Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
1 HIGHWAY 190+500 190+600 RHS C & G Soil dozing & Levelling SQM 1 100.000 15.000 1500.00
2 HIGHWAY 192+560 192+600 RHS Excavation upto Drain PCC Bottom CUM 1 40.000 2.000 1.000 80.00
Total Nos. 1 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
1 HIGHWAY 192+600 192+650 LHS Excavation upto Drain PCC Bottom CUM 1 50.000 2.000 1.000 100.00
2 HIGHWAY 192+560 192+600 RHS C & G Soil dozing & Levelling SQM 1 100.000 15.000 1500.00
Total Nos. 1 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
1 HIGHWAY 192+650 192+700 LHS Excavation upto Drain PCC Bottom CUM 1 50.000 2.000 1.000 100.00
Total Nos. 1 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
1 HIGHWAY 192+700 192+740 LHS Excavation upto Drain PCC Bottom CUM 1 40.000 2.000 1.000 80.00
2 HIGHWAY 193+100 193+350 LHS Diversion Maintanance
Total Nos. 1 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
Er.Venkatrao,
1 HIGHWAY 190+300 190+400 RHS C & G and Soil grading & Levelling SQM 1 100.000 10.000 1000.00 Sr.highway engineer
Safety Sticks & Safety bags Fixing Er.Venkatrao,
2 HIGHWAY 214+200 214+460 LHS
Purpose Sr.highway engineer
Total Nos. 3 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
Er.Venkatrao,
1 HIGHWAY 182+780 183+150 LHS Median WMM rectification Work SQM 1 370.000 1.500 555.00 Sr.highway engineer
Er.Venkatrao,
2 HIGHWAY 182+450 195+000 LHS All Diversion Watering Sr.highway engineer
3 HIGHWAY 216+400 216+600 LHS Safety Sides & Radium Stickker Fixing Er.Kutumbarao
Sr.Highway Engineer
Total Nos. 3 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
Er.Venkatrao,
1 HIGHWAY 192+740 192+780 LHS Excavation upto Drain PCC Bottom CUM 1 40.000 2.000 1.000 80.00 Sr.highway engineer
Er.Venkatrao,
2 HIGHWAY 193+100 195+000 All Diversion Watering Sr.highway engineer
Total Nos. 1 0
Nature of Work B) Distrubances
Chainge
Meterial Received Name of the Sub
Sl.No. Dept. Section Side Details of Activity Grade Unit No's L B D Quantity From B.Plant/HM Contractor
From To Plant
Er.Venkatrao,
1 HIGHWAY 192+780 192+810 LHS Excavation upto Drain PCC Bottom CUM 1 40.000 2.000 1.000 80.00 Sr.highway engineer
Er.Venkatrao,
2 HIGHWAY 193+100 195+000 All Diversion Watering Sr.highway engineer
Total Nos. 1 0
Nature of Work B) Distrubances