The document is a letter from the Technical Director of Waterfall Prime Trust Limited to the Managing Director providing a work schedule and bill of quantities for the proposed procurement and installation of a 500kVA, 33/0.415kV transformer. It includes 6 items describing the work to be done such as procuring poles, overhead lines, the transformer, cables and other substation accessories. The total cost for all the items is estimated to be 17 million naira.
The document is a letter from the Technical Director of Waterfall Prime Trust Limited to the Managing Director providing a work schedule and bill of quantities for the proposed procurement and installation of a 500kVA, 33/0.415kV transformer. It includes 6 items describing the work to be done such as procuring poles, overhead lines, the transformer, cables and other substation accessories. The total cost for all the items is estimated to be 17 million naira.
The document is a letter from the Technical Director of Waterfall Prime Trust Limited to the Managing Director providing a work schedule and bill of quantities for the proposed procurement and installation of a 500kVA, 33/0.415kV transformer. It includes 6 items describing the work to be done such as procuring poles, overhead lines, the transformer, cables and other substation accessories. The total cost for all the items is estimated to be 17 million naira.
Work Schedule for Proposed Procurement and Installation of 500kVA, 33/0.415kV
Transformer for Waterfall Trust Limited, Ibadan.
The above subject refers
Description Specification standard Cost
Submission of Application for Approval to Install 1 300kVA, 33/0.415kV Transformer for Waterfall 2,200,000.00 Prime Trust Limited (i)Concrete pole depth is 6ft, stay (i) Procurement of Concrete Poles, 150mm2 Al. depth is 4ft beneath floor level, conductor and line Accessories. Span of poles is 45-50m 2 (ii) Pegging, digging and erection of 10.05 3,457,200.00 (ii) Length of concrete poles is 10.05 &12.19m Concrete pole, Weaving of Stay wire, and 12.19m, all other accessories cutting and drilling of channel iron, Stringing of conforms with IBEDC standard 33kV lines with pole dressing specification
Haulage of all overhead line accessories, Al.
3 280,000.00 conductor, Poles and substation accessories.
Procurement, Testing and Haulage of 500kVA,
4 Equipment is to IBEDC standards 8,461,000.00 33/0.415kV Transformer Procurement and installation of cables, feeder All equipment is to IBEDC standards 5 pillar, Gang isolator, lighting arrester, d-fuse 2,431,800.00 specification and substation accessories &MD meter Installation of transformer, substation All Installation is to IBEDC standards 6 accessories, Silicon gang Isolator, termination of 170,000.00 spec. PVC cables and MD meter
TOTAL 17,000,000.00 I hereby present the Bill of Engineering Measurement and Evaluation for the proposed Procurement and Installation of Waterfall 500kVA, 33/0.415kV Transformer which amounts to Seventeen Million Naira Only. (N17, 000,000; 00).