You are on page 1of 1

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A A

Casting concrete by

570
Concrete Hopper

1250

1244
Purlin ☐50×50×2@250 Purlin ☐50×50×2@250

Plywood formwork 18mm Purlin ☐50×100×2@500 Purlin ☐50×100×2@500


Triangle Jack
Tie Ø16@500 Tie Ø16@500 Tie Ø16@500

1075
B B
Purlin 50×50×2@250 Longitudinal Plywood formwork 18mm Plywood formwork 18mm
Reinforcement
Purlin 50×100×2@500 Stirrup Working Deck Working Deck

400

400
Working Deck Vibrating rod

296

388
418
Working Deck

250

560
750
C 5 C

250
418

388
290
400

400

1080
D D

Working Deck

1250

1250

554
E E

150 1350 296 250 250 250 250 243 1350 150
1512 488 560 488 1500
2000 560 2000

B B1 Rebar Erection Formwork Installation Concrete Casting


1 2 3
Column Construction plan layout
F 4 F
1 : 25

5
B1 B
+29.800 +29.800
Floor 8 Floor 8
Scaffodlding Working Deck
170 Hopper Specifications
Working Stair
Dimension of funnel (D × R × C): 1.7 ×
468

Purlin 50×100×2@500 Bracing


298
668

G
Working deck 1.6 × 2.3m G
203

Tie Ø16@500
Volume: 1.5m3
322
332

Purlin 50×100×2@500
Purlin 50×50×2@250 Diameter of outlet: Ø270
500
537

Purlin 50×50×2@250
Pouring type: valve wiper
500
500

Triangle Jacking Tie Ø16@500 Elephant trunk pipe: 3m


L-Anchorage
500
500

Triangle Jack
3400

3400

H H
Bracing cable
500
500

2180
2192

500
500

60°

60°

60°
60°
500
500

I I

+26.400 +26.400
108
100

Floor 7 Floor 7
50

102
250 1250 100193100 750 150143103 1250 250 275 1300 388 560 388 1300 275 102
1250 2190 1250
1500 488 280 280 491 1250 50
200 4690
4548
K K
Column - Side Elevation Column - Front Elevation
6 5
1 : 25 1 : 25

3D- Working Deck- Column Concrete Hooper


7 8
NOTE:
• Column concrete is used as fresh concrete, is produced at the factory and shipped to the construction site by vehicles transporting concrete. BACHELOR DISSERTATION OF CIVIL ENGINEERING K2016
• Time of concrete for producing, transporting to the factory must be less than 4 hours to avoid harden concrete before applying. If concrete is hardened, it shall not be used for construction, must return to the
HO CHI MINH CITY UNIVERSITY OF TECHNOLOGY
L factory. FALCUTY OF CIVIL ENGINEERING OFFICE OF THE PARTY L
DEPARTMENT OF STRUCTURAL
• Concrete after being transported to the construction site, must be carried out sampling and testing before conducting slump concrete. ENGINEERING
CITY
• Casting concrete is carried out after rebar erection and formwork installation are completed, then acceptance is carried out by documents. When pouring concrete for wall, concrete is pumped into the funnels wall COMMITTEE
by tower crane or the pipe from truck. Workers in concreting area adjusted for concrete falling into the wall to create thickness of concrete based on the design, workers use vibrator down to vibrate the concrete, Head of dept Assoc Prof NGO HUU CUONG
period for vibrating at each position is 25 seconds. Vibrator always submerged in concrete before concreting 10cm. DESIGN OF COLUMN FORMWORK
Structural
• Concrete must be cured after casting to ensure there is no dehydration caused surface cracking. After pouring the concrete, maintaining concrete by watering outside of formwork and continue watering after the Instructor
Assoc Prof HO DUC DUY

M concrete is hardened. In the first two days, need to water it 1 time for every 2 hours. In the next days, need to water it 1 time for every 3 to 10 hours. Concrete must be cured for at least 7 days. In the process of Construction
Instructor
Dr NGUYEN ANH THU START 30/3/2020 DRAWING M

curing concrete, need to process immediately the defects if there is any problem. Student NGUYEN NGOC ANH TRAM 1652622 FINISH 17/7/2020 CONS.01
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

You might also like