# Description Drawing Number Sheet Numbers


1 Map showing Different Lots in Oyo RAAMP 1
2 Map showing Phase I and II in Oyo RAAMP 1
3 Map Showing Ona Ara Roads 1
4 Road layout for Lot 1 Roads SEC/OYRAAMP/23D/LOT1/C02 1
5 Legend SEC/OYRAAMP/23D/LOT1/C03 1
6 Horizontal Curve Setting Out Data SEC/OYRAAMP/23D/LOT1/C04 1
7 Road Safety Signs SEC/OYRAAMP/23D/LOT1/C05 1
8 Typical Road Cross Section SEC/OYRAAMP/23D/LOT1/C06 1
9 Road Setting Out Data 10
10 Horizontal and Vertical Curve Data 11
11 Schedule of Culverts 2
Plan and Profile Drawings for Agbejoda – Olorunda
12 SEC/OYRAAMP/23D/LOT1/001-01 - 11 12
Road
Plan and Profile Drawings for Agbejoda – Ogunran
13 SEC/OYRAAMP/23D/LOT1/002-01 - 08 09
Road
Plan and Profile Drawings for Gbeleyi – Bioku –
14 SEC/OYRAAMP/23D/LOT1/003-01 - 08 09
Dagbolu Road
15 Junction Details SEC/OYRAAMP/23D/LOT1/001-J1 02
SEC/OYRAAMP/23D/LOT/CVO1 –
16 Culvert Drawings
CV15
17 Cross Section Drawings SEC/OYRAAMP/23D/LOT1/001-CS 242