Purpose
TotalView Dashboards
CPI Indicator
• Availability: The percentage of time that the equipment is available for operation.
Availability = (Total Time – Scheduled Down Time – Unscheduled Down Time) * 100
________________________________________________________
Total Time
• Use of Availability: The percentage of time that the equipment is running relative
to the time it is available.
MTBS/MTBF/MTTR
• MTBF (Mean Time Between Failures (For Trucks, Drills, and Loader
Fleets)): The measure of frequency of unscheduled maintenance production
interruptions. (Stops do not include scheduled maintenance, or operation
shutdowns such as a shift change, lunch, or fueling.)
• Operated Time: The number of stops for unscheduled maintenance.
1
Technical
Notes
• Working Time: The time the equipment is running and doing productive work.
• Delay Time: The time the equipment is running but not doing productive work.
• Standby Time: The time the equipment is available for operation but not
running.
• Down Time: The time the equipment is not operating because of maintenance.
Down Time Duration Hours = Down + Unscheduled Down + Scheduled Down + Operational
Down + Maintenance Delay
Deliverability
Deliverability = (Total Time – Scheduled Down Time – Unscheduled Down Time) * 100
_______________________________________________________
Equipment Count
Status By Fleet
Status Equipment
CPI Indicator
Status Hours
• Working Time: The time the equipment is running and doing productive work.
• Delay Time: The time the equipment is running but not doing productive work.
2
Technical
Notes
• Standby Time: The time the equipment is available for operation but not
running.
• Down Time: The time the equipment is not operating because of maintenance.
Down Time Duration Hours = Down + Unscheduled Down + Scheduled Down + Operational
Down + Maintenance Delay
Deliverability
Deliverability = (Total Time – Scheduled Down Time – Unscheduled Down Time) * 100
_______________________________________________________
Equipment Count
Tonnage By Hour
Displays the sum load tonnage group by hour, day, and month.
Status Metric
Status Equipment
Production
Displays the sum load tonnage group by hour, day, and month.
The TotalView system computes queue and hang times from the following measured
events:
- Shovel Status Changes
- Truck Arrivals At Shovels
- Truck Departures At Shovels
Conceptually, the definition of queue and hang times are quite simple.
• Queue Time: The total time when more than one truck is at a given shovel
multiplied by the number of trucks queued.
• Hang Time: The total time zero trucks are at a given shovel.
3
Technical
Notes
Average Speed
CPI Indicator
• Availability: The percentage of time that the equipment is available for operation.
Availability = (Total Time – Scheduled Down Time – Unscheduled Down Time) * 100
________________________________________________________
Total Time
• Use of Availability: The percentage of time that the equipment is running relative
to the time it is available.
4
Technical
Notes