Professional Documents
Culture Documents
PEKERJAAN : PEMASANGAN KERAMIK ANTI SLIP PADA LANTAI DAPUR KANTIN DAHAI (TAM
LOKASI : KANTIN DAHAI
I PEKERJAAN PERSIAPAN Rp -
IV PEKERJAAN PENGECATAN Rp -
T O T A L Rp 68,557,200.00
DIBULATKAN Rp 68,557,000.00
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMASANGAN KERAMIK ANTI SLIP PADA LANTAI DAPUR KANTIN DAHAI (TAMBAHAN)
LOKASI : KANTIN DAHAI Durasi waktu pelaksanaan : 20 Hari kalender
Sub Total I Rp -
II PEKERJAAN LANTAI KERAMIK
Supply dan pasang Lantai Keramik area chef room uk 60x60 anti slip Merk
1
Infiniti Sandstone Grey 43.27 m2 Rp 5,704,375.00
a upah pasang kramik 60x60 43.27 m2 Rp 62,500.00 Rp 2,704,375.00
b keramik infinity sandstone grey 60x60 8.00 Dus Rp 270,000.00 Rp 2,160,000.00
c pasir pasang 2.00 m3 Rp 150,000.00 Rp 300,000.00
d PC semen Chonch 9.00 zak Rp 60,000.00 Rp 540,000.00
Supply dan pasang Lantai Keramik area Pantry Nonstaff uk 60x60 anti slip
2
Merk Infiniti Sandstone Grey 30.83 m2 Rp - Rp 4,266,875.00
a upah pasang kramik 60x60 30.83 m2 Rp 62,500.00 Rp 1,926,875.00
b keramik infinity sandstone grey 60x60 6.00 Dus Rp 270,000.00 Rp 1,620,000.00
c pasir pasang 2.00 m3 Rp 150,000.00 Rp 300,000.00
d PC semen Chonch 7.00 zak Rp 60,000.00 Rp 420,000.00
Supply & Instal Keramik Dinding Lis Miring uk 60x60 anti slip Merk Infiniti
3
Sand Stone Grey 302.48 m2 Rp - Rp -
a upah pasang kramik dinding 60x60 302.48 m2 Rp 58,500.00 Rp 17,695,080.00
b keramik infinity sandstone grey 60x60 54.00 Dus Rp 270,000.00 Rp 14,580,000.00
c pasir pasang 14.00 m3 Rp 150,000.00 Rp 2,100,000.00
d PC semen Chonch 61.00 zak Rp 60,000.00 Rp 3,660,000.00
4 Bongkar + Supply dan Pasang Keramik Dinding dan Parit ukuran 20x33 Polos
27.86 m2 Rp - Rp 4,989,810.00
a upah pasang kramik dinding dan parit 20x33 27.86 m2 Rp 58,500.00 Rp 1,629,810.00
b keramik 20x33 27.00 Dus Rp 100,000.00 Rp 2,700,000.00
c pasir pasang 2.00 m3 Rp 150,000.00 Rp 300,000.00
d PC semen Chonch 6.00 zak Rp 60,000.00 Rp 360,000.00
5 Supply & instal ramp parit Stainless di area stock room 20x20
0.08 m2 Rp - Rp 150,000.00
a suplai dan pasang ram parit stainless 20x20 ( tukang las) 1.00 OH Rp 150,000.00 Rp 150,000.00
b Besi siku stainles 4x4 mm m' Rp 100,000.00 Rp -
c besi as steinless diameter 6 mm m' Rp 126,000.00 Rp -
6 Supply & instal ramp parit Stainless di area stock room 50x50
0.75 m2 Rp - Rp 150,000.00
a suplai dan pasang ram parit stainless 50x50 (tukang las) 1.00 OH Rp 150,000.00 Rp 150,000.00
b Besi siku stainles 4x4 mm m' Rp 100,000.00 Rp -
c besi as steinless diameter 6 mm m' Rp 126,000.00 Rp -
Sub Total II Rp 68,557,200.00
III PEKERJAAN PENGECATAN
1 Pengecatan dinding dalam kantin dahai dengan cat Dulux Pentalite Warna
394.47 m2 Rp - Rp -
Lakestone
2 Pengecatan dinding dalam kantin dahai dengan cat Dulux Wheather Warna
121.45 m2 Rp - Rp -
Lakestone
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOL SAT
(Rp) (Rp)
3
Pengecatan pintu dan jendela dengan cat Platone NP 633 Tudor Brown 81.73 m2 Rp - Rp -
HARGA UPAH C
I
HARGA
No UPAH Kode SATUAN P
Rp.
T
A
1 Mandor L.001 Hari 175,000.00
###
K
2 Tukang Kepala L.002 Hari 170,000.00
###
A
3 Pekerja L.003 Hari 145,000.00
### R
4 Tukang Bangunan L.006 Hari ### Y
150,000.00
A
5 Tukang batu L.007 Hari 160,000.00
6 Tukang kayu L.008 Hari 162,000.00
7 Tukang cat L.009 Hari 150,000.00
###
8 Tukang besi L.010 Hari 160,000.00
###
9 Tukang Pipa L.011 Hari 150,000.00
###
H
HARGA MATERIAL A
No BAHAN SATUAN SATUAN HARGA R
G
A
1 Batu gunung M.001 m3 375,000.00
###
2 Kerikil cor M.002 m3 355,000.00
###
3 Split/ batu pecah M.003 m3 512,500.00
###
4 Pasir Beton M.004 m3 212,500.00
###
5 Pasir urug M.005 m3 225,000.00
6 Pasir Pasang M.006 m3 212,500.00
7 Tanah Urug Pilihan M.007 m3 150,000.00
###
8 Batu bata M.008 bh 1,150.00
###
9 Batako semen M.009 bh 5,500.00
10 Semen PC (50 kg), Tonasa M.010 kg 1,680.00
###
11 Semen Warna M.011 kg 6,000.00
###
12 Tulangan besi beton M.012 kg 12,500.00
###
13 Kawat Bendrat M.013 kg 18,500.00
###
14 Plint Keramik 10 x 33.3 (menengah) M.014 bj 7,500.00
15 Plint Keramik 10 x 20 (menengah) M.015 bj 5,500.00
###
16 Keramik 40 x 40 (menengah), unpolished M.016 m2 95,000.00
17 Keramik 30 x 30 (menengah) M.017 m2 75,000.00
###
18 Keramik 33.3 x 33.3 (menengah), anti selip M.018 m2 85,000.00
###
19 Keramik 20 x 20 (menengah), anti selip M.019 m3 90,000.00
20 Keramik 20 x 25 (menengah) M.020 m2 90,000.00
###
21 Kayu Bekisting M.021 m3 2,800,000.00
###
22 Papan Begisting M.022 m3 1,500,000.00
23 List profil gypsum M.023 M1 15,000.00
###
24 List Profil kayu bangkirai 15/2.5 cm M.024 M2 35,000.00
25 Balok Lanan merah/Meranti M.025 m3 3,500,000.00
###
26 Papan lanan merah/Meranti M.026 m3 3,500,000.00
###
27 Balok Karuing M.027 m3 3,500,000.00
###
28 papan Karuing M.028 m3 4,000,000.00
###
29 Balok Bengkirai M.029 m3 5,500,000.00
###
30 Papan Bengkirai M.030 m3 5,500,000.00
###
31 Galam Dia. 10-12 mm - 4 m M.031 btg 18,000.00
###
32 Galam Dia. 6-8 mm - 4 m M.032 btg 17,500.00
###
33 Paku Ulin M.033 kg 20,000.00
###
34 paku Seng M.034 kg 25,000.00
###
35 paku rupa-rupa M.035 kg 17,000.00
###
36 Playwood 6 mm M.036 lembar 85,000.00
###
37 Playwood 9 mm M.037 lembar 125,000.00
38 Nusa Board, t = 3.5 mm M.038 lembar 80,000.00
39 Nusa Board, t = 5 mm M.039 lembar 120,000.00
40 Besi hollow M.040 btg 45,000.00
41 Gypsum t=9 mm M.041 lembar 180,000.00
###
42 Hollow 40/40 M.042 batang 30,000.00
43 Cat dasar alkali primer M.043 kg 46,000.00
###
44 Cat dasar M.044 kg 15,000.00
###
45 Dempul M.045 kg 16,000.00
###
46 Cat Tembok ex Dulux weathershield M.046 kg 168,000.00
###
47 Cat Tembok ex Dulux pentalite M.047 kg 76,000.00
###
48 Cat Tembok ex danabrite M.048 kg 37,000.00
###
49 Cat Kilap M.049 kg 65,000.00
###
50 Cat Manie M.050 kg 23,000.00
###
51 Minyak Cat M.051 liter 8,000.00
###
52 Minyak bekisting/oli bekas M.052 Liter 15,000.00
53 Amplas M.053 lembar 6,000.00
###
54 Closet duduk CW660J ex Toto M.054 set 4,500,000.00
###
55 Washlet shower spray ivory ex Toto THX20NBPIV M.055 set 275,000.00
###
56 Bath mixer shower ex Toto TS308RYNZ M.056 set 1,460,000.00
57 Paper holder TX720ACR M.057 set 350,000.00
58 Floor drain ex Toto TX1B M.058 set 365,000.00
59 Floor drain Toto TX1AV M.059 set 190,000.00
60 Half pedestal lavatory ex Toto LW240CJ LW240HFJ M.060 set 2,100,000.00
61 Lavatory Faucet ex. Toto type TX1111LRYR M.061 set 1,270,000.00
HARGA SATUAN UPAH KERJA HARGA BAHAN JUMLAH
URAIAN
Rp. Rp. Rp. Rp.
I ANALISA BIAYA KONSTRUKSI PEKERJAAN PERSIAPAN
1 1 M' Pengukuran dan pemasangan bouwplank
0.012 m3 Galam Dia. 6-8 mm - 4 m 17,500.00 - 210.00 210.00
0.020 kg Paku rupa-rupa 17,000.00 - 340.00 340.00
0.007 m3 Kayu bekisting 2,800,000.00 - 19,600.00 19,600.00
0.100 Oh Pekerja 145,000.00 14,500.00 - 14,500.00
0.005 Oh mandor 175,000.00 875.00 - 875.00
0.100 Oh Tukang bangunan 150,000.00 15,000.00 - 15,000.00
0.010 Oh Tukang kepala 170,000.00 1,700.00 - 1,700.00
32,075.00 20,150.00 52,225.00
II ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH DAN PONDASI
1 1 M3 Galian tanah biasa sedalam 1 M
0.400 Oh Pekerja 145,000.00 58,000.00 - 58,000.00
0.040 Oh Mandor 175,000.00 7,000.00 - 7,000.00
HARGA SATUAN UPAH KERJA HARGA BAHAN JUMLAH
URAIAN
Rp. Rp. Rp. Rp.
65,000.00 - 65,000.00
2 1 M3 Galian tanah biasa sedalam 3 M
0.735 Oh Pekerja 145,000.00 106,575.00 - 106,575.00
0.073 Oh Mandor 175,000.00 12,775.00 - 12,775.00
119,350.00 - 119,350.00
3 1 M3 Urugan kembali
0.192 Oh Pekerja 145,000.00 27,840.00 - 27,840.00
0.019 Oh Mandor 175,000.00 3,325.00 - 3,325.00
31,165.00 - 31,165.00
4 1 M3 Pemadatan Tanah
0.500 Oh Pekerja 145,000.00 72,500.00 - 72,500.00
0.050 Oh Mandor 175,000.00 8,750.00 - 8,750.00
81,250.00 - 81,250.00
5 1 M3 Urugan pasir
1.200 m3 Pasir Urug 225,000.00 - 270,000.00 270,000.00
0.300 Oh Pekerja 145,000.00 43,500.00 - 43,500.00
0.010 Oh Mandor 175,000.00 1,750.00 - 1,750.00
45,250.00 270,000.00 315,250.00
6 1 M3 Tanah urugan pilihan
1.200 m3 Tanah Urug Pilihan 150,000.00 - 180,000.00 180,000.00
0.300 Oh Pekerja 145,000.00 43,500.00 - 43,500.00
0.010 Oh Mandor 175,000.00 1,750.00 - 1,750.00
45,250.00 180,000.00 225,250.00
3 1 M2 Pemasangan 1 m2 acian
3.250 kg Semen PC (50 kg), Tonasa 1,680.00 - 5,460.00 5,460.00
0.200 org/hr Pekerja 145,000.00 29,000.00 - 29,000.00
0.100 org/hr Tukang Bangunan 150,000.00 15,000.00 - 15,000.00
0.010 org/hr Tukang kepala 170,000.00 1,700.00 - 1,700.00
0.013 org/hr Mandor 175,000.00 2,187.50 - 2,187.50
47,887.50 5,460.00 53,347.50
399,897.50 - 399,897.50
Profit 10% 39,989.75
439,887.25
II. KAWAT
1 Kawat beton / bindrat M.B.II.01 kg Rp 24,500 Rp 24,500
2 Kawat ayakan M.B.II.02 m2 Rp 18,000 Rp 18,000
3 Kawat nyamuk M.B.II.03 m2 Rp 23,100 Rp 23,100
4 Kawat duri M.B.II.04 roll Rp 82,000 Rp 82,000
5 Kawat harmonika M.B.II.05 roll Rp 102,500 Rp 102,500
6 Pipa galvanis dia. 1/2" t. 2,4 mm M.B.II.06 btg Rp 169,000 Rp 169,000
7 Pipa galvanis dia. 3/4" t. 2,4mm M.B.II.07 btg Rp 221,000 Rp 221,000
8 Pipa galvanis dia. 1" t. 2,4mm M.B.II.08 btg Rp 268,000 Rp 268,000
9 Pipa galvanis dia. 1 1/2" t. 2,4mm M.B.II.09 btg Rp 415,000 Rp 415,000
10 Pipa galvanis dia. 3" t. 2,4mm M.B.II.10 btg Rp 910,000 Rp 910,000
11 Pipa galvanis dia. 4" t. 2,4mm M.B.II.11 btg Rp 1,260,000 Rp 1,260,000
12 Besi siku t. 5,5mm M.B.II.12 btg Rp 260,000 Rp 260,000
I. CAT
1 Cat kayu se kualitas Danalac M.C.I.01 kg Rp 56,400 Rp 56,400
2 Cat besi se kualitas Danalac M.C.I.02 kg Rp 56,400 Rp 56,400
3 Cat tembok/cat semen se kualitas Danabrite 5 kg M.C.I.03 ember Rp 175,000 Rp 175,000
4 Cat tembok/cat semen se kualitas Danabrite 1 kg M.C.I.04 kg Rp 35,000 Rp 35,000
5 Plamir Tembok M.C.I.05 kg Rp 20,000 Rp 20,000
6 Cat dasar meni besi type A (cepat kering) se kualitas Jago M.C.I.06 kg Rp 41,000 Rp 41,000
7 Cat duco M.C.I.07 kg Rp 76,900 Rp 76,900
8 Dempul kayu typa A (putih) se kualitas Jago/kembang M.C.I.08 kg Rp 28,200 Rp 28,200
9 Plamir kayu se kualitas Jago M.C.I.09 kg Rp 30,800 Rp 30,800
10 Politur jadi M.C.I.10 ltr Rp 71,800 Rp 71,800
11 Teak oil sekualitas Fuji M.C.I.11 ltr Rp 66,700 Rp 66,700
12 Pernis M.C.I.12 kg Rp 71,800 Rp 71,800
13 Minyak cat M.C.I.13 ltr Rp 18,000 Rp 18,000
14 Thinner M.C.I.14 ltr Rp 40,000 Rp 40,000
15 Kuas roll Imundex M.C.I.15 bh Rp 25,000 Rp 25,000
16 Kuas ukuran 4" M.C.I.16 bh Rp 25,000 Rp 25,000
17 Kuas ukuran 3,5" M.C.I.17 bh Rp 22,500 Rp 22,500
18 Kuas ukuran 3" M.C.I.18 bh Rp 20,000 Rp 20,000
19 Kuas ukuran 2,5" M.C.I.19 bh Rp 15,000 Rp 15,000
20 Kuas ukuran 2" M.C.I.20 bh Rp 12,000 Rp 12,000
21 Kuas ukuran 1,5" M.C.I.21 bh Rp 11,000 Rp 11,000
22 Kuas ukuran 1" M.C.I.22 bh Rp 10,000 Rp 10,000
23 Amplas M.C.I.23 lbr Rp 7,700 Rp 7,700
24 Teer kayu M.C.I.24 ltr Rp 25,000 Rp 25,000
25 Flincoat M.C.I.25 kg Rp 82,000 Rp 82,000
V. KAYU LAPIS
1 Plywood 3 mm (120x240 cm) M.C.V.01 lbr Rp 56,400 Rp 56,400
2 Plywood 4 mm (120x240 cm) M.C.V.02 lbr Rp 71,800 Rp 71,800
3 Plywood 6 mm (120x240 cm) M.C.V.03 lbr Rp 94,900 Rp 94,900
4 Plywood 9 mm (120x240 cm) M.C.V.04 lbr Rp 123,000 Rp 123,000
5 Teak wood ( 90 x 240 ) M.C.V.05 lbr Rp 71,800 Rp 71,800
VII. PAKU
1 Paku gording 125 x 5,1 mm M.C.VII.01 kg Rp 23,100 Rp 23,100
2 Paku gording 100 x 4,2 mm M.C.VII.02 kg Rp 25,700 Rp 25,700
3 Paku usuk 80 x 3,8 mm M.C.VII.03 kg Rp 20,500 Rp 20,500
4 Paku reng 55 x 3,1 mm M.C.VII.04 kg Rp 20,500 Rp 20,500
5 Angkur / baut M.C.VII.05 bj Rp 2,600 Rp 2,600
6 Paku asbes M.C.VII.06 kg Rp 51,300 Rp 51,300
7 Paku genteng metal M.C.VII.07 kg Rp 38,500 Rp 38,500
8 Paku sekrup 3.5" M.C.VII.08 kotak Rp 35,900 Rp 35,900
9 Paku beton M.C.VII.09 kotak Rp 45,000 Rp 45,000
10 Paku beton M.C.VII.10 kotak Rp 80,000 Rp 80,000
11 Paku gypsum M.C.VII.11 kotak Rp 87,200 Rp 87,200
12 Paku hak panjang 15 cm M.C.VII.12 kg Rp 28,000 Rp 28,000
13 Paku Ulin M.C.VII.13 kg Rp 37,000 Rp 37,000
14 Paku Biasa / Rupa-Rupa M.C.VII.14 kg Rp 20,000 Rp 20,000
15 Paku Kalsiboard M.C.VII.15 kg Rp 22,000 Rp 22,000
D. HARGA SATUAN DASAR KAYU DAN BAHAN BANGUNAN TERBUAT DARI KAYU
I. KAYU BANGKIRAI
1 Balok bangkirai M.D.I.01 m3 Rp 5,765,700 Rp 5,765,700
2 Papan Bangkirai M.D.I.02 m3 Rp 5,996,300 Rp 5,996,300
V. KAYU KRUING
1 Kayu kruing balok M.D.V.01 m3 Rp 3,536,300 Rp 3,536,300
2 Kayu kruing papan M.D.V.02 m3 Rp 3,792,500 Rp 3,792,500
3 Balok kruing ukuran 8/8 M.D.V.03 batang Rp 78,700 Rp 78,700
4 Balok kruing ukuran 5/7 M.D.V.04 batang Rp 43,000 Rp 43,000
5 Balok kruing ukuran 4/6 M.D.V.05 batang Rp 29,500 Rp 29,500
6 Balok kruing ukuran 4/4 M.D.V.06 batang Rp 19,600 Rp 19,600
7 Balok kruing ukuran 3/5 M.D.V.07 batang Rp 18,400 Rp 18,400
8 Papan kruing ukuran 2/20 M.D.V.08 batang Rp 54,900 Rp 54,900
9 Papan kruing u'lantai 2/15 M.D.V.09 batang Rp 41,200 Rp 41,200
I. PIPA PVC
1 Pipa PVC abu-abu dia. 1/2" setara Wavin M.E.I.01 btg Rp 23,600 Rp 23,600
2 Pipa PVC abu-abu dia. 3/4" setara Wavin M.E.I.02 btg Rp 31,800 Rp 31,800
3 Pipa PVC abu-abu dia. 1" setara Wavin M.E.I.03 btg Rp 44,100 Rp 44,100
4 Pipa PVC abu-abu dia. 1 1/2" setara Wavin M.E.I.04 btg Rp 47,200 Rp 47,200
5 Pipa PVC abu-abu dia. 2" setara Wavin M.E.I.05 btg Rp 60,500 Rp 60,500
6 Pipa PVC abu-abu dia. 2 1/2" setara Wavin M.E.I.06 btg Rp 81,000 Rp 81,000
7 Pipa PVC abu-abu dia. 3" setara Wavin M.E.I.07 btg Rp 107,700 Rp 107,700
8 Pipa PVC abu-abu dia. 4" setara Wavin M.E.I.08 btg Rp 170,200 Rp 170,200
9 Pipa PVC abu-abu dia. 6" setara Wavin M.E.I.09 btg Rp 346,500 Rp 346,500
10 Pipa PVC putih dia. 1/2" setara Wavin M.E.I.10 btg Rp 23,600 Rp 23,600
11 Pipa PVC putih dia. 3/4" setara Wavin M.E.I.11 btg Rp 30,800 Rp 30,800
12 Pipa PVC putih dia. 1" setara Wavin M.E.I.12 btg Rp 41,000 Rp 41,000
13 Pipa PVC putih medium dia. 3" setara Wavin M.E.I.13 btg Rp 102,500 Rp 102,500
14 Pipa PVC putih tebal dia. 3" setara Wavin M.E.I.14 btg Rp 184,500 Rp 184,500
15 Pipa PVC putih medium dia. 4" setara Wavin M.E.I.15 btg Rp 153,800 Rp 153,800
16 Pipa PVC putih tebal dia. 4" setara Wavin M.E.I.16 btg Rp 292,200 Rp 292,200
17 Atap plastik gelombang PVC M.E.I.17 lbr Rp 61,500 Rp 61,500
I. BATAKO
1 Batako berlubang ( 40x20x10 ) M.G.I.01 bj Rp 2,900 Rp 2,900
II. PIPA/GORONG-GORONG
1 Pipa beton bertulang dia. 40 cm panjang 1 m M.G.II.01 m1 Rp 261,400 Rp 261,400
2 Pipa beton bertulang dia. 60 cm panjang 0,5 m M.G.II.02 m1 Rp 179,400 Rp 179,400
3 Pipa beton bertulang dia. 60 cm panjang 1 m M.G.II.03 m1 Rp 358,800 Rp 358,800
4 Pipa beton bertulang dia. 80 cm panjang 0,5 m M.G.II.04 m1 Rp 230,700 Rp 230,700
5 Pipa beton bertulang dia. 80 cm panjang 1 m M.G.II.05 m1 Rp 461,300 Rp 461,300
6 Pipa beton bertulang dia. 100 cm panjang 0,5 m M.G.II.06 m1 Rp 292,200 Rp 292,200
7 Pipa beton bertulang dia. 100 cm panjang 1 m M.G.II.07 m1 Rp 584,300 Rp 584,300
IV. LAINNYA
1 Roster 25/25 M.G.IV.01 bh Rp 15,400 Rp 15,400
2 Roster 30/30 M.G.IV.02 bh Rp 16,400 Rp 16,400
3 Roster 15/20 M.G.IV.03 bh Rp 14,400 Rp 14,400
4 Roster 10/20 M.G.IV.04 bh Rp 14,400 Rp 14,400
5 Cansten (30x20x20) P. 50 cm M.G.IV.05 bh Rp 97,400 Rp 97,400
V. READY MIX
1 Mutu Beton K - 125 M.G.V.01 m3 Rp 1,522,200 Rp 1,522,200
2 Mutu Beton K - 175 M.G.V.02 m3 Rp 1,629,800 Rp 1,629,800
3 Mutu Beton K - 225 M.G.V.03 m3 Rp 1,664,000 Rp 1,664,000
4 Mutu Beton K - 250 M.G.V.04 m3 Rp 1,771,600 Rp 1,771,600
5 Mutu Beton K - 275 M.G.V.05 m3 Rp 1,916,800 Rp 1,916,800
6 Mutu Beton K - 300 M.G.V.06 m3 Rp 1,872,400 Rp 1,872,400
7 Mutu Beton K - 350 M.G.V.07 m3 Rp 1,865,500 Rp 1,865,500
8 Mutu Beton K - 400 M.G.V.08 m3 Rp 2,403,700 Rp 2,403,700
1 AHSP SNI 2005 Anl.II.1 M3 Membongkar 1 m3 Dinding Bata (Jika Bongkaran Dipakai Lagi) Rp 350,800 Rp - Rp - Rp 350,800
4 AHSP SNI 2005 Anl.II.4 M2 Membongkar 1 m2 Genteng / Sirap (Jika Bongkaran Tidak Dipakai) Rp 5,300 Rp - Rp - Rp 5,300
5 AHSP SNI 2005 Anl.II.5 M2 Membongkar 1 m2 Genteng / Sirap (Jika Bongkaran Dipakai) Rp 10,500 Rp - Rp - Rp 10,500
6 AHSP SNI 2005 Anl.II.6 M2 Membongkar 1 m2 Rangka Atap / Reng Kaso (Jika Bongkaran Dipakai) Rp 48,500 Rp - Rp - Rp 48,500
11 AHSP SNI 2005 Anl.II.11 M2 Membongkar 1 m2 Plafond (Jika Bongkaran Tidak Dipakai) Rp 21,800 Rp - Rp - Rp 21,800
12 AHSP BOW 2010 Anl.II.12 M2 Membongkar 1 M2 loteng,dinding luar,lantai jembatan(dari kayu) Rp 47,600 Rp - Rp - Rp 47,600
7 AHSP SNI 2016 A.2.3.1.13. M2 Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan Rp 27,900 Rp 48,300 Rp - Rp 76,200
8 AHSP SNI 2016 A.2.3.1.14. M3 Pengurugan 1 m3 sirtu padat Rp 46,500 Rp 371,800 Rp - Rp 418,300
9 AHSP SNI 2016 A.2.3.1.14.a M3 Pengurugan 1 m3 tanah padat Rp 46,500 Rp 138,000 Rp - Rp 184,500
1 AHSP SNI 2016 A.3.2.1.2. M3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP Rp 416,300 Rp 907,300 Rp - Rp 1,323,600
2 AHSP SNI 2016 A.3.2.1.9. M3 (K3) Pemasangan 1 m3 batu kosong (anstamping) Rp 216,500 Rp 666,000 Rp - Rp 882,500
3 AHSP SNI 2016 A.4.1.1.7 M3 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K-225) Site Mix Rp 346,900 Rp 1,101,900 Rp - Rp 1,448,800
4 AHSP SNI 2016 A.4.1.1.17 10 kg Pembesian 10 kg dengan besi polos atau besi ulir Rp 25,900 Rp 187,600 Rp - Rp 213,500
5 AHSP SNI 2016 A.4.1.1.17.a Kg Pembesian 1 kg dengan besi polos atau besi ulir Rp 2,600 Rp 18,800 Rp - Rp 21,400
6 AHSP SNI 2016 A.4.1.1.20 M2 (K3) Pemasangan 1 m2 bekisting untuk pondasi Rp 145,200 Rp 149,800 Rp - Rp 295,000
7 AHSP SNI 2016 A.4.1.1.21 M2 (K3) Pemasangan 1 m2 bekisting untuk sloof Rp 145,200 Rp 167,500 Rp - Rp 312,700
8 AHSP SNI 2016 A.4.1.1.22 M2 (K3) Pemasangan 1 m2 bekisting untuk kolom Rp 184,300 Rp 232,700 Rp - Rp 417,000
9 AHSP SNI 2016 A.4.1.1.23 M2 (K3) Pemasangan 1 m2 bekisting untuk balok Rp 184,300 Rp 243,300 Rp - Rp 427,600
10 AHSP SNI 2016 A.4.1.1.24 M2 (K3) Pemasangan 1 m2 bekisting untuk lantai Rp 184,300 Rp 280,100 Rp - Rp 464,400
11 AHSP SNI 2016 A.4.1.1.25 M2 (K3) Pemasangan 1 m2 bekisting untuk dinding Rp 184,300 Rp 239,300 Rp - Rp 423,600
12 AHSP SNI 2016 A.4.1.1.26 M2 (K3) Pemasangan 1 m2 bekisting untuk tangga Rp 184,300 Rp 208,400 Rp - Rp 392,700
13 AHSP SNI 2016 A.4.1.1.27 M2 Pemasangan 1 m2 jembatan untuk pengecoran beton Rp 36,800 Rp 82,000 Rp - Rp 118,800
VI. AHSP SNI 2016 A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALUMUNIUM
1 AHSP SNI 2016 A.4.2.1.5 10cm Pengerjaan 10 cm pengelasan dengan las listrik Rp 10,900 Rp 14,700 Rp - Rp 25,600
2 AHSP SNI 2016 A.4.2.1.10 M2 Pemasangan 1 m2 pintu rolling door alumunium Rp 368,200 Rp 345,000 Rp - Rp 713,200
3 AHSP SNI 2016 A.4.2.1.11 M1 Pemasangan 1 m kusen pintu alluminium Rp 15,800 Rp 142,700 Rp - Rp 158,500
4 AHSP SNI 2016 A.4.2.1.12 M2 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm Rp 31,300 Rp 896,200 Rp - Rp 927,500
5 AHSP SNI 2016 A.4.2.1.13 M2 Pemasangan 1 m2 pintu kaca rangka alluminium Rp 31,500 Rp 1,247,200 Rp - Rp 1,278,700
6 AHSP SNI 2016 A.4.2.1.14 M2 Pemasangan 1 m2 venetions blinds dan vertical blinds Rp 32,700 Rp 138,000 Rp - Rp 170,700
7 AHSP SNI 2016 A.4.2.1.15 M2 Pemasangan 1 m2 terali besi strip (2 x 3) mm Rp 614,700 Rp 297,200 Rp - Rp 911,900
8 AHSP SNI 2016 A.4.2.1.16 M2 Pemasangan 1 m2 kawat nyamuk Rp 616,300 Rp 122,300 Rp - Rp 738,600
9 AHSP SNI 2016 A.4.2.1.18 M1 Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm Rp 74,700 Rp 141,800 Rp - Rp 216,500
VII. AHSP SNI 2016 A.4.4.1 HARGA SATUAN PEKERJAAN DINDING PASANGAN
4 AHSP SNI 2016 A. 4.4.1.25. M2 Pemasangan 1 m2 dinding bata ringan tebal 7 cm dengan mortar siap pakai Rp 375,400 Rp 80,000 Rp 80,000 Rp 535,400
1 AHSP SNI 2016 A. 4.4.2.35.a M2 Pemasangan 1m2 lantai keramik ukuran 40 cm x 40 cm Rp 194,300 Rp 158,600 Rp - Rp 352,900
2 AHSP SNI 2016 A. 4.4.2.35. M2 Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm Rp 194,300 Rp 129,400 Rp - Rp 323,700
XI. AHSP SNI 2016 A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
2 AHSP SNI 2016 A.4.5.2.32.a M2 Pemasangan 1 m2 genteng metal ukuran 80 x 80 atap pelana Rp 43,300 Rp 46,300 Rp - Rp 89,600
4 AHSP SNI 2016 A.4.5.2.33.a M2 Pemasangan 1 m2 genteng metal ukuran 80 x 80 atap jurai Rp 43,300 Rp 67,400 Rp - Rp 110,700
5 AHSP SNI 2016 A.4.5.2.37. M1 Pemasangan 1 m’ nok genteng metal Rp 75,000 Rp 30,000 Rp - Rp 105,000
Pemasangan 1 m’ nok atap seng gelombang / atap alumunium
6 AHSP SNI 2016 A.4.5.2.37. M1 Rp 75,000 Rp 30,000 Rp - Rp 105,000
gelombang setara soka jempol
7 AHSP SNI 2016 A.4.5.2.39. M2 Pemasangan 1 m2 atap seng gelombang Rp 33,500 Rp 41,000 Rp - Rp 74,500
Pemasangan 1 m2 atap seng gelombang / atap alumunium gelombang
8 AHSP SNI 2016 A.4.5.2.39. M2 Rp 33,500 Rp 48,400 Rp - Rp 81,900
setara soka jempol
9 AHSP SNI 2016 A.4.5.2.40. M1 Pemasangan 1 m’nok atap seng Rp 40,600 Rp 10,400 Rp - Rp 51,000
3 AHSP SNI 2016 A.4.6.1.10. M2 Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II, kayu bengkirai Rp 587,400 Rp 417,700 Rp - Rp 1,005,100
8 AHSP SNI 2016 A.4.6.1.15. M3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II, kayu bengkirai Rp 5,313,800 Rp 7,918,300 Rp - Rp 13,232,100
18 AHSP SNI 2016 A.4.6.1.21.a M1 Pemasangan 1 m’ lisplank kalsiplang ukuran lebar 20 cm Rp 58,800 Rp 14,900 Rp - Rp 73,700
24 AHSP SNI 2016 A.4.6.1.26. M2 Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I, papan ulin Rp 475,900 Rp 79,600 Rp - Rp 555,500
XIII. AHSP SNI 2016 A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
1 AHSP SNI 2016 A.4.6.2.2. Buah Pemasangan 1 buah kunci tanam biasa Rp 105,400 Rp 171,000 Rp - Rp 276,400
2 AHSP SNI 2016 A.4.6.2.5. Buah Pemasangan 1 buah engsel pintu Rp 33,500 Rp 24,800 Rp - Rp 58,300
3 AHSP SNI 2016 A.4.6.2.6. Buah Pemasangan 1 buah engsel jendela kupu-kupu Rp 22,300 Rp 33,400 Rp - Rp 55,700
4 AHSP SNI 2016 A.4.6.2.8. Buah Pemasangan 1 buah spring knip (untuk pintu) Rp 34,900 Rp 28,800 Rp - Rp 63,700
5 AHSP SNI 2016 A.4.6.2.9. Buah Pemasangan 1 buah kait angin Rp 34,900 Rp 11,800 Rp - Rp 46,700
6 AHSP SNI 2016 A.4.6.2.11. Buah Pemasangan 1 buah kunci slot Rp 44,600 Rp 23,000 Rp - Rp 67,600
7 AHSP SNI 2016 A.4.6.2.17. M2 Pemasangan 1 m2 kaca tebal 5 mm Rp 33,500 Rp 192,600 Rp - Rp 226,100
8 AHSP SNI 2016 A.4.6.2.19. M2 Pemasangan 1 m2 kaca buram tebal 12 mm Rp 55,800 Rp 636,500 Rp - Rp 692,300
9 AHSP SNI 2016 A.4.6.2.20. M2 Pemasangan 1 m2 kaca cermin 5 mm Rp 34,900 Rp 170,800 Rp - Rp 205,700
2 AHSP SNI 2016 A.4.7.1.2. M2 1 m2 Pencucian bidang permukaan tembok yang pernah dicat Rp 26,600 Rp 500 Rp - Rp 27,100
5 AHSP SNI 2016 A.4.7.1.8. M2 Pelaburan 1 m2 bidang kayu dengan cat residu dan ter Rp 17,800 Rp 10,100 Rp - Rp 27,900
7 AHSP SNI 2016 A.4.7.1.11. M2 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup) Rp 13,100 Rp 12,100 Rp - Rp 25,200
XV. AHSP SNI 2016 A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
1 AHSP SNI 2016 A.5.1.1.1. Buah (K3) Pemasangan 1 buah closet duduk/monoblock Rp 784,400 Rp 1,828,500 Rp - Rp 2,612,900
2 AHSP SNI 2016 A.5.1.1.2. Buah Pemasangan 1 buah closet jongkok porselen Rp 501,100 Rp 349,900 Rp - Rp 851,000
3 AHSP SNI 2016 A.5.1.1.3. Buah Pemasangan 1 buah closet jongkok teraso Rp 501,100 Rp 359,600 Rp - Rp 860,700
4 AHSP SNI 2016 A.5.1.1.4. Buah (K3) Pemasangan 1 buah urinoir Rp 378,700 Rp 2,309,600 Rp - Rp 2,688,300
5 AHSP SNI 2016 A.5.1.1.5. Buah (K3) Pemasangan 1 buah wastafel Rp 506,000 Rp 605,100 Rp - Rp 1,111,100
6 AHSP SNI 2016 A.5.1.1.8. Buah (K3) Pemasangan 1 buah bak mandi batu bata vol 0,30 m3 Rp 1,613,300 Rp 208,500 Rp - Rp 1,821,800
7 AHSP SNI 2016 A.5.1.1.10. Buah Pemasangan 1 buah bak air fiberglass vol 1 m3 Rp 144,000 Rp 875,800 Rp - Rp 1,019,800
8 AHSP SNI 2016 A.5.1.1.14. Buah Pemasangan 1 buah floor drain Rp 22,900 Rp 17,700 Rp - Rp 40,600
9 AHSP SNI 2016 A.5.1.1.19. Buah Pemasangan 1 buah kran diameter ½” atau ¾ ” Rp 83,600 Rp 32,600 Rp - Rp 116,200
10 AHSP SNI 2016 A.5.1.1.25. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter ½” Rp 18,500 Rp 11,000 Rp - Rp 29,500
11 AHSP SNI 2016 A.5.1.1.26. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter ¾” Rp 18,500 Rp 14,300 Rp - Rp 32,800
12 AHSP SNI 2016 A.5.1.1.27. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter 1” Rp 18,500 Rp 19,100 Rp - Rp 37,600
13 AHSP SNI 2016 A.5.1.1.28. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter 1 1/2” Rp 27,800 Rp 22,000 Rp - Rp 49,800
14 AHSP SNI 2016 A.5.1.1.29. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” Rp 27,800 Rp 28,200 Rp - Rp 56,000
15 AHSP SNI 2016 A.5.1.1.30. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter 2 1/2” Rp 41,600 Rp 37,700 Rp - Rp 79,300
16 AHSP SNI 2016 A.5.1.1.31. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter 3” Rp 41,600 Rp 50,200 Rp - Rp 91,800
17 AHSP SNI 2016 A.5.1.1.32. M1 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” Rp 41,600 Rp 79,300 Rp - Rp 120,900
Harga Satuan Dasar Tenaga GA Departemen
Harga Satuan
Harga Satuan Harga Satuan Per Harga K3 Per Harga Satuan + Harga Satuan +
No. Nama Tenaga Kode Satuan PPN 10 % Dasar + K3 +
Dasar Per Hari Jam Jam K3 Per Jam K3 Per Hari
PPN 10%
(7 Jam)
I II III IV V VI = V : 7 VII VIII = VI + VII IX = VII x 7 X = IX x 10% XI = IX + X
No. Sumber Kode Unit Uraian Kode Sat. Koefisien Harga Satuan Jumlah Harga (Rp.)
Data Pekerjaan Harga (Rp.) Tenaga Bahan Alat
a b c d e f g h i j=hxi k=hxi l=hxi