Project Title: PROPOSED TWO-STOREY RESIDENTIAL BUILDING

Location: CONSOLACION, CAGAYAN DE ORO CITY, MISAMIS ORIENTAL, PHILIPPINES

Name: Arias, Krizza


Section: BSCE-3Q

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description: B.3 Permits and Clearances
Unit of Measurement: l.s
Output per hour: 1

Designation No. of Person No. of Days Daily Rate Amount


Labor

A Liaison Incharge 1 5 450.00 2250.00

Sub-total for A 2250.00


Name and Capacity No. of Equipment No. of Days Daily Rate Amount
Equipment

Sub-total for B 0.00


C Total (A+B) 2250.00
D Output per hour = 1 l.s
Name and Specifications Quantity Unit Unit Cost Amount
Materials
Building Fee 1 l.s 3500 3500
Electrical Fee 1 l.s 370.00 370.00
Plumbing Fee 1 l.s 350.00 350.00
E
Accessories of the
1 l.s 2000.00 2000.00
Building/Structure Fee
Miscellaneous 1 l.s 2500.00 2500.00
Sub-total for E 8720.00
F Direct Cost (C+E) 10970.00
G Overhead, Contingencies and Miscellaneous (12%) 1067.52
H Contractor's Profit (CP) (8%) 711.68
I Value Added Tax (VAT) (12%) 1281.02
J Total Unit Cost 14030.22