You are on page 1of 16

Tunnelling and

Underground Space
Technology
incorporating Trenchless
Technology Research
Tunnelling and Underground Space Technology 20 (2005) 463–478
www.elsevier.com/locate/tust

Design of Pyongtaek LPG storage terminal underneath


Lake Namyang: A case study
a,1 b,* c,2
Jung Joo Park , Seokwon Jeon , Young Shik Chung
a
Department of Civil and Environmental Engineering, University of Ulsan, San 29 Muger 2-dong Nam-gu, Ulsan 680-749, Republic of Korea
b
School of Civil, Urban and Geosystem Engineering, Seoul National University San 56-1 Shilim-dong Gwanak-gu, Seoul 151-744, Republic of Korea
c
Department of Civil and Environmental Engineering, University of Ulsan, San 29 Muger 2-dong Nam-gu, Ulsan 680-749, Republic of Korea

Received 10 December 2001; received in revised form 9 March 2005; accepted 23 March 2005
Available online 5 May 2005

Abstract

This paper presents the geo-engineering problems and approaches in the design of the first LPG storage terminal constructed
underneath a lake in the western part of Korea. Pyongtaek LPG Storage Terminal was proposed to be constructed underneath Lake
Namyang to facilitate the storage caverns within the limited property boundary complicated with complex geological conditions and
potential interference with the neighboring storage caverns in operation. In order to precisely characterize the geological features of the
bedrock underneath the lake with very limited information from the outcrops, a new method of geophysical investigation was applied.
In addition, discreet evaluation of geological data and numerical analyses were carried out to predict the potential hydrogeological
interference with the neighboring caverns. As a result, vertical and horizontal water curtain systems were constructed to prevent
the detrimental drawdown of water level nearby the neighboring caverns. The depth and geometry of the new cavern were determined
based on consideration of the in situ stresses and operation pressure to have as large capacity as possible to overcome the spatial con-
straints. Continuous monitoring during the construction of the storage caverns and tunnels provides favorable measurements for the
final tightness of the storage cavern. In May 1999, the first LPG supply in the cavern was made successfully after the completion of
acceptance test.
 2005 Elsevier Ltd. All rights reserved.

Keywords: LPG storage cavern; Geotechnical design; Water curtain

1. Introduction have the primary reinforcement without lining and store


the content at ambient temperature and at high pressure.
Korea faces increasing demand for additional storage The underground storage caverns have been reported to
facilities of energy resources including crude oil and have many advantages in construction cost, environmen-
hydrocarbon gases. This is due to the fact that the current tal protection, and operation safety (Bittkow et al., 1997;
stockpiling capacity of 45 days cannot cope with the Hamberger, 1991; Lee et al., 1997; Sturk and Stille, 1995;
increasing energy consumption. Currently, there are five True, 1998; Winqvist, 1989; Zhao and Bergh-Christen-
underground LPG storage facilities in Korea, which only sen, 1996; Zhao et al., 1996).
Pyongtaek LPG storage terminal is the first storage
facility constructed underneath a lake. This project dem-
*
Corresponding author. Tel.: +82 2 880 8807; fax: +82 2 871 8938. onstrates a possible solution for efficient use of the heav-
E-mail addresses: jjoopark2000@hanmail.net (J.J. Park), sjeon@
snu.ac.kr (S. Jeon), yschung@mail.ulsan.ac.kr (Y.S. Chung).
ily crowded land. In addition, the successful completion
1
Tel.: +82 2 2222 4030; fax: +82 2 539 1361. of this construction project shows that the characteriza-
2
Tel.: +82 52 259 2261; fax: +82 52 259 2629. tion of the bedrock underneath the lake as well as the

0886-7798/$ - see front matter  2005 Elsevier Ltd. All rights reserved.
doi:10.1016/j.tust.2005.03.001
464 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

evaluation of hydrogeological issues are carried out suc- weaker than the gneiss (Sun-Kyung Construction Co.,
cessfully in the designing process. This paper presents 1992). The gneiss gets narrower approaching to the lake
the issues considered in the designing stage including in its extent. The schist and gneiss group are separated
storage cavern location, geometry, layout, hydrogeolog- by the fault zone which intrudes into the bottom of the
ical interference with the neighboring underground stor- lake. Fig. 2 shows the typical geological profile of the pro-
age facility in operation, and stability of the neighboring ject site. The soil layer is about 30 m thick at the surface
structures. and 30–65 m thick at the bottom of the lake.
Namyang Dike is sitting on a weak ground in the
west of the project site, and the neighboring butane cav-
2. Geological site investigation erns in operation are located in the southeast of the site
as shown in Fig. 3. The new caverns must have a good
The construction site is located at the southern part of distance of separation with the existing caverns as well
Lake Namyang, an artificial lake made by Namyang as with the dike to prevent the hydrogeological interfer-
Dyke (Latitude 3700 0 and Longitude 12648 0 ). This ence and to guarantee the stability of the existing struc-
coastal area consists of Pre-Cambrian Kyonggi Massif ture. Therefore, selection of the site is spatially limited.
banded gneiss and mica schist as shown in Fig. 1. Accord- In order to obtain the accurate underground geologic
ing to the borehole logging data, mica schist layer in the information, both the marine and land-marine seismic
low part of gneiss includes graphite seams and limestone refraction survey were carried out. The results indicated
lens which implies that the mica schist is geologically that P-wave velocities ranged between 4000 and

Fig. 1. Tectonic provinces in Korea (Lee, 1988). h Location of the Pyongtaek project site.
J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 465

Fig. 4. P-wave velocity distribution of sound bedrock.

Fig. 2. Typical geological profile in the project site.


jor fault zones among which the one located beneath
the lake and 250–300 m from the southern edge of
Lake Namyang is the most dominant with the orienta-
tion of N70–80W. Due to this fault zone, the location
of the caverns was shifted 30 m to the south from its
original location in the preliminary design (Sun-Kyung
Construction Co., 1995).
The orientation of the discontinuities was not able to
be determined due to the lack of outcrops nearby the
lake. Instead, the geometry of the three joint sets ob-
served in the neighboring caverns was used as shown
in Fig. 5. The joint set 3 disappears at depth of the cav-
ern, but the joint set 1 and 2 coincide with the minor
joint sets observed in the recovered cores from the pro-
ject site. Thus, the orientation of the caverns was
decided to be parallel to the existing caverns to minimize
the hydrogeological interference. In conclusion, the
location of the new cavern complex was decided to be
30 m south of the original location due to the observed
Fig. 3. Overview of the project site. fault zone as shown in Fig. 4, which is 170 and 350 m
apart from the Namyang Dike and the existing caverns
(L-1), respectively. Fig. 6 shows the location of the cav-
6000 m/s for the bedrock underneath the lake, which cor-
ern complex with the proposed layout, which overlaps
respond to the P-wave velocity of weak rock. However,
with the fault zones at a minimum extent.
there was a low velocity band (i.e., vP < 4000 m/s) along
the south bank of the lake. This low velocity zone was as-
sumed to be a fractured gneiss zone or a fault zone. In
particular, the zone coincided with the valley of the lake
as shown in Fig. 4. Therefore, this low velocity zone was
considered very important in determining the layout of
the caverns.
In order to investigate the low velocity zone, four
vertical holes were drilled and a large fractured zone
was observed sub-vertical to the north as shown in
Fig. 4. However, it was not appropriate to accurately
determine the lower boundary of the vertically oriented
fractured zone only with the vertical holes. Therefore,
six holes out of the 14 in total were drilled with an
inclination (h = 30, 45, 45, 60, 70, 70). From the
drilling log, it was determined that there exist three ma- Fig. 5. Orientation of discontinuities.
466 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

Fig. 6. Geological map at the elevation of 122 m.

3. Geotechnical design as large as possible. To characterize the rock mass,


rock classification is done according to Q-system
3.1. Characteristics of rock mass at the project site (Barton et al., 1992). The distribution of Q-values
based on the recovered rock drill core are shown in
The existence of Namyang Dike in the west and Fig. 7. Over 80% of the Q-values belonged to fair
the existing caverns in the east of the project site lim- or very good rock mass type. However, the graphite
its the extent of the new cavern. This makes it neces- seams or minor faults belonged to the extremely poor
sary for the cross-sectional area of the cavern to be class.
J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 467

Fig. 7. Distribution of RQD and Q-value.

Table 1 Table 1 summarizes the results of the laboratory tests


Mechanical properties of the rock and joint at the Pyongtaek project for the mechanical properties of intact rock and joint of
site
the site. The in situ stress measurement was done by
Rock material properties Gneiss Mica Schist hydraulic fracturing method and the results are tabulated
Compressive strength (MPa) 90–210 55–200 in Table 2. As shown in Table 2, the horizontal stress ra-
Tensile strength (MPa) 7–15 5–19 tio K was determined to be equal to 1 below 130 m level.
YoungÕs modulus (MPa) 56,000 33,500–63,000
PoissonÕs ratio 0.20 0.24
Since the compressive strength of the rock was high and
Density (g/cm3) 2.7 2.64–2.94 the K value was small, the in situ stress was not likely to
Friction angle () 35 38 affect the stability of the caverns to a great extent.
Cohesion (MPa) 14 14.2 The reinforcement design at the Pyongtaek site was
Joint properties determined based on the rock mass classification by
Contact shear stiffness (GPa/m) 1.3–2.0 Q-system. The rock mass was classified into five different
Contact normal stiffness (GPa/m) 4.0–39 types and the reinforcement design differed in each case.
Residual cohesion (MPa) 0 Table 3 and Fig. 8 present the different rock mass types
Residual dilatancy angle () 0
and the reinforcement design for each type of rock mass
Residual friction angle () 20
at the site.

Table 2
In situ stress measurement at the Pyongtaek project site
Borehole ID Depth (m) P pdr
s (MPa) P pv
r (MPa) Pb (MPa) Sv (MPa) Sh (MPa) SH (MPa) T (MPa) K Orientation ()
ST-1 121.0 4.16 6.93 10.26 3.27 4.16 4.35 3.33 1.27–1.33
130.0 3.37 5.97 9.92 3.51 3.37 4.14 3.95 0.96–1.18 95 ± 5.0
136.0 3.64 7.04 10.94 3.67 3.64 3.88 3.90 0.99–1.05
(1) P pdr
s is the shut-in pressure estimated from pressure-decay rate (pdr) method using bilinear best-fit.
(2) P pv
r is the reopening pressure estimated from P–V bilinear method.
(3) Pb is the initial breakdown pressure.
(4) Sv is the vertical stress calculated assuming rock density = 2.7 g/cm3.
(5) Sh and SH are the minimum and the maximum horizontal principal stress, respectively.
(6) T is the insitu tensile strength calculated by initial breakdown pressure and secondary breakdown pressure.
(7) K is the in situ horizontal stress ratio (K = rh,in situ/rv,in situ).
(8) Orientation is determined from the oriented impression packer with respect to True North.

Table 3
Rock classification at the Pyongtaek project site
Type: A B C D E
Description Sound gneiss with Sound gneiss with joints Weathered gneiss with Weathered mica Poor mica schist
scattered joints or sound mica schist joints, clay filled schist with joints
Quality Q Quality Q Quality Q Quality Q Quality Q
Roof Good 14 Fair 9.4 Fair 5 Poor 3.33 Ext. Poor –
Wall Very Good 70 Good 23.5 Good 12.5 Fair 8.3 Ext. Poor –
Intersection Fair 4.7 Poor 3 Poor 1.7 Poor 1.11 Ext. Poor –
468 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

Fig. 8. Reinforcement design in different rock mass types.

Fig. 9. Typical cross-section of the storage cavern.


J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 469

3.2. Determination of cavern geometry vation method, reinforcement pattern, and construction
cost also need to be considered. The bottom line is that
Determination of the cavern geometry requires infor- the compressive stress regime to prevent the opening of
mation on in situ stress and mechanical properties of the discontinuities around the crown should be guaran-
rock as well as hydrogeological feature at the site. Exca- teed. In addition, the compressive stress on the wall and

Fig. 10. Behavior of rock blocks around the storage cavern by UDEC analysis.
470 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

the stress concentration around the corners should be studied (Hoek and Brown, 1980). The cross-sectional
minimized. In this project, egg shaped cross-section area was designed to be 320 m2 which was the greatest
was selected considering the stress distribution and exca- figure given the limited geological conditions. Fig. 9
vation efficiency after many domestic case histories of shows the typical cross-sectional dimension of the
the egg shaped tunnel cross-section were collected and cavern.

Fig. 11. Distribution of stress and displacement around the storage cavern by FLAC analysis.
J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 471

3.3. Stress analysis 4. Hydrogeological design

Stress analysis around the cavern was done by using 4.1. Hydrogeological investigations
numerical methods, DEM and FDM. The input param-
eters for the DEM analysis are as follows: The most important issue in the construction of an
For isotropic rock mass: underground hydrocarbon storage facility is the pre-
vention of leakage. In order to prevent the leakage,
YoungÕs modulus (E) = 50 GPa the water curtain system was constructed under the
PoissonÕs ratio (m) = 0.25 design criteria as shown in Table 4. Fig. 12 shows
cross-sectional view of the cavern and the water cur-
For anisotropic rock mass: tain tunnel. The groundwater pressure distribution
around the storage cavern before and after the con-
YoungÕs modulus (E1) = 1.2 GPa struction of water curtain was analyzed using a
YoungÕs modulus (E2) = 3.4 GPa FEM code. To obtain the input parameters, the fol-
Shear modulus (G) = 3.5 GPa lowing field tests have been conducted (SK Construc-
PoissonÕs ratio (m) = 0.25 tion Co., 1998).
*Measured from the laboratory tests.
(a) Water level observation during and after drilling in
The input parameters for UDEC analysis were all boreholes.
YoungÕs modulus of 50 GPa and PoissonÕs ratio of (b) In situ testing in boreholes.
0.25. CoulombÕs failure criterion was used in this analy-  falling head test,
sis. The results of the analyses showed that there was no  short duration water injection test: Lugeon test
tensile stress regime around the cavern and the inward and injection fall-off test,
displacement of the wall was less than 20 mm. Thus, it  long duration water injection test: constant
was concluded that the caverns are stable and safe. pressure flow test,
Figs. 10 and 11 show the results of UDEC and FLAC  long duration interference test,
analyses, respectively.  long duration pumping test.

Table 4
Design criteria of water curtain system
Facilities Tunnel interval (m) Injection pressure (bar) Water curtain depth (msl) Tunnel length (m) Distance from cavern (m)
Pyongtaek 10 9.5–10 90 100–110 25

Fig. 12. Cross-sectional view of the cavern and the water curtain tunnel.
472 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

Table 5
Determination of cavern depth
Parameters Values
Maximum allowed storage pressure [1] 88 m water head
Shape factor [2] 12 m water head
Safety factor [3] 15 m water head
Water level in access tunnel [4] 0 m sea level
Storage depth [5] = [4]  [1]  [2]  [3] = 115 m sea level

The hydraulic conductivity was measured to be


1 · 106 m/s at the depth of less than 40 m from the sur-
face. The pumping and short-term injection tests re-
vealed that there was lateral continuity in hydraulic
conductivity. The layer had the porosity of 10% and
the conductivity ranged from 4 · 106 to 4 · 104 m/s.
At the depth of 115 m below sea level where the cavern
was to be constructed, the conductivity was as low as
1 · 1012 m/s. The numerical analysis revealed a very
low flow rate around the cavern and weak continuity
at this depth. Therefore, the results of hydrogeological
Fig. 13. Conceptual view of the tightness of the cavern. investigations indicated that the condition at the site

Fig. 14. Surface layout of the water curtain tunnels.


J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 473

was favorable toward construction of underground 4.3. Water curtain system design
LPG storage caverns underneath the Lake Namyang.
In order to prevent the hydrogeologic interference
with the existing caverns and to guarantee the tightness
4.2. Hydrogeological condition
of the storage cavern, three types of water curtain sys-
tem were installed: vertical surface water curtain, verti-
The tightness of the unlined rock cavern is obtained
cal underground water curtain, and horizontal
by the hydrogeological design. The pressure head
underground water curtain system. The vertical surface
around the cavern should be greater than that inside
water curtain was installed between the entrance of the
the cavern on order to have the flow directed inward
access tunnel and the existing butane storage caverns
the cavern as shown in Fig. 13. The condition for the
as shown in Fig. 14. This was intended to prevent the in-
tightness can be expressed using the following equation.
flow of surface water through the access tunnel and the
U0 P Ustor þ ðS f þ SÞ; ð1Þ inflow in the process of constructing the shaft. The ver-
tical underground water curtain system was constructed
where U0 is the hydraulic head at the crown, Ustor is the at the depth between 55 and 155 m at an interval of
maximum pressure head inside the cavern, Sf is shape 20 m as shown in Fig. 15. Thus, the hydrogeologic inter-
factor, and S is the factor of safety. The designed depth ference between the new and the existing caverns can be
of the cavern was determined as shown in Table 5. minimized. The horizontal water curtain system pre-
Fig. 12 shows the proposed depth of the cavern and vents the dewatering in the rock mass and guarantees
its cross-sectional view. the maximum allowable storage pressure of 8.87

Fig. 15. Underground layout of the water curtain tunnels.


474 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

kg/cm2 which satisfies the tightness condition. The hor- was carried out as shown in Fig. 17. The boreholes were
izontal system was installed from the horizontal water drilled from the water surface for the blast vibration mon-
curtain tunnels located 25 m above the cavern in the itoring: borehole y-14 as the blasting hole and boreholes
downward direction (from EL 89 to EL 95 m) with BH2 and BH3 as monitoring holes. The maximum dis-
the same interval. The interval was determined to be placement at the dike was measured at 0.08 mm and the
10 m in order to minimize the number of tunnels consid- peak particle velocity due to the blasting at 2.8 mm/s.
ering the frictional head loss of 5–10 m and the con- The frequency of the dike body was determined to be
struction cost. Fig. 16 shows the plan view of the 7.55 cycles/s.
water curtain tunnels. The preliminary stability analysis of the dike was in-
cluded in the earlier feasibility study of the project. In
the stability analysis, nonlinear behavior of the rock
5. Stability of the existing structures mass due to the blasting was modeled using two-
dimensional discrete element method (UDEC). Results
5.1. Stability of the existing dike of the analysis presented the time-dependent distribu-
tion of the displacements and the particle velocities of
In order to ensure stability of Namyang Dike located the surface and underground structures due to the
in the west of the cavern, blast vibration monitoring test blasting in vicinity of the cavern. Fig. 18 shows mesh

Fig. 16. Plan view of the horizontal water curtain tunnels.


J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 475

Fig. 17. Schematic diagram of the blast vibration monitoring test.

Fig. 18. Mesh generation for the numerical analysis. Fig. 19. Displacement vector plot at the elapsed time of 0.6 s.

generation within the boundary of the analysis, 400 m in ern should be prevented by constructing the vertical
width and 138 m in depth. Figs. 19 and 20 present the water curtain system around the access tunnels and the
distribution of the displacement and particle velocity shaft. The preliminary design suggested the separation
vector in the vicinity of the dike, respectively. It was distance between the caverns to be 400 ± 25 m, however,
concluded that the blasting did not greatly affect the sta- considering the results of the numerical study on hydro-
bility of the embankment (Park, 1993). geological data along with the installation of the vertical
water curtain system, the separation distance was set at
5.2. Stability of the neighboring butane caverns 350 m.

One of the immediate concerns in construction and


operation of the new cavern is the stability of the neigh- 6. Layout of the cavern
boring caverns. For this reason, the caverns should be
separated at a safe amount of distance. In addition, The final location of the caverns was determined after
the dewatering of the rock mass around the existing cav- consideration of the followings: geology, hydrogeological
476 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

characteristics and mechanical properties of rock


mass, stability of the neighboring structures, and com-
plaints of the neighbors near the project site. Among
them, the most important factors considered are as
follows:

(a) fault zone in the northern edge,


(b) minor fault in the eastern edge,
(c) safe distance from the fault zone,
(d) safe distance from the existing caverns,
(e) safe distance from wells in the residential
area,
(f) safe distance (40 m) from the nearest residential
area,
(g) access tunnel entrance, plug installation position,
and topography,
(h) long-term stability and tightness.
Fig. 20. Particle velocity vector plot at the elapsed time of 0.6 s.

Table 6
Dimension of caverns and tunnels at the Pyongtaek project site
Cavern A Cavern B Cavern C Cavern D Cavern Total Connection tunnel Construction tunnel Plug
Length (m) 80.00 232.00 278.00 150.00 740 364.00 181.45 5.23
Width · height (m · m) 13.5 · 14.5 17.5 · 22.0 17.4 · 22.0 17.4 · 22.0 – 8.0 · 7.5 8.0 · 7.5 8.0 · 7.5
Area (m2) 160.2 320.34 320.34 320.34 – 53.13 53.13 53.13
Capacity (m3) 12,816 74,319 89,055 48,051 224,241 19,339 9640 –

Fig. 21. Plan view of the finalized cavern layout.


J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478 477

Fig. 22. Cross-sectional view of the finalized cavern layout.

The followings outline the final layout of the cavern. Oct. 6, 1997: Excavation of the shaft began.
Nov. 6, 1997: Completion of the vertical water cur-
(a) Distance to the fault zone: 30 m, tain system.
(b) clearance to the site boundary: 40 m, Nov. 15, 1997: Excavation of the horizontal water
(c) distance to the existing caverns: 350 m, curtain began.
(d) avoid areas of poor rock mass condition as much Jan. 24, 1998: Completion of the horizontal water
as possible. curtain system.
Feb. 2, 1998: Completion of the access tunnel.
The final cavern complex was 740 m in length and Feb. 24, 1998: Excavation of the storing cavern gal-
224,000 m3 in capacity, which was smaller than the pro- lery began.
posed capacity by 75,000 m3 (SK Construction Co., Nov. 16, 1998: Completion of the storing cavern
1999). Table 6 summarized the dimension and capacity bench II.
of caverns at the site. Figs. 21 and 22 show the plan Jan. 30, 1999: Installation of the shaft plug began.
and cross-sectional view of the finalized cavern layout. Mar. 10, 1999: Completion of the shaft plug
installation.
Feb. 25, 1999: Installation of the access tunnel plug
7. Conclusions began.
Mar. 27, 1999: Completion of the access tunnel plug
The design of the LPG storage terminal construction installation.
underneath a lake required a considerable amount of Mar. 29, 1999: Water filling in the access tunnel.
engineering judgments concerning the stability of the cav- Jul. 5, 1999: LPG supply in the storage cavern.
ern, tightness of the cavern, and the hydrogeological
interference with the neighboring storage cavern. For
the best result, many different types of geophysical and References
hydrogeological investigation and evaluation methods
Barton, N., Grimstad, E., Aas, G., Opsahl, O., Bakken, A., Pedersen,
were successfully used. Continuous monitoring during L., Johansen, E.D., 1992. Norwegian Method of Tunnelling. World
the construction and operation of the project demon- Tunnelling (June/August).
strated that the design of the cavern was done successfully. Bittkow, P., Riechel, M., Boor, G., 1997. Management of a
From a practical viewpoint, this type of storage cavern is complex cavern storage facility for natural gas. In: Proceedings
of particular importance in efficient use of the land. of the SPE Annual Technical Conference and Exhibition, pp.
219–228.
Hamberger, U., 1991. Case History: Blowout at an LPG storage
cavern in Sweden. Tunnelling and Underground Space Technology
8. Major construction milestone 6, 119–120.
Hoek, E., Brown, E.T., 1980. Underground Excavations in Rock.
IMM, London.
Jun. 4, 1997: First blasting for the access tunnel. Lee, D.S., 1988. Geology of Korea, second ed. Kyohak-sa, Seoul.
Sep. 2, 1997: Excavation of the vertical water curtain Lee, Y.N., Suh, Y.H., Kim, D.Y., Jue, K.S., 1997. Stress and
began. deformation behavior of oil storage caverns during excavation.
478 J.J. Park et al. / Tunnelling and Underground Space Technology 20 (2005) 463–478

International Journal of Rock Mechanics and Mining Sciences 34, Sun-Kyung Construction Co., 1995, Report of preliminary design of
573. Pyongtaek LPG storage terminal, Korea.
Park, J.J., 1993. A study on the simulation of blasting in tunnels using True, W.R., 1998. Monitoring safety systems for LNG and LPG
numerical models. MasterÕs Thesis, Yonsei University, Seoul operators. Oil and Gas Journal 96, 49–51.
Korea. Winqvist, T., 1989. Proposed future underground projects in
SK Construction Co., 1998, Report of structural and hydrogeological Sweden. Tunnelling and Underground Space Technology 4,
analysis in Pyongtaek LPG storage terminal project, Korea. 143–149.
SK Construction Co., 1999, Final report of Pyongtaek LPG storage Zhao, J., Bergh-Christensen, J., 1996. Construction and utilization of
terminal project, Korea. rock caverns in Singapore – Part D: Two proposed cavern schemes.
Sturk, R., Stille, H., 1995. Design and excavation of rock caverns for Tunnelling and Underground Space Technology 11, 85–91.
fuel storage – A case study from Zimbabwe. Tunnelling and Zhao, J., Choa, V., Broms, B.B., 1996. Construction and utilization of
Underground Space Technology 10, 193–201. rock caverns in Singapore – Part B: Development costs and
Sun-Kyung Construction Co., 1992, Report of geological site inves- utilization. Tunnelling and Underground Space Technology 11,
tigation of Pyongtaek LPG storage terminal, Korea. 73–79.

You might also like