Chapter
7 Gantt Chart
7.2 NUMERICALS
C-6
2 4
G -5
A-8
D-8
H-6 J - 10
1 5 7 8
E-4
B-7 I-6
3 6
F-8
If the resources are limited to 20 workers, then the days of over allocation of
resources are on 8th , 9th , 10th and 11th day.
If the resources are limited to 25 workers, then the days of over allocation of
resource does not arise.
Q.2. A project consists of nine activities for which the relevant data is given
in table.
Activity Immediate Duration Total Cash Flow
Predecessor (Days) Reqd. for activity (Rs. Lakhs)
Gantt Chart 143
A -- 5 25
B -- 5 30
C A 10 40
D B 7 28
E A 6 12
F C, D 8 24
G C, D 6 15
H E, F 5 10
I G 4 12
(MMM/MFM MUMBAI UNIVERSITY 2008)
i. Draw the network and find the project completion time.
ii. Compute EST, EFT, LST, LFT and Total float for each activity.
iii. Draw the Gantt chart for the project.
iv. What is the maximum requirement of cash and on which day does it
occur?
Solution :
(1)
E-6
2 4
A-5 C- 10 H-5
F-8
1 5 7
I-4
D- 7
B- 5 G- 6
3
6
(2)
Activity Duration EST EFT LST LFT Total Float
A 5 0 5 0 5 0
B 5 0 5 3 8 3
C 10 5 15 5 15 0
144 Project Management (M.M.S. Sem. IV)
D 7 5 12 8 15 3
E 6 5 11 17 23 12
F 8 15 23 15 23 0
G 6 15 21 18 24 3
H 5 23 28 23 28 0
I 4 21 25 24 28 3
Critical path A-C-F-H= 28 days
(3)
(4) The maximum requirement of cash is Rs 80 Lacs and this happens on day 6
to day 11.
❑ ❑ ❑