This procedure applies to all COTELCO-PPALMA’s employees, staff, contractors and others
who undertake high risk work.
Definitions:
Hazardous/High Risk Work: is work that involves hazards, which must be either eliminated
or effectively controlled to ensure all risks are reduced so far as is reasonably practicable.
Permit to Work: A formal process that authorizes work considered hazardous and/or high
risk. Permits to work are written documents which authorize certain people to undertake
specific work, at the stated times and dates. The permit to work system requires the
intended work methods and risk control measures to be established, documented and
agreed to prior to the high-risk activity commencing. The permit to work system also
establishes communication and understanding between the COTELCO-PPALMA personnel
and those who are undertaking the high-risk work.
Authorized Person - A person(s) with appropriate competency, technical skill and authority
to issue Permits to Work.
Job Safety Analysis (JSA) - A method of evaluating the health and safety aspects of a job or
activity. The job/activity is broken down into steps or tasks and the health and safety
hazards/risks are identified, assessed and control measures determined. A JSA provides a
written record of the process that is going to be used to carry out a task. JSA's compliment
and inform the permit to work system. JSAs may also be called a Safe Work Method
Statement (SWMS), Work Safety Plan or Job Safety Assessment.
Roles Responsibilities
Management Management of the permit to work system at the
cooperative.
A permit to work is required when the following hazardous or high risk work is to be
carried out:
Height at work:
All work performed at heights greater than 2 metres above ground level or when
somebody may fall more than 2 metres (e.g. open penetrations). Examples include when
work:
Any activity where there is a risk of fire or smoke e.g. the activity produces flames, sparks
or heat. Examples include welding, grinding, use of heat guns. Note: Fire Indicator Panel
(FIP) /Detector Alarm Signalling Equipment (ASE) isolation may be required.
Excavation:
When the depth of the trenching or excavation works are going to exceed 450mm.
Electrical:
Powered trucks:
Where Forklifts, cranes, scissor boom lifts etc. are used in or required to do the job.
Drilling or Cutting:
If work involves drilling or cutting into buildings or facilities VU Facilities Managers need to
be consulted as a permit to work may be required. For this type of work, the asbestos
registers need to be checked and the Permit to Work must be issued by an authorised
person from the VU Facilities Department.
Validity of permit:
When the authorised person and person(s) completing the high risk activity have
both signed the permit, it becomes valid and authorises the commencement of
work within the period and time specified on the permit.
Permits are valid for a maximum of a twelve-hour period i.e. working day or shift
but may be extended by the authorised person.
If the permit is required for longer than twelve hours, the authorised person must
re-inspect the area where the high risk activity is being undertaken and re-approve
the permit at the commencement of each shift or working day. The authorised
person must endorse the extensions on the permit form.
Lost Permit
Work in progress must cease until a replacement permit has been authorised.
The authorised person shall, in conjunction with the permit holder and supervisor
(where relevant):
a. Identify all lock out /tag out devices (e.g. energy isolating devices, danger
- do not operate tags) associated with the lost permit,
b. Thoroughly inspect the isolated plant/area,
c. Issue a new permit,
d. Arrange where possible, to have all of the personnel who had previously
signed the lost permit, sign the new permit. A notation must be
recorded on the new permit to indicate that the above steps have been
undertaken.