Professional Documents
Culture Documents
2050
Wind: 24 GW (2)
PV: 32 GW (2)
x3
2030
Wind: 9 GW (1)
PV: 12 GW (1)
2018 x5
Wind: 3,1 GW
PV: 1,4 GW
Wind
PV
700
600
500
442
M€
400
346
319
300
243
203 204
200 157
100
13 22 23
2 1
0
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
5
Main motivations for introducing a Redispatch
optimization tool
• Optimisation to limit
redispatch costs
• Reduce workload of op. planning
operators during DACF / IDCF Data from 2022
Introduction of a self-developed
tool in 2018
Go-Live in October 2022
Development of a Proof of
Concept in 2019
(Unit Commitment @ PowerFactory)
Development of a professional
RAO tool in 2020
© Austrian Power Grid 6
Agenda
1. Background and motivation
2. Requirements from operational
planning / features
3. Solution architecture and GUI
4. Operational experience
5. Conclusion
• Feasible results: considering the time coupling of the optimization problem (minimum on/off time,
lead time, ...)
• Execution as automated as possible
• Input data automatically gathered, processed, validated / corrected
• User interaction: operator able to modify data
(e.g. cancel planned disconnections, correct gen. availability)
• Visualisation of input and output data and reporting - configurable plots
(e.g. generation profile, n-1 loading, redispatch volume, …)
• Flexible use by operator (fulfil about 15 use cases)
- Repeat calculations with modified parameters (e.g. modified redispatch, max. acceptable n-1 loading)
- Consider scenarios (e.g. scenario with lack of wind generation)
• Stable and fast enough to be used in operational processes (DACF and IDCF)
© Austrian Power Grid 8
Features and implementation aspects (1/2)
• Merge of (up to) 24 UCTE models into one project as a prerequisite to the optimization
(time coupling)
• Use of Virtual Power Plants (VPP) for generators in the 110kV network not modelled (GSK)
[not relevant anymore since the 110 kV network is now modelled]
• Thermal rating considered
• Remedial actions:
• Fully part of the optimisation:
- PSTs and transformers
- Redispatch
• Not part of the optimisation (decision based on comparison / operator experience):
- Cancelling of planned outages if they can be postponed
- Special switching states (e.g. 2 nodes operation): can be freely defined and considered
(hourly activation) in the calculation
• Constrains modelled as soft to ensure a solution is always found
© Austrian Power Grid 9
Features and implementation aspects (2/2)
• Verification after modification: calculated remedial actions can be modified and a new calculation
is performed (verification)
• Individual configuration of the maximal loading (safety margin) or selection between standard and
extended margins
• Project structure in PowerFactory (operation scenarios, network variations, ...) allows efficient
ex-post analyses (e.g. switch between before / after Redispatch, activation / deactivation of special
switching states...)
• Possibility to calculate only selected time stamps (without time coupling) for a faster first result
• Scenarios to take into account specific uncertainties to come in the near future
• Main blocks
• parametrization
• versioning
• sanity check
• data correction
• data modification (generators, PST/transformers)
• calculation
• report generation
• visualisation
Klassifizierung: INTERN 15
GUI – User Selection
Selection of:
• Business day and calculation time
• Process (DACF / IDCF)
• Model version
• Time range
• Contingency list to be used
(with e.g. exceptional contingencies)
• ...
• Special switching states to be applied
• Deviations between forecasted and real time n-1 loading can exceed 30%!
• Passed approach: keep remedial actions which can be quickly activated (e.g. PST taps)
in reserve.
However, keeping e.g. ±10 from ± 30 PST taps for uncertainties does not guarantee that they can be
effectively used...
• Main uncertainty factors:
• Model error (grid element status (on/off),
topological error, PST tap position...) can be avoided / limited
• Short-term trade (mainly pump storage hydro)
Explicitly
(dedicated
• Forecast of renewable generation (Wind, PV) scenario)
• Load forecast (incl. geographical distribution) shall be taken into account
• Regulating power Implicitly
(safety
• ...
margin)
© Austrian Power Grid 21
Using larger safety margins?
• Study performed for about 20 interesting days (complex situation with large Redispatch amount)
• with default settings (e.g. max. loading of 97%) and default PST range (e.g. ±5 taps)
• with extended margins (e.g. max. loading of 80%) and extended PST range (all ±30 taps)
• Time consuming preparation work in the development project and parallel run:
• data preparation and validation – high data quality standard required for
operational use!
• parametrization, testing and validation
• Training of operators is important to ensure that the tool is well understood and to
ensure that it can fully support operations (fast, reliable, ...)
• RAO is a complex process since many operational aspect have to be considered
(cancelling planned disconnections, special switching states, safety margins...).
The final decision is still taken by operators, who report significant deviations from
the results
• Ensuring a fast execution is of prime importance – work in progress
• Valuable experience for APG in the context of the introduction of an international
process (ROSC)