You are on page 1of 6

MONSOON EXTREME WEATHER PLAN

PRINCIPAL HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

Contents

1. Purpose of the Plan ………………………………………………………………………..2


2. Project Description………………………………………………………………………....2
3. Procedures……………………………………………………………………………………...2

3.1. Rain…………………………………………………………………………………….3
3.2. Working with electrical power tools……………………………………3
3.3. Drawing……………………………………………………………………………...3
3.4. Collapse……………………………………………………………………………...3
3.5. Work at height…………………………………………………………………….3

4. Resources……………………………………………………………………………………….3
5. Heavy Rainy situation Management……………………………………………….4
6. Wind and Dust………………………………………………………………………………..4

6.1. Lifting…………………………………………………………………………………4
6.2. Work Activity……………………………………………………………………..4
6.3. Work at height……………………………………………………………………4
6.4. Store/ Stacked material……………………………………………………..4

7. Resources……………………………………………………………………………………….4
8. Heavy windy situation Management………………………………………………5
9. Emergency Response………………………………………………………………………5
MONSOON EXTREME WEATHER PLAN
PRINCIPAL HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

PROJECT EIGHTEEN – ISLAMABAD

Project Pavilion-06,07 Consultant Meinhardt

Task Construction of Grey Date 17-06-2021


Description Structure

Contractor PCPL Discipline HSE

1. Purpose of the Plan

The purpose of the plan is to provide a guidance as to the actions to be taken if the site or workers are
subject to extreme weather.

2. Project Description

CONSTRUCTION OF Pavilion-06, 07 residential apartments.


Abbreviations
HSE Health, Safety and environment

PCPL Principal Constructors Pvt. Ltd.

3. Procedures

3.1 Rain
Once the rain starts all permits to work approvals will be automatically cancelled and concerned
supervision reissue the permit after completing and approval from site engineer and HSE department.

3.2 Working with electrical power tools- there is some potential for such a tool, if damaged
to electrocute the user. We use 110v equipment and center-wired arrangements to minimize the
current but there is still a danger. Tools therefore must be inspected every day before use. Therefore,
MONSOON EXTREME WEATHER PLAN
PRINCIPAL HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

during prolonged rain power tools use shall be suspended until the stops. After rain all electrical
installations and portable power tools/items must be inspected by competent electrician.

3.3 Drawing- if work is being carried out in any area where the rain water is pudding or forming a
deep reservoir even if temporary then there is some potential for a worker to get into difficult in that
water. Similarly if there are excavations or boreholes, then a significant depth of water could build up
inside and with steep sides, if a worker fell in he would have a difficulty is escaping from the water. All
such boreholes and excavations must be safely barricaded to prevent workers entering a Zone
immediately adjacent to the opening.

3.4 Collapse- if the rain is prolonged and heavy it can destabilize any excavations open at the time.
Therefore, during such ran all workers shall be removed from excavations until rain has stopped and an
inspection of the opening made to verify there are no problems. After the rain all excavations and
possible water accumulation areas including manholes to be inspected by site engineer and HSE
department. Work will commence after the safe to work confirmation from HSE department.

3.5 Work at height- Once the rain start all work at height activities will be suspended and work will
commence only after completing the inspection by the area supervisor revalidate the scaffolding tag.

4. Resources
 Water pump for dewatering
 Tankers for dewatering the huge quantity of water from excavation
 Competent electrician

5. Heavy Rainy situation management


 Site engineer shall report to construction manager
 Site safety officer shall coordinate with site engineer and assess the situation
 Safety officer shall suspend all external activities like scaffold work, roof work, work on
balconies, excavation related work, hot work activities and power tools operation by informing
the concerned site engineer.
 Project manager and HSE manager shall take a decision in coordination with project director to
stop the site further.
MONSOON EXTREME WEATHER PLAN
PRINCIPAL HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

6. Wind and dust


If the wind picks up a number of work areas need to be monitored and if necessary stopped.

6.1 Lifting- if the winds reaches 35kph, all crane activity shall be suspended until the wind speed
drops again

6.2 Work activity- if the wind is sufficiently strong that the lives or health of the workforce is in
danger then the site shall be evacuated until the wind subsides.

6.3 Work at height- if the wind reaches more than 38Mph, all work at height activities will be
suspended during heavy wind and scaffolding will be re-inspected and scaffolding tag will be validated
by scaffolding inspector.

6.4 Store/stacked material-care should be taken when stacking stored items but in the event of
the wind it becomes potentially unstable and with injury or property damage consequences. / All
workforces should have received a TBT to cover the dangers of site working

7. Resources
 Anemometer in site and on tower crane
 Climate forecast update from authority

8. Heavy windy situation management


 In case of any heavy winds, lifting supervisors shall report to construction manager of each area
to stop all lifting operation. Lifting supervisor shall coordinate with crane operators to stop all

lifting operation and leave all tower carne on free slewing mode after keeping the trolley near to
mast.
 Construction manager in coordination with site engineers and supervisor to secure all loose
materials on typical floors edges from flying away.
 Site engineers shall suspend all external activities where workers are exposed to high wind and
flying objects.
 Site engineer shall stop all scaffold erection and dismantling as well as all work at height
including the roof work.
 Store keeper shall secure all loose materials at store area.
MONSOON EXTREME WEATHER PLAN
PRINCIPAL HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

9. Emergency response
If an emergency event comes as a result of extreme weather, the emergency procedure below must be
followed

 In the event of an emergency situation, the procedure is as follows:


 The person discovering the emergency shall inform emergency coordinator who shall
immediately call emergency coordinator on the site emergency hotline following telephone
numbers.

Sr.No Name Contact Number Department

01 M. Jamshaid Malik 0308-8799247 PM ( Pavilion-06,07)

02 Khurram Shahzad 0300-4886001 HSE Manager (Pavilion-06,07)

03 Naseem Shiekh 0306-3224851 Admin (Pavilion-06,07)

04 M. Rashid Kashmiri 0347-5810614 Supervisor( Pavilion-06,07)

 Once connected, he shall give clear information when asked, including: time of the event,
company name, location of the incident, people involved, assessment of the injuries or damage
and who else might be immediately affected.
 Project manager shall contact his relevant consultant Meinhardt and project management
consultant Mace
 If the event is classed as a reportable incident, the project manager shall arrange to notify the
local authorities.
 The HSE manager shall contact the Meinhardt HSE Manager.
 The HSE manager or his HSE Engineer shall then attend the site of the incident to get an update
on the situation and ensure directional and rescue arrangement for the emergency services
have been organized.
 If not already done, he shall dispatch sentries to the approach of the incident to guide the
emergency services to the scene of the incident.
MONSOON EXTREME WEATHER PLAN
PRINCIPAL HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

 With the help of HSE officers and the construction team, the incident site shall be secured, and
photographs shall be taken for record and reporting purposes.
 The HSE officers shall interview and take statement from all and any witnesses.
 Within 24 hours, the initial report shall be produced and circulated to engineer office
 Within 5 days the final report shall be produced and circulated

Submitted by;
Khurram Shahzad
HSE Manager
PCPL-Eighteen Islamabad

You might also like