RENCANA ANGGARAN BIAYA

PEKERJAAN : Pengadaan dan Pemasangan Airfield Lighting System (AFL), Serta Pergeseran dan Pemasangan PAPI Akibat
Perpanjangan Landas Pacu, 1 Paket.
LOKASI : Bandar Udara Oesman Sadik - Labuha
ANGGARAN : DIPA Tahun 2016

No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga


Rp. Rp.
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
- Melaksanakan pekerjaan inventarisasi peralatan Airfield Lighting System 1 Lot 5,000,000 5,000,000
AFL yang dibutuhkan, pembongkaran, pembersihan dan perapihan ruangan
Jumlah Rp. 5,000,000
A. TOTAL PEKERJAAN PERSIAPAN Jumlah Rp. 5,000,000
B. PEKERJAAN PENGADAAN MATERIAL

I PENGADAAN RUNWAY EDGE LIGHT


1 High Intensity elevated Runway light complete clear /clear 150 W/6.6 A. 8 Unit 5,250,000 42,000,000
2 Isolating Transformer 150 W;6,6 A 8 Pcs 4,000,000 32,000,000
3 Connector kit terdiri dari FAA-plug dan socket single pole. 8 Set 1,300,000 10,400,000
4 Two pole plug connector kit. 8 Pcs 500,000 4,000,000
5 Series cable FL2XCY 1x6 Sqmm, 3/6 kV. 1500 M' 40,000 60,000,000
6 Secondary cable NYYHY 2 x 2.5 Sqmm 20 M' 15,000 300,000
7 Pipe diameter 2" pave shoulder termasuk instalasi. 20 M' 100,000 2,000,000
Joint sleeve FL2XCY 1x 6 Sqmm 3/6 kV. 4 Set 500,000 2,000,000
9 Base plate 8 Pcs 1,000,000 8,000,000
Jumlah Rp. 160,700,000
II PENGADAAN THRESHOLD LIGHT

1 Connector kit terdiri dari FAA-plug dan socket single pole. 16 Set 1,300,000 20,800,000
2 Two pole plug connector kit lengkap 16 Pcs 500,000 8,000,000
3 Secondary cable NYHY 2 x 2,5 Sqmm 500 M 20,000 10,000,000
4 Pipa PVC 5/8" pelindung kabel NYHY 2 x 2,5 sqmm 20 M' 100,000 2,000,000
Jumlah Rp. 40,800,000

III PENGADAAN TURNING AREA LIGHT

1 Omnidirectional Elevated Light Complete Blue 100 W;6.6A. 8 Unit 4,750,000 38,000,000
2 Isolating transformer 100 W; 6,6 A. 8 Pcs 3,750,000 30,000,000
3 Connector kit terdiri dari FAA-plug dan socket single pole. 8 Set 1,300,000 10,400,000
4 Pipe PVC diameter 2" pave shoulder termasuk instalasi 8 Pcs 250,000 2,000,000
5 Base plate. 8 Pcs 1,000,000 8,000,000
Jumlah Rp. 88,400,000

IV PENGADAAN PAPI

1 PAPI unit complete. 4 Unit 45,000,000 180,000,000


2 Isolating transformer 200 W; 6.6/6,6 A. 8 Pcs 4,500,000 36,000,000
3 Series cable FL2XCY 1 x 6 Sqmm, 3/6 kV. 3000 M' 40,000 120,000,000
4 Connector kit terdiri dari FAA-plug dan socket single pole. 16 Pcs 1,300,000 20,800,000
5 Two pole plug connector kit. 16 Pcs 500,000 8,000,000
6 Control cable 2 x 10 x 0,8 sqmm/1kV 20 M' 40,000 800,000
7 Power Cable NYY 4 x 10 Sqmm 20 M' 98,000 1,960,000
8 Joint Sleeve FL2XCY 1x 6 sqmm, 3/6 kV 4 Set 500,000 2,000,000
9 CCR 4/5 kVA 220 V , 5 Step, include selector cabinet 1 Unit 150,000,000 150,000,000
Jumlah Rp. 519,560,000

V PENGADAAN GROUNDING UNTUK AFL


1 BC 50 2000 M' 60,000 120,000,000
2 BC 16 300 M' 20,000 6,000,000
3 Kabel grounding 6 mm 20 M' 15,000 300,000
4 Baut, nepel, cable schoen. 1 Lot 2,000,000 2,000,000
Jumlah Rp. 128,300,000
B. TOTAL PENGADAAN MATERIAL Jumlah Rp. 937,760,000

Page 1
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
C. PEKERJAAN CIVIL WORK
I PEKERJAAN PEMBONGKARAN, PEMBERSIHAN
DAN PENYIMPANAN PERALATAN AFL

1 Threshold light :
a. Lampu Threshold light 150 W/6,6 A 16 Pcs 150,000 2,400,000
b. Isolating transformer 150 W/6,6 A 16 Pcs 150,000 2,400,000
c. Two pole plug connector kit 16 Pcs 150,000 2,400,000
d. Anchor stake/baseplate 16 Pcs 150,000 2,400,000
Jumlah Rp. 9,600,000
2 PAPI
a. Box PAPI 4 unit 150,000 600,000
b. Isolating transformer 150 W/6,6A 8 Pcs 150,000 1,200,000
c. Two pole plug connector kit 8 Pcs 100,000 800,000
d. Anchor stake/baseplate 8 Pcs 100,000 800,000
Jumlah Rp. 3,400,000

II PEKERJAAN PEMBUATAN BAK TRAFO


1 Size 1.
a. Runway light. 8 Pcs 750,000 6,000,000
c. PAPI. 8 Pcs 750,000 6,000,000
Jumlah Rp. 12,000,000

2 Size 2
- Threshold light 2 Pcs 1,500,000 3,000,000
Jumlah Rp. 3,000,000

III PEKERJAAN PEMBUATAN PONDASI


1 Base plate Runway light berikut tapring 1m2. 14 Pcs 1,000,000 14,000,000
2 Base plate Threashold light berikut tappring 1 m2 16 Pcs 1,000,000 16,000,000
3 Base plate Turning area light berikut tapring 1m2. 8 Pcs 1,000,000 8,000,000
4 Pondasi PAPI. 8 Pcs 1,500,000 12,000,000
5 Pembuatan lantai box PAPI ukuran 3 x 30 meter 2 Pcs 7,000,000 14,000,000
6 Pondasi Ground check PAPI 8 Pcs 300,000 2,400,000
Jumlah Rp. 66,400,000

IV PEKERJAAN PENANAMAN KABEL SERIES,


POWER, CONTROL, DAN BC 50 SQMM.
1 Untuk size 1 (1-5 jalur) 2000 meter
a. Galian tanah 800 M3 40,000 32,000,000
b. Pasir urug 170 M3 155,000 26,350,000
c. Batu bata 30000 Buah 1,000 30,000,000
d. Penggelaran : - Kabel series FL2XCY 7000 M' 2,000 14,000,000
- BC 50 Sqmm 2000 M' 2,000 4,000,000
- BC 16 Sqmm 300 M' 2,000 600,000
e. Urugan kembali 630 M3 22,200 13,986,000
Jumlah Rp. 120,936,000
C. TOTAL CIVIL WORK Jumlah Rp. 215,336,000
D. INSTALASI
I INSTALASI RUNWAY LIGHT
1 Pekerjaan pengukuran tempat-tempat kedudukan Runway light. 1 Paket 5,000,000 5,000,000
2 Pekerjaan pemasangan base plate pada pondasi. 8 Pcs 200,000 1,600,000
3 Pekerjaan pemasangan dan penyetelan Runway light terdiri dari:
a. High Intensity elevated Runway light complete clear/clear 150 W; 6,6 A. 8 Pcs 200,000 1,600,000
4 Pekerjaan pemasangan dan instalasi iso trafo 150 W; 6,6 A. 8 Pcs 200,000 1,600,000
5 Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit untuk sambungan series cable. 8 Pcs 200,000 1,600,000
b. Two pole plug connector kit. 8 Set 200,000 1,600,000
c. Series cable FL2XCY 1 x 6 Sqmm/1kV. 2000 M' 2,000 4,000,000
Jumlah Rp. 17,000,000
II INSTALASI THRESHOLD LIGHT

1 Pekerjaan pengukuran tempat-tempat kedudukan Threshold Light 1 Paket 3,000,000 3,000,000


2 Pekerjaan pemasangan Base plate 16 Pcs 200,000 3,200,000
3 Pekerjaan pemasangan dan penyetelan :
a. High Intensity elevated threshold light Complete green 150 W;6.6A 10 Unit 200,000 2,000,000
b. High Intensity elevated threshold light Complete Red 150 W;6.6A 6 Unit 200,000 1,200,000
4 Pekerjaan pemasangan dan instalasi :
a. Isolating transformer 150 W; 6.6/6,6 A. 16 Pcs 200,000 3,200,000
b. Connector kit untuk sambungan kabel series 16 Set 200,000 3,200,000
c. Two pole plug connector kit 16 Set 200,000 3,200,000
Jumlah Rp. 19,000,000

Page 2
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6

Page 3
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
III INSTALASI TURNING AREA LIGHT

1 Pekerjaan pengukuran tempat-tempat kedudukan turning area light 1 Paket 3,000,000 3,000,000
2 Pekerjaan pemasangan Base plate 8 Pcs 200,000 1,600,000
3 Pekerjaan pemasangan dan penyetelan Turning Area Light 100 W;6,6 A 8 Pcs 200,000 1,600,000
4 Pekerjaan pemasangan dan instalasi iso trafo 100 W; 6,6 A 8 Pcs 200,000 1,600,000
5 Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit untuk sambungan cable series. 8 Pcs 200,000 1,600,000
Jumlah Rp. 9,400,000

IV INSTALASI PAPI
1 Pekerjaan pengukuran tempat-tempat kedudukan letak PAPI. 1 Paket 5,000,000 5,000,000
2 Pekerjaan pembuatan gambar design lokasi PAPI 1 Paket 5,000,000 5,000,000
3 Pekerjaan pemasangan anchor stake PAPI pada pondasi. 8 Set 200,000 1,600,000
4 Pekerjaan pemasangan dan instalasi iso trafo 200 W; 6,6/6,6 A 16 Pcs 200,000 3,200,000
5 Pekerjaan pemasangan/montage Box PAPI. 8 Pcs 200,000 1,600,000
6 Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit untuk sambungan series cable. 8 Pcs 200,000 1,600,000
b. Two pole plug connector kit. 16 Pcs 200,000 3,200,000
c. Series cable FL2XCY 1 x 6 Sqmm,3/6 kV. 3000 M 2,000 6,000,000
Jumlah Rp. 27,200,000

V INSTALASI POWER DAN CONTROL PAPI


- Pekerjaan instalasi CCR 4/5 kVA, 220 V, 5 Step ke MVSB eksisting dan 1 Lot 5,000,000 5,000,000
Marshalling Cabinet termasuk instalasi kontrol kabel dan power Jumlah Rp. 5,000,000

C. TOTAL INSTALASI Jumlah Rp. 77,600,000


D. Bimbingan teknis, pembuatan shop drawing, lokal training 1 Lot 10,000,000 10,000,000
evaluasi serta dokumentasi Jumlah Rp. 10,000,000
E. Commissioning 1 Lot 20,000,000 20,000,000
Jumlah Rp. 20,000,000
TOTAL A + B + C + D + E + F + G Jumlah Rp. 1,265,696,000
PPN 10 % Jumlah Rp. 126,569,600
BIAYA TOTAL Jumlah Rp. 1,392,265,600
DIBULATKAN Jumlah Rp. 1,392,300,000

MENGETAHUI, Labuha, Maret 2015


KEPALA SUBDIREKTORAT KUASA PENGGUNA ANGGARAN
PERALATAN DAN UTILITAS BANDAR UDARA BANDAR UDARA OESMAN SADIK

DJOKO PRIAMBODO INVANTRIS JAYA ALAM, S.Sos, MM.


Pembina (IV/a) Penata (III/c)
NIP. 19621023 198803 1 003 NIP. 19731215 199803 1 002

Page 4
RENCANA ANGGARAN BIAYA

PEKERJAAN : PENGADAAN DAN PEMASANGAN AIRFIELD LIGHTING SYSTEM


LOKASI : BANDAR UDARA KOMODO - LABUAN BAJO
ANGGARAN : DIPA T.A 2007

No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga


Rp. Rp.
1 2 3 4 5 6

A. PENGADAAN MATERIAL

I. PENGADAAN MEDIUM APPROACH LIGHT SYSTEM


(MALS 420 M)

1. Unidirectional Elevated light complete, clear 100 W;6,6 A 45 Unit 5,000,000 225,000,000
2. Isolating transformer 100 W;6,6 A 45 Pcs 4,000,000 180,000,000
3. Connector kit terdiri dari FAA-plug dan socket single pole 19 Set 500,000 9,500,000
4. Special resin 280 cc, 5 kV 19 Pcs 800,000 15,200,000
5. Two pole plug connector kit 45 Pcs 500,000 22,500,000
6. Flexible pipe diameter 2" 130 M' 200,000 26,000,000
7. Series cable Fl2XCY 1 x 6 Sqmm, 3/6 kV 9000 M' 40,000 360,000,000
8. Joint sleeve FL2XCY 1 x 6 Sqmm, 3/6 kV 12 Set 500,000 6,000,000
9. Power cable NYY 3 x 16 Sqmm, 1 kV 30 M' 55,000 1,650,000
10. Control cable 2 x 10 x 0,8 Sqmm, 1 kV 30 M' 20,000 600,000
11. Tiang konstruksi MALS (tiang double + tiang tunggal) 7 Set 70,000,000 490,000,000
12. Base plate 10 Pcs 1,000,000 10,000,000
13. CCR 10 kVA 220 V, 5 Step 2 Unit 180,000,000 360,000,000
Jumlah Rp 1,706,450,000
II. PENGADAAN RUNWAY EDGE LIGHT

1. High Intensity elevated runway light complete, clear/clear 150 W;6,6 A 35 Unit 5,500,000 192,500,000
3. High Intensity elevated runway light complte, clear/yellow 150 W;6,6 A 20 Unit 5,500,000 110,000,000
5. Isolating transformer 150 W;6,6 A 55 Pcs 4,500,000 247,500,000
6. Connector kit terdiri dari FAA-plug dan socket single pole 55 Set 500,000 27,500,000
7. Special resin 280 cc FAA-plug, 5 kV 55 Pcs 800,000 44,000,000
8. Two pole plug connector kit 55 Set 500,000 27,500,000
9. Series cable FL2XCY 1 x 6 Sqmm, 3/6 kV 9500 M' 40,000 380,000,000
10. Base plate 55 Pcs 1,000,000 55,000,000
11. Pipe PVC diameter 2" pave shoulder termasuk instalasi 55 Pcs 200,000 11,000,000
12. Joint sleeve FL2XCY 1 x 6 Sqmm, 3/6 kV 15 Set 500,000 7,500,000
13. Power cable NYY 3 x 16 Sqmm, 1 kV 30 M' 67,250 2,017,500
14. Control cable 2 x 10 x 0,8 Sqmm, 1 kV 30 M' 30,000 900,000
15. CCR 10 kVA 220 V, 5 Step. 2 Unit 180,000,000 360,000,000
Jumlah Rp 1,465,417,500
III. PENGADAAN TURNING AREA LIGHT

1. Omnidirectional Elevated Light Complete Blue 30/45 W;6.6A. 10 Unit 4,500,000 45,000,000
2. Isolating transformer 30/45 W; 6.6/6,6 A. 10 Pcs 3,500,000 35,000,000
3. Connector kit terdiri dari FAA-plug dan socket single pole. 10 Set 500,000 5,000,000
4. Special resin 280 cc FAA-plug, 5 kV. 10 Set 800,000 8,000,000
5. Two pole plug connector kit. 10 Set 500,000 5,000,000
6. Base plate 10 Pcs 1,000,000 10,000,000
Jumlah Rp. 108,000,000
IV. PENGADAAN THRESHOLD LIGHT.

1. High Intensity elevated threshold light Complete green/red 150 W;6.6A 12 Unit 5,500,000 66,000,000
2. High Intensity elevated threshold light Complete green/blank 150 W;6.6A 8 Unit 5,500,000 44,000,000
3. Isolating transformer 150 W; 6.6/6,6 A. 20 Pcs 4,500,000 90,000,000
4. Connector kit terdiri dari FAA-plug dan socket single pole. 8 Set 500,000 4,000,000
5. Special resin 280 cc FAA-plug, 5 kV. 20 Set 800,000 16,000,000
6. Two pole plug connector kit lengkap dengan kabel 20 Pcs 700,000 14,000,000
NYHY 2 x 2,5 Sqmm
7, Pipa PVC 5/8" pelindung kabel NYHY 2x2 sqmm 120 M 100,000 12,000,000

Page 5
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
8, Base plate 20 Pcs 1,000,000 20,000,000
Jumlah Rp. 266,000,000

Page 6
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
IV. PENGADAAN TAXIWAY EDGE LIGHT DAN APRON
LIGHT

1. Omnidirectional Elevated light complete blue 30/45 W;6,6 A 15 Unit 4,500,000 67,500,000
2. Omnidirectional Elevated light complete red 30/45 W;6,6 A 9 Unit 4,500,000 40,500,000
3. Isolating transformer 30/45 W;6,6 A 24 Pcs 3,500,000 84,000,000
4. Connector kit terdiri dari FAA-plug dan socket single pole 24 Set 500,000 12,000,000
5. Special resin 280 cc FAA-plug, 5 kV 24 Pcs 800,000 19,200,000
6. Two pole plug connector kit 24 Pcs 500,000 12,000,000
7. Pipe PVC diameter 2" pave shoulder termasuk instalasi 24 M' 200,000 4,800,000
8. Series cable FL2XCY 1 x 6 Sqmm, 3/6 kV 2000 M' 40,000 80,000,000
9. Base plate 24 Pcs 1,000,000 24,000,000
10. Joint sleeve FL2XCY 1 x 6 Sqmm, 3/6 kV 5 Set 500,000 2,500,000
11. Power cable NYY 3 x 16 Sqmm, 1 kV 30 M' 67,250 2,017,500
12. Control cable 2 x 10 x 0,8 Sqmm, 1 kV 30 M' 30,000 900,000
13. CCR 7,5 kVA 220 V(1 phase) 5 Step 1 Unit 130,000,000 130,000,000
Jumlah Rp. 479,417,500
V. PENGADAAN PAPI

1. PAPI unit complete. 4 Unit 45,000,000 180,000,000


2. Isolating transformer 200 W; 6.6/6,6 A. 8 Pcs 3,500,000 28,000,000
3. Series cable FLYCY 1x6 Sqmm/ 3/6 kV. 6000 M' 40,000 240,000,000
4. Selector cabinet. 1 Unit 80,000,000 80,000,000
5. Connector kit terdiri dari FAA-plug dan socket single pole. 8 Set 500,000 4,000,000
6. Special resin 280 cc FAA-plug, 5 kV. 8 Set 1,000,000 8,000,000
7. Two pole plug connector kit. 8 Pcs 250,000 2,000,000
8. Clinometer 1 Unit 40,000,000 40,000,000
9. CCR 4 kVA 220 V (1 phase) 5 step 1 Unit 110,000,000 110,000,000
Jumlah Rp. 692,000,000
VI. PENGADAAN RTIL

1. Lampu RTIL lengkap dengan Gear Box control unit. 2 Unit 100,000,000 200,000,000
2. Ground Power Cable NYFGbY 4 x 10 Sqmm, 1 kV. 1200 M' 57,000 68,400,000
3. Control Cable 2 x 10 x 0,8 Sqmm. 300 M' 32,500 9,750,000
4. Flexible conduit. 2 Set 100,000 200,000
Jumlah Rp. 278,350,000
VII. PENGADAAN POWER DAN CONTROL SYSTEM AFL

1. Power cable NYFGbY 4 x 50 Sqmm/1kV 50 M' 190,000 9,500,000


2. Control cable 60 x 2 x 0,8 Sqmm 500 M' 40,000 20,000,000
3. Alat bantu instalasi 1 Lot 5,000,000 5,000,000
Jumlah Rp. 34,500,000
VIII. PENGADAAN GROUNDING UNTUK MALS, REH dan TXE
1. BC 50 6000 M' 50,000 300,000,000
2. BC 16 1300 M' 20,000 26,000,000
3. BC 6 300 M' 10,000 3,000,000
4. Copper Rod (1 M) 17 Pcs 500,000 8,500,000
Jumlah Rp. 337,500,000
IX. PENGADAAN SUKU CADANG AFL

1. Bulb untuk TXA/TXE 30 W; 6,6 A 5 Pcs 500,000 2,500,000


2. Bulb R/W light 150 W; 6,6 A 5 Pcs 600,000 3,000,000
3. Bulb untuk PAPI 200 W; 6,6 A 5 Pcs 600,000 3,000,000
4. Bulb untuk T/H light 150 W; 6,6 A 5 Pcs 600,000 3,000,000
5. Isolating transformer 150 W; 6,6/6,6 A 5 Pcs 3,500,000 17,500,000
6. Isolating transformer 30/45 W; 6,6/6,6 A 5 Pcs 3,500,000 17,500,000
6. High Intensity Elevated Light Complete clear 150W;6.6A. 5 Unit 5,500,000 27,500,000
7. High Intensity Elevated Light Complete Blue 30W;6.6A. 5 Unit 4,500,000 22,500,000
8. High Intensity Elevated Light Complete clear 100 W;6,6 A 5 Unit 5,500,000 27,500,000
Jumlah Rp. 124,000,000

Page 7
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
A. TOTAL PENGADAAN MATERIAL Jumlah Rp. 5,491,635,000

Page 8
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
B. PEKERJAAN CIVIL WORK

1. PEKERJAAN PEMBUATAN BAK TRAFO


1. Size 1 :
a. Runway Edge Light 55 Pcs 750,000 41,250,000
b. Turning Area 10 Pcs 750,000 7,500,000
c. Taxiway/Apron Light 24 Pcs 750,000 18,000,000
2. Size 2 :
a. MALS 9 pcs 1,500,000 13,500,000
b. Threshold Light 4 Pcs 1,500,000 6,000,000
Jumlah Rp. 86,250,000
II. PEKERJAAN PEMBUATAN PONDASI

1. CCR Runway Edge Light 2 Pcs 1,500,000 3,000,000


2. CCR MALS 2 Pcs 1,500,000 3,000,000
3. CCR Taxiway dan Apron Light 1 Pcs 1,500,000 1,500,000
4. CCR PAPI 1 Pcs 1,500,000 1,500,000
5. Konstruksi REIL 2 Pcs 1,500,000 3,000,000
6. Konstruksi MALS 7 Pcs 1,500,000 10,500,000
7. Pembersihan lahan untuk pemasangan tiang lampu MALS 1 Lot 10,000,000 10,000,000
8. Ground Mounted 10 Pcs 750,000 7,500,000
9. Base plate Runway Edge Light 55 Pcs 750,000 41,250,000
10. Base plate Turning Area Light 10 Pcs 750,000 7,500,000
11. Base plate Taxiway dan Apron Light 24 Pcs 750,000 18,000,000
12. Base plate Threshold Light 20 Pcs 750,000 15,000,000
Jumlah Rp. 121,750,000
III. PENANAMAN KABEL SERIES, POWER, CONTROL
DAN BC 50 Sqmm.
1. Untuk size 1 (1 - 5 jalur) 5600 meter.
a. Galian tanah 2240 M3 33,700 75,488,000
b. Pasir urug 476 M 3
87,700 41,745,200
c. Batu bata 84000 Buah 440 36,960,000
d. Penggelaran : - Series cable 5600 M' 2,000 11,200,000
- BC 50 Sqmm 4800 M' 1,000 4,800,000
- Power cable 2000 M' 2,500 5,000,000
- Control cable 300 M' 2,500 750,000
e. Urugan kembali 1764 M3 25,000 44,100,000
2. Untuk size 2 (6 - 10 jalur) 2800 meter.
a. Galian tanah 1456 M3 33,700 49,067,200
b. Pasir urug 343 M 3
87,700 30,081,100
c. Batu bata 84000 Buah 440 36,960,000
d. Penggelaran : - Series cable 2800 M' 2,000 5,600,000
- BC 50 Sqmm 2200 M' 1,000 2,200,000
e. Urugan kembali 1113 M3 25,000 27,825,000
1 Untuk size 3 (10-15 jalur) 500 meter.
a. Galian tanah 330 M3 33,700 11,121,000
b. Pasir urug 76.5 M3 87,700 6,709,050
c. Batu bata 17500 Buah 440 7,700,000
d. Penggelaran : - Series cable 5400 M' 2,000 10,800,000
- BC 50 Sqmm 500 M' 1,000 500,000
e. Urugan kembali 250 M3 25,000 6,250,000
3. Cutting aspal jalan raya untuk jalan kabel MALS 10 M' 500,000 5,000,000
4. Cutting aspal Taxiway untuk jalan kabel dengan PVC dan 50 M' 500,000 25,000,000
pengaspalan kembali Jumlah Rp. 444,856,550
B. TOTAL CIVIL WORK Jumlah Rp. 652,856,550

Page 9
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6

C. PEKERJAAN INSTALASI
I. INSTALASI MEDIUM APPROACH LIGHT SYSTEM
(MALS 420 M) R/W-32

1. Pekerjaan pembersihan dan perataan tanah didaerah approach 1 Paket 10,000,000 10,000,000
2. Pekerjaan pengukuran tempat-tempat kedudukan approach 1 Paket 5,000,000 5,000,000
light (MALS).
3. Pekerjaan pembuatan peta ukur untuk elevasi tanah 1 Paket 3,500,000 3,500,000
4. Pekerjaan pemasangan tiang konstruksi MALS 7 Set 1,500,000 10,500,000
5. Pekerjaan pemasangan ground mounted 10 Pcs 1,500,000 15,000,000
6. Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit terdiri dari FAA-plug dan socket single pole 27 Set 250,000 6,750,000
b. Two pole connector kit 45 Set 250,000 11,250,000
c. Series cable FL2XCY 1 x 6 Sqmm, 3/6 kV 9000 M' 2,000 18,000,000
d. Joint sleeve FL2XCY 1 x 6 Sqmm, 3/6 kV 15 Set 2,500 37,500
e. Power cable NYY 3 x 16 Sqmm, 1 kV 30 M' 2,500 75,000
f. Control cable 2 x 10 x 0,8 Sqmm, 1 kV 30 M' 2,500 75,000
6. Pekerjaan pemasangan/montage CCR 10 kVA keatas pondasi 2 Unit 2,500,000 5,000,000
dan instalasi series cable approach light.
7. Pekerjaan pemasangan lampu MALS pada tiang konstruksi 45 Pcs 500,000 22,500,000
8. Pekerjaan pemasangan dan instalasi iso trafo 150 W;6,6 A 45 Pcs 300,000 13,500,000
9. Line up dan test 1 Lot 5,000,000 5,000,000
Jumlah Rp. 126,187,500
II. INSTALASI RUNWAY EDGE LIGHT

1. Pekerjaan pengukuran tempat-tempat kedudukan Runway light. 1 Paket 5,000,000 5,000,000


2. Pekerjaan pemasangan dan penyetelan Runway light terdiri dari:
a.High Intensity elevated runway light complete, clear/clear 150 W;6,6 A 35 Unit 300,000 10,500,000
c.High Intensity elevated runway light complte, clear/yellow 150 W;6,6 A 20 Unit 300,000 6,000,000
3. Pekerjaan pemasangan dan instalasi iso trafo 150 W; 6,6 A. 55 Pcs 300,000 16,500,000
4. Pekerjaan pemasangan Base plate pada pondasi 55 Pcs 200,000 11,000,000
5. Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit untuk sambungan series cable. 55 Set 250,000 13,750,000
b. Two pole plug connector kit. 55 Set 250,000 13,750,000
c. Control cable 2x10x0,8 Sqmm. 30 M' 2,500 75,000
6. Pekerjaan pemasangan/montage CCR 10 kVA ke atas pondasi 2 Unit 2,500,000 5,000,000
dan instalasi kabel series R/W.
7. Line up dan test. 1 Lot 5,000,000 5,000,000
Jumlah Rp. 86,575,000
III. INSTALASI TURNING AREA LIGHT
1. Pekerjaan pengukuran tempat-tempat kedudukan Turning 1 Paket 5,000,000 5,000,000
Area Light.
2. Pekerjaan pemasangan Base plate 10 Pcs 300,000 3,000,000
3. Pekerjaan pemasangan dan penyetelan Turning Area Light 10 Pcs 300,000 3,000,000
30 watt;6,6 A.
4. Pekerjaan pemasangan dan instalasi iso trafo 30/45 W; 6,6 A 10 Pcs 300,000 3,000,000
5. Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit untuk sambungan cable series. 10 Pcs 250,000 2,500,000
b. Two pole plug connector kit 10 Pcs 250,000 2,500,000
6. Line up dan test. 1 Lot 3,000,000 3,000,000
Jumlah Rp. 22,000,000

Page 10
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
IV INSTALASI THRESHOLD LIGHT
1. Pekerjaan pengukuran tempat-tempat kedudukan Threshold. 1 Paket 5,000,000 5,000,000
2. Pekerjaan pemasangan Base plate 20 Pcs 250,000 5,000,000
3. Pekerjaan pemasangan dan penyetelan :
a. Bidirectional Elevated complete green/red 15 W; 6,6 A. 12 Unit 300,000 3,600,000
b. Bidirectional Elevated complete green/blank 15 W; 6,6 A. 8 Unit 300,000 2,400,000
4. Pekerjaan pemasangan dan instalasi :
a. Isolating transformer 150 W; 6,6/6,6 A. 20 Pcs 300,000 6,000,000
b. Connector kit untuk sambungan kabel series 8 Set 250,000 2,000,000
c. Two pole plug connector kit 20 Set 250,000 5,000,000
6. Line up dan test. 1 Lot 5,000,000 5,000,000
Jumlah Rp. 34,000,000
V. INSTALASI TXE DAN TXA
1. Pekerjaan penngukuran tempat-tempat kedudukan TXE dan 1 Paket 5,000,000 5,000,000
TXA light.
2. Pekerjaan pemasangan Base plate 24 Pcs 300,000 7,200,000
3. Pekerjaan pemasangan dan penyetelan TXE dan TXA terdiri
dari :
a. Omnidirectional Elevated Light complete blue 30 W; 6,6A. 13 Unit 300,000 3,900,000
b. Omnidirectional Elevated Liight complete red 30 W; 6,6 A 8 Unit 300,000 2,400,000
4. Pekerjaan penyambungan dan instalasi :
a. Connector kit untuk sambungan series cable. 24 Set 250,000 6,000,000
b. Two pole plug connector kit. 24 Set 250,000 6,000,000
5. Pekerjaan pemasangan dan instalasi iso trafo 30/45 W;6,6/6,6A 24 Pcs 300,000 7,200,000
6. Line up dan test. 1 Lot 3,000,000 3,000,000
Jumlah Rp. 40,700,000
VI. INSTALASI RTIL

1. Pekerjaan pengukuran tempat-tempat kedudukan RTIL 1 Paket 5,000,000 5,000,000


2. Pekerjaan pemasangan lampu RTIL ke tempat pondasi 2 Unit 500,000 1,000,000
3. Pekerjaan penyambungan dan instalasi :
a. Lampu RTIL lengkap dengan Gear box control unit 2 Unit 500,000 1,000,000
b. Control cable 2 x 10 x 0,8 Sqmm 1000 M 2,500 2,500,000
5. Pekerjaan pemasangan Flexible conduit 2 Set 100,000 200,000
6. Line up dan test. 1 Lot 5,000,000 5,000,000
Jumlah Rp. 14,700,000
VII.INSTALASI PAPI
1. Pekerjaan pengukuran tempat-tempat kedudukan letak PAPI. 1 Paket 17,500,000 17,500,000
2. Pekerjaan pembuatan gambar peta ukur ketinggian tanah. 1 Paket 5,000,000 5,000,000
3. Pekerjaan pemasangan anchor stake PAPI pada pondasi. 8 Pcs 500,000 4,000,000
4. Pekerjaan pemasangan dan instalasi iso trafo 200 W; 6,6/6,6 A 8 Pcs 200,000 1,600,000
5. Pekerjaan pemasangan/montage Box PAPI. 4 Pcs 3,000,000 12,000,000
6. Pekerjaan pemasangan, penyambungan dan instalasi :
a. Connector kit untuk sambungan series cable. 8 Set 250,000 2,000,000
b. Two pole plug connector kit. 8 Pcs 100,000 800,000
c. Series cable FLYCY 1x6 Sqmm, 3/6 kV. 6000 M' 2,000 12,000,000
7. Line up dan test. 1 Lot 10,000,000 10,000,000
Jumlah Rp. 64,900,000
VIII. INSTLASI POWER DAN CONTROL SYSTEM

1. Pekerjaan penyambungan dan instalasi :


a. Power cable 4 x 50 Sqmm 50 M' 2,500 125,000
b.Control cable 60 x 2 x 0,8 Sqmm 500 M' 2,500 1,250,000
c. Power Cable NYFGbY 4 x 120 Sqmm 50 M' 2,500 125,000
Jumlah Rp. 1,500,000

Page 11
No. Jenis Pekerjaan Volume Satuan Harga Satuan Jumlah Harga
Rp. Rp.
1 2 3 4 5 6
IX. INSTALASI CCR

1. Instalasi CCR 10 kVA termasuk instalasi kabel power dari 4 Unit 9,000,000 36,000,000
MVSB ke CCR dan kabel control dari Marshalling Cabinet
2. Instalasi CCR kapasitas 4 kVA termasuk instalasi kabel 2 Unit 8,000,000 16,000,000
power dari MVSB ke CCR dan kabel control dari Marshaling
Cabinet
3. Instalasi CCR kapasitas 7,5 kVA termasuk instalasi kabel 1 Unit 8,000,000 8,000,000
power dari MVSB ke CCR dan kabel control dari Marshalling Jumlah Rp. 60,000,000
Cabinet

X. INSTALASI CONTROL DESK


1. Instalasi Control Desk lengkap termasuk instalasi kabel power 1 Unit 20,000,000 20,000,000
dan control. Jumlah Rp. 20,000,000
C. TOTAL INSTALASI Jumlah Rp. 470,562,500
D. Factory Training 2 Orang 62,500,000 125,000,000
E. Commissioning meliputi : 1 Lot 50,000,000 50,000,000
a. Bimbingan teknis peralatan
b. Evaluasi teknis peralatan
TOTAL A + B + C + D + E Jumlah Rp. 6,790,054,050
PPN 10 % Jumlah Rp. 679,005,405
BIAYA TOTAL Jumlah Rp. 7,469,059,455
DIBULATKAN Jumlah Rp. 7,500,000,000

labuan Bajo, Nopember 2006

KEPALA
BANDAR UDARA KOMODO

DWY SETIJOADIE
NIP. 120 087 618