CSE-401
Time: 10+ 5 =15 Minutes
Answer the following question- Marks- 10
Q1 Consider the details of a project shown in the table. i) Construct the 10
CPM network and find project completion time ii) Determine the
critical path iii) Is there an option to delay one activity without
delaying the entire merge project? Which activity would you delay
and why?
Activity Immediate Predecessor(S) Duration(Day)
A P,Q 10
B C 8
C A 7
D C 6
P -- 5
Q -- 4