Jaigad R.R. Water Supply Scheme. (Stage II, Part - I) Tal & Dist. Ratnagiri.

Raising height of Kalzondi Dam, J


Sl.
PREV. Qty Present Qty. UPTO date Qty.
No.
1.000
1.010 8258.88

8258.88

1.020 0 1264.556521 1264.56

1.030 3368.15 3368.15

1.040 0 0.00

1.050 0 0.00

1.060 0.75 0.75

1.070 0 0.00

1.080 1870.5 1870.50

1.090 0 561 561.15


1.100 0 0.00

1.110 0 0.00
1.120 0 0.00

1.121 0 0.00

1.122 0 2247.48 2247.48

1.130 0.00

1.140 0 0.00

1.150 0 32.67 32.67

1.160 0 0.00

1.161 0 0.00
1.162 0 0.00
1.170 0 0.00

1.180 0 0.00

1.190 0 0.00

1.200 0 0.00

1.210 0 0.00

1.220 0 0.00

1.230 0 0.00

1.240 0 0.00

1.250 0 0.00
1.260 0 0.00
1.270 0 0.00

1.280 0 0.00

2.000 0 0.00
2.010 0 0.00

2.020 0 0.00

2.030 0 0.00

2.040 0 0.00

2.050 0 0.00

2.060 0 0.00

2.070 0 0.00
2.080 0 0.00
2.090 0 0.00

2.100 0 0.00

2.110 0 0.00

2.120 0 0.00

2.130 0 0.00

2.140 0 0.00

2.150 0 0.00
2.151 0 0.00
2.152 0 0.00
2.153 0 0.00
2.154 0 0.00
2.155 0 0.00
2.156 0 0.00
3.010 717.2 717.20

3.020 88 88.00
3.030 1 1.00

3.040 14.8834 14.88

3.050 111.896 111.90

3.060 0 0.00

3.070 0 0.00

3.080 0 0.00

3.090 0 0.00

3.091 0 0.00
3.092 0 0.00
3.100 0 0.00
3.110 0 0.00

3.120 0 0.00

3.130 0 0.00

3.140 0 0.00
3.150 0 0.00

3.160 0 0.00

3.170 0 0.00

3.180 0 0.00

3.190 0 0.00

3.200 0 0.00
3.201 0 1 1.00
3.202 0 1 1.00
3.203 0 0.00
3.204 0 1 1.00
3.205 0 1 1.00
3.206 0 0.00
3.207 0 1 1.00
3.208 0 1 1.00
3.209 0 1 1.00
3.210 0 1 1.00
4.000 0 0.00
4.010 0 0.00

4.020 0 0.00

4.030 0 0.00
4.040 0 0.00

4.050 0 0.00

4.060 0 0.00

4.070 0 0.00

4.080 0 0.00

4.090 0 0.00

4.100 0 0.00

4.110 0 0.00
4.111 0 0.00

4.112 0 0.00
4.113 0 0.00
4.114 0 0.00
4.115 0 0.00
4.116 0 0.00
4.117 0 0.00

Rs. In Words :
ABSTRACT OF WORK DONE
ge II, Part - I) Tal & Dist. Ratnagiri. Raising height of Kalzondi Dam, Jacketing & Grouting, Diversion Varawade Kalzond
Road, and Construction of Bridges & C.D. Works for road.
Item Description Tender Rate

Rising height of Kalzondi Dam.


Excavation in hard murum including boulders upt 0.6m dia.m. (0.113 Cum) for canal, 109.64
seating of embankment, filter drain / catch water drain etc. and placing the
excavated material neatly in dump area or for formation of service road as directed
including cost of all materials, machinery, labour, dressing bed and sides to required
level and profile etc. complete with lead upto 1.0 Km and 6 M lift.

Excavation in hard rockof all toughness by breaker including boulders above 0.6 M 530.55
dia. (0.113 cum) minimizing damage to side slopes of excavation and placing the
excavated rock neatly in approved dump area as directed including cost of all
materials, machinery, labour, leveling bed etc. complete with lead upto 1.0 Km and
lift upto 6 M.

Providing, constructing coffer dam in river basin/dam storages as per type design 682.00
including excavation, filling, the middle portion with B. C. soil (in gunny bags if
required) Providing impervious/ semiprevious materials on both side of B.C. Soil (in
gunny bags if required) including ramming, compacting to the satisfaction of
Engineer-in-charge, till the completion of work including dismantling coffer dam after
completion of works and disposing off the materials as directed by the Engineer-in-
charge.

Dismantling the stone masonary in cement morter including stacking the material as 223.92
directed with 15 M lead and 1.5 M lift etc. complete.
Dismantling the old lime concrete or cement concrete including stacking the 269.77
materials as directed with 15 M lead and 1.5 M lift etc. complete.
Dewatering the excavated trenches and pools of water in the building 6,375,600.00
trenches/pipeline trenches, well works by using pumps and other devices including
disposing off water to safe distance as directed by Engineer-incharge (including cost
of macheniery, labour, fuel) etc. complete.
Drilling 40 mm dia holes in masonry or concrete structure with providing and fixing 871.00
0.5 M long G.I. Pipe line for pressure grouting including all Material, labour cost and
machinery charges, etc. complete.
Drilling 32 mm dia. grout holes in concrete/rock by per cusion dirlling using jack 400.31
hammer as directed to speficifed depth for consolidation / contact grouting including
cost of all materials, machinery, labour, cleaning holes, venteliation, lightening,
drainage and all other ancillary operation etc. complete

Grouting cement slurry in grout holes under specified pressure for consolidation/ 10,585.71
contact grouting including cost of all materials, machinery, labour, re-drilling
whereever necessary, ventilation, lightening, drinage and other ancillary operations
etc. complete with lead upto 1.0 Km and all lifts.
Taking trial bores for detailed investigation with NX diamond drill double tube in all
sorts of soils like soft murum, hard murum and boulders including all materials such
as casing pipes, accessiories, grease, steel balsams and other such materials and
or as required including conveying such materials and machinery to site of works
preserving these loose sample in glass / plastic jars and core samples serially
numbered at site of work and conveying the same to the headquarter of concerned
office as directed and submission of detailed bore log sheet complete as directed by
Engineer in Charge.

Hard rock other than quartizite. 3,902.64


Carring out water intake test / permeability test at any stage or depth as may be 726.14
directed by Engineer in Charge by filling the bore hole with water or air at specific
pressure of specified limit as and where directed etc. complete.
A) Providing and laying in situ C.C. of grade M-15 of trap /trap/ granite/ gneiss/ 6,527.67
quartzite graded metal for foundation and grading with Batching Plant and Transit
Mixure (compacting curing etc. complete with an initial leads of 50 M and lift of 1.5 M
(40 MSA)
B) Providing and laying in situ C.C. of grade M-20 of trap / granite / gneiss / quartzite 7,242.92
/ graded metal for RCC work of gallery, sluice, spill way crest, spill way down stream
test, energy dissipting structures, intact structure, training walls, pears, abutments,
slab etc. with batching plant and transist Mixutre including shuttering and
scapffolding compacting, curring etc. complete with and intial lead of 50M and lift of
1.5 M. (40 M.S.A.)

Providing and laying in situ C.C. of grade M-20 of trap / granite / gneiss / quartzite / 7,138.51
graded metal for RCC work of gallery, sluice, spill way crest, spill way down stream
test, energy dissipting structures, intact structure, training walls, pears, abutments,
slab etc. with batching plant and transist Mixutre including shuttering and
scapffolding compacting, curring etc. complete with and intial lead of 50M and lift of
1.5 M. (20 M.S.A.)

Providing and fixing of BITUFLEX CLOSE CELL FOAM of size 30 mm x 30 mm in 2,190.00


double layer in the expansion joints in R.C.C. framed structure (at floor level / at
terrace level / interior columns) for overlapping of closed cell foam joints, applying
TP-40 PRIMER on both the sides of concrete surface, filling the 25 mm x 25 mm
gap with the POLYDEE-41 highly flexible sealant and covering the joint with
Polydee-LM, 150 mm width in 2 coats etc. complete.

Providing and fixing in position steel bar reinforecement of various diameters for 73,502.00
RCC piles, caps, footings, foundations, slabs, beams, columns, canopies, staircase,
newels, chajjas, lintels, pardies, copings, fins, arches, etc. as per detailed designs,
drawings and schedules, including cutting, bendings, hooking the bars, binding with
wires or tack welding and supporting as required etc. complete.(Including cost of
Binding wire)

Providing and laying salt glazed stone ware pipe of following diameter including fiting
such as bends, tees, single, junction, double junction, laying, jointing including
excavation and refilling trenches complete.
a) 150 mm diametere 394.00
b) 225 mm diametere 433.00
Providing and laying sand bedding behind the abutement, returns, wings or walls for 3,630.49
filter including compacting and dressing etc.
Providing and laying metal below revetment from rubble stone of approved quality 1,528.19
from borrow area to the specific thikness of 10 cm includng hand packing ramming
etc. complete with all leads and lifts.
Providing and fixing 80 mm diameter A.C/P.V.C. pipes, weep holes at 1.5 M c/c 201.00
staggered including cost of all materials and labour involved with all leads and lifts
etc.complete.
Providing casing embankment using selected pervious material from approved 172.15
borrow areas in layers including cost of all materials, machiniery, labour all other
operations such as collection of soil, spreading soil in layer of specified thickness,
sorting out, breaking clods, levelling sectioning edges / sides watering, compacting
each layer to density control of not less than 95 percent or as stipulated using
vibratory compactor etc. complete with lead upto 1 Km and 6 M lift.

Providing and supplying ISI mark C.I. S/S pipe (push on joints pressure pipes of 4,961.00
following class and diameters confirming to the I. S. specification inclusive cost of
jointing materials (Rubber gasket of EPDM Quality) excluding GST levied by GOI &
GOM in all respect including Third party inspection charges of TPI Agency approved
by MJP including Transit insurance, Railway Freight, Unloading from railway wagon,
Loading into Truck, Transportation to departmental store, unloading, stacking etc.
completed as directed by Engineer in charge (IS 1536/2001 for pipes and IS
158/1969 and IS 12820/ 1989 or latest edition/ revision with amendments for Rubber
Gaskets. (IS-1536 / 2001)
(Suitable for Tyton / Pig lead joints)

Lowering, laying and jointing CI 'B' Class connecting mains with rubber gaskets 284.00
including transportation of pipes from store to site of works, cost of jointing materials,
cost of rubber gasket with all leads and lifts etc. complete
Providing double flange sluice valve confirming for IS-14846 including worn gear 36,471.00
arrangements as per test pressure, stainless steel spindle, caps, including
inspection charges, transportation upto departmental store, unloading, stacking
excluding GST levied by GOI & GOM in all respect etc. complete.

Lowering, laying and jointing in position following CID/F Reflux valves, Butterfly 5,019.00
valves and Sluice valces including cost of all labour jointing material, including nut
bolts and giving satisfactory hydraulic testing etc. (Rate for all class of valves.)

Giving satisfactory hydrolic testing of following CID./F Sluice valves. 558.00


Providing and supplying ISI standard CI flanged / S& S specials excluding GST 73.00
levied by GOI & GOM in all respect including railway freight, insurance, unloading
from railway wagon, loading into truck transport to departmental store, unloading
stacking etc. complete) (Rate as per R.A. No. 24) (300 mm dia. D/F. Specials.)
Providing structural steel work in rolled sections like joints, channels, angles, tees, 74,618.00
etc. as per detailed designs and drawings including fising in position without
connecting plates, braces, etc. and one coat of anticorrosive paint and over it two
coats of oil painting of approved quality & shade, etc. complete.

Dismantling dead pipe line of C.I. pipe including cost of necessary excavation & 274.00
refilling of trenches, breaking the joints, lifting the pipes and stacking to the place as
directed by Engineer-in-charge with all leads and lifts including cleaning the surface,
etc. complete.
Diversion of Varavade Kalzondi Road Due to Raising Height of Dam
Excavation for catch / side water gutter in all sorts of soils to the specified section 104.00
including stacking the excavated stuff in a regular bund and disposing of unsuitable
or excess stuff as directed all sorts of soils.
Excavation for catch / side water gutters in Hard rock strata to the specified section 1,208.00
including stacking the excavated stuff in a regular bund by chiselling and wedging
and disposing of unsuitable or excess stuff as directed.
Providing earth work in embankment with approved materials obtained from 421.05
departmental land upto lead of 50m. including all lifts, laying in layers of 20cm. to
30cm. thickness breaking clods, dressing to the required lines, curves, grades &
section, watering and compaction with vibratory roller to achieve not less than 97 %
of standard proctor density etc. complete.
(Material obtained from departmental Land)

Providing, laying, spreading and compacting stone aggregates of specific sizes to 2,760.90
water bound macadam specification including spreading in uniform thickness, hand
packing to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering
and compacting with Intelligent Compactor with compaction analyzer and V-Sat
attachment. to the required density. Grading I (Using Screening Type A (13.2) mm
Aggregate)

Providing, laying, spreading and compacting stone aggregates of specific sizes to 2,822.65
water bound macadam specification including spreading in uniform thickness, hand
packing to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering
and compacting with Intelligent Compactor with compaction analyzer and V-Sat
attachment. to the required density. Grading II (Using Screening Type B (11.2 mm)
Aggregate)

Supplying hard murum/ kankar at the road site, including conveying and stacking 615.05
complete.
Spreading hard murum for side width etc. complete 74.00
Compacting the hard murum side widths including laying in layers on each side with 19.00
power roller including artificial watering etc. complete.
Providing and constructing 50 mm. thick Modified Penetration Macadam (MPM) 272.85
road surface including all mataerials, preparing the existing road surface, spreading
40mm. stone metal layers 30% crusher broken metal + 70% Hand broken (by
breaking rubble obtained by blasting) heating and spraying the bitumen of VG-30
grade @ 1.75 kg/sqm, spreading 12mm.size chips compacting with static roller
having weight 8 to 10 MT. to achive the desired degree of compaction as per
Technical Specification Clause 506 etc. complete.

Open Graded Premix Surfacing- Providing and Laying OGC 20 mm thickness 202.75
composed of 13.2 mm to 5.6 mm aggregates premixed with bituminous binder
transported to site with VTS , laid over a previously prepared surface, finished to the
required grade, level, alignment, and rolling to achieve the desired compaction VG-
30 Bitumen, including providing and laying seal coat sealing voids in a bituminious
surface laid to the specified level and cross fall using Type A seal coat but excluding
prime / tack coat. For Bitumen VG-30 bulk--USING drum mix type hot mix plant with
SCADA, Paver and Vibratory roller
With plastic

Providing bituminous Type A liquid seal coat on bituminous surface including 80.10
supplying all materials and bitumen of specified grade preparing existing road
surface, heating and applying bitumen @ 0.98 KgSqm. by mechanical means,
spreading chips and rolling, by static roller having weight 8 to 10 MT. etc. complete.
(VG-30 bulk bitumen rates are considered to arrive at rates)

Providing and fixing R.C.C. 1:2:4 ordinary km. stones including painting numbering 2,970.00
etc. complete for N.H./ S.H./ M.D.R. etc. as per IRC design for highway km stone
and fixing in standard size C.C. 1:4:8 block etc. complete.
Providing and fixing R.C.C. 200 metre stones as per I.R.C. standard including fixing 969.00
in standard size C.C.1:4:8 block including curing, painting lettering etc. complete.

Providing and fixing M-15 R.C.C. guard stone/ indicator stones/ boundary stones of 885.00
standard size and shape including fixing in C.C. 1:4:8 and white washing etc.
complete.
Payement of testing charges if contractor produced authorised results
A)Pentration, S.P.,F.F.,Sp.Gr. 3,135.00
B) Impact crushing value,Water absorption specific gravity 2,600.00
C) Gradiation 690.00
D) F.I.& E.I 850.00
E) Abrasion 1,170.00
F) Binder content ( Extraction ) 1,595.00
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum 225.00
including shoring and strutting as necessary and disposing off excavated stuff as
directed etc. complete.
Excavation for foundation in hard rock by blasting including shoring and strutting as 1,168.00
necessary and disposing off excavated stuff as directed etc. complete.
Dewatering in perinnial River or stream including diversion of stream providing 28,950.00
cofferdam, bunds etc. as may be necessary for foundation and other parts of work
and bailing out and pumping out water below the actual initial natural water level for
start of that particular component till completion of bridge etc. Complete.
A) For Abutments

Providing and laying in situ / ready mix cement concrete of M15 proportion with trap 7,693.35
metal in foundation including necessary form work, compacting and curing etc.
complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer))
with SCADA with Natural / VSI standard Artificial Sand)
Providing and laying in situ / ready mix M-20 plain cement concrete of trap metal for 9,393.80
cast in citu piers, abutment, returns, wings etc. including provision of "V" shaped
false joints to form suitable panels on the faces to approve design with compacting
by vibrating and curing complete, including plywood/steel form work centering
( excluding dewatering by means of pump) and including bailling out water and
curing finishing in CM 1:3 etc. complete. as directed by engineer in charge basic
rate shall be increased for height above 5.00 m in followinh manners

Providing and laying in situ / ready mix controlled M-25 cement concrete of of trap 9,876.90
metal for reinforced cement concrete caps over piers and abutments including
necessary sacffolding plywood/steel formwork, compacting by vibrating, finishing in
CM 1:3 and curing etc complete (Excluding reinforcement)

Providing and laying in situ / ready mix M25 controlled cement concrete of trap metal 11,988.75
for RCC work in solid/ deck slab etc. including ramming, vibrating, curing, formwork,
centering and finishing in cement plaster excluding reinforcement etc. complete.
(height up to 4 meter with fully automatic micro processor based PLC with SCADA
enabled concrete batch mix plant / pan mixer with Natural / VSI standard Artificial
Sand)

Providing and laying in situ / ready mix M 25 RCC of trap metal for RCC work of 11,361.90
ballast walls, kerbs and box returns including scaffolding, compaction, formwork
finishing and curing etc. complete. (excluding reinforcement, with fully automatic
micro processor based PLC with SCADA enabled concrete batch mix plant / pan
mixer with Natural / VSI standard Artificial Sand)

Providing and cutting bending, hooking, laying in position and tying HCRM/ CRS for
reinforcement as per detailed drawings for R.C.C. work.
A) Sub Structure 69,033.00
B) Super structure 69,033.00
Providing tar paper bearing including laying in proper position etc. complete. 92.00
Providing expansion joints with 25mm thick bituminous pad as per detailed drawings 993.00
etc. complete.
Providing 100mm diameter GI water spouts as per detailed drawings in RCC slab 988.00
and wearing surface / kerb etc. complete.
Providing and laying weep holes of 100 mm diameter AC/PVC pipes as per drawing 482.00
for abutment returns, return walls etc. Complete.
Back filling behind abutment, wing wall and return wall as per drawings and technical 867.05
specifications etc. complete. (by granular material)
Providing and laying 0.90 meter thick metal mat consisting of rubble, oversize metal 1,593.05
and normal size metal in specified thickness as per detailed drawing including
supplying all materials, hand packing of rubble, spreading metal in layers and hard
murum including watering and compaction with power roller etc. complete.

Providing selected hard murum filling including laying in layers of 15 to 20cm with 216.00
watering and compacting etc. complete.(Only labour charges )
Providing and laying in situ / ready mix M 25 CC of trap metal for wearing course 13,039.10
8cm thick including compacting, finishing, curing and filling in joints with bitumen etc.
complete. (with fully automatic micro processor based PLC with SCADA enabled
concrete batch mix plant / pan mixer with Natural / VSI standard Artificial Sand)

Providing RCC railing of cast in situ / ready mix RCC posts with M20 CC of trap 2,089.00
metal for horizontal and vertical members as per detailed drawings including
reinforcement, scaffolding, centering, formwork, compaction, finishing and curing
with watering chemical compound etc. complete. (fully automatic micro processor
based PLC with SCADA enabled with reversible drum type mixer/ concrete batch
mix plant (pan mixer) )

Providing and fixing 90 cm x 60 cm Marble plate engraving 10 cm. height letter, 7,356.00
figures including painting the lefters/figures with approved colour and shade
complete.
Payment of testing charges if contractor produced authorised results
1) Basic test of Cement 3,770.00
2) Fineness Modulus (Sieve analysis) Silt & Clay Content 1,380.00
3) Chloride & Sulphate Content L/S approach 795.00
4) Sieve analysis 690.00
5) Water Absorption Impact & crushing value 2,600.00
6) Abrasion 1,170.00
7) Flakiness & Elongation Index 850.00
8) Wt. per meter Ultimate tensile stress, Yield stresss & Elongation test 1,595.00
9) Conc. Mix design 13,755.00
10) Compressive strength 2,495.00
Consruction of C.D. Works For Road
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum 225.00
including shoring and strutting as necessary and disposing off excavated stuff as
directed etc. complete.
Excavation for foundation in hard rock by blasting including shoring and strutting as 1,168.00
necessary and disposing off excavated stuff as directed etc. complete.

Providing and laying in situ / ready mix cement concrete of M10 proportion with trap/ 7,693.35
granite/ quartzite/ gneiss metal in foundation including necessary form work,
compacting and curing etc. complete. (with reversible drum type mixer/ concrete
batch mix plant (pan mixer)) with SCADA with Natural / VSI standard Artificial Sand)
Providing and casting in situ / ready mix PCC M20 grade of trap metal for coping to 11,148.80
head walls / parapet including centering, form work, compaction and curing etc.
complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer)
with SCADA with Natural / VSI standard Artificial Sand)
Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 900mm 8,233.00
diameter in proper line, level and slope including providing and fixing collars in
cement mortar 1:2 and curing etc. complete.
Providing selected hard murum filling including laying in layers of 15 to 20cmwith 216.00
watering and compacting etc. complete.
Scarifying the existing granular road surface to a depth of 50 mm and disposal of 44.00
scarified material within all lifts and leads upto 1000 metres.
Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm 1,514.05
thick including hand packing and compacting etc. complete.
Providing, laying, spreading and compacting stone aggregates of specific sizes to 2,760.90
water bound macadam specification including spreading in uniform thickness, hand
packing to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering
and compacting ?with Intelligent Compactor with compaction analyzer and V-Sat
attachment.to the required density. Grading I (Using Screening Type B (11.2 mm)
Aggregate)

Construction of granular sub-base by providing close graded Material, mixing in a 2,822.65


mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in
uniform layers with motor grader / Paver on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete as per clause 401 --
Plant Mix Method and Grading - II Material

Payement of testing charges if contractor produced authorised results


Cement ( Standard Consistancy, Fineness, Sp. Grav., Sett time, Comp stren, 3,770.00
Soundness)
Metal (WA, Sp Grav, Impact, Crush Value,) 2,600.00
Seive Analysis 690.00
Flakiness & elongation 850.00
Abrasion 1,170.00
Sand ( Fineness Modu, Silt & clay content) 1,380.00
C C Cube (Comp. Strength) 690.00
DONE
ion Varawade Kalzondi AMOUNT
Units Remarks
PREV Upto Date

Cum 905,504.12

Cum 670,910.46

Cum 2,297,078.30

Cum -

Cum -

Job (Lum 4,781,700.00


Sum)
55.825/BHP

Rmt -

Rmt 748,779.86

M.T. 5,940,171.17
-

Rmt -
Test -

Cum -

Cum 16,278,333.91

Cum -

Rmt -

M.T. 2,401,315.62

Rmt -
Rmt -
Cum -

Cum -

Rmt -

Cum -

Rmt -

Rmt -

No. -

No. -

No. -
Kg. -
M.T. -

Rmt -

-
Cum -

Cum -

Cum -

Cum -

Cum -

Cum -

Cum -
Sqm -
Sqm -

Sqm -

Sqm -

Nos. -

Nos. -

Nos. -

-
Nos. -
Nos. -
Nos. -
Nos. -
Nos. -
Nos. -
Cum 161,370.00

Cum 102,784.00
Job (L/s) 28,950.00

Cum 114,503.21

Cum 1,051,128.64

Cum -

Cum -

Cum -

M.T. -
M.T. -
Sqm -
Sqm -

Nos. -

Rmt -

Cum -
Sqm

Cum

Sqm

Rmt

No.

Nos.
No.
No.
Nos.
No.
No.
No.
No.
No.
Nos.

Cum

Cum

Cum
Cum

Rmt

Cum

Sqm

Cum

Cum

Cum

No.

No.
Nos.
Nos.
Nos.
No.
Nos.

TOTAL 35,482,529.28
Add 1.06% above 376,114.81
TOTAL 35,858,644.09
1 Constructi item1 10 1 Nos

1.01 Supplying,item1 123.223 Nos

1.02 Constructi item2 213 Nos


Raising height of Kalzondi Dam.
drain / catch water drain etc. and placing the excavated material neatly in dump area or for formation of serv
directed including cost of all materials, machinery, labour, dressing bed and sides to required level and pro

Avg.Exc Bottom Top width Mean


Chainage Avg.GL Depth M Area(sqm)
avation width M M area(sqm)
RL
Upstream non-over flow section
RHS (Ch. 0 at RHS End)
0 105.5 94.249 11.251 3.7 9.33 73.27
62.30
5 102.6 94.139 8.461 3.95 8.18 51.32
50.12
10 102.03 94.209 7.821 4.3 8.21 48.92
47.56
15 101.74 94.064 7.676 4.1 7.94 46.20
44.69
20 101.5 94.209 7.291 4.1 7.75 43.18
37.23
25 100.68 94.484 6.196 3.5 6.60 31.28
37.31
30 100.06 92.255 7.805 3.6 7.50 43.33
39.94
35 99.6 92.265 7.335 3.15 6.82 36.56
34.65
40 99.1 92.285 6.815 3.1 6.51 32.74
34.94
45 98.82 92.24 6.58 4 7.29 37.14
35.28
50 98.31 92.42 5.89 4.2 7.15 33.41
62.06
55 97.8 85.5 12.3 4.3 10.45 90.71
78.39
58 94.576 84.402 10.174 3.95 9.04 66.07
Upstream over flow section (Ch 0 starts at junction of
NOF &OF Section)
0 94.576 84.402 10.174 4.3 9.39 69.63
58.59
5 92.426 84.580 7.846 4.1 8.02 47.56
45.57
10 91.796 84.453 7.343 4.1 7.77 43.58
40.11
15 91.436 84.453 6.983 3.5 6.99 36.63
35.98
20 90.996 84.298 6.698 3.6 6.95 35.33
35.09
25 90.916 83.834 7.082 3.15 6.69 34.85
34.99
30 90.641 83.464 7.177 3.1 6.69 35.13
36.40
35 90.106 82.975 7.131 3.5 7.07 37.67
49.78
40 90.066 79.963 10.103 3.6 8.65 61.89
74.62
45 90.146 77.934 12.212 4.1 10.21 87.35
89.81
50 90.726 77.853 12.873 3.95 10.39 92.27
100.38
55 92.601 77.895 14.706 3.7 11.05 108.48
91.50
60 90.916 78.837 12.079 3.15 9.19 74.53
71.71
64 92.041 80.52 11.521 3.1 8.86 68.90
NOF LHS Upstream Side (Ch o starts at junction of OF
&NOF Section)
0 94.378 82.6 11.778 4.15 10.04 83.56
79.47
5 94.478 82.755 11.723 3.5 9.36 75.39
63.69
10 94.598 85.162333 9.435667 3.15 7.87 51.98
54.60
15 95.698 86.029 9.669 3.5 8.33 57.22
54.58
20 96.218 87.194 9.024 3.5 8.01 51.94
46.24
25 96.348 88.44 7.908 3.15 7.10 40.54
39.27
30 96.948 89.77 7.178 3.5 7.09 38.00
38.28
34 96.848 89.693 7.155 3.6 7.18 38.55
Excavation in hard rockof all toughness by breaker including boulders above 0.6 M dia. (0.113 cum) minimiz
to side slopes of excavation and placing the excavated rock neatly in approved dump area as directed inclu
all materials, machinery, labour, leveling bed etc. complete with lead upto 1.0 Km and lift upto 6 M.
Hard rock C.O.T.Bo Bottom Top width Mean
CH. Depth M Area(sqm)
top ttom width M M area(sqm)

Upstream non-over flow section RHS


0 94.249 89.996 4.253 3.7 6.45 21.58
21.54
4 94.139 89.966 4.174 3.95 6.35 21.49
23.11
8 94.209 89.795 4.414 4.3 6.9 24.72
23.72
12 94.064 89.818 4.247 4.1 6.6 22.72
23.61
16 94.209 89.713 4.497 4.1 6.8 24.51
24.86
20 94.484 89.725 4.759 3.5 7.1 25.22
19.51
24 92.255 89.688 2.567 3.6 7.15 13.80
14.47
28 92.265 89.42 2.845 3.15 7.5 15.15
15.10
32 92.285 89.27 3.015 3.1 6.89 15.06
19.93
36 92.24 87.544 4.696 4 6.56 24.80
27.46
40 92.42 86.891 5.529 4.2 6.7 30.13
31.57
44 92.52 86.703 5.818 4.3 7.05 33.01
34.86
48 92.62 86.151 6.469 4.25 7.1 36.71
36.39
52 92.51 86.238 6.273 4.2 7.3 36.07
middle portion with B. C. soil (in gunny bags if required) Providing impervious/ semiprevious materials on
B.C. Soil (in gunny bags if required) including ramming, compacting to the satisfaction of Engineer-in-cha
completion of work including dismantling coffer dam after completion of works and disposing off the ma
Bottom Bottom Top width Mean
CH. Top RL Depth M Area(sqm)
RL width M M area(sqm)

0 95.495 89.20 6.30 13.20 6.00 60.43


56.96
5 94.65 89.30 5.35 13.50 6.50 53.48
54.55
10 94.55 88.96 5.59 13.60 6.30 55.62
59.94
15 95.15 88.85 6.30 14.00 6.40 64.26
62.99
20 94.95 89.10 5.85 14.10 7.00 61.72
63.90
25 94.975 88.80 6.18 13.90 7.50 66.07
65.43
30 95.02 88.79 6.23 13.80 7.00 64.79
63.56
35 94.94 88.90 6.04 13.75 6.89 62.33
61.51
40 95.25 89.30 5.95 14.00 6.40 60.69
61.88
45 95.1 89.21 5.89 14.20 7.20 63.07
62.24
50 94.76 89.06 5.70 14.25 7.30 61.42
63.80
55 94.9 88.70 6.20 13.90 7.45 66.19
65.90
60 94.985 88.75 6.24 13.85 7.20 65.62
59.69
65 94.45 88.85 5.60 13.20 6.00 53.76
55.97
70 94.93 88.90 6.03 13.10 6.20 58.19
57.64
75 94.91 88.84 6.07 12.50 6.30 57.10
Total Qty.
Tender Qty.
Qty as per tender rate=TendeR Qty.+25%
Dewatering the excavated trenches and pools of water in the buildingQty. goes in clause 38
trenches/pipeline trenches, well work
pumps and other devices including disposing off water to safe distance as directed by Engineer-incharge (i
cost of macheniery, labour, fuel) etc. complete.
As major work of Upstream side below GL is completed, 75 % Job is proposed
Drilling 32 mm dia. grout holes in concrete/rock by per cusion dirlling using jack hammer as directed to spe
for consolidation / contact grouting including cost of all materials, machinery, labour, cleaning holes, vente
lightening, drainage and all other ancillary operation etc. complete
Upstream
Particulars No.Of holes Depth Rmt
For Anchor bar 537 2.25 1208.25
For grouting 161 2.25 362.25
160 1.5 240
For bridge no.2 40 1.5 60
Total includin
Grouting cement slurry in grout holes under specified pressure for consolidation/ contact grouting qty
materials, machinery, labour, re-drilling whereever necessary, ventilation, lightening, drinage and other anc
operations etc. complete with lead upto 1.0 Km and all lifts.

Total length (grouting+anchoring) 1870.5 m cement consumption per rmt 6 bag


1870.5 6 11223.00 bags
B) Providing and laying in situ C.C. of grade M-20 of trap / granite / gneiss / quartzite / graded metal for RCC
gallery, sluice, spill way crest, spill way down stream test, energy dissipting structures, intact structure, tra
pears, abutments, slab etc. with batching plant and transist Mixutre including shuttering and scapffolding c
curring etc. complete with and intial lead of 50M and lift of 1.5 M. (40 M.S.A.)

Concrete EGL
Chainage Side Top Bottom
Depth Avg.Depth Length Area

58 RHS 100.170 89.996 10.174


10.208 5.0 51.04
53 100.165 89.923 10.242
10.174 5.0 50.87
48 99.975 89.869 10.106
10.073 5.0 50.36
43 99.870 89.831 10.039
9.997 5.0 49.98
38 99.680 89.725 9.955
10.001 5.0 50.01
33 99.550 89.503 10.048
10.106 5.0 50.53
28 99.445 89.280 10.165
10.113 2.0 20.23
26 99.330 89.270 10.060

26 98.580 89.270 9.310


10.188 5.0 50.94
21 98.455 87.390 11.065
11.436 5.0 57.18
16 98.500 86.693 11.808
12.040 5.0 60.20
11 98.590 86.318 12.272

11 94.942 86.318 8.624


9.061 5.0 45.30
6 94.998 85.500 9.498
10.032 6.0 60.19
0 CENTRE 94.968 84.402 10.566
10.466 5.0 52.33
5 94.953 84.588 10.365
10.382 3.0 31.14
8 94.858 84.460 10.398

8 92.033 84.46 7.573


7.510 5.0 37.55
13 91.988 84.54 7.448
7.541 5.0 37.71
18 92.003 84.368 7.635
7.827 5.0 39.13
23 91.873 83.854 8.019
7.992 5.0 39.96
28 91.603 83.638 7.965
7.950 4.0 31.80
32 91.573 83.638 7.935
8.337 5.0 41.68
37 91.523 82.784 8.739
8.863 2.0 17.73
39 91.528 82.54 8.988 0.000

39 90.843 82.54 8.303


10.773 5.0 53.87
44 90.833 77.59 13.243
13.134 5.0 65.67
49 90.943 77.918 13.025
13.107 5.0 65.53
54 91.083 77.895 13.188
12.915 5.0 64.58
59 91.328 78.686 12.642
11.748 5.0 58.74
64 91.373 80.52 10.853 0.000

Zero ch. For


0 91.373 80.52 10.853
LHS
9.720 5.0 48.60
5 LHS 91.903 83.316 8.587
7.542 5.0 37.71
10 92.018 85.521 6.497

10 93.148 85.521 7.627


7.357 5.0 36.78
15 93.313 86.227 7.086
6.748 5.0 33.74
20 93.603 87.194 6.409
5.865 5.0 29.33
25 93.613 88.292 5.321
4.480 5.0 22.40
30 93.408 89.77 3.638
4.029 4.0 16.12
34 94.113 89.693 4.420

Extra work 1.500 98.0

Extra work
for deep
holes
formed
0.500 30.000 1.0
due loose
stone fall
in rhs
upstream

Grand Total

foundations, slabs, beams, columns, canopies, staircase, newels, chajjas, lintels, pardies, copings, fins, arc
per detailed designs, drawings and schedules, including cutting, bendings, hooking the bars, binding with w
identification bar,ø Seating Spacing Total no. length total length unit weight
lenth At c/c of bars
26 to 58/RHS/upstream
outterface

32
main vertical 16 0.24 134 11.1 1491.10 1.58
Distribution
horizontal 16 10.1 0.24 43 32 1378.46 1.58
Laps 16 2869.5646 11.04 259.92433 0.96 249.53 1.58
11 to 26/RHS/upstream
outterface
main vertical 16 15 0.24 64 12.9 819.15 1.58
Distribution ho 16 11.9 0.24 50 15 757.23 1.58
Laps 16 1576.3826 11.04 142.78828 0.96 137.08 1.58

11 to 0 & 0 to
8/RHS &
centre/upstre
am
outterface
main vertical 16 19 0.24 80 10.9 873.82 1.58
Distribution ho 16 9.9 0.24 42 19 802.75 1.58
Laps 16 1676.5667 11.04 153 0.96 146.75 1.58
8 to 39 centre/upstream
outterface
main vertical 16 31 0.24 130 9 1171.50 1.58
Distribution ho 16 8.0 0.24 34 31 1069.20 1.58
Laps 16 2240.6968 11.04 204 0.96 195.80 1.58
39 to 64 centre/upstream
outterface
main vertical 16 25 0.24 105 12.9 1356.65 1.58
Distribution ho 16 11.9 0.24 50 25 1262.05 1.58
Laps 16 2618.7044 11.04 238 0.96 228.67 1.58
0 to 10 LHS/upstream
outterface
main vertical 16 10 0.24 43 5.267 224.73 1.58
Distribution ho 16 8.0957778 0.24 35 10 347.32 1.58
Laps 16 572.04941 11.04 53 0.96 50.70 1.58
10 to 34 LHS/upstream
outterface
main vertical 16 24 0.24 101 6.8 686.80 1.58
Distribution ho 16 5.8 0.24 25 24 599.02 1.58
Laps 16 1285.8 11.04 117 0.96 112.77 1.58

CH-0 to 58, 0
to 64, 0 to 34
Inner face
main vertical 16 156 0.24 651 1.5 976.50 1.58
Distribution ho 16 1.5 0.24 7 156 1131.00 1.58
Laps 16 2107.5 11.04 191 0.96 183.26 1.58

Anchor Bars
25 537 3.375 1812.38 3.86
This bill
Previous bill qty
Uptodate

Soft Strata
Bridge no.2 101.66 98.4 3.26 11
This bill qty

Hard Strata

Bridge no.2 98.4 98 0.4 11


This bill qty

necessary for foundation and other parts of work and bailing out and pumping out water below the actual in
water level for start of that particular component till completion of bridge etc. Complete.
job 1

Providing and laying in situ / ready mix cement concrete of M15 proportion with trap metal in foundation
necessary form work, compacting and curing etc. complete. (with reversible drum type mixer/ concrete bat
PCC For Abutment Piers (pan mixer)) with SCADA with Natural / VSI standard Artificial Sand)
Nos L W Depth M
2 5.6 5.285 0.2
1 6.09 2.5 0.2

returns, wings etc. including provision of "V" shaped false joints to form suitable panels on the faces to ap
with compacting by vibrating and curing complete, including plywood/steel form work centering ( excluding
by means of pump)
Footing nos and including
L bailling
W out water
Depth M and curing finishing in CM 1:3 etc. complete. as dir
Abutment 2 5.6 5.285 0.8
PIER 1 6.09 2.5 1.2

Sub-structure Area
Abutment 2 5 2.406 1.936
2 5 1.936 1.936 1.874
PIER
rectangular
1 4.25 1.2 2
portion
curve area 2 0.1297703 2

This bill qty

2 0.7854 (0.55+0.6)
a or for formation of service road as
o required level and profile etc.

Length Quantity(cum)

5 311.48

5 250.60

5 237.81

5 223.46

5 186.17

5 186.53

5 199.71

5 173.23

5 174.70

5 176.39

5 310.31

3 235.17

5 292.97

5 227.86

5 200.53

5 179.89

5 175.43

5 174.93
5 182.00

5 248.90

5 373.09

5 449.06

5 501.89

5 457.52

4 286.85

5 397.37

5 318.43

5 272.99

5 272.90

5 231.22

5 196.37

4 153.12

Totalminimizing
dia. (0.113 cum) 8258.88
damage
mp area as directed including cost of
nd lift upto 6 M.

Length Quantity(cum)

4 86.15

4 92.42

4 94.87

4 94.45

4 99.45
4 78.03

4 57.89

4 60.42

4 79.71

4 109.86

4 126.29

4 139.45

4 145.55

Total
miprevious materials 1264.56
on both side of
action of Engineer-in-charge, till the
and disposing off the materials as

Length Quantity(cum)

5 284.78

5 272.75

5 299.70

5 314.94

5 319.48

5 327.16

5 317.81

5 307.56

5 309.39

5 311.21

5 319.01
5 329.52

5 298.46

5 279.87

5 288.21

4579.85
3286.00
R Qty.+25% 3368.15
use
line38
trenches, well works1211.70
by using
by Engineer-incharge (including

75 % Job
mmer as directed to speficifed depth
ur, cleaning holes, venteliation,

Total including
ontact grouting qty 1870.5
cost of all
g, drinage and other ancillary

e / graded Qty in MT
metal 561.15
for RCC work of
ures, intact structure, training walls,
ering and scapffolding compacting,

Width Quantity

1.50 76.56

1.50 76.30

1.50 75.54

1.50 74.98

1.50 75.01
1.50 75.80

1.50 30.34

1.50 76.41

1.50 85.77

1.50 90.30

1.50 67.96

1.50 90.29

1.50 78.49

1.50 46.72

1.50 56.33

1.50 56.56

1.50 58.70

1.50 59.94

1.50 47.70

1.50 62.53

1.50 26.59

1.50 80.80

1.50 98.50

1.50 98.30

1.50 96.86
1.50 88.11

1.5 72.90

1.50 56.57

1.50 55.17

1.50 50.61

1.50 43.99

1.50 33.60

1.50 24.17

Total 2188.38
0.30 44.1

1.00 15

Grand Total 2247.48

ardies, copings, fins, arches, etc. as


g the bars, binding with wires or tack
weight M.T

2355.938 2.36

2177.974 2.18
394.25322 0.39

1294.257 1.29
1196.4276 1.20
216.58127 0.22

1380.6303 1.38
1268.345 1.27
231.86248 0.23

1850.97 1.85
1689.331 1.69
309.36906 0.31

2143.507 2.14
1994.0459 1.99
361.30401 0.36

355.06603 0.36
548.77204 0.55
80.111414 0.08

1085.144 1.09
946.4595 0.95
178.17797 0.18

1542.87 1.54
1786.98 1.79
289.55217 0.29

Total 25.68

6992.1428 6.99
qty 32.67
vious bill qty 0.00
32.67

20 717.20
717.20

20 88.00
88.00

water below the actual initial natural


plete.
50 % Job

trap metal in foundation including


type mixer/ concrete batch mix plant
ficial Sand)

11.84
3.05
Total 14.88

anels on the faces to approve design


ork centering ( excluding dewatering
1:3 etc. complete. as directed by
47.35
18.27
total 65.62

46.58
18.74

10.20
0.52
total 141.66

This bill qty 141.66