You are on page 1of 5

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/292137796

Paramesha PIICON 2014 07117734

Data · January 2016

CITATIONS READS
0 187

1 author:

Vishwanath Hegde
Malnad College of Engineering
29 PUBLICATIONS   234 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Lightning Protection View project

Condition monitoring of Electrical Machines View project

All content following this page was uploaded by Vishwanath Hegde on 28 January 2016.

The user has requested enhancement of the downloaded file.


Techno-economic Reasons for Construction of
Electrical Substations on Step-like Ground Surface
and Related Open Issues
K Paramesha Vishwanath Hegde
Karnataka Electricity Regulatory Commission Department of Electrical Engineering
Bangalore, 560001, India Malnad College of Engineering
kparamesha@gmail.com Hassan, 573 201, India
hegde_mce@rediffmail.com

Abstract — This paper is intended to analyze the reasons switch gears, control and protective relays, current and voltage
behind the Construction of Electrical Substations by the transformers, lightning arrestors, incoming and outgoing lines
utilities on Step-like ground surfaces. Due to urbanization and associated bus bar arrangements.
and increased cost of land, the Electrical Power An elaborative earthing arrangement will be necessary at the
Transmission utilities are finding it very difficult to get substation for several reasons: (i) during an earth fault in the
suitable uniform levelled land for construction of transmission system, the fault current finds its path through
substations. This has made the utilities to use the available soil towards the substation where the neutral grounding is
land area and design tailor made substation layouts. This employed. The convergence of this large magnitude current
paper deals with the technical and economic aspects of raises the potential and potential gradient in the soil posing
such problems and that for the commonly adopted solution serious threat to the personnel at the substation. Therefore, an
– construction of substation on step-like ground. Two of elaborate grounding/earthing arrangement and earth mat
the already constructed substation will be taken for design [3] is necessary to limit the magnitude of step and
illustration. Further, the open problem associated with the touch potential to safe levels and (ii) every equipment in the
grounding for such substations will be enumerated giving Electrical substation needs to be earthed properly to facilitate
the direction for the future work. operation of the protective devices to quickly isolate the faulty
section.
Keywords— Substation grounding, Construction on step-
like ground, cost of levelling. During the monopolar operation of the HVDC line, earth
serves as a return conductor and very good substation earthing
I. INTRODUCTION is necessary not only to ensure safe operation but also to
Electrical power plays a major role in the economic minimize the energy loss. It may be noted here that the present
development of the nation as the modern society is totally work is mainly on HVAC systems and therefore, above issue
dependent on the electrical power for their day-to-day needs. is not relevant and hence not discussed.
This requirement has made power companies to adhere to
stringent reliability and quality standards so as to maintain The earth mat is interconnected to individual earth
continuous power supply to the end consumers. Practically, connections of all equipments. The chemical treatment around
the generation and utilization centres do not co-exist. the earth mat strips would be applied for better bonding of
Typically, the generation availability would be far away from earth around the earth strips.
the loads and the generated power needs to be carried to the The typical dimensions of substations constructed by utilities
load centres through long transmission lines [1]. Transmission with minimum number of terminal bays are as follows:
of power from the point of generation to the load centres is
facilitated by high voltage transmission lines and the loads are a) 400 kV substation: 400 m X 450 m
catered through different voltage substations as per the b) 220 kV substation: 150 m X 200 m
requirement [1]. c) 110 kV substation: 60 m X 80 m
d) 66 kV substation: 40 m X 60 m
Electrical substation plays a key role in power transmission
system and houses equipments for transferring and controlling The actual dimension of the substation can be larger when
the electrical energy across different voltage levels. The higher number of terminal bays are employed.
reliability and availability of substation is most important for
providing continuous power supply to the consumers. The The typical substation earth mat is designed as per the
Electrical substation mainly contains power transformers, standards to keep touch and step potentials within the safe

978-1-4799-6042-2/14/$31.00 ©2014 IEEE


limits [3]. The size and spread of earth mat in a substation
depends on the earth resistance and area available for
construction of earth mat and also the method of design. In a
substation constructed in an area of 40 m X 60 m dimension,
typically, three fourth of the area would be covered by earth
mat.

At present, availability of land with uniform surface (levelled


land) to the extent stated above is becoming very difficult to
find. The main reasons are urbanization, increasing cost of
land and non-availability of suitable size of land. This has
forced the utilities to construct substations in the available
land itself with tailor made and modified layouts.
The objective of the present work is to study the techno- Step 1 Step 2 Step 3
economic factors which force the utilities to construct (Level difference = 1.54 Mtrs)
substations in a non-uniform un-levelled terrain trimmed into
different levels (steps). Fig. 2. side view of a substation constructed on step-like ground (involving
three steps Thallak, KPTCL)
II. PRESENT WORK
The cutting and filling involved for a Techno-economical
As indicated earlier, because of cost of land and urbanization, construction of above substation in step like land surface is
the land available for construction of the substations are given in the table I.
becoming very scarce to the extent of required dimensions.
The land which are found to be available many a times have Table I- Cutting and filling Requirement in the substation area
non-uniform level (as shown in Fig. 1).
Economical Cutting Filling
Now, if the substations are to be constructed on a levelled land Level in in
from the topography of land shown in Fig.1, the construction RL-M Cu-M Cu-M
cost of the substation by levelling of the land would become 220 kV Yard 100.76 4179 4151
higher as explained in the case studies taken up below. Control Room, 99.22 1746 1728
Road and 100
MVA
Transformer
area
66 kV Yard 97.88 2991 2958
Total 8916 8837

From the above table, a total of 8916 cubic meter and 8837
cubic meter of cutting and filling has to be carried out for a
substation constructed in step like land surface. A simple
calculation of cutting and filling for normal dry soil for the
above would be Rs. 14.91 Lakh (with only Rs. 84 per cubic
meter of cutting and filling charges [2]). But, the same
substation, if decided to be constructed by levelling the
surface into a uniform single level surface, the requirement of
cutting and filling would be almost doubled with a cost of Rs.
Fig. 1. Non–uniform land for substation construction
29.82 Lakhs. This would have cost impact along with
2.1 Case studies associated technical issues discussed later.

Case study 1 Case study 2


Typical substations constructed in step levels by the utilitiy in A 220/66 kV substation is constructed in a place called
order to retain the originality of the soil and to reduce the cost Chikkamagalur in Karnataka which has two different levels in
of project are discussed below: the substation area as shown in Fig. 3.

A 220/66kV substation is constructed in a place called Thallak The cutting and filling details in the substation was planned as
in Karnataka, wherein there are three different levels in the 14785 cubic meter and 19799 cubic meter respectively. Here
substation area as shown in Fig. 2. the case is somewhat different, which calls for more filling
compared to cutting, that means the soil has to be brought
from outside for filling with a cost double that of cutting cost
i.e Rs. 164 per cubic meter [2]. This clearly shows that, when
the entire land for the substation is to be levelled to have a
uniform levelled land surface, the cost of cutting and filling
along with the cost of extra soil to be filled would cost more
than double along with other technical issues discussed later.

2.2 General technical issues


Apart from the economic issue, there exists a few technical
issues with land filling and it will be dealt here. Even after a
careful land filling, the originality of the earth would be lost
even though Proctor density as per standard is maintained after
leveling [4]. After cutting and filling is carried out for
Fig. 4 . Substation with three levels
leveling, the filled up soil would have problems associated
with soil conductivity because, the original soil density would
The construction of substations involve cutting and filling of
have been lost.
the land to install equipment in different level in the form of
step like formation and the involved civil works as against the
The other problem associated with the levelled land by above
total approximate cost of substation is given in table II.
process could be, running away of the loose soil if proper
retaining walls at intermediate levels are not provided to check Table II. Typical cost of different Voltage substations and the civil cost in
the displacement of soil, which would once again add to the KPTCL
cost of civil work. Also, the filled soil in the substation yard
may yield when the movement of heavy equipment like power Voltage Class of Approximate Approximate
transformer may take place, if sufficient care is not taken Substation Cost of Cost of Civil
while making provision for roads in the substation yard. substation in Rs. works in Rs.
It can therefore be concluded that both cost and importantly Crores: Crores
the other related technical issues do not favour construction of 400 kV 90 12 to 14
substation by levelling the uneven ground.
220 kV 35 1 to 1.5
2.3 Alternative approach 110 kV 5 to 8 0.5 to 0.6

As an alternative, the substations layout can be designed 66 kV 5 to 8 0.5 to 0.6


retaining the major ground level, which invariably calls for
different bays/sections placed at different ground levels. This
will not only retain the soil stability but also would lead to III. ISSUES PERTAINING TO GROUNDING
reduced civil works. As practical examples, Figs. 3 & 4
presents two of the working KPTCL substations which are While the construction of substation in step-like terrain is a
constructed at two to three steps owing to non-availability of practically employed solution, a closer look into the substation
levelled land. grounding indicates several open issues. The associated
technical challenges, which need suitable quantitative
answers, are:

1. The earth termination resistance at different points in the


substation: As such, the international standards including
IEEE deals with analytical and empirical formulas for
substation earthing resistance, step and touch potentials
only for the case of construction on levelled earth [3 - 9].
Therefore there is an urgent need to reliably scrutinise and
quantify these quantities for substation constructed on
step-like land surface.

2. Ground grid interconnections between earth mats laid in


different levels and their impact on current distribution
during the fault. Variation of the step and touch potential
between the different levels for different injection point
Fig. 3. Substation with two levels needs a careful adjudication.
[6] Dawalibi, F., Bauchard, M., and Mukhedkar, D., “Survey on power
system grounding design practices,” IEEE Transactions on Power
3. Finally, considering the practical demand for construction Apparatus and Systems, vol. PAS-99, no. 4, pp. 1396–1405, July/ Aug.
of substation at step-like land surface, it is necessary to 1980.
search for critical issues with the grounding and possibly [7] Leonid Grcev, Farid Dawalibi “on Electromagnetic Model for transients
develop general guidelines for a safe ground grid design in grounding system” IEEE Transactions on Power Delivery, Vol. 11,
No. 2, April 1996, Pp 815-823.
methods.
[8] Grcev L and Dawalibi F., “An Electromagnetic model for Transients in
Grounding System”, IEEE Trans. On Power Delivery, Vol. 5, No. 4,
In other words, more research efforts are necessary for Nov. 1990, pp. 1773-1781.
handling this problem of imminent practical interest. [9] Grcev, L. and M. Heimbach, "Frequency dependent and transient
characteristics of substation grounding system," IEEE Transactions on
Power Delivery, Vol 12, No.1, Jan 1997, pp172-178.
IV. SUMMARY AND CONCLUSIONS

Availability of levelled land for the construction of power


substation is becoming increasingly difficult. Both from
economic point of view, as well as, due to associated technical
issues, levelling the ground surface is not suggested. This has
forced the utilities to construct substations in the available
land with tailor made and modified layouts, which invariably
results in bays at different ground levels. The associated
techno-economic issues are explained in this paper.

Further, in the present work, a very critical technical issue


pertaining to substation constructed on step-like land surface
is brought out. It is noted that the prevailing
international/national standards do not address the earthing
design for substation constructed on step-like land surface.
Therefore it is stated that there is an urgent need to
quantitatively evaluate the earthing resistance, step and touch
potentials for such substation earthing. At present the research
is in progress to find out the answers to the issues of practical
importance discussed in the present work.
ACKNOWLEDGMENT

Authors thank Prof. Udaya Kumar of Indian Institute of


Science, Bangalore, for his valuable discussions and
suggestions.

Authors also thank the authorities of Karnataka Power


Transmission Corporation Limited (KPTCL) for the images
and information on the substations constructed in step like
land surface.

REFERENCES

[1] Allen J Wood and Bruce F. Wollenberg “Power generation, Operation


and Control”, Wiley Interscience Publications, John Wiley & sons, Inc,
2nd Edition, 1996.
[2] Karnataka Power Transmission Corporation Limited (KPTCL),
“Schedule of Rates”, 1.4.2013.
[3] IEEE standard 80-2000, “IEEE Guide for Safety in AC Substation
Grounding”.
[4] Indian Standards equivalence of modified Proctor test (heavy
compaction) (IS: 2720, Part VIII-1983).
[5] Dawalibi F. P., and Mukhedkar, D., “Resistance measurement of large
grounding systems,” IEEE Transactions on Power Apparatus and
Systems, vol. PAS-98, no. 6, pp. 2348–2354, Nov./Dec. 1979.

View publication stats

You might also like