BE605 - TWF Group 12 - Weekly Project Status Report #1

Prepared by: Vasudev Narayanamangalathu Mana (Communication Manager)

June 12, 2023 Color

code:

Main activities this week (June 7 to June 13):

● The following sections were completed this week and will be submitted to TWF client on
bitrix portal as per the approved schedule:

o SLO Set I - Oral Communication Skills

● The team members in-person meeting was held on Sunday, June 11, and where we compiled
the links searched by every team member regarding competency A (Oral Communication
Skills).
● The quality manager checked the quality of the collected material for deliverable one and
passed the deliverable one document as per the quality control objectives. And updated the
quality control log, as well as passed the document to the project manager for final review by
June 12th, 2023.
● Project Manager reviewed complete documents of deliverable one and submitted it to the
client by June 12th, 2023.

Activities for next week (June 14 to June 20):

● Meetings will be organized for developing the strategy to search the contents regarding
deliverable two.
● The quality manager will be updating a quality assurance log on 14th June.
● Project manager will review the final document and will submit the deliverable two to the
client according to the deadline mentioned in project plan.

Issues:
Fortunately, we are proud to announce that no major issues regarding the development of the
project were encountered during the present week.