the soil on the temperature rise of Technical Program Committee for presentation at
is derivable theoretically. The finite diam- a buried cable is well known. It is of par- the AIEE Summer General Meeting, Minneapolis,
eter of the needle is taken into account by Minn., June 23-27, 1952. Manuscript submitted
ticular importance for the newer directly March 24, 1952; made available for printing April
adjusting the zero time to a value found by buried and pipe-type installations in 16, 1952.
plotting dtlde against t. The effects of the
finite length of the needle are difficult to which the temperature rise through the V. V. MASON and M. KURTZ are with The Hydro-
Electric Power Commission of Ontario, Toronto,
assess but appear to be unimportant for the soil forms a larger part of the total rise Ont., Canada.