You are on page 1of 1

Annexure- 4

Technical Specifications for 10,000 MT Capacity Ammonia Storage Tank


greater than 5% shall be stress relieved after forming.

6.21 All erection lugs shall be removed before hydro–pneumatic testing. All other
temporary attachments may be allowed to remain only after attachment weld is
inspected with MP examination as per API 620.

6.22 Welding of all parts must be completed before heat treatment, wherever
applicable.

6.23 The contractor shall submit PQR and WPS for GNFC / PDIL approval for
welding of inter-connecting piping and tank.

6.24 Contractor shall submit the complete write up for the site fabrication, erection &
assembly with all the details but not limited to handling storage attachment, fit
up and welding etc. up to and including the final testing and cleaning along with
offer.

6.25 Contractor shall prepare detailed fabrication drawings including Bill of


Quantities and shall submit the same for M/s GNFC approval.

6.26 The Contractor shall comply in all respects with the provision of the applicable
codes, standards and specification during fabrication with respect to tolerances,
welding, fabrication, radiography, heat treatment, inspection, testing and quality
control etc. unless & otherwise specified.

6.27 Plates of different thicknesses shall be made flush with the inner surfaces of
tank unless otherwise stated.

6.28 All welding shall be carried out by qualified welders using approved
procedures in compliance with the requirements of codes, standards &
specifications and shall be duly certified by the concerned inspecting authority.

6.29 All welding procedures & welding consumables specifications / make must be
got approved from GNFC before starting any fabrication job as per ASME
section IX. Welding of all parts must be completed before heat treatment. For
all welds, Welding Procedure Specification (WPS) must be provided.

6.30 All sharp corners shall be rounded off with smooth radius. Inside edge of
manhole and hand hole at the internal surface shall be rounded to minimum
radius 5 mm.

6.31 All flange bolts shall straddle center line unless otherwise stated.

6.32 In case of nozzle with butt-end construction, extra length shall be provided to
facilitate hydraulic testing and subsequently cutting and edge preparation to suit
piping welding.

6.33 All nozzles less than or equal to NB 50 mm shall be stiffened with three equi-

08_Tech_Spec_LSTK_D1003AM1_Annexure-4 Page 15 of 26

You might also like