5. Draw the network diagram from the following table and find the critical path. [15]
PA
Optimistic Time Most likely time Pessimistic time
Predecessor
Activity estimate (to estimate (tm estimate (tp
Activity
days) days) days)
PE
A - 2 4 6
B A 3 6 9
C A 8 10 12
R
D B 9 12 15
S
E C 8 9 10
F D,E 16 21 26
N
G D,E 19 22 25
O
H F 2 5 8
I G 1 3 5
V