Risk Management Plan

Issue: Traffic Congestion

Traffic Control Plan

Traffic Engineer
➢ The Proponent shall retain a qualified Traffic Engineer in accordance with the Traffic Management
Guidelines for Work on Roadways, who is responsible for designing, sealing and approving the Traffic
Control Plan(s), including all drawings and layouts.

Proponent's Traffic Control Supervisor


➢ The Proponent shall designate a qualified Traffic Control Supervisor for the works, per the
requirements. The designated Traffic Control Supervisor may be the same individual that is
designated as the Traffic Manager, or may be a separate individual qualified for the responsibilities of
this function.

Traffic Control Schedule


➢ The Proponent shall prepare a weekly traffic control schedule that documents anticipated traffic
control activities during the upcoming week. The schedule shall provide brief descriptions of the
traffic control activity (e.g. lane closure, lane shift, detour), its location, approximate implementation
date and duration. The schedule shall be provided to the Ministry Representative on a weekly basis

Provision of Services
➢ The Proponent shall be responsible for and shall bear the costs of all traffic control, including the
provision of necessary personnel and equipment, on a "lump sum" basis. All traffic control
personnel shall be qualified in accordance with WCB regulations.

Developing Traffic Management Strategies