Proyek Instalasi Balai Latihan Kerja

The document provides details of construction materials and quantities needed for a Rusun Balai Latihan Kerja Pasar Rebo project. It lists CCTV, access card, fire alarm, electrical, water, and waste water installation requirements including pipe lengths, units, and total quantities for ground floor and floors 2-12. Muhammad Ihsan Efendi is noted as the technical officer for the electrical works.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views6 pages

Proyek Instalasi Balai Latihan Kerja

The document provides details of construction materials and quantities needed for a Rusun Balai Latihan Kerja Pasar Rebo project. It lists CCTV, access card, fire alarm, electrical, water, and waste water installation requirements including pipe lengths, units, and total quantities for ground floor and floors 2-12. Muhammad Ihsan Efendi is noted as the technical officer for the electrical works.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Proyek : Rusun Balai Latihan Kerja Pasar Rebo

Pekerjaan : Pekerjaan Mekanikal


TO By : Muhammad Ihsan Efendi

CCTV
Jenis panjang Satuan Banyak Lantai Total
Lantai Dasar UTP Cat 64 pairs ( kabel CCTV) 156.77 m1 1 156.77
Equipment CCTV Security Control 1 Unit 1 1
Dome Camera CCTV 6 BH 1 6
Lantai 2 - 12 UTP Cat 64 pairs ( kabel CCTV) 600.188 m1 11 6602.068
Dome Camera CCTV 5 BH 11 55

Acces Card
Lantai Dasar Acces Control Unit 1 Unit 1 1
Lantai 2 - 12 Kabel power NYM 3 x 2,5 mm2 474.767 m1 11 5222.437
Acces Card 16 BH 11 176

Fire Alarm
Lantai Dasar RACK MCFA 1 Unit 1 1
NYMHY 2 X 1,5 mm2 283.3 m1 1 283.3
Smoke Detector 40 BH 1 40
Equipment In Hedrant Box 2 Unit 1 2
R.o.R (Rate of Rise) Detector Type 4 BH 1 4
Flow Swtch 1 BH 1 1
Tampered Switch 1 BH 1 1
Lantai 2 - 12 NYMHY 2 X 1,5 mm2 277.86 m1 11 3056.46
Smoke Detector 64 BH 11 704
Equipment In Hedrant Box 2 Unit 11 22
R.o.R (Rate of Rise) Detector Type 2 BH 11 22
Flow Swtch 1 BH 11 11
Tampered Switch 1 BH 11 11
Proyek : Rusun Balai Latihan Kerja Pasar Rebo
Pekerjaan : Pekerjaan Elektrikal
TO By : Muhammad Ihsan Efendi

Instalasi Penerangan
Jenis Panjang Satuan Banyak lantai Total
Lantai Dasar TL 2 x 36 W , TYPE BALOK 14 bh 1 14
Down light PLC 1 x 18 w 60 bh 1 60
Down light PLC 1 x 18 w L/D Emergency battery 8 bh 1 8
Lampu EXIT TL 1 x 10 w L/D Emergency battery 3 bh 1 3
Lampu Baret TLE 20 w L/D Emergency battery 4 bh 1 4
Sakalar Tunggal 10 A 23 bh 1 23
Saklar Seri 10 A 24 bh 1 24
Stop Kontak 46 bh 1 46
NYM 3 x 2,5 mm2 282.51 m1 1 282.51
Lantai 2 - 12 TL 2 x 36 W , TYPE BALOK 1 bh 11 11
Down light PLC 1 x 18 w 21 bh 11 231
Down light PLC 1 x 18 w L/D Emergency battery 5 bh 11 55
Lampu EXIT TL 1 x 10 w L/D Emergency battery 3 bh 11 33
Lampu Baret TLE 20 w L/D Emergency battery 4 bh 11 44
Sakalar Tunggal 10 A 64 bh 11 704
Saklar Seri 10 A 38 bh 11 418
Stop Kontak 91 bh 11 1001
Down light outbow 18 w fitting E27 96 bh 11 1056
NYM 3 x 2,5 mm2 148.52 m1 11 1633.72
Instalasi Air bersih
Jenis Panjang Satuan
Lantai dasar Pipa air bersih Ø100 40.67 m1
Pipa air bersih Ø40 27.34 m1
Pipa air bersih Ø15 1.42 m1
Pipa air bersih Ø32 21.33 m1
Over Head Pipe 2 bh
Pipa air bersih elbow Ø100 3 bh
Pipa air bersih elbow Ø40 3 bh
Pipa air bersih tee Ø40 2 bh
Pipa air bersih elbow Ø32 2 bh

Lantai 2 - 12 Pipa air bersih Ø20 19.7 m1


Pipa air bersih Ø15 4.5 m1
Pipa air bersih Ø50 111.21 m1
Pipa air bersih elbow Ø15 1 bh
Pipa air bersih elbow Ø20 32 bh
Pipa air bersih tee Ø20 1 bh
Pipa air bersih elbow Ø50 5 bh
Pipa air bersih tee Ø50 16 bh
Gate valve 1 bh
Instalasi air kotor dan Air bekas
Lantai dasar Pipa air kotor Ø250 32.84 m1
Pipa air kotor Ø100 4875.55 m1
Pipa air kotor Ø150 6.06 m1
Pipa air bekas Ø100 4861.05 m1
Pipa air bekas Ø200 73.44 m1
Pipa air bekas Ø80 13.36 m1
Pipa air bekas Ø50 14.25 m1
Pipa air bekas Ø150 4738.72 m1
Biofilter 100 m3 / day 1 unit
Grease Trap 1 unit
Pipa Vent 3483.6 m1
Vent cup 8 bh
Pipa air kotor elbow Ø250 2 bh
Pipa air kotor Tee Ø250 1 bh
Pipa air kotor elbow Ø150 2 bh
Pipa air kotor elbow Ø100 1 bh
Pipa air bekas elbow Ø200 5 bh
Pipa air bekas Tee Ø200 2 bh
Pipa air bekas elbow Ø80 1 bh
Pipa air bekas elbow Ø50 1 bh

Lantai 2 - 12 Pipa air kotor Ø250 71.6 m1


Pipa air bekas Ø200 140.2 m1
pipa air kotor Elbow Ø250 10 bh
Pipa air kotor Tee Ø250 4 bh
pipa air bekas Elbow Ø200 20 bh
Pipa air bekas Tee Ø200 6 bh
Banyak lantai Total
1 40.67
1 27.34
1 1.42 50.92
1 21.33
1 2
1 3
1 3
1 2
1 2

11 216.7
11 49.5
11 1223.31
11 11
11 352
11 11
11 55
11 176
11 11

1 32.84 820.44
1 4875.55
1 6.06
1 4861.05
1 73.44 1615.64
1 13.36
1 14.25
1 4738.72
1 1
1 1
1 3483.6
1 8
1 2 112
1 1 45
1 2
1 1
1 5 225
1 2 68
1 1
1 1

11 787.6
11 1542.2
11 110
11 44
11 220
11 66