Professional Documents
Culture Documents
Back Filling
Back Filling
0 SCOPE OF WORK
4.0 RESPONSIBILITIES
The backfilling will follow the sequence shown below (Figure 5.1).
The backfill will consist of several horizontal layers not exceeding a thickness of
150mm.
Each layer will initially be backfilled by excavators and then manually leveled by
site workers.
This will then allow for the compaction (both in the x and y direction). Depending
on the site condition either allow for the 1 ton roller, plate vibrator and/or rammer
to be used.
The following points will be carried out to ensure the quality of backfill.
Continuous monitoring shall be carried out to ensure the ground water table is
below from the level of excavation.
The Sand cone test & Standard Proctor Compaction Test will be carried out to
measure the degree of compaction of the layer according to the below location table.
Initially sand cone test will be carried out for one compacted layer of backfill
material with the rammer. Along with the results of Standard Proctor Compaction
Test, this will enable the required compaction to achieve the needed degree of
compaction. Based on above results, similar compaction level will be followed to
the following backfilling layers.
A California Bearing Ratio (CBR) test will be carried out on the request of the
consultant
Required final level will be checked according to the detail drawings and with
referring to TBM.
Anti-termite Treatment shall be done with the guidance of the specialized
contractor, Separate method statement will be provided.
Types of Backfilling (control & uncontrol) in site relevant locations given below,
Control
Backfilling Uncontrol
Location Backfilling
with testing
9.0 REFERENCES
Structural Specifications