Mineral Exploration & Consultancy Limited

Project Name : Gorhi Mahloi Project

I)Daily Drilling progress Date: 30.06.23

Urgent Requirement
Unit No / Cumulative of Requirement pending at Date of Start/ Date of
BH NO/P. NO From To Day Night Total Remarks
Make Month (Indent to be CHQ /Date Shifting Hours Closing
sent) of Indent

A. Block Name: Teram Client Name: CMPDIL, RI-V

MEC-343
127.00 Rig is idle 27.05.23
(RD-100)

MEC-385 B/D: 4 hr, Repair


MTR-35 (R-11) 342.00 381.00 15.00 24.00 39.00 1110.00 22.06.23 11.06.23
(KDR-1000) the Alternator

A. Day Total: 39.00 C. Cumulative for the Month: 2262.00 mtr

B. Daily Drilling Target: 60 mtr D. Drilling target for the Month: 1767 mtr

II)Sampling Status
No. of
samples for
No. of
No.of which
No. of contract
No. of samples analytical No. of samples
No. of samples samples workers
samples sent to results pending at Remarks
prepared pending at engaged for
generated Chemical received Chemical Lab
camp sample
Labs from
preparation
Chemical
Lab
0 0 0 0 0 0 0

III) Total no of Contract Workmen Engaged:


Unskilled Skilled Semi Skilled Watch & Ward Total
Sl. No.
Drilling Helper Khalasi Survey Sampling Comp. Oprtr Driver Drill Operator
14 2 0 0 0 3 2 0 9 32

IV) Total No. of Regular Manpower Available:

No. of Regular Manpower Available


Sl. No. Drilling Sampling Driver Mechanic Survey Office Staff Total
Executives

3 11 0 1 0 1 3 19

V) No of Departmental Vehicles Available:


a) Trucks : 02 nos
b) Light Vehicle: 01 nos

Vi) No of Private Vehicles running


a) Light Motor Vehicle: NIL
b) Tractor carrying water tanker - Nil

Vii)Details of the Work done in respect to the Work Order Received from the client

% of
Field Work Date of Achievemen
Date of
Date of Completion Submission Daily Drilling t in respect
Sanctioned Meter Starting Achievement Remarks
Sanction Time as per the of GR as per Target to the
Work
WO WO Cumulative
Name of the
Target
Block

Name of the Project Manager: Mitesh Kumar