Professional Documents
Culture Documents
APPROVED FOR
TECNICAS REUNIDAS SAUDIA SAUDI ARAMCO
□APPROVED □APPROVED
NAME NAME
SIGNATURE SIGNATURE
DATE DATE
ISSUE STATUS
Rev Date Prepared by Sign Approved By Sign
TABLE OF CONTENTS:
1 PURPOSE
2 SCOPE
6 REQUIREMENTS
7 SETUP PROCEDURE
9 SAFETY
11 ATTACHMENTS
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
1 PURPOSE
This procedure establishes the minimum requirements to assure that Heat Treatment is
performed in accordance with the applicable codes and contract requirements.
2 SCOPE
The scope shall state that the procedure is for the "local PWHT of piping joints" in RAS
TANURA REFINERY CLEAN FUELS PROJECT
4 DEFINITIONS
Stress Relieving:
The uniform heating of pipe weld joint to a specified temperature below the critical
temperature of the material for a period of time to relieve major portion of residual
Stresses, and then cool at a uniform regulated rate.
The equipment shall be calibrated, approved and should bear appropriate electrical
power input/output notices.
Power distribution (supply) shall be of 380V- 3 phase, with either single phase
secondary output or step down transformer secondary output (heat treatment unit)
supplying low voltage circuits. The temperature control equipment shall be operated
manually or through regulators or it shall be (made) operated automatically with the
help of modular controls. The chart type temperature recorder shall be used for
recording temp.
Temperature recorders shall be calibrated every three months and a current calibration
sticker shall be maintained on the recorder. The calibration frequency may be extended
to 12 months with the approval of Company Inspection if the documented calibration
checks for that particular recorder demonstrate acceptable accuracy for a suitable
period.
If the furnace is not using, the insulation should be properly applied
5.2 Materials
5.2.1Ceramic Heaters Mats.
Heating Elements used for PWHT shell be flexible ceramic mat heaters of
standards sizes are 300 x 300 mm,300 x
400mm, 300 x 560mm,300 x 718mm & 300 x 888mm,240 x 1040 and flexible
ceramic Coil of various length.
Ceramic heaters are designed to use up to 1050 0 C. End of the heaters are
provided with cam lock plug & socket connections. Heaters should be thoroughly
checked before wrapping on the job & connecting to the circuit.
5.2.2 Arrangements of Elements.
The circumferential band width which has to be heated shall be minimum three (3)
times the thickness of the shell material being welded from each edge of the weld,
but not less than 25 mm, whichever is greater.
For weld on pipe diameter 250 mm, the elements shall be divided in to two or
more control zones, being top & bottom with pads applied symmetrically.
If the elements arrangements is not being capable of desired configuration then,
The center line circumferential gap between two bands shall not exceed 30 mm or
“t” whichever is lesser.
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
The longitudinal gaps between elements shall not be more than the wall thickness
or 50mm, whichever is less. We should be careful to ensure that there are no gaps
in “6” o clock position.
If the welds are of two separate wall thickness, then the elements should be so
arranged to give side to side control in addition to top & bottom control.
In the case of inclined or vertical welds the pads shall be arranged about the weld
to give independent control above & below weld centerline.
5.2.3 Thermal Insulation
Thermal insulation should be achieved by following means, In some cases,
minimum requirements shall be 50mm thick. Densities (90 Kg/m3 ) if mineral wool
shall be used.
If Super wool LT, Carbowool or equivalent blanket, 25mm thick, having a minimum
density of 96 kg/m3 shall be used as an alternative.
The insulation distance shall be up to a minimum distance of 300 mm beyond the
edges of the heating bands or up to a distance determined by the product of bore
radius times the maximum wall thickness whichever is less.
The number of layers & extent of insulated area shall be dependent on
Wall thickness.
Pipe or fitting diameter.
Gradient requirements.
Site conditions.
Insulation shall be fixed using black annealed iron wire taking care, not damaging
or cutting in to the insulation.
By following proper PWHT cycle, the items are the particular joint shall be
completed & the cooling rate should be controlled under insulation.
5.3 Surface Conditions
The welds to be heat treated shall be prepared free of grease, lubricants, dust and
coatings to avoid damage and short circuiting of accessory equipment. Any wood
or plastic end cover protections shall be removed.
During heat treatment it shall be necessary to protect from oxidation flange faces
or threaded holes, threads by the application of coating such as de oxaluminite or
any other suitable coating material.
6 REQUIREMENTS
6.1 Special Requirement
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
WPS utilized in performing the affected welds shall be qualified for PWHT when
required by applicable code.
All temporary attachment within the heat affected zone shall be removed.
7 SETUP PROCEDURE:
7.1 General
Visit site with client representative to evaluate work, select safe work area for
equipment and personnel for heat treatment work to be performed.
Clean-up the surface area of pipe to a minimum of 1 feet each side of the element band
to be used. Make sure that the surface is free of oil, grease, tar, bitumen or other
contaminations and is dry/free of moisture/condensation before insulation of
thermocouples and elements.
Ensure that pipe ends are closed off and sealed with insulation to prevent air drafts and
heat loss on inner surface through a chimney effect.
Protect machined surfaces such as flanges, threaded sockets, etc. From oxidation by
applying a coat of Deoxaluminite or other high temperature grease approved as per
ARAMCO specification.
Preparations for protection of work being heat treated against possible rain and/or
extreme weather conditions utilizing scaffolding and weather proof sheeting to cover as
needed.
All heating elements are to be checked for defects before installation. Elements with
broken beads, exposed wire or damaged twist locks shall not be used. This will ensure
the electrical and insulation integrity of elements.
All equipment and materials are to be in good working order prior to the start of work.
Before proceeding with heating cycle check all cables/connections for electrical integrity
and maintain good housekeeping in work area.
Prior to the start of PWHT, components shall be checked to ensure that all restraints are
removed, the component is free to expand and contract, and suitable and sufficient
supports are used. In addition the PWHT chart shall be marked, prior to PWHT, with
identification number of the weld(s).
7.2 Thermocouple Attachment and Positioning
Thermocouples shall be Type 'K' twin insulated wire (chromelalumel) and 2 meters long
connected to thermocouple plug.
Positioning of thermocouples on circumferential welds shall be as follows, position
designated by the time clock i.e., 12,3,6 and 9 0' clock.
As per SAES-W-011 Up to 12" 1 TIC
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
7.4 Insulation
Ceramic fibre insulation mats have standard dimension of 25mm thick by 600mm wide,
lengths to fit pipe circumference and density of 128kg/cum and encased in stainless
steel mesh.
For PWHTs that are not perform in a furnace, insulation shall be applied a minimum of
300mm on either side of the weld that is to be PWHTed. The insulation shall not be
removed before the temperature has cooled to below 150℃. The ends of open lines
shall be closed off in order to eliminate drafts or air circulation that could lower the
temperature on the inside surface of the joint unless the internal surface is also
insulated.
Insulation must not cover the element cold tails junction to avoid burn out of tail
junction.
The insulation to be secured in place by using iron tie wire or for larger diameters mild
steel banding.
PWHT is used to improve the toughness and reduce the hardness of a weld, refine grain
structure and increase ductility and relieve residual stresses.
Attach thermocouples as described, pipe diameter and number of heating zones
regulates the minimum number of thermocouples required.
Place heating elements centrally over weld, and heating zones elements with care
centrally over thermocouples. For larger/thicker pipe or flanges it may be necessary to
use two heating bands each side of weld and each band controlled by its own individual
thermocouples.
Connect secondary supply leads/splitters to element and heat treatment unit; connect
thermocouples and compensating cables to temperature recorder. Check all electrical
cables/connectors for electrical integrity before switching on power.
Thermocouples and temperature recorder shall monitor and provide a record of
heating, soaking and cooling cycle. The technician shall check the recorder chart speed
at the start of each heat treatment cycle and indicate the chart speed on the strip chart.
The PWHT heating and cooling rates above 316℃ shall not exceed 222℃/hr divided by
the weld thickness in inches, but in no case shall it be more than 222℃/hr.
The specified PWHT shall be applied over an area extending at least 3 times the
thickness of the material being welded from each edge of the weld but not less than
25mm from each edge of the weld, whichever is greater.
Soak temperature shall be considered to start when all thermocouples are just reached
the lower limit of the soaking temperature required for each material.
The minimum PWHT soak time shall be one (1) hour and if hardness limits are specified
the soak time for production welds shall not be less than 80% of the PQR soak time
unless approved by CSD.
For all Quenched and tempered materials the PWHT temperature shall be at least
250℃ below the tempering temperature.
All temperatures within the heated zone for furnace or localized PWHT shall exceed the
specified minimum holding temperature. The actual temperature range for the soak
period, as recorded by thermocouples, shall not have a spread of more than 40℃.
Welding or heating to joints that have been PWHTed requires rePWHT. Post Weld Heat
Treatment shall follow all welding and repairs but shall be performed prior to any hydro
test.
At 300℃ power can be turned off and the weld cool unrestricted to ambient, and
insulation/elements removed.
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
9 SAFETY
All heating elements shall be thoroughly examined before use in order to ensure that
the element wire is not exposed.
Twist lock connection shall be examined to ensure that the insulation is sound and a
good electrical joint is made.
All cable connection must be properly insulated.
The component surface should be free of contaminations.
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
Every day morning, a list of joints heat-treated previous day along with all the relevant
details including Time-Temperature graphs (chart) shall be submitted to Q.C.
department for approval. All the identification of joints must be noted in chart and
signed, mentioned start time by the technician prior to start of PWHT.
PWHT report form is SATR-W-2005 (see attachment)
11 ATTACHMENTS
Table-1
Ceramic Mats Description and Dimensions
If the required heating element is not available. Select the next size that meets these
requirements.
TYPE WIDTH(Inch) LENGTH(Inch)
CM3 3 26
CM4 4 19.5
CM6 6 13
CM8 8 9.75
CMIO 10 8
CM12 12 6.5
CM15 15 5.75
CM18 18 5
CM21 21 4
CM24 24 3.25
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00
CM48 48 1.75
B - 2 T C- Pipe Diameter from 14 inch -24 inch (Top and Bottom side or left and Right side)
D- 1 TC pipe Diameter equal and less than 1 inch (Elbow & Tee)
Project Title:
RAS TANURA REFINERY CLEAN FUELS
PROJECT
Location: Document Number: Revision
RAS TANURA -SAUDI ARABIA 10100-25345/25380 00