Professional Documents
Culture Documents
net/publication/282337442
Analysis of soldier pile wall with jet-grouting as retaining system for deep
excavation
CITATIONS READS
0 1,487
3 authors, including:
Some of the authors of this publication are also working on these related projects:
COST Action TU1202 – Impact of climate change on engineered slopes for infrastructure View project
All content following this page was uploaded by Josif Josifovski on 01 October 2015.
RÉSUMÉ Cet article présente une analyse et d'exécution les mesures de protection du fouille en profondeur dans le centre de la ville de
Skopje de bâtiment administratif de trois étages souterrains. Les frontières de 1155 m2 avec fosse de deux rues adjacentes fréquentes, un
bâtiment de grande hauteur existant et un autre chantier. La profondeur des fondations est -12.6 m autour de 3.5 m sous le niveau de la
nappe phréatique, donc la solution technique devrait offrir la stabilité et l'équilibre hydraulique adéquate de la fouille. Une enquête détaillée
du site a détecté gravier sableux jusqu'à -32 m qui continue ainsi marnes compactées. Ensemble Une combinaison entre le mur de soutène-
ment de la pile de soudure avec des ancres et des éléments „jet-grouting” doit former une barrière hydraulique, sceller complètement le
puits de flux direct de l'eau du sol dans la fosse. En outre, le „jet-grouting” aura certains effets sur la stabilité à travers l'amélioration du sol
de la matière locale. Un jet de fluide à double-injection a été choisi comme la plus efficace, car un diamètre d'érosion plus grande était né-
cessaire. Le calcul a été effectué en utilisant la méthode des éléments finis, tandis que les paramètres „jet-grouting” ont été définies selon la
norme EN 12716 et plus tard confirmées par les enquêtes de sentiers. Dans un délai de 2 mois 1344 colonnes de „jet-grouting” avec une
longueur totale de 4893 m avait été exécutée, à la réussite suivie par la construction de la structure souterraine.
1 INTRODUCTION
The location of the new public administration build- task. Especially when from all four sides the site is
ing in the Skopje city centre is not far away from the surrounded by existing structures or streets which
main square on the corner of the Macedonia and cannot be closed for the execution period. Beside ad-
Dame Gruev Street (Figure 1). The building should jacent streets (up and left on Figure 1) to the site, on
have 3 underground floors for parking and 8 floors the right side there is block of flats on six floors. On
above the terrain for offices. distance of around 10 m from the bottom, there is a
The protection of 52.35 x 22.8 m excavation pit or high-rise building with 16 floors. The protection of
area of 1155 m2 with depth of -12.6 m, 3.5 m under the excavation pit beside the ground stability had to
the ground water level is a formidable engineering
3953
Geotechnical Engineering for Infrastructure and Development
ensure hydraulic stability and dry conditions for con- a solution with stiff anchored pile retaining wall has
struction. been primarily considered. At some stage beside this
one also other possibilities were analyzed such as di-
aphragm wall. The design concept considers addi-
tional jet-grouting columns (soilcrete elements) add-
ed as curtain and carpet sealing the site from ground
water inflow. They also introduce improvement ef-
fects on the local soil material.
The pile retaining wall is constructed of 101 piles
with diameter of 80 cm spaced at 140 cm is discon-
tinuous soldier pile barrier sealed with additional ver-
tical soilcrete elements in between (Figure 2). To sta-
bilize the wall, anchors were added at level -3 m at
every opening in between the reinforced concrete
piles. Together with the horizontal barrier (carpet)
the pit is going to be complete secured from ground
water infiltration from side and bottom.
2 GROUND CONDITIONS
3954
Josifovski, Susinov and Markov
(а)
(а)
(b)
Figure 3. Excavation pit (a) Base plan and (b) Cross section 2-2.
4 JET-GROUTING PROCEDURE
3955
Geotechnical Engineering for Infrastructure and Development
terial was modeled using the МC and HS model in variations in the stiffness and dimensions. On dis-
contrast to the linear elastic model for the concrete tance of 1.25 m from the wall, a uniform surface load
material. The material properties of the soil and soil- q=33.33 kPa is assumed as design traffic load.
crete material are presented in Table 1. The total displacements on the top are smaller than
6 mm while at the toe of the wall it is between
Table 1. Material properties.
10 mm and 12 mm, see Figure 5(b). The maximum
Material SFc Soilcrete deformation of 28 mm in upward direction is in the
Unsat. unit weight un(kN/m3) 21,5 22,0 middle of the pit. It is a result of the water pressure
Sat. unit weight un(kN/m3) 22 22 but more as an effect of the unloading (3 m of exca-
Cohesion c (kPa) 2 658 vation) which realistically may not occur. In Figure
Angle of internal friction 35 37
5c the vertical distribution of the total pressure is pre-
Young’s modulus E50 (MPa) 40 8.000
Poisons ratio 0,3 0,2 sented where the maximum registered acting on the
Permeability k (m/s) 10-4 10-8 wall is 196 kPa and 50-120 kPa in the zone from the
wall to centre of the pit. To certain amount the total
pressure is influenced by the active pore pressure un-
A special attention has been put to definition of the der the GWL (Figure 6а).
soilcrete material according to the results from the The pore pressure is linearly distributed starting
laboratory tests. The characteristic UCS after 28 days from zero at -8.5 m finishing with 55 kPa at the toe
was adopted conservatively as 8 MPa although there of the wall. Another very important indicator which
were others ranging up to 17 MPa. The Hoek-Brown limits the bearing capacity and stability of the soil is
material model has been used for transformation to the potential for developing plastic and tension points
MC model according the measured parameters. For (Figure 6b). The sliding mechanism is depicted by
the deformation parameters the recommendation the red plastic zone in the toe and in combination
from the literature were followed defining the Hooks with tension zone in the middle of the pit. Although
modulus as Е = 1000*UCS (MPa), but again the tests the plastic zone is formed, the total resisting capacity
gave much greater value. The analysis had been per- at the toe is still not reached. This fact is confirmed
formed for static loads without seismic acceleration with the diagram of wall displacement depicted in
because the protection of the pit has temporal charac- Figure 6(c) and FOS calculation. Hence, displace-
ter. To be able to simulate the execution of the pro- ments are described with rotating mechanism with a
tection in different phases, a stage construction ap- centre positioned relatively low (in the lower third of
proach in calculation has been employed, in four the wall) resulting in 10 mm toe deformation which
consecutive phases: is result of the anchor. The rotation angle of the wall
1. Partially excavated pit with soldier pile wall is 1/475 which below allowed value of 1/500. The
with anchors (-8.5 m depth); global stability of the system is confirmed through so
2. Execution of jet-grouting elements; called /c reduction procedure resulting with a global
3. Complete excavation of the pit (-12.5 m FOS =1.64 far larger than the 1.1 allowed for tempo-
depth); rary structures.
4. FOS (φ- c reduction) procedure. All design measures for protection of the excava-
In this paper only the results from phase no. 3 will tion pit had been executed as planned, but the antici-
be presented and discussed in details. The modeling pated deformation had not occurred at least not in
process begins with definition of the geometry as such extent. For the whole process the site was in-
well as others, such as: anchors, load, soilcrete and strumented registering the deformations on the wall
soil material as depicted in Figure 5(a). The anchor and outside. Finally, the excavation in the pit had fin-
capacity is 250 kN/m’ calculated according to the ished in March 2014 after two months of work when
provisions from EN1997-1. As such it was modeled the construction of the structure started (Figure 7).
with inclination of 15 degrees, bond length of 7 m
and total length of 12 m. The pile wall is discretized
as equivalent diaphragm taking in consideration the
3956
Josifovski, Susinov and Markov
5
3 4
2
(а) (a)
(b)
(b)
(c)
(c)
Figure 5. (a) Discretization of elements and materials, (b) Total
displacements |u| from the excavation phase and (c) Vertical Figure 6. (a) Active pore pressure pactive from the excavation
stresses yy from the excavation phase. phase, (b) Plastic and tension points from the excavation phase and
(c) total displacement |u| of the retaining construction from the ex-
cavation phase.
3957
Geotechnical Engineering for Infrastructure and Development
6 CONCLUSIONS
REFERENCES
In this paper an analysis for protection of deep exca-
vation pit in the city Centre of Skopje has been pre- EN 1997-1:2012 Eurocode 7: Geotechnical design – Part 1: Gen-
sented. A set of different measures had been used to eral rules.
secure the 1155 m2 pit with depth of 12.6 m exactly EN 12716:2010 Execution of special geotechnical works – Jet
grouting.
3.5 m under the GWL. The task becomes even more Verlag fur Architektur und technische Wissenschaften GmbH &
difficult because of the fact that the site borders with Co. KG. 2003. Recommendations on Excavations. German Society
two very frequent streets, adjacent an existing high- for Geotechnics (Deutsche Gesellschaft fur Geotechnike.V.), Ernst
rise building and another construction site. The pre- & Sohn, Berlin, ISBN 3-433-01712-3.
Josifovski J. & Gjorgjevski S. 2013. Comparative Study of Differ-
sented solution had been able to provide an ade- ent Deep Excavation Retaining Systems. Proceedings,18th
quate hydraulic and equilibrium stability of the ex- ICSMGE- International Conference on Soil Mechanics and Ge-
cavation pit without unexpected situation during the otechnical Engineering, Vol. 3, (Eds. P. Delage et al.), 2095-2098,
construction period. Presses des Ponts, Paris, France, ISBN 978-2-85978-476-8.
Josifovski J., Gjorgjevski S. & Jovanovski M. 2012. Numerical
This solution has been chosen because it has Analysis of 20.5m Deep Excavation with Anchored Diaphragm
several advantages over other, such as: complete wa- Wall. Geotechnical Aspects of Underground Construction in Soft
ter sealing, ground improvement etc. Ground (Ed. Giulia Viggiani), 835-843, CRC Press / Balkema,
This experience has been most positive creating Taylor & Francis Group, London UK, Print ISBN: 978-0-415-
68367-8.
perfect water barrier without any infiltration of water. Josifovski J., Gjorgjevski S. & Jovanovski M. 2011. Deep Excava-
The registered displacement of the wall was smaller tion With Multi-Anchored Diaphragm Wall. Proceedings of 15th
than 2 mm, thus all the nearby infrastructure and European Conference on Soil Mechanics and Geotechnical Engi-
buildings were safe at all stages of construction. This neering, Part 3, (Eds. A. Anagnostopoulos et al.), 1485-1490, IOS
Press, Athens, Greece, ISBN 978-1-60750-800-7.
method has proved exceptionally advantageous in Kempfert, H.G. & Gebreselassie, B. 2006. Excavations and Foun-
comparison to others for sandy gravel soil dominant dations in Soft Soils. Springer-Verlag Berlin, Heidelberg, ISBN
in the greater region of Skopje. Beside the technical 540-32894-7.
aspects also the economic ones were in favor over Plaxis 2D AE. 2012. Scientific Manuel, Plaxis bv.
Potts, D.M. & Zdravkovic, L. 2001. Finite element analysis in
some classical solution of diaphragm wall in combi- geotechnical engineering: application. Imperial College of Sci-
nation with deep exfiltration wells. ence, Technology and Medicine, Thomas Telford Publishing,
The numerical modeling is powerful tool with Thomas Telford Ltd. ISBN 0-7277 2753-2.
many advantages over the analytical solutions ena-
3958