JVCGCINTHIEICO-HSE-FORM-008 Rev00

JOB SAFETYAnnexe
ANALYSIS
A (JSA)
Location: AL03/Section-03 Person in charge (Applicant): Libingkui, Date: 02/07/2023
HSE-JSA-Thrust Block -001 Rev00
Work activity or Job: Pipe Line Trench excavation, Backfilling
Work team /JSA prepared by: Dang Chun, Libingkui, Long.
Reviewed by: JV-HSE
Hazards/Events and their potential
Job steps (in sequence) Control measure to eliminate or reduce the potential and
consequence associated with each step

1. Equipment to be used Struck with Heavy machineries/ overhead or ● EXCAVATOR Operators Must be competent.
(Excavator, JCB ) underground electrical or utility lines, Noise,
● Have valid third-party Certificates for Operator
Vibration, Dust
● Valid ROP Mulkia and Insurance
● Rigger /Banksman certified
● Do not operate during adverse weather
● Equipment pre use Inspection using checklist
● Pre inspection at Site

2. Work Area Inspection Employee Protection Slips, trips, falls, uneven ● Ensure Excavation Permit by Municipality /Authorities and available
and Preparation surfaces
● All staff & worker should take the HSE induction.
● employees to be medically fit for the activities
● Ensure NOC for Underground service providers (Telecom, Electrica
● Check any overhead lines get approval from Mazoon as required
● Use cable detectors to check Underground cables
● Toolbox shall be conducted by the Supervisor.
● Use of necessary PPE shall be checked and enforced by the safety
etc.)
● Physically inspect work areas prior to start of work
● Follow good housekeeping practices: create walkways
Page 2 of 4

JVCGCINTHIEICO-HSE-FORM-008 Rev00
● Assure materials & debris do not block traffic
● Keep work areas clean & neat, free from rubbish & debris
● Watch where you walk.
● Be careful on slopes or wet/muddy areas
● Be aware of reptiles and snakes
● Emergency Response Plan should be in place

3. Working outdoors Adverse Hot weather & Heavy wind, reptiles & ● Wear cotton clothing.
snakes, medical emergency ● Provide shaded area
● Provision of cold drinking water
● Wear light-colored, cotton clothing.
● Slow down work rate and increase breaks in hot weather.
Restrict working at open areas of high temperature at noon, from 12:30
Compliance to applicable MD 286/2008 requirements
● Slow down work rate and increase breaks in hot weather.
● Do not operate during heavy wind
● Emergency Response Procedure Awareness, HSE Induction, use st
● Always check wind speed

4. Trench excavation& ● Men, Material (string pipes etc.), ● Excavations deeper than 3 ft in depth requires adequate planning an
Pipe laying Animals falling on trench,
● Wall collapse, engulfment ● Daily inspection and validation of permit /authorization by Site Engin
● snakes, reptiles, ● All excavation access /egresses shall be inspected
● Struck-by or crushing accidents, ● Provide secured access and egress to trench (Nobody should enter i
● Improper positioning of excavator ● Excavate slopes to 1.5 to 1 ratio, (34 ½ Degrees), install trench box
● Machinery failure
● Incompetent operator Hitting buried ● Watch for signs of collapse (tension cracks, ground settlement, wate
utilities, ● Safe-off excavation area as required.
● Property Damage, ● Use Electrical Cable detector to check the underground services
● Electrocution, Crushing, flying, debris &
● Barricade the area /Warning signages
noise
Page 3 of 4

JVCGCINTHIEICO-HSE-FORM-008 Rev00
● Dust, Noise and Vibration ● HSE officer to oversee the activity
● The work shall be done under supervision of JV Supervisors /Engine
● Tool Box Talk before activity
● Allow only necessary personnel into areas where equipment is opera
● Use of competent banksman for the job
● Maintain line of sight with operators.
● Keep spoils pile at least three feet from edge of excavation.
● Keep non-essential personnel away from work activities
● Establish and use appropriate hand signals.
● equipment inspection will be performed each day by Operator prior
● Bucket and attachments must be grounded when not in use.
● Only trained and qualified Operators are allowed to run the equipme
● Use spotters where high noise levels or poor visibility interfere with
equipment.
● Utilize safety vests at all times.
● Swing radius is to be barricaded while working around ground perso
● Keep all personnel out from under loads.
● Permanent barricade to be installed with adequate warming signage
● If near to Public Road warning lights /permanent barricading to be i

5. Back filling the trench ● Stuck by machinery /Personal Injury ● Use banksman
after pipe lowering
● Dust, Noise & Vibration ● Use dust mask
● Collapse of machinery (excavator) ● Inspected /third party approved excavator to be used
● Traffic accidents ● Trained /competent operator
● Asset damage ● Keep away unauthorized personnel
● Traffic control on movement of Vehicles and machinery/Heavy equip
6. Grading ● Struck by, Caught in between, Noise ● Ensure that all reverse alarms and other safety equipment are worki
● Wear safety glasses.
Page 4 of 4

JVCGCINTHIEICO-HSE-FORM-008 Rev00
● Wear hearing protection during operations when required by noise l
● Safety vests to be worn at all times.
● Keep in sight of operator.
7. Dust Control ● Breathing & Eyes irritant, property ● Use Dust masks as needed
damage
● Google to be used

PPE / SYSTEMS /STANDARDS / PROCEDURES REQUIRED TO DO THE JOB


Standard PPE Additional PPE Specific procedures / Standards: Other systems
Hard hat Face shield Scaffolding
Safety boots /shoes Chemical resistant apron Barrier tape
Coverall Chemical resistant gloves Warning signs
Standard work gloves Chemical resistant boots Lockout/tagout
Safety glasses Respiratory protection Work permit required
Goggles Dielectric gloves Hot work permit
Ear plug Personal fall protection Confined space permit
Ear defenders Others (specify) Excavation
Welding apron
Welding Helmet