Professional Documents
Culture Documents
PROJECT NAME:……………………………………………………………………………
ELEMENT 5.19.3
JOB SAFETY PRACTICES
Poor heavy inside store Maintain proper housekeeping inside store to avoid any injury
Provide sufficient drinking water and scheduled breaks.
High ambient temperature
Drinking containers shall be protected from direct exposure from the sun
during walking towards
Provision of rest shelter area if outside the building.
store
Provide shuttle vehicle to drop and pick from store
Work Supervisor obtaining Work Permit and SWP before the start of material
Congestion due to other
delivery and crane positioning.
ground activity
Safety signage shall be posted to communicate the hazards and activity
Struck by maneuvering Provide flagman and spotter to guide the trailer operator when maneuvering for
heavy equipment its position
Trailer blind spot Trained Flagman/spotter guiding the crane/trailer when going into work location
Positioning of crane and Inexperienced or untrained Verification of Crane Operator’s 3rd party certification and Trailer Drivers driving
6 trailer in preparation for operator license before allowing them to enter the site.
lifting activity
Supervisor/Foreman with the Crane/Trailer operator making walkthrough of the
Site access limitation
access and work area before entering site.
Responsible Engineer and his Supervisor/ Foreman inspection of exclusion
Soft ground /Uncompact fill
zone/staging area for compaction and level of the ground.
Overhead/Nearby Barricading the exclusion zone/ working radius once crane and trailer are in
obstructions position
Struck into adjacent Barricade the working area around the trailer and crane to prevent unnecessary
structures or worker workers to enter the area
7 Installation / Lifting of Unavailability of approved Lifting plan shall be prepare and approved prior to erection of transformer, etc.
Capacitor Banks lifting plan for critical lifting Appropriate size / capacity of the equipment should be mobilized as per the lifting
works (erection of plan
transformer, etc.) Site engineer and the rigging supervisor should discuss the approve lifting plan to
the operator and rigger prior to lifting works
Safety personnel should check and verify the approve lifting plan
Lifting plan shall be made and prepare by the competent and certified rigging
supervisor.
Closed supervision is required from the engineers, supervisor / foreman and
safety personnel during the erection
Closed coordination with SEC / NG site engineers during preparation and
erection
Approved lifting plan must be readily available at site for immediate reference
Refer to equipment manual for correct operation
Continuous safety training and awareness related to lifting operation
To provide proper and sufficient anchorage point / lifeline
Only use approve materials for anchorage point / lifeline
Approve design and calculation for anchorage point must be secured
In-charge supervisor and foreman shall check and verify the availability of the
The workers in elevated anchorage point / lifeline.
areas have no anchorage
Anchorage point / lifeline must be install by the competent person
point or lifeline during the
To comply with 100% tie-off
installation capacitor bank
shade. Provision of retractable lifeline
Continuous safety training and awareness related to working at heights
Civil engineer should conduct pre-inspection in the area before the lifting works
Anchorage point lifeline shall cater the suspended load, minimum strength of 22
KN for free fall
Periodical inspection or color coding for all lifting gears
Rigger performing the regular inspection for all lifting gears
Lifting gears (shackles, sling Tagging system or marking for faulty lifting gears
belt, leg chain, chain blocks,
Only certified rigging inspector are allowed for the inspection
___, etc.) used for the
All lifting gears must be inspected by the third parties
erection of transformer, etc.
has no inspection All lifting gears rated capacity / SWL must be available or clearly visible
All lifting gears must be properly stored, handled and labelled in the storage area
Quarantine box for all damage / defective lifting gears
Ground must be stable, leveled, firm and compacted
Out rigger must be fully extended on a stable and flat even ground
Poor set-up of lifting Appropriate and sufficient size of outrigger pads must be provided
equipment (mobile crane, Site engineer should make an assessment and conform the stability of the ground
___, etc.) on an uneven and Consider to provide spare pads or steel plates
lose ground surface. Crane operator shall evaluate the ground if capable to withstand the equipment
and the load
Conduct pre-planning on which crane will be positioned
The heavy equipment Heavy equipment used on the site shall have a valid third party certification
(mobile crane, boom truck, Operator conduct pre-inspection of the equipment and checking of documents
____, etc.) used for the Supervisor check and verify the certification
erection of transformer, etc. Ensure to lease heavy equipment with valid certification must be from establish
has no valid certification. company
Third party certification must be from the accredited and approve company
Daily verification of equipment documents from the safety personnel
Administration personnel should process the renewal before the expiration date
Heavy equipment must have valid registration and insurance
Operator on the site shall have a valid third party certification
Operator conduct daily checking of documents
The operator of heavy Supervisor should check and verify the certification
equipment (mobile crane, Supplied heavy equipment operator must be from establish and approve
boom truck____, etc.) used company
for lifting works has no valid Third party certification must be from the accredited and approve company
certification. All heavy equipment operator must have valid Saudi Driving license
Daily verification of equipment documents from the safety personnel
Administration personnel should process the renewal before the expiration date
Periodical maintenance for all heavy equipment
Operator conduct pre-inspection of the equipment and complete the checklist
Used of defective heavy
Ensure that only heavy equipment with good and satisfactory condition used at
equipment (mobile crane,
site
boom truck,____, etc.) for
All heavy equipment should send to workshop for proper maintenance
the erection of transformer,
etc. Immediate repair / replacement for any comments / issues in the equipment
checklist
Ensure sufficient stocks of equipment spare parts
Provide rigger with proper identification (different color of helmet, reflective vest,
etc.)
Ensure the competency level of operator and rigger regarding the international
communication- hand signal
No assigned certified rigger Supervisor and equipment operator should not allow any lifting works without the
for the lifting works and rigger
erection of transformer, etc. Ensure that the rigger has valid certification
Consider the rigger level (I, II, III) when obtaining the rigger certification
Rigger certification must be from the accredited and recognized company
Mobilized supplemental certified rigger if there’s a blind spot during lifting works
Continuous safety training and awareness related to the lifting operation
The worker / rigger in To provide proper and sufficient anchorage point / lifeline
elevated areas has no Only use approve materials for anchorage point / lifeline
anchorage point or lifeline Approve design and calculation for anchorage point must be secured
during the installation of In-charge supervisor and foreman shall check and verify the availability of the
transformer accessories anchorage point / lifeline.
To provide good and inspected scaffolding platform.
Civil engineer should conduct pre-inspection in the area before the lifting works
Anchorage point lifeline shall cater the suspended load, minimum strength of 22
KN for free fall
Unattended unsafe parking Mobile equipment shall properly parked on a designated equipment laydown
Unsecured electrical
equipment, energized
Electrical equipment shall be properly secured, distribution board closed and
padlocked
equipment