Method Statement for Excavation and Dewatering
• After reaching the required level of excavation dewatering system will be
provided to continue the working arrangement without ponding by water.
• During machinery bulk excavation of main lift pit area, dewatering pits shall be located
at corners. Water collecting trenches shall be formed and excess water shall be directed
to the dewatering pits. The collected water in the pits shall be pumped out by using the
submersible pumps.
6
Method Statement for Excavation and Dewatering
• It shall be maintained 400mm wide; 500mm depth trench right round the lift pit area
and at the same time, there shall be water collecting pits around.
Submersible
Sediment
Ground 500m pump
basing trap
Water Level
Perforated
barrel
Aggregate
• If the work is to be carried out below the groundwater level (original), ensure that the
local water level is at least 0.5 m from the bottom level of the work area.
• Dewatering should be carried out in to ensure that the weight of the structure/sub soil
at any stage of construction is at least two times the up thrust at all times.
• All works shall comply with safety procedure or instruction set out in project safety
plan
Refer the Sanken Lanka Safety Manual for further safety precaution and regulations.
8.0 REFERENCES
• Structural Specifications.
7
Method Statement for Excavation and Dewatering