ALMAGRO II - FENCE

TEMPORARY FACILITIES
Fabrication and Construction of Warehouse
EARTHWORKS
Site Clearing
Layout of Stakes and Batterboards
Excavation of Footing
Excavation of Wall Footing
STRUCTURAL WORKS
Gravel Bedding
Preparation of Rebars and Ties for Footings, Wall Footings, Columns, Horizontal and Vertical Bars
Fabrication of Rebars and Ties for Footings, Wall Footings, Columns, Horizontal and Vertical Bars
Installation of Rebars for Footings, Wall Footings, Columns and Vertical Bars
Fabrication of Forms for Footings and Columns
Installation of Forms for Footings and Columns
Concrete Pouring for Footings, Wall Footings and Columns
Removal of Forms
MASONRY WORKS
CHB Laying and Installation of Horizontal Bars
Plastering
PAINTING WORKS
Waterproofing
Application of Skimcoat (1st Coating)
Application of Skimcoat (2nd Coating)
Preparation for Painting
Application of Primer
Painting of 1st Coating
Painting of 2nd Coating
Finishing and Retouching
OTHER STEEL WORKS
Preparation and Fabrication of Tubular Steel and GI Pipe
Welding of Fence Railings
Installation of Barbed Wire
Welding of Gate Framing
Preparation for Painting
Application of Epoxy Primer
Painting of Fence Railings
Painting of Gate Framing
Finishing and Retouching
ACCESSORIES
Preparation for Painting Hardie Planks
Painting of Hardie Planks
Finishing and Retouching
Installation of Hardie Planks in Fence Railings
Installation of Hardie Planks in Gate Framing
COMMISSIONING
Punch listing