Professional Documents
Culture Documents
Roofing works
Drainage works
ARSE ABI 1
Supply and install electrical parts (thermoplastic conduit of 13.3mm, screw
Reinforced concrete type c-30 filled into from work to columns, beams and
roof slab
Provide cut, bend and fix in position reinforced steel to columns, roof slab
Supply and fix external galvanized steel (6m) and internal stainless steel
(5.5m) ladder complete with saftly cage as per design to satisfaction of the
Engineer
Supply and install external water level indicator complete with necessary
accessories
provide and fix 6mm sheet metal access cover with latch and lock for valve
paint with water proof for the wall and floor base
Provide and place single brick layer cover to protect the asphalt coat from the
backfill material
Provide and construct 400mm thick pointed stone masonry valve chamber for
inlet, outlet, overflow and drain valves as per the drawing (top slab C-25)
Compound Work
ARSE ABI 2
Install & Fix all necessary pipes & fittings with all necessary accessories
Reinforced concrete type c-30 filled into from work to columns, beams and
roof slab
Provide cut, bend and fix in position reinforced steel to columns, roof slab
Supply and fix external galvanized steel (6m) and internal stainless steel
(5.5m) ladder complete with saftly cage as per design to satisfaction of the
Engineer
Supply and install external water level indicator complete with necessary
accessories
provide and fix 6mm sheet metal access cover with latch and lock for valve
paint with water proof for the wall and floor base
Provide and place single brick layer cover to protect the asphalt coat from the
backfill material
Provide and construct 400mm thick pointed stone masonry valve chamber for
inlet, outlet, overflow and drain valves as per the drawing (top slab C-25)
Compound Work
Install & Fix all necessary pipes & fittings with all necessary accessories
ARSE ABI 3
Welding of air valve 3
Bedding 1,800m
ARSE ABI 4