JOB TITLE / AIM: Scaffolding erection and dismantling in Process area


JSA DATE: 16/03/2007 JSA NO./ REVISION:
SUPERVISOR/ JSA LEADER: Haji Aziz SCRIBE: ABDULLAH
PARTICIPANTS: Ashiq, Rabnawaz,
LIST ASSOCIATED PROCEDURES/WORK INSTRUCTIONS OR TEMPORARY WIs:
Attach copies of any relevant documentation/ drawings.
Part 2: Job Safety Analysis
Job Steps: List the main sequential steps. each step should accomplish a specific component of the task.

1.Mobilization of equipment and materials


2.Manual hauling of materials
3.Erection of scaffolding
4.Dismentling of scaffolding
5.Demobilization

Alternatives Considered: What are other possible means of achieving the job outcome?
Above ground cable tray.

Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the HSE personnel is the first response in case of
emergency

Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 . Mobilization of equipment and Unauthorised equipment/tools brought out Before mobilizing any equipment/tools make
materials to site sure that the materials got inspected
Ensure that Scaffold material shall be color
coded prior to mobilization..
Ensure that all personnel prior to start the
have been inducted and oriented about the
hazard in the job site.
Workers starting the job unfit to work All personnel must undergone fitness
certificate from the Del doctor. not fit to work
shall not be allowed to work at the project
site.
Ensure all the persons take part in the tool
box meeting discussion. JSA was discussed
to workers and signed at the back & work
permit is in placed and discussed
Hand Injury Ensure proper hauling of materials/get help if
required/Wear hand gloves.
Exposure of workers to various hazard like Ensure workers are complying with the min.
hand injury, dust, eye injury PPE req..Safety shoes, helmet, safety glass,
dust mask,

2. Manual hauling of Exposure of workers to various hazard like Ensure workers are complying with the min. PPE
materials hand injury, dust, eye injury req..Safety shoes, helmet, safety glass, HI
Visibility vest shall not be worn during all the
activity.
Heat Stress/Exhaustion Ensure potable water/sufficient shelter is available
each area where workers are doing the job. ORS
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
is available at the area
Back injury Workers will be oriented about the proper posture
and positioning during the execution of the job.
Unskilled and uninducted personnel starting Ensure that toolbox meeting was regularly
the job conducted and people are aware of the job and the
hazard enclosed in the job they are performing.
JSA was discussed and signed at the back’
Workers must wear Red ID cards at all times.
Personnel and equipment interface Ensure that during unloading of materials it will
be unloaded at the safe side not in traffic side. A
watchman must be available during unloading
area shall be barricaded.
Fall of materials to worker
Materials should not be thrown down during
unloading instead there will be two person at the
trolley and three person shall stand down
Hand injury receiving the rebars at a time and place at the
ground.
Ensure workers are wearing the hand gloves

Trips Ensure materials are properly staged

3. Erection of scaffolding Fall of Workers or Materials Ensure workers are wearing appropriate full body
harness and tie-off 100% on yellow tag
scaffolding. No one should access a scaffold if
there is a red tag or no tag. Works on scaffold
must be supervised at all times. No equipment
andtools will be stored on the scaffold. All
persons working on scaffold must be trained on
working at heights and use of harnesses. All
harness must be checked daily by a competent
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
person and inspected monthly and logged. NO
workers should alter the scaffolding Ensure that
no tools or materials will be stored at the working
platform Ensure that no throwing of materials at
elevated area Ensure that area was secured and
barricaded Ensure that the scaffold is approved
inspected by BHPB person prior to used and
tagged
Back injury Ensure workers properly inducted about the
proper positioning Ensure workers are complying
with the min. PPE req..Safety shoes, helmet,
safety glass, dust mask, Ensure workers have
provided water and proper shade.

Heat Stress/Exhaustion Ensure potable water/sufficient shelter is available


each area where workers are doing thejob. First
aid kit available at site. Water collers should be
sealed and signed by water handler and should be
filled from UV Filter source located at del camp.
4 Dismantling of Fall of Workers or Materials Ensure workers are wearing appropriate full body
scaffolding harness and tie-off 100% on yellow tag
Scaffolding. No one should access a scaffold if
there is a red tag or no tag. Works on scaffold
must be supervised at all times. No equipment and
tools will be stored on the scaffold. All persons
working on scaffold must be trained on working
at heights and use of harnesses. All harness must
be checked daily by a competent person and
inspected monthly and logged. NO workers
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
should alter the scaffolding Ensure that no tools or
materials will be stored at the working platform
Ensure that no throwing of materials at elevated
area Ensure that area was secured and barricaded
Ensure that the scaffold is approved inspected by
BHPB person prior to used and tagged
Ensure workers properly inducted about the
Back injury proper positioning Ensure workers are complying
with the min. PPE req..Safety shoes, helmet,
safety glass, dust mask, Ensure workers have
provided water and proper shade.

Heat Stress/Exhaustion Ensure potable water/sufficient shelter is available


each area where workers are doing the job. First
aid kit available at site. Water collars should be
sealed and signed by water handler and should be
filled from UV Filter source located at del camp.
5 Demobilization Poor house keeping Ensure that the area is left clean and tidy after
finishing the job.