Tender Inviting Authority: SUPERINTENDING ENGINEER, WESTERN CIRCLE-II

Name of Work: Construction of 55 numbers of RCC Bridges Over Drainage Channels and Irrigation Canals in Connection with Infrastructure GAP
Project in the districts of Bankura, in West Bengal

SCHEDULE OF WORK / ITEM(S)


NPCC
Sl.No Description of Work / Item(s) No.of Qty Units
Rate Amount
4.00 Providing and constructing Temporary Service Road of width not less than 3.75 1,877.155 metre 17,853.00 3,35,12,839.43
m over river for movement of men, equipment and construction machineries from
one pier / abutment location to another pier / abutment location considering
necessary stability and safety aspects by providing and driving suitable piles,
providing fitting, fixing suitable R.S. Joist, Channels, angles and wooden sleeper
as per design requirement including dismantling and taking out the entire service
road after construction.
ii) With R. S. Joist Pile
Height of deck above bed level above
2.25 m & upto 3.25 m.
6.00 Construction of Temporary Island by construction of outer annular layer with two 28.000 Each 4,37,140.00 1,22,39,920.00
rows of bullahs, suitable spaced, of dia. not less than 150 mm, driven at least half
of the total length, properly tied, braced and supported and filling the annular
space with sand / soil filled bags, protected by drum sheet walling on both side
and filling the core portion with locally available materials including the
dismantling, removing and cleaning the site of the construction of main
component of the structure. i) Area of Island between 100 sqm.- 120 sq.m a)
Height above bed level upto 2.25 m.
14.00 Performing confirmatory subsoil exploration by drilling boreholes of 40m depth ( 94.000 Each bore 75,000.00 70,50,000.00
min) at pile cap/abutment locations during construction stage and submission of hole
the soil report complete as per IRC/IS specification and direction of Engineer in
charge
38.00 Clearing grass and removal of rubbish up to a distance of 30 m outside the 5.405 Hectare 18,134.00 98,020.22
periphery of the area as per Technical Specifications Clause 201 for Rural Roads
of MORD.
By Manual Means
48.00 Cutting of trees, including cutting of trunks, branches and removal of stumps & -
roots, refilling, compaction of backfilling and stacking of serviceable material by
manual means with all lifts as per Technical Specifications Clause 201 for Rural
Roads of MORD.
B. Lead upto 1000 m
48.01 ii) Girth above 600 mm to 900 mm 35.000 Each 468.00 16,380.00
48.02 iii) Girth above 900 mm to 1800 mm 37.000 Each 911.00 33,707.00
48.03 iv) Girth above 1800 mm to 2700 mm 72.000 Each 1,728.00 1,24,416.00
70.00 Dismantling of existing structures like culverts, bridges, retaining walls and other 2,364.536 cum 2,200.00 52,01,978.44
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead
of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.
Clause 202 for Rural Roads of MORD.
(I) By Manual Means c) Reinforced Cement Concrete
R Earthwork in excavation in all kinds of soil for making embankments, repairs to 13,389.344 Cum 223.00 29,85,823.77
the embankment, closing breaches etc. as per profile including supply and
transporting the earth by truck or tractor or any other mechanical means on land ,
including loading, transporting, unloading and stacking with all lifts bothways and
head load where necessary and depositing the same on embankments, clannels,
filling depressions in requisite profile, levelling as per direction of the Engineer-in-
charge within a lead of,
NB :- Measurement to be taken on the basis of stack measurement / prepost
work section measurement after deduction of void as per norms. No extra
payment will be made for stacking.
A) Beyond 500 m and upto 1.00 km
78.00 Supplying Jhaw / Eucalyptus bullah piles at work site, including dressing and 13,614.754 Metre 350.00 47,65,163.93
making one end pointed.
(iii) 15 cm av. Diameter
79.00 Supplying, fitting and fixing with iron nails half split bullah wailing pieces and 3,606.557 Metre 377.00 13,59,672.13
cross pieces etc. complete with cost of all materials and carriage to site. (b)
Width of thinner end above 15 cm. (i) Jhaw / Eucalyptus.
80.00 Labour for driving Jhaw / Eucalyptus bullah piles by monkey in all sorts of soil 6,807.377 Metre 170.00 11,57,254.10
including hoisting and placing piles in position, protecting the pile head with iron
ring and cutting and shaping heads before and after driving and including hire
and labour for necessary driving appliances and all tackles. (iii) 15 cm av.
Diameter
81.00 Supplying to site empty cement polythene bags (capacity 50kg) in good condition 1,79,918.000 Each 6.00 10,79,508.00
including stacking, incedental charges etc. all complete (capacity 50 kg).
82.00 Labour charges for filling empty cement gunny bag / polythene bag (capacity 50 1,79,918.000 Each bag 7.00 12,59,426.00
kg) with all kinds of earth (wet or dry), sand or agreegates(stone / brick) and
sewing as done in case of cement bags ,(tying with a knot after filling will not be
accepted ) , and stacking within a lead of 30 metre as per direction of Engr-in-
charge (cost is excluding the cost of any types of filling materials). NB:- Volume
of earth/ sand filled bags should not be less than 0.028 cum/ bag.

83.00 Extra rate for item no above for each additional lead of 60 metre or part thereof 1,79,918.000 Each bag 2.00 3,59,836.00
beyond the initial lead of 30 metre.
84.00 Dumping in position earth / sand filled gunny / poly bags (capacity 50kg) within a 1,79,918.000 Each bag 5.00 8,99,590.00
lead of 30 metre inclusive of all lifts.
99.00 Providing and laying reinforced cement concrete pipe NP4 as per design in single 219.775 metre 3,600.00 7,91,188.52
row
Providing and laying reinforced cement concrete pipe NP4 with spigot socket for
culverts on first class bedding of granular material in single row including fixing
with cement mortar 1:2 as per Technical Specification Clause 1106 for Rural
Roads of MORD.
(D) 1000 mm dia
100.00 Providing and laying reinforced cement concrete pipe NP4 as per design in 1,440.369 metre 7,200.00 1,03,70,655.74
double row
Providing and laying reinforced cement concrete pipe NP4 with spigot socket for
culverts on first class bedding of granular material in double row including fixing
with cement mortar 1:2 as per Technical Specification Clause 1106 for Rural
Roads of MORD.
(D) 1000 mm dia
103.00 Providing and constructing Temporary Service Road of width not less than 3.75 649.180 metre 8,327.00 54,05,724.59
m over river for movement of men, equipment and construction machineries from
one pier / abutment ocation to another pier / abutment location considering
necessary stability and safety aspects by providing and driving suitable piles,
providing fitting, fixing suitable R.S. Joist, Channels, angles and wooden sleeper
as per design requirement including dismantling and taking out the entire service
road after construction.
As per Drawing of EIC
i) With Eucaliptus Bullah pile
(height of deck above bed level upto 2.25 m)

Total in Figures 8,87,11,103.88


N.B:- GST WILL BE EXTRA AS PER WEST BENGAL STATE GOVERNMENT RULE