1. Visual Inspection
pass - ✓
fail - X
a. Visually inspect for installation works of all refrigerant pipe, drain pipe and all electrical system satisfy by manufacturer
requirement
b. Verify that the module is properly installed and that internal and external wiring is correct and tightened
c. Verify that all input and output power cables, earth and control cables are connected to the A/C unit
d. Verify that proper ductings and mountings are installed and operating properly
e. Visual checking of physical conditions of the following items:
e (i). Refrigerant Circuit
- coil condition
- compressor condition
e (ii). Fan Motor
- fan condition
- belt condition and tension
- drives & pullys for lightness & alignment
- fan rotation
e (iii). Electrical Parts
- cleanliness of control panel
- cleanliness of MCB and electrical circuit
- tightness of wiring connections
e (iv). Others
- drain pan & drain condition
- filter condition
- electronic components

2. Additonal Refrigerant Charge


ø 6.35 mm M ø 9.52 mm M
ø 12.70 mm M ø 15.88 mm M
ø 19.05 mm M Total Additonal Charge kg

3. Model & Serial for whole set of refrigerant circuit


Model Serial No Install Location

No.1
No.2

No.3
No.4

No.5

No.6

No.7

No.8
Outdoor Unit
No.9

No.10

No.11

No.12

No.13

No.14

No.15

No.16
Model Serial No Install Location

No.1

No.2

No.3

No.4

No.5

No.6

No.7

No.8

No.9

No.10
No.11

No.12
No.13

No.14
No.15

No.16
Indoor Unit
No.17

No.18

No.19

No.20

No.21

No.22

No.23

No.24

No.25

No.26

No.27
No.28

No.29
No.30

No.31
No.32

4. Pressure Test and Vacuum Test Record


4.1. Pressure Test Record

Genreral Specification Requirement / Maunfacturer


Refrigerant Type Test Result
Requirement

psi / kPa psi / kPa

4.2. Vacuum Test Record

Genreral Specification Requirement / Maunfacturer


Refrigerant Type Test Result
Requirement

psi / kPa psi / kPa


4.3 Evacuation Test (For refer General Specification)
In performing pressure test for refrigerant system and circuit containing blend refrigerant, e.g. R407C and R410a, manufacturer’s
recommended procedures and test pressure shall be followed.

Evacuation Test - (Remark: The evacuation shall be pulled down to between 170 Pa absolute and 340 Pa absolute)- Refer to the General Specification

1st Duration of Test 4 hours


2nd Duration of Test 3 hours
3rd Duration of Test 2 hours

5. Enviromential Assessment
Location Before VRF Operation VRF Operation

6. Power Source Record


Equipment No. L1-L2 L2-L3 L1-L3

7. Operation Record

Ambient Temperature ℃ Ambient Humidity %

7.1 Outdoor Unit

Refrigerant Circuit

Suction Pressure psi Discharge Pressure psi

Suction pipeline
℃ Discharge pipeline Temperature ℃
Temperature
Liquid pipeline Condenser Air Temperature
℃ ℃
temperature (In)
Condenser Air Compressor No.1 Running
℃ A
Temperature (Out) Current
Compressor No.2 Running Compressor No.3 Running
A A
Current Current
Condenser Fan No.1 Condenser Fan No.2 Running
A A
Running Current Current
Condenser Fan No.3 Condenser Fan No.4 Running
A A
Running Current Current
Condenser Fan No.5 Condenser Fan No.6 Running
A A
Running Current Current
Condenser Fan No.7 Condenser Fan No.8 Running
A A
Running Current Current
Control Current A Running Hertz Hz
7.2 Indoor Unit
EEV Status Fan Motor Running Room Tempature Supply Air
Indoor No. Current Room Temperature Return Air Tempature
(%) Setpoint Temperature
No.1 A ℃ ℃ ℃ ℃

No.2 A ℃ ℃ ℃ ℃

No.3 A ℃ ℃ ℃ ℃

No.4 A ℃ ℃ ℃ ℃

No.5 A ℃ ℃ ℃ ℃

No.6 A ℃ ℃ ℃ ℃

No.7 A ℃ ℃ ℃ ℃

No.8 A ℃ ℃ ℃ ℃

No.9 A ℃ ℃ ℃ ℃

No.10 A ℃ ℃ ℃ ℃

No.11 A ℃ ℃ ℃ ℃

No.12 A ℃ ℃ ℃ ℃

No.13 A ℃ ℃ ℃ ℃

No.14 A ℃ ℃ ℃ ℃

No.15 A ℃ ℃ ℃ ℃

No.16 A ℃ ℃ ℃ ℃

No.17 A ℃ ℃ ℃ ℃

No.18 A ℃ ℃ ℃ ℃

No.19 A ℃ ℃ ℃ ℃

No.20 A ℃ ℃ ℃ ℃

No.21 A ℃ ℃ ℃ ℃

No.22 A ℃ ℃ ℃ ℃

No.23 A ℃ ℃ ℃ ℃

No.24 A ℃ ℃ ℃ ℃

No.25 A ℃ ℃ ℃ ℃

No.26 A ℃ ℃ ℃ ℃

No.27 A ℃ ℃ ℃ ℃

No.28 A ℃ ℃ ℃ ℃

No.29 A ℃ ℃ ℃ ℃

No.30 A ℃ ℃ ℃ ℃

No.31 A ℃ ℃ ℃ ℃

No.32 A ℃ ℃ ℃ ℃

pass - ✓
8. Functional test for safety device fail - X
a. To press E-Stop button to cutout equipment operation

b. To test low refrigerant pressure alarm recommended by manufacturer

c. To test high refrigerant pressure alarm recommended by manufacturer

d. To test temperature sensor recommended by manufacturer