Project NEOM GREEN HYDROGEN PROJECT
Power Transmission & Distribution
Doc. No: PM210012-XXXXXXXXXXXXXX Rev No: 01 Date: XX.XX.2022 Page 1 of 13
PM210012-LTT5XXX-XXX-XXXXXX
Method Statement for ceramic tiles
Project: NEOM GREEN HYDROGEN PROJECT
NEOM GREEN HYDROGEN PROJECT
Page 1 of 13
XXXXXXXXXXXXXXX
Project NEOM GREEN HYDROGEN PROJECT
Doc. No: PM210012-XXXXXXXXXXXXXX Rev No: 01 Date: XX.XX.2022 Page 2 of 13
Discipline Civil
Revision History
Purpose of
Rev. Description of Changes Date
Issue
00 XXXXXXXX IFA DD.MM.YYYY
01 XXXXXXXX IFA DD.MM.YYYY
02 XXXXXXXX IFA DD.MM.YYYY
Status Codes:
IFR: Issued for Review
IFA: Issued for Approval
IFC: Issued for Construction
CONTENTS
1. PURPOSE.......................................................................................................................................................................
2. SCOPE............................................................................................................................................................................
3. REFERENCES..................................................................................................................................................................
4. ACRONYMS & DEFINITIONS.........................................................................................................................................
5. ROLES & RESPONSIBILITIES..........................................................................................................................................
6. PLANT, EQUIPMENT, TOOLS & TACKLES......................................................................................................................
7. MATERIALS...................................................................................................................................................................
8. WORKFORCE.................................................................................................................................................................
9. WORK METHODOLOGY................................................................................................................................................
10. APPENDICES..............................................................................................................................................................
APPENDIX – A............................................................................................................................................................
APPENDIX – B............................................................................................................................................................
APPENDIX – C............................................................................................................................................................
1. PURPOSE
To ensure the Fixing of ceramic tiles has been done and inspected according to the NEOM /
AP requirements, project drawings specifications, and safety compliance, to protect the
people and to prevent damages and completion of work on time.
2. SCOPE
Site preparation.
Fixing ceramic tiles.
3. REFERENCES
HSE Management Plan.
Project Technical Specifications.
ASTM D-482
Applicable local regulation.
1.
2.
3.
4.
5.
5.1. Project Manager
Provide the team with appropriate resources to ensure that works are done in
accordance with the project Quality and EHS requirements and shall be responsible for
the approval of method statement and overall project management.
Co-ordinate with Quality in charge for scheduling inspection & approval as per ITP.
Make all necessary arrangements for inspection of work as per ITP.
5.5. Surveyor
Study drawing and establish control points as per plot plan / approved drawing.
Acquire information from reference stations & datum level provided by client; establish
new control points at site & cross verify with reference station/s and datum level.
Conduct survey, prepare survey report, and maintain records.
Provide route markings and obtain approvals.
Ensure calibration of survey equipment and its maintenance.
7. MATERIALS
7.1 Materials
Ceramic tiles.
Fixing product.
Nitotile GP: General purpose tile adhesive (…… …….. …..).
Nitobond (SBR): water resistant polymer bonding admixture (…… ………. …).
7.2 Consumable
Stainless steel 8 m/m rod corner protection.
Cross plastic spacers (6 m/m).
8. WORKFORCE
for one shift of 8hrs / day
1 engineer
1 Forman
tiles fixer as needed
workers as needed
9. WORK METHODOLOGY
9.1 Leveling & alignment
The level & alignment point must be done carefully before starting the work.
Backing to wall filling must be completed in accordance with technical specification.
Corner protection shall be fixed in each corner to protect ceramic tiles edges.
It consist of a stainless steel Y8 m/m rod fixed with plastic universal anchors
(fisher).
9.2 Fixing ceramic tiles
The application procedure for fixing ceramic tiles using Nitotile GP & Nitobon SBR.
All leakage through dW to be rectifired before setting.
All surfaces must be soundness, clean and free from all traces of grease and oil.
All loose particles of mortar and deleterious materials must be removed.
Concrete substrate should be soaked with water.
Approximately 3 ltr. Of Nitobond SBR, and 3 ltr. Of clean water should be
added to 25 kg of Nitotile GP that mixed with a slow speed drill until a uniform,
lump free consistency is achieved.
Allow the mix to stand for about 10 minutes mix again, then it is ready for use.
Mixed Nitotile GP is spread on the substrate to a thickness not exceeding 10
m/m with a notched trowel. The tiles are then placed firmly into the adhesive
bed with a twisting motion.
As an alternative, the product may be spread on the substrate to a thickness
of approximately half the total thickness of the bed, while the remaining
thickness is applied on the back of the tiles.
After 4 to 5 days minimum of fixing the ceramic tiles, filling of joints must be
done with approved material.